0005_NSP_ELECTRICAL SAFETY PROCEDURE REQUIREMENTS.docx

DOCX document 33 KB Posted

Attached to
USNS GRAPPLE Rudder Dry Dock Federal contract opportunity
Solicitation number
N32205-15-R-4008
Issued by
Department of the Navy Military Sealift Command

About this file

WI 5

View the file

Other files for this federal contract opportunity

Other files attached to USNS GRAPPLE Rudder Dry Dock, newest first.
File Type Posted
N32205-15-R-4008-0001.doc DOC document
Attachment J - 13 Past Performance Questionnaire.docx DOCX document
0030_B_CONTINUATION OF SERVICES.docx DOCX document
0001_NSP_INTENT SCOPE GEN REQUIREMENTS DEFINITIONS.docx DOCX document
Attachment J - 4 GFM List.docx DOCX document
0003_NSP_ APPROACH BERTH AND MOORING.docx DOCX document
Attachment J - 9 Disclosure of Lobbying Activities SF-LLL.docx DOCX document
Attachment J - 11 Dry Dock Evaluation Form.docx DOCX document
0024_N_Physical Security at Private Contractor's Facility REV 22 NOV 2013.doc DOC document
902 Additional Days in Dry Dock.doc DOC document
0006_NSP_HEAVY WEATHER PLAN.docx DOCX document
0021_A_Clean Gas Free Tanks.docx DOCX document
0018_A_DELIVERY AND REDELIVERY.docx DOCX document
Attachment J - 12 Past Performance Data.docx DOCX document
0004_NSP_TESTING AND QUALITY ASSURANCE.docx DOCX document
Emergent Rudder Repairs Work Item Index.docx DOCX document
Attachment J - 10 Interport Differential.docx DOCX document
0011_A_GENERAL SERVICES FOR SHIP T ARS.docx DOCX document
0404_A_SPEED LOG REPLACEMENT Final.doc DOC document
0020_A_GAS FREE CERTIFICATES.docx DOCX document
908_A_STBD Rudder and Rudder Stock Renewal Rev A.doc DOC document
0010_A_FURNISH OFFICE FOR OMT.docx DOCX document
0022_A_DOCK TRIALS AND SEA TRIALS.docx DOCX document
Attachment J - 3 Category B Work Items.xlsx XLSX spreadsheet
0002_NSP_TECHNICAL REPRESENTATIVES.docx DOCX document
N32205-15-R-4008.doc DOC document
Attachment J - 8 Request for Spec Clarification.docx DOCX document
Attachment J - 2 Category A Work Items.xlsx XLSX spreadsheet
Attachment J - 7 MSC Ship Repair Facility Survey.docx DOCX document
Attachment J - 14 Technical Data Non-Disclosure.docx DOCX document
0901_A_DOCKING AND UNDOCKING New.docx DOCX document
0016_A_FIRE PROTECTION AND SHIPS SAFETY PROGRAM.docx DOCX document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS GRAPPLE

(T-ARS 53)

GENERAL SERVICES & REQUIREMENTSN32205-15-R-4008
ITEM NO. 005CATEGORY “N”4 JUNE 2012
ELECTRICAL SAFETY PROCEDURE REQUIREMENTSMSC/N43D/WTB

ABSTRACT:

This work item establishes shipboard electrical safety requirements for both low voltage and high voltage applications. These requirements and procedures shall be followed by all contractors and subcontractors in the accomplishment of all work requirements.

REFERENCES:

1.1 MSC Safety Management System Procedure 2.1-004-ALL, Lock-out/Tag-out

1.2 MSC Safety Management System Procedure 2.1-016-AKE, High Voltage Systems

1.3 29CFR 1910.335 Electrical Safety Related Work Practices; Safeguards for Personnel Protection

1.4 NFPA 70E Standard for Electrical Safety Requirements for Employee Workplaces

ITEM LOCATION:

1.5 Throughout the ship and as applicable while working 404, Speed Log Replacement and 908, Ruddder and Ruddder Stock Replacent.

GOVERNMENT FURNISHED MATERIAL (GFM): None

NOTES:

5.1Comply will all MSC General Technical Requirements (GTRs) as applicable to this work item.
5.2Review other work items under this contract to determine their effect on the work required by this work item.
5.3Review Work Item 001 for definitions of terms used in this work item.
5.4These Work Item requirements apply to all Contractor and sub-Contractor personnel regardless of tier.
5.5T-AKE class ships use a 6600 volt AC main bus distributed throughout the ship to various load centers and equipment. High Voltage areas require special awareness and access control. “High Voltage” (per ABS Rules 4-8-5 paragraph 3) is defined as 1000 volts and above.

QUALITY ASSURANCE REQUIREMENTS: None additional.

STATEMENT OF WORK:

1.6 Electrical Safety - Lock-out/Tag-out Procedures

1.6.1 The Contractor shall have an established electrical safety lock-out/tag-out program in place to provide adequate protection against electrical hazards in the accomplishment of the work specified in this work package. A written description of the contractor’s electrical safety lock-out/tag-out procedures shall be provided to the MSCREP, ship’s Master and Chief Engineer upon vessel arrival at the contractor’s facility, along with a discussion on the procedures.

1.6.2 Ship’s force shall maintain their existing lock-out/tag-out procedures, in accordance with reference 2.1 for low voltage applications and reference 2.2 for high voltage applications, in addition to the contractor’s procedures, to provide a redundant safety measure for these systems. The contractor shall co-ordinate electrical safety lock-out/tag-out procedures with the MSCREP and the ship’s Chief Engineer to ensure the plans complement each other and provide maximum electrical safety for ship’s crew and contractor personnel.

1.6.3 Do not accomplish work on any piece of mechanical, electrical or electronic equipment, circuit, or system that has not been isolated from its energy source (electrical, mechanical, hydraulic, pneumatic, chemical, or thermal) and tagged-out in accordance with the shipyard’s electrical safety plan and references 2.1 and 2.2.

1.6.4 Do not attempt to operate any piece of mechanical, electrical or electronic equipment, circuit, or system that is tagged-out by either the contractor, ship or both. Tags must be properly cleared through both the contractor’s procedures and the ship’s procedures before systems and equipment can be safely energized and operated.

1.6.5 All contractor and subcontractor personnel intended to work on electrical circuits and equipment onboard MSC vessels shall provide and utilize proper personnel protective equipment (PPE) and tools in accordance with references 2.3 and 2.4. Contractor and subcontractor personnel will not be permitted to perform electrical systems work onboard if they are found to not possess the proper tools and PPE.

1.7 High Voltage Systems (T-AKE 6600V Systems)

1.7.1 Ensure all Contractor and sub-Contractor personnel comply with the ship’s High Voltage System procedures (T-AKE Vessels) of reference 2.2, in addition to the contractor’s internal procedures.

1.7.2 Obey all High Voltage (HV) signs and verbal directions of the ship’s force “Competent Person In-charge” (CPIC).

1.7.3 Ensure all Contractor personnel possess awareness and exercise vigilance regarding HV safety, watch for all signs indicating HV, and take prudent action to preclude unauthorized entry into HV areas.

1.7.3.1 Provide formal briefing to all Contractor and sub-Contractor personnel of HV concerns.

1.7.3.2 Submit a report to the MSCREP listing all personnel formally briefed on HV safety no less than five (5) days prior to start of the period of performance.

1.7.4 Do not disturb, cut, move or damage HV cables in any fashion.

1.7.5 Do not paint HV cables.

1.7.5.1 Temporarily mask, cover or protect HV cables when painting in spaces that contain HV cables.

1.7.6 Do not work on or test HV equipment:

1.7.6.1 For which Contractor personnel do not possess a ship’s force issued “High Voltage Permit to Work” (HVPTW) or "High Voltage Sanction For Test” (HVSFT) permit.

1.7.7 Ensure only Contractor and sub-Contractor personnel designated as “qualified” work on HV equipment.

1.7.7.1 Prepare a list of all Contractor and sub-Contractor personnel identified as “qualified” to:

a. Work in HV spaces

b. Work on HV equipment.

1.7.7.2 Include on the list the specific type of formal qualification training possessed by each individual.

1.7.7.3 Submit copies of the list to the MSCREP and the ship’s Chief Engineer before any individual commences HV permit request.

8.0 GENERAL REQUIREMENTS: None Additional

005-1