0003_NSP_ APPROACH BERTH AND MOORING.docx

DOCX document 31 KB Posted

Attached to
USNS GRAPPLE Rudder Dry Dock Federal contract opportunity
Solicitation number
N32205-15-R-4008
Issued by
Department of the Navy Military Sealift Command

About this file

WI 3

View the file

Other files for this federal contract opportunity

Other files attached to USNS GRAPPLE Rudder Dry Dock, newest first.
File Type Posted
N32205-15-R-4008-0001.doc DOC document
Attachment J - 13 Past Performance Questionnaire.docx DOCX document
0030_B_CONTINUATION OF SERVICES.docx DOCX document
0001_NSP_INTENT SCOPE GEN REQUIREMENTS DEFINITIONS.docx DOCX document
Attachment J - 4 GFM List.docx DOCX document
0005_NSP_ELECTRICAL SAFETY PROCEDURE REQUIREMENTS.docx DOCX document
Attachment J - 9 Disclosure of Lobbying Activities SF-LLL.docx DOCX document
Emergent Rudder Repairs Work Item Index.docx DOCX document
Attachment J - 10 Interport Differential.docx DOCX document
0011_A_GENERAL SERVICES FOR SHIP T ARS.docx DOCX document
0404_A_SPEED LOG REPLACEMENT Final.doc DOC document
0020_A_GAS FREE CERTIFICATES.docx DOCX document
908_A_STBD Rudder and Rudder Stock Renewal Rev A.doc DOC document
0010_A_FURNISH OFFICE FOR OMT.docx DOCX document
Attachment J - 11 Dry Dock Evaluation Form.docx DOCX document
0024_N_Physical Security at Private Contractor's Facility REV 22 NOV 2013.doc DOC document
902 Additional Days in Dry Dock.doc DOC document
0006_NSP_HEAVY WEATHER PLAN.docx DOCX document
0021_A_Clean Gas Free Tanks.docx DOCX document
0018_A_DELIVERY AND REDELIVERY.docx DOCX document
Attachment J - 12 Past Performance Data.docx DOCX document
0004_NSP_TESTING AND QUALITY ASSURANCE.docx DOCX document
0022_A_DOCK TRIALS AND SEA TRIALS.docx DOCX document
Attachment J - 3 Category B Work Items.xlsx XLSX spreadsheet
0002_NSP_TECHNICAL REPRESENTATIVES.docx DOCX document
N32205-15-R-4008.doc DOC document
Attachment J - 8 Request for Spec Clarification.docx DOCX document
Attachment J - 2 Category A Work Items.xlsx XLSX spreadsheet
Attachment J - 7 MSC Ship Repair Facility Survey.docx DOCX document
Attachment J - 14 Technical Data Non-Disclosure.docx DOCX document
0901_A_DOCKING AND UNDOCKING New.docx DOCX document
0016_A_FIRE PROTECTION AND SHIPS SAFETY PROGRAM.docx DOCX document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS GRAPPLE

(T-ARS 53)

GENERAL SERVICE & REQUIREMENTS N32205-15-R-4008

ITEM NO. 003CATEGORY “N”4 JUNE 2012
APPROACH, BERTH, AND MOORINGMSC/N43D/WTB

1.0 ABSTRACT

1.1 The Contractor shall provide a safe and adequate approach route, safe and secure berth, and moor the vessel.

2.0 REFERENCES

2.1 MIL. STD. MIL-C-28628D, dtd. July 1991; Camels.

2.2 MIL. STD. MIL-F-29248, dtd. 21 November 1986; Fenders, Marine, Foam Filled, Netless

2.3 MSC Drawing No. 802-5364378, General Arrangement Main Deck and Below.

2.4 MSC Drawing No. 802-5364379, General Arrangement Plan 01 and Above.

3.0 ITEM LOCATION/DESCRIPTION

3.1 The following vessel characteristics and expected arrival conditions are provided:

3.1.1 Length: 255

3.1.2 Breadth: 51

3.1.3 Draft: 17’0”

3.1.4 Expected arrival draft: Fwd: 16’0”, Aft: 16’0”

3.1.5 Highest Point Above Baseline: 126’6” (Aft Kingpost Mast)

3.2 Approach route(s) to Contractor facility and berth(s).

3.3 Contractor secure berth(s) and berth arrangement chart.

3.4 Contractor mooring locations and mooring plan.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None

5.0 NOTES

5.1 The contractor and all subcontractors regardless of tier shall consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7.

5.2 The contractor and all subcontractors regardless of tier are advised to review other work items under this contract, inclusive of work items 006, 007, 011 and 019, to determine the collaborative effects of these work requirements. Many of the definitions relating to performance of this work item are found in Work Item 001.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.

7.0 STATEMENT OF WORK REQUIRED

7.1 The ship must be afforded a safe approach, secure berth, and safe mooring at all times.

7.2 APPROACH:

7.2.1 The ship shall be afforded an unobstructed approach to the Contractor’s facility (plant); including rented, leased, subcontracted facilities, or the facilities of any subcontractor where the vessel will be berthed and moored, for any part of the performance period. There must be no danger of the ship grounding, or colliding with all overhead obstructions during transit. This applies for delivery to the Contractor, redelivery to the Government, or any inter/intra facility transits.

7.2.2 Consistent with ship’s draft condition, the ship shall remain afloat without any danger of grounding and avoid colliding with all overhead obstructions during all transits.

a) A minimum “Air Draft” clearance of not less than Ten (10) Feet shall be afforded between the highest vertical projection of the vessel at mean high water, all bridges and any cables passing above/across the marked channel along the entire route.

7.2.3 The minimum amount of water under the deepest / lowest projection from keel baseline at all times all tides during transit/approach shall be as follows:

a) From the sea buoy to a point in the navigable channel where the contractor takes delivery of the vessel, minimum clearance shall be 3 Feet of water under the lowest projection at mean low water.

b) From the point in the navigable channel where the contractor takes delivery of the vessel, and vessel has Pilot aboard with adequate tug support to proceed dead stick to the intended pier, minimum clearance shall be 2 Feet of water under the lowest projection at mean low water.

7.2.4 Offerors must submit with their proposals copies of all the latest National Oceanographic and Atmospheric Administration (NOAA) (or US Army Corps of Engineers) waterway approach charts to their facility. Charts are to show the entire route of transit from the sea buoy to the Contractor’s facility, including any for proposed inter/intra facility transits. Charts must provide adequate demonstration that the Offeror has positively determined the route(s) providing safe vessel transit.

7.2.5 Offerors must submit an approach chart with their proposals. The approach chart shall be equal to the berthing chart in dimensions and contain the following data:

7.2.5.1 Offerors shall furnish current depth soundings for the approach to the pier and/or dry-dock from the main channel.

7.2.5.2 Soundings must indicate the depths over the full length of the approach, from the point in the navigable channel where the contractor takes delivery of the vessel to the pier and/or dry dock at a maximum of one hundred (100) foot intervals. Adequate breadth of soundings shall be provided to demonstrate sufficient underwater clearance for vessel arrival, departure and any required turning evolutions. Approach soundings shall be considered current if taken within two hundred and seventy (270) days from the date of issue of the solicitation. NOAA charts or excerpts of such documents will not be accepted.

7.2.5.3 All information must be readily available to clearly chart the progress of the ship from arrival at the port to safe mooring or dry-docking. The ship must be afforded safe access and egress to and from the Contractor’s pier and/or dry-dock.

7.3 BERTH:

7.3.1 Consistent with ship’s anticipated arrival drafts, the ship shall remain afloat (except when dry-docked), with no danger of grounding during the entire performance period.

7.3.2 The Contractor's assigned berth for the vessel shall be at a suitable pier where the ship will remain afloat (not resting on the bottom) at all times. The minimum amount of water under the deepest / lowest projections from keel baseline at all times while at the pier and all tides shall be no less than three (3) feet of water except when weather conditions exist per work items 006 and 007. Paragraph 7.3.5 of this work item requires the offeror to show adequate water in their berthing chart.

7.3.3 The ship must be afloat during any anticipated severe weather, as covered under work items 006 and 007.

7.3.4 Offerors must submit with their proposal all information relative to berthing facilities. Information must include the following characteristics of the pier:

· Location

· Pier number and/or name

· Street address, city, state, and zip code

· Geographic reference to a current navigational chart using longitude and latitude coordinates.

· Length

· Width

7.3.4.1 Each Offeror shall draw the ship to scale, in the exact location it will occupy during the performance period, using the ship characteristics given in this solicitation on the berthing chart. For the berth chart the ship is to be superimposed over the water depth soundings grid, the entire grid to be clearly legible.

7.3.5 The Offerors shall prepare a berth chart. The berth chart shall contain the following data. A sample berthing chart is provided as reference 2.4:

a. It shall furnish current soundings taken at Mean Low Water of the berthing area.

b. The soundings must list depth in a ten (10) foot grid pattern from the pier string piece. The grid pattern for the intended ship berth shall extend for the entire length of the pier and outward from the pier for a minimum of one hundred (100) feet.

c. Soundings shall be taken by a qualified waterways surveyor and certified by same. Soundings shall be considered current if taken within two hundred and seventy (270) days from date of issue of the solicitation and should indicate the date they were taken.

d. The Offeror’s berthing chart shall be made up in blueprint form approximately two (2) feet by three (3) feet minimum with a geographic reference point of latitude and longitude and a geographic indicator of north.

7.3.6 The individuals/firms preparing the berthing and approach charts shall be qualified by possession of valid licenses (or certificates of competency), as issued by the state (or federal) agency tasked within the geographic locality of the Offeror with this licensing responsibility, and be stamped/illustrated on the charts, and shall indicate the date prepared.

7.4 MOORING:

7.4.1 The ship shall be provided a safe and secure mooring capable of withstanding the force of winds at a speed of thirty two (32 to 38) thirty eight miles per hour received perpendicularly on the beam at drafts consistent with minimum acceptable dry-docking displacement or the light load condition, (which ever is greater as stated in the solicitation). Not less than seventy five percent (75%) of the ship shall be alongside the pier. Should any portion of the ship extend beyond the pier, a minimum of three (3) separate additional mooring points shall be provided for each extension. These shall be in addition to those on the pier. The additional mooring points shall be distributed on both the Port and Starboard sides of the ship.

7.4.2 Offerors must submit with their proposal all information relative to mooring facilities.

7.4.3 Information must include the following characteristics of the mooring arrangement:

a. Location, pier number and/or name, street address, city, and state with geographic reference to current navigational chart using longitude and latitude.

b. Length

c. Width

d. Locations, type, design and proof test loads for all mooring fittings, e.g., bollards, bits, cleats, deadmen, etc.

e. The arrangement of all mooring lines between the ship and mooring securements.

f. The angle of the mooring lines between the ship and each mooring securement point.

g. Quantity, size, locations and securement method of all camels and fenders.

h. General construction characteristics including: type, location, quantity of pilings; surface type and condition; location and sizes of drains; buildings and structures (sheds); width of apron and access limits for vehicles.

i. All permanently installed services, e.g.’, shore power, fire water mains, potable water lines, telephone lines, steam, compressed air. In addition, the locations where portable services equipment (when necessary), will be parked shall be indicated.

j. Location of and distances to nearest fire alarm call boxes.

k. Fences and gates

7.4.4 Each Offeror shall draw the ship to scale, in the exact location it will occupy during the performance period, using the ship characteristics given in this solicitation on the mooring chart.

7.4.5 Offerors shall furnish a chart made up in blueprint form approximately two (2) feet by three (3) feet minimum with a geographic reference point of latitude and longitude and a geographic indicator of North. The chart shall be prepared by a qualified surveyor and certified by name. The chart shall be current. The chart shall illustrate to scale, all information required above in sub-paragraphs of 7.4.3.

7.4.6 The mooring chart as it reflects the physical characteristics of the pier as identified is subparts 7.4.3 shall be prepared by a licensed professional engineer.

7.4.7 Certification shall be by the affixing to the mooring chart (original and copies), of a stamp or statement attesting to the accuracy of the chart by the preparer(s). The certification shall indicate the name(s) of the individual(s) and firm(s) which prepared the chart, the date(s) the survey was conducted and the dates(s) the chart was prepared (drawn). It shall be signed and dated by the preparer(s).

7.4.8 Documentation of design load calculations for mooring appurtenances shall be furnished. Calculations shall demonstrate design and construction to be capable of withstanding; wind speeds of seventy three (73) to one hundred thirty six (136) miles per hour, when received perpendicularly on the beam (at drafts consistent with minimum acceptable dry-docking displacement or the light load condition, (which ever condition in the solicitation creates the greater sail area), and not be torn out.

7.4.8.1 In those instances where the documentation of the design loads for securement appurtenances cannot be provided, it shall be required to have furnished copies of the most recent test certificates.

7.4.8.2 Test certificates shall be considered recent if tests were conducted within five (5) years of the date of issue of the solicitation, and the pier has not been subject to potential collision or weather related damage. NOAA charts or excerpts of such documents will not be accepted.

7.4.8.3 All mooring appurtenances regardless of design type, i.e., bollards, bitts, or cleats, must be in an upright position and have; bases or pedestals in sound condition without any broken securement bolt holes in the base mounting flanges. All securements (bolts, washers, nuts, etc.) installed, tightly in place, and in good condition. All arms and horns in place with none missing, broken, bent, misshaped or distorted. Concrete foundations shall be in sound condition without excessive spalling and cracks or chipped and damaged concrete. Damage due to spalling, cracking, and chipping over ten percent of a foundation’s area is not acceptable. Wood and pier mooring appurtenance foundations, stringpiece mountings and support structures shall be in sound condition without cracks, rips, splits, or missing portions. Damage due to cracks, rips, splits, or missing portions of wood on the appurtenance foundations, stringpiece mountings and support structures are not acceptable.

7.4.8.4 All information must be readily available to clearly ascertain the safety afforded by the mooring arrangement offered the ship.

7.4.9 Camels and/or fenders:

7.4.9.1 Camels and/or fenders shall be used at all times to breast out (separate) the ship from the pier. Camels shall be single or multiple, of hardwood in accordance with or equal to reference 2.1.

7.4.9.2 Fenders shall be of the suspended foam filled design in accordance with or equal to reference 2.2, or solid rubber dock suspended type.

7.4.9.3 Floating camels and /or suspended fenders shall be a minimum of four (4) feet wide/ diameter and six (6) feet long.

7.4.9.4 Dock mounted fenders shall provide for a minimum clearance for FOUR (4) feet.

7.4.9.5 The quantity and frequency of placement for camels/fenders shall be no less than one camel/fender for each two hundred (200) feet of the ship’s length over all, and adequate to protect the ship form contacting the side of the pier.

7.4.10 In instances where it is necessary to breast the ship out from the pier by use of a barge to facilitate achieving adequate depth of water for berthing, or when a floating crane is brought alongside in performing a work item(s), the barge or crane shall be fended off from the side of the ship by use of camels or fenders. Truck or heavy construction machinery tires are not acceptable.

7.4.11 During the course of this repair/overhaul period, no other ship will be docked alongside of or tied up to this vessel, nor shall this ship be docked alongside of or tied up to any floating dry-dock.

8.0 GENERAL REQUIREMENTS: None Additional

003-9