Attachment_5_JMPS_Master_Schedule_-_DRAFT.xlsx

XLSX spreadsheet 392 KB Posted

Attached to
PMA-281 Systems Lifecyle Support
Solicitation number
N00421-17-R-0014
Issued by

About this file

JMPS Master Schedule

View the file

Other files

File Type Posted
N00421-17-R-0014_-_Q&A_Part_2.pdf PDF
Attachment_P6_CLIN_Breakout_Spreadsheet.xlsx XLSX spreadsheet
Attachment_P7__Annual_Fully_Burdened_Labor_.xlsx XLSX spreadsheet
N00421-17-R-0014-0001.pdf PDF
Attachment_P4_Past_Performance_Information_Form.docx DOCX document
N00421-17-R-0014_-_Q&A.pdf PDF
Attachment_9_WD_15-5611_(Rev._-3).pdf PDF
Attachment_P6_CLIN_Breakout_Spreadsheet.xls XLS spreadsheet
Attachment_12_WD_15-5799_(Rev._-4)_.pdf PDF
Attachment_5_WD_15-4341_(Rev._-6).pdf PDF
Attachment_1_DD_Form_254.pdf PDF
Attachment_7_WD_15-5547_(Rev._-4).pdf PDF
Attachment_6_WD_15-4539_(Rev._-3).pdf PDF
Exhibit_A_A001-A028.pdf PDF
Attachment_10_WD_15-5635_(Rev._-6).pdf PDF
N00421-17-R-0014.pdf PDF
Attachment_P7__Annual_Fully_Burdened_Labor_.xlsx XLSX spreadsheet
Attachment_3_Surveillance_Activity_Checklist_(SAC).pdf PDF
Attachment_11_WD_15-5781_(Rev.-3).pdf PDF
Attachment_P4_Past_Performance_Information_Form.pdf PDF
Attachment_4_JMPS_IGS_Schedule.pdf PDF
Attachment_8_WD_15-5597_(Rev._-4.pdf PDF
Attachment_2_GFP.pdf PDF
Attachment_P5__Contractor_Performance_Assessment_(CPAQ)_.pdf PDF
Draft_RFP_N00421-17-R-001_Q&A_Part_2_of_2.pdf PDF
Draft_RFP_N00421-17-R-0014_-_Q&A_Part_1_of_2.pdf PDF
Attachment_P4_Past_Performance_Information_Form.pdf PDF
Attachment_P6_CLIN_Breakout_Spreadsheet.xls XLS spreadsheet
Attachment_3_Surveillance_Activity_Checklist_(SAC).docx DOCX document
Exhibits_A001_-_A028.xls XLS spreadsheet
Attachment_4_Integrated_Government_Schedule_-_DRAFT.pdf PDF
Attachment_P5__Contractor_Performance_Assessment_Questionnaire_(CPAQ).pdf PDF
Attachment_1_DD_Form_254.pdf PDF
Attachment_2_Government_Furnished_Equipment.xlsx XLSX spreadsheet
Attachment_P7_Fully_Burdened_Labor_Rates_Spreadsheet.xlsx XLSX spreadsheet
N00421-17-R-0014.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Unique IDTeam or IPT NameNameDurationPredecessorsSuccessorsStartFinishActual StartActual FinishBaseline StartBaseline FinishBaseline DurationMajor Event
3TACAIR3931 daysMon 8/4/14Mon 8/27/29Mon 8/4/14NANANA0 days?No
16777217F-18 3.1.0F-18 3.13686 daysMon 8/4/14Fri 3/16/29Mon 8/4/14NANANA0 days?No
201327129F-18 3.1.0F-18 3.1.03686 daysMon 8/4/14Fri 3/16/29Mon 8/4/14NAMon 8/4/14Thu 9/14/283554 days?No
16777219F-18 3.2.0F-18 3.2.03775 daysFri 9/12/14Mon 8/27/29Fri 9/12/14NANANA0 days?No
184549664F-18 3.2.0MPE Start0 days43,49,50,51,52,53,54,55,39Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
184549629F-18 3.2.0Platform Milestones (Level One)571 daysMon 6/1/15Fri 9/29/17Mon 6/1/15NAMon 6/1/15Thu 9/1/16309 daysNo
184549630F-18 3.2.0Platform Requirements Received (External Task)0 daysMon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
184549788F-18 3.2.0Framework Requirement0 days5Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
184549790F-18 3.2.0JSIM Delivery0 days4Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
184549827F-18 3.2.0BMPE Delivery0 daysMon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
184549631F-18 3.2.0UPC Delivery Iteration 10 days129FFMon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/150 daysYes
184549887F-18 3.2.0UPC Delivery Iteration 20 daysMon 9/21/15Mon 9/21/15Mon 9/21/15Mon 9/21/15Mon 9/21/15Mon 9/21/150 daysYes
184549632F-18 3.2.0UPC Delivery Iteration 30 days140FFMon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/160 daysYes
184549634F-18 3.2.0OTRR (External Task)1 day31248Wed 10/5/16Wed 10/5/16Wed 10/5/16Wed 10/5/16Thu 9/1/16Thu 9/1/160 daysNo
184549893F-18 3.2.0H12 OT First Event1 dayWed 10/12/16Wed 10/12/16Wed 10/12/16Wed 10/12/16NANA0 days?No
184549892F-18 3.2.0H12 OT Last Event0 days13Fri 3/31/17Fri 3/31/17NANANANA0 days?No
184549891F-18 3.2.0H12 OT Data Reduction an Report Production65 days12249SSThu 6/15/17Fri 9/15/17NANANANA0 days?No
184549890F-18 3.2.0H12/MPE 3.2 Fleet Release0 daysFri 9/29/17Fri 9/29/17NANANANA0 days?No
184549778F-18 3.2.0Platform Need Date0 daysMon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
184549635F-18 3.2.0Training (External Task)0 daysMon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
184549638F-18 3.2.0Milestones (Level Two)758 daysThu 11/20/14Mon 1/22/18Thu 11/20/14NAThu 11/20/14Fri 7/14/17638 daysNo
184549639F-18 3.2.0IRR Approval (Milestone A)0 days7093,173Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/140 daysYes
184549640F-18 3.2.0CRR Approval (Milestone B)0 days75130,192,178Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/150 daysYes
184549641F-18 3.2.0External Deliveries, Iteration 1 Received0 days129130Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/150 daysNo
184549642F-18 3.2.0SI Build Review 1 Complete0 days130133Mon 6/8/15Mon 6/8/15Mon 6/8/15Mon 6/8/15Mon 6/8/15Mon 6/8/150 daysNo
184549643F-18 3.2.0MPE Disk Set 1 Delivered0 days137241,198Fri 7/31/15Fri 7/31/15Fri 7/31/15Fri 7/31/15Fri 7/31/15Fri 7/31/150 daysNo
184549644F-18 3.2.0EDT 1 Completed0 days242243,61,246Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/150 daysYes
184549645F-18 3.2.0DT Test MPE Build 1 Completed0 days20190,140Mon 9/28/15Mon 9/28/15Mon 9/28/15Mon 9/28/15Mon 9/28/15Mon 9/28/150 daysNo
184549646F-18 3.2.0External Deliveries, Iteration 3 Received0 days140141Fri 5/6/16Fri 5/6/16Fri 5/6/16Fri 5/6/16Mon 5/9/16Mon 5/9/160 daysNo
184549647F-18 3.2.0SI Build Review 3 Complete0 days141144Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/16Fri 5/13/16Fri 5/13/160 daysNo
184549648F-18 3.2.0MPE Disk Set 4 Delivered0 days148,154207Wed 6/22/16Wed 6/22/16Wed 6/22/16Wed 6/22/16Mon 6/13/16Mon 6/13/160 daysNo
184549650F-18 3.2.0DT Test MPE Build 3 Completed0 days21077,109,91,216,64Thu 7/28/16Thu 7/28/16Thu 7/28/16Thu 7/28/16Tue 7/19/16Tue 7/19/160 daysNo
184549752F-18 3.2.0DT End of Test0 days216282Tue 8/2/16Tue 8/2/16Tue 8/2/16Tue 8/2/16Wed 7/20/16Wed 7/20/160 daysNo
184549828F-18 3.2.0MMI Disk Completed Post Final Iteration0 days220248Thu 7/14/16Thu 7/14/16Thu 7/14/16Thu 7/14/16Thu 6/30/16Thu 6/30/160 daysNo
184549652F-18 3.2.0JMPS Operational Test Readiness Review (OTRR) Completed0 days80248,10Thu 9/22/16Thu 9/22/16Thu 9/22/16Thu 9/22/16Wed 11/2/16Wed 11/2/160 daysYes
184549653F-18 3.2.0Operational Test (OT) Completed0 days248249Thu 6/15/17Thu 6/15/17NANAWed 4/12/17Wed 4/12/170 daysNo
184549654F-18 3.2.0MMI Disk Completed (Post OT)0 days230,227282Tue 9/19/17Tue 9/19/17NANAWed 5/10/17Wed 5/10/170 daysNo
184549655F-18 3.2.0Deployment Readiness Review (DRR) Approval (Milestone C)0 days85,277FS+12 days,22388Mon 11/20/17Mon 11/20/17NANAWed 5/31/17Wed 5/31/170 daysYes
184549656F-18 3.2.0Fleet Release Shipped0 days88283Thu 12/7/17Thu 12/7/17NANAThu 6/15/17Thu 6/15/170 daysYes
184549657F-18 3.2.0Training Completed0 days280285Mon 1/22/18Mon 1/22/18NANAFri 7/14/17Fri 7/14/170 daysNo
184549377F-18 3.2.0Internal PMA-2813775 daysFri 9/12/14Mon 8/27/29Fri 9/12/14NAFri 9/12/14Tue 3/13/293655 daysNo
184549443F-18 3.2.0Program Management786 daysFri 9/12/14Thu 12/7/17Fri 9/12/14NAFri 9/12/14Thu 6/15/17666 daysNo
184549448F-18 3.2.0Draft Schedule1 day140Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549773F-18 3.2.0Draft Budget (Cost Estimate)1 day3967FFTue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/151 dayNo
184549774F-18 3.2.0Development Plan277 daysFri 9/12/14Mon 11/2/15Fri 9/12/14Mon 11/2/15Fri 9/12/14Mon 11/2/15277 daysNo
184549444F-18 3.2.0CONOPS124 daysFri 9/12/14Thu 3/26/15Fri 9/12/14Thu 3/26/15Fri 9/12/14Thu 3/26/15124 daysNo
184549445F-18 3.2.0Start Preliminary CONOPS1 day144Fri 9/12/14Fri 9/12/14Fri 9/12/14Fri 9/12/14Fri 9/12/14Sat 9/13/141 dayNo
184549446F-18 3.2.0Route CONOPS for Peer Review10 days4345Mon 9/15/14Fri 9/26/14Mon 9/15/14Fri 9/26/14Mon 9/15/14Fri 9/26/1410 daysNo
184549588F-18 3.2.0Update CONOPS100 days4446Mon 9/29/14Mon 3/9/15Mon 9/29/14Mon 3/9/15Mon 9/29/14Mon 3/9/15100 daysNo
184549589F-18 3.2.0Route CONOPS for Signature7 days4547Tue 3/10/15Wed 3/18/15Tue 3/10/15Wed 3/18/15Tue 3/10/15Wed 3/18/157 daysNo
184549584F-18 3.2.0CONOPS Published5 days4648,101,67FF,172,254Thu 3/19/15Wed 3/25/15Thu 3/19/15Wed 3/25/15Thu 3/19/15Wed 3/25/155 daysNo
184549585F-18 3.2.0Provide Published CONOPS to NAWCWD1 day4793Thu 3/26/15Thu 3/26/15Thu 3/26/15Thu 3/26/15Thu 3/26/15Thu 3/26/151 dayNo
184549858F-18 3.2.0Develop Iteration Plan1 day167FF,172,254Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549857F-18 3.2.0Identify Stakeholders1 day167FF,172,254Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549856F-18 3.2.0Define Versioning and Nomenclature1 day167FF,172,254Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549855F-18 3.2.0Define User Documentation Requirements1 day167FF,172,254Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549854F-18 3.2.0Identify Certifications Required1 day167FF,172,254Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549861F-18 3.2.0Identify H/W Configuration1 day167FF,172,254Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549860F-18 3.2.0Identify Architecture1 day167FF,172,254Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/151 dayNo
184549739F-18 3.2.0Test Management443 daysTue 11/4/14Thu 9/1/16Tue 11/4/14Thu 9/1/16Tue 11/4/14Wed 7/27/16417 daysNo
184549744F-18 3.2.0WIPT #1244 daysTue 11/4/14Thu 11/5/15Tue 11/4/14Thu 11/5/15Tue 11/4/14Thu 11/5/15244 daysNo
184549745F-18 3.2.0Gather WIPT #1 Materials1 day17359Thu 11/5/15Thu 11/5/15Thu 11/5/15Thu 11/5/15Thu 11/5/15Thu 11/5/151 dayNo
184549746F-18 3.2.0Conduct WIPT #1 Meeting0 days58188,72,174Tue 11/4/14Tue 11/4/14Tue 11/4/14Tue 11/4/14Tue 11/4/14Tue 11/4/140 daysYes
184549747F-18 3.2.0WIPT #22 daysFri 11/20/15Mon 11/23/15Fri 11/20/15Mon 11/23/15Fri 11/20/15Mon 11/23/152 daysNo
184549748F-18 3.2.0Gather WIPT #2 Materials1 day200,202,246,2362Fri 11/20/15Fri 11/20/15Fri 11/20/15Fri 11/20/15Fri 11/20/15Fri 11/20/151 dayNo
184549740F-18 3.2.0Conduct WIPT #2 Meeting1 day61144Mon 11/23/15Mon 11/23/15Mon 11/23/15Mon 11/23/15Mon 11/23/15Mon 11/23/151 dayYes
184549741F-18 3.2.0WIPT #323 daysTue 8/2/16Thu 9/1/16Tue 8/2/16Thu 9/1/16Wed 7/20/16Wed 7/27/166 daysNo
184549742F-18 3.2.0Gather WIPT #3 Materials22 days209,2865Tue 8/2/16Wed 8/31/16Tue 8/2/16Wed 8/31/16Wed 7/20/16Tue 7/26/165 daysNo
184549743F-18 3.2.0Conduct WIPT #3 Meeting1 day6477Thu 9/1/16Thu 9/1/16Thu 9/1/16Thu 9/1/16Wed 7/27/16Wed 7/27/161 dayYes
184549458F-18 3.2.0IRR Brief232 daysThu 11/20/14Wed 11/4/15Thu 11/20/14Wed 11/4/15Thu 11/20/14Wed 11/4/15232 daysNo
184549459F-18 3.2.0Draft IRR Brief1 day255FF,47FF,49FF,50FF,51FF,52FF,53FF,54FF,55FF,40FF68Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/151 dayNo
184549460F-18 3.2.0Provide IRR Read Aheads1 day6769Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/151 dayNo
184549461F-18 3.2.0Conduct IRR0 days6870Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/140 daysNo
184549462F-18 3.2.0IRR Approval (Milestone A)0 days6918Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/14Thu 11/20/140 daysNo
184549476F-18 3.2.0CRR Brief115 daysThu 5/28/15Mon 11/9/15Thu 5/28/15Mon 11/9/15Thu 5/28/15Mon 11/9/15115 daysNo
184549477F-18 3.2.0Draft CRR Brief1 day175FF,190FF,99,103FF,256FF,5973Fri 11/6/15Fri 11/6/15Fri 11/6/15Fri 11/6/15Fri 11/6/15Fri 11/6/151 dayNo
184549478F-18 3.2.0Provide CRR Read Aheads1 day7274Mon 11/9/15Mon 11/9/15Mon 11/9/15Mon 11/9/15Mon 11/9/15Mon 11/9/151 dayNo
184549479F-18 3.2.0Conduct CRR0 days7375Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/150 daysNo
184549480F-18 3.2.0CRR Approval (Milestone B)0 days7419Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/15Thu 5/28/150 daysNo
184549481F-18 3.2.0OTRR Brief14 daysFri 9/2/16Thu 9/22/16Fri 9/2/16Thu 9/22/16Thu 10/6/16Wed 11/2/1619 daysNo
184549482F-18 3.2.0Draft OTRR Brief2 days192FF,193FF,65,106FF,118,121FF,2878,184SSFri 9/2/16Tue 9/6/16Fri 9/2/16Tue 9/6/16Thu 10/6/16Thu 10/27/1615 daysNo
184549483F-18 3.2.0Provide OTRR Read Aheads1 day7779Wed 9/7/16Wed 9/7/16Wed 9/7/16Wed 9/7/16Fri 10/28/16Tue 11/1/163 daysNo
184549484F-18 3.2.0Conduct OTRR1 day78,23680Thu 9/22/16Thu 9/22/16Thu 9/22/16Thu 9/22/16Wed 11/2/16Wed 11/2/161 dayNo
184549485F-18 3.2.0OTRR Approval (Milestone C)0 days7931Thu 9/22/16Thu 9/22/16Thu 9/22/16Thu 9/22/16Wed 11/2/16Wed 11/2/160 daysNo
184549489F-18 3.2.0DRR Brief9 daysTue 11/7/17Mon 11/20/17NANAThu 5/4/17Wed 5/31/1719 daysNo
184549490F-18 3.2.0Draft DRR Brief5 days250,260,215FF83,87Tue 11/7/17Tue 11/14/17NANAThu 5/4/17Wed 5/24/1715 daysNo
184549491F-18 3.2.0Provide DRR Read Aheads3 days8284Wed 11/15/17Fri 11/17/17NANAThu 5/25/17Tue 5/30/173 daysNo
184549492F-18 3.2.0Conduct DRR1 day8385Mon 11/20/17Mon 11/20/17NANAWed 5/31/17Wed 5/31/171 dayNo
184549493F-18 3.2.0DRR Approval (Milestone C)0 days84,123,125,124FF34,286Mon 11/20/17Mon 11/20/17NANAWed 5/31/17Wed 5/31/170 daysNo
184549486F-18 3.2.0Fleet Release Message15 daysWed 11/15/17Thu 12/7/17NANAThu 5/25/17Thu 6/15/1715 daysNo
184549487F-18 3.2.0Draft Fleet Release Message10 days8288Wed 11/15/17Thu 11/30/17NANAThu 5/25/17Thu 6/8/1710 daysNo
184549488F-18 3.2.0Finalize Fleet Release Message5 days87,3435Fri 12/1/17Thu 12/7/17NANAFri 6/9/17Thu 6/15/175 daysNo
184549381F-18 3.2.0Systems Engineering628 daysFri 9/12/14Thu 4/20/17Fri 9/12/14NAFri 9/12/14Tue 11/29/16537 daysNo
184549449F-18 3.2.0Initial SERB Review1 day24,244209Mon 11/23/15Mon 11/23/15Mon 11/23/15Mon 11/23/15Mon 11/23/15Mon 11/23/151 dayNo
184549406F-18 3.2.0Final SERB Review1 day28216Tue 8/2/16Tue 8/2/16Tue 8/2/16Tue 8/2/16Wed 7/20/16Wed 7/20/161 dayNo
184549382F-18 3.2.0Functional Requirements Document (FRD)251 daysFri 9/12/14Thu 9/24/15Fri 9/12/14Thu 9/24/15Fri 9/12/14Thu 9/24/15251 daysNo
184549397F-18 3.2.0Draft Statement of Intent (SOI), Statement of Functionality(SOF) and Statement of Requirements (SOR)0 days48,1894Fri 9/12/14Fri 9/12/14Fri 9/12/14Fri 9/12/14Fri 9/12/14Sat 9/13/140 daysNo
184549403F-18 3.2.0Send FRD to Stakeholders7 days9395Thu 12/11/14Fri 12/19/14Thu 12/11/14Fri 12/19/14Thu 12/11/14Wed 12/24/147 daysNo
184549404F-18 3.2.0Peer Review FRD9 days9496,188Thu 1/8/15Wed 1/21/15Thu 1/8/15Wed 1/21/15Thu 1/8/15Wed 1/21/159 daysNo
184549405F-18 3.2.0WD Updates FRD9 days9597Thu 3/26/15Tue 4/7/15Thu 3/26/15Tue 4/7/15Thu 3/26/15Tue 4/7/159 daysNo
184549586F-18 3.2.0Re-Deliver Updated FRD to PMA-28110 days9698,101Wed 4/8/15Tue 4/21/15Wed 4/8/15Tue 4/21/15Wed 4/8/15Tue 4/21/1510 daysNo
184549587F-18 3.2.0Route FRD for PMA Signature11 days9799Wed 4/22/15Wed 5/6/15Wed 4/22/15Wed 5/6/15Wed 4/22/15Wed 5/6/1511 daysNo
184549701F-18 3.2.0Publish FRD98 days9872Thu 5/7/15Thu 9/24/15Thu 5/7/15Thu 9/24/15Thu 5/7/15Thu 9/24/1598 daysNo
184549702F-18 3.2.0Deployment Specification44 daysFri 9/12/14Fri 11/14/14Fri 9/12/14Fri 11/14/14Fri 9/12/14Fri 11/14/1444 daysNo
184549676F-18 3.2.0Assemble Deployment Package Specification0 days97,47102Fri 9/12/14Fri 9/12/14Fri 9/12/14Fri 9/12/14Fri 9/12/14Fri 9/12/140 daysNo
184549703F-18 3.2.0Draft Deployment Package Specification5 days101103Mon 9/15/14Fri 9/19/14Mon 9/15/14Fri 9/19/14Mon 9/15/14Fri 9/19/145 daysNo
184549704F-18 3.2.0Peer Review Package Specification5 days10272FF,104Mon 9/22/14Fri 9/26/14Mon 9/22/14Fri 9/26/14Mon 9/22/14Fri 9/26/145 daysNo
184549705F-18 3.2.0Update Deployment Package Specification5 days103105Mon 9/29/14Fri 10/3/14Mon 9/29/14Fri 10/3/14Mon 9/29/14Fri 10/3/145 daysNo
184549706F-18 3.2.0Route Deployment Package Specification for Signature5 days104106Mon 10/6/14Fri 10/10/14Mon 10/6/14Fri 10/10/14Mon 10/6/14Fri 10/10/145 daysNo
184549707F-18 3.2.0Publish Deployment Package Specification23 days10577FF,263Tue 10/14/14Fri 11/14/14Tue 10/14/14Fri 11/14/14Tue 10/14/14Fri 11/14/1423 daysNo
184549425F-18 3.2.0NAWCWD CSAA MPE Development C&A Process178 daysMon 7/25/16Thu 4/20/17Mon 7/25/16NATue 6/14/16Wed 9/28/1675 daysNo
184549579F-18 3.2.0Initial Steps17 daysMon 7/25/16Tue 8/16/16Mon 7/25/16Tue 8/16/16Tue 7/19/16Wed 8/3/1611 daysNo
184549580F-18 3.2.0Finalize MPE Build, Draft C&A Plan, and security Test Request Approval Form Submitted for IAT&E (Kickoff Event)0 days28110Thu 7/28/16Thu 7/28/16Thu 7/28/16Thu 7/28/16Tue 7/19/16Tue 7/19/160 daysNo
184549581F-18 3.2.0Set-up, Scan, and Analysis2 days109111Mon 7/25/16Mon 8/1/16Mon 7/25/16Mon 8/1/16Wed 7/20/16Thu 7/21/162 daysNo
184549582F-18 3.2.0Generate Technical Validation of Scan Results, STIG Checks10 days110112Tue 8/2/16Mon 8/15/16Tue 8/2/16Mon 8/15/16Fri 7/22/16Mon 8/1/167 daysNo
184549583F-18 3.2.0Generate Final C&A Summary1 day111113Tue 8/9/16Tue 8/16/16Tue 8/9/16Tue 8/16/16Tue 8/2/16Wed 8/3/162 daysNo
184549576F-18 3.2.0Initial Complete (Diamond)0 days112115Tue 8/16/16Tue 8/16/16Tue 8/16/16Tue 8/16/16Wed 8/3/16Wed 8/3/160 daysNo
184549426F-18 3.2.0Memorandum of Change (MOC) Process12 daysWed 8/17/16Thu 9/1/16Wed 8/17/16Thu 9/1/16Thu 8/4/16Wed 8/24/1615 daysNo
184549749F-18 3.2.0Complete Technical Analysis Report1 day113116Wed 8/17/16Wed 8/17/16Wed 8/17/16Wed 8/17/16Thu 8/4/16Thu 8/4/161 dayNo
184549750F-18 3.2.0Obtain Technical Security Lead Memo2 days115117Thu 8/18/16Fri 8/19/16Thu 8/18/16Fri 8/19/16Fri 8/5/16Mon 8/8/162 daysNo
184549751F-18 3.2.0Obtain TSLM Signature0 days116118,123Tue 8/23/16Tue 8/23/16Tue 8/23/16Tue 8/23/16Tue 8/9/16Tue 8/9/161 dayNo
184549429F-18 3.2.0No Change in Security Posture Complete0 days11777,119Tue 8/23/16Tue 8/23/16Tue 8/23/16Tue 8/23/16Tue 8/9/16Tue 8/9/160 daysNo
184549779F-18 3.2.0Develop MOC Package for PMA-281 Routing0 days118120Tue 8/23/16Tue 8/23/16Tue 8/23/16Tue 8/23/16Wed 8/10/16Fri 8/12/163 daysNo
184549780F-18 3.2.0Staff MOC Package0 days119121Tue 8/23/16Tue 8/23/16Tue 8/23/16Tue 8/23/16Mon 8/15/16Fri 8/19/165 daysNo
184549781F-18 3.2.0Obtain PMA Signature (MOC)7 days12077FFWed 8/24/16Thu 9/1/16Wed 8/24/16Thu 9/1/16Mon 8/22/16Wed 8/24/163 daysNo
184549782F-18 3.2.0Marine Core Enterprise Network (MCEN)156 daysWed 8/24/16Thu 4/20/17Wed 8/24/16NATue 6/14/16Wed 9/28/1675 daysNo
184549783F-18 3.2.0Obtain MCEN Certification97 days11785Wed 8/24/16Fri 1/27/17Wed 8/24/16Fri 1/27/17Wed 8/10/16Wed 9/28/1635 daysNo
184549871F-18 3.2.0SVT: External Agent Certification150 days14885FFThu 9/1/16Thu 4/20/17Thu 9/1/16NATue 6/14/16Tue 7/5/1615 daysNo
184549870F-18 3.2.0Certification Validation133 days14885Tue 9/27/16Thu 4/20/17Tue 9/27/16NAWed 7/6/16Tue 7/19/1610 daysNo
184549378F-18 3.2.0PMP553 daysMon 6/1/15Fri 9/1/17Mon 6/1/15NAMon 6/1/15Tue 4/25/17461 daysNo
184549384F-18 3.2.0MPE Integration553 daysMon 6/1/15Fri 9/1/17Mon 6/1/15NAMon 6/1/15Tue 4/25/17461 daysNo
184549385F-18 3.2.0Iteration 144 daysMon 6/1/15Fri 7/31/15Mon 6/1/15Fri 7/31/15Mon 6/1/15Fri 7/31/1544 daysNo
184549738F-18 3.2.0IT. 1: SVT: Initial UPC/Component1 day7FF20Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/15Mon 6/1/151 dayNo
184549736F-18 3.2.0IT. 1: Component Check In5 days19,2021,131Tue 6/2/15Mon 6/8/15Tue 6/2/15Mon 6/8/15Tue 6/2/15Mon 6/8/155 daysNo
184549796F-18 3.2.0IT. 1: Pre-build Coordination1 day130133,196Tue 6/9/15Tue 6/9/15Tue 6/9/15Tue 6/9/15Tue 6/9/15Tue 6/9/151 dayNo
184549872F-18 3.2.0IT. 137 daysWed 6/10/15Fri 7/31/15Wed 6/10/15Fri 7/31/15Wed 6/10/15Fri 7/31/1537 daysYes
184549386F-18 3.2.0IT. 1: Assemble MPE20 days21,131135,134SSWed 6/10/15Wed 7/8/15Wed 6/10/15Wed 7/8/15Wed 6/10/15Wed 7/8/1520 daysNo
184549797F-18 3.2.0IT. 1: Create MPE VDD5 days133SS135Wed 6/10/15Tue 6/16/15Wed 6/10/15Tue 6/16/15Wed 6/10/15Tue 6/16/155 daysNo
184549388F-18 3.2.0IT. 1: Create Silver Disks6 days133,134136Thu 7/9/15Thu 7/16/15Thu 7/9/15Thu 7/16/15Thu 7/9/15Thu 7/16/156 daysNo
184549387F-18 3.2.0IT. 1: Smoke Testing8 days135137Fri 7/17/15Tue 7/28/15Fri 7/17/15Tue 7/28/15Fri 7/17/15Tue 7/28/158 daysNo
184549379F-18 3.2.0IT. 1: Distribute Silver Disk3 days13622,268Wed 7/29/15Fri 7/31/15Wed 7/29/15Fri 7/31/15Wed 7/29/15Fri 7/31/153 daysNo
184549885F-18 3.2.0IT. 217 daysMon 9/21/15Wed 10/14/15Mon 9/21/15Wed 10/14/15Mon 9/21/15Wed 10/14/1517 daysYes
184549390F-18 3.2.0Iteration 319 daysFri 5/6/16Thu 6/2/16Fri 5/6/16Thu 6/2/16Fri 5/6/16Mon 6/13/1626 daysNo
184549662F-18 3.2.0IT. 3: SVT:UPC/Component Updates1 day9FF,2425Fri 5/6/16Fri 5/6/16Fri 5/6/16Fri 5/6/16Fri 5/6/16Mon 5/9/161 dayNo
184549737F-18 3.2.0IT. 3: Component Check In1 day2526,142Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/16Fri 5/13/165 daysNo
184549801F-18 3.2.0IT. 3: Prebuild Coordination0 days141144,205Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/16/16Mon 5/16/161 dayNo
184549873F-18 3.2.0IT. 317 daysTue 5/10/16Thu 6/2/16Tue 5/10/16Thu 6/2/16Tue 5/17/16Mon 6/13/1619 daysYes
184549391F-18 3.2.0IT. 3: Assemble MPE6 days26,62,142145Tue 5/10/16Mon 5/23/16Tue 5/10/16Mon 5/23/16Tue 5/17/16Mon 5/23/165 daysNo
184549802F-18 3.2.0IT. 3: Create MPE VDD1 day144146Mon 5/23/16Tue 5/24/16Mon 5/23/16Tue 5/24/16Tue 5/24/16Fri 5/27/164 daysNo
184549392F-18 3.2.0IT. 3: Create Silver Disks10 days145147,159Tue 5/10/16Mon 5/23/16Tue 5/10/16Mon 5/23/16Tue 5/31/16Thu 6/2/163 daysNo
184549380F-18 3.2.0IT. 3: Smoke Testing3 days146148Tue 5/24/16Thu 5/26/16Tue 5/24/16Thu 5/26/16Fri 6/3/16Wed 6/8/164 daysNo
184549393F-18 3.2.0IT. 3: Distribute Silver Disk3 days14727,162,271,124,150,100Tue 5/31/16Thu 6/2/16Tue 5/31/16Thu 6/2/16Thu 6/9/16Mon 6/13/163 daysNo
184549900F-18 3.2.0IT.410 daysThu 6/9/16Wed 6/22/16Thu 6/9/16Wed 6/22/16NANA0 days?Yes
184549903F-18 3.2.0IT. 4: Assemble MPE6 days148151SS,152SSThu 6/9/16Thu 6/16/16Thu 6/9/16Thu 6/16/16NANA0 days?No
184549902F-18 3.2.0IT. 4: Create MPE VDD5 days150SSFri 6/10/16Thu 6/16/16Fri 6/10/16Thu 6/16/16NANA0 days?No
184549901F-18 3.2.0IT. 4: Create Silver Disks6 days150SS153Thu 6/9/16Thu 6/16/16Thu 6/9/16Thu 6/16/16NANA0 days?No
184549899F-18 3.2.0IT. 4: Smoke Testing1 day152154Tue 6/14/16Tue 6/14/16Tue 6/14/16Tue 6/14/16NANA0 days?No
184549898F-18 3.2.0IT. 4: Distribute Silver Disk3 days15327Mon 6/20/16Wed 6/22/16Mon 6/20/16Wed 6/22/16NANA0 days?No
184549907F-18 3.2.0Iteration 516 daysTue 8/8/17Tue 8/29/17NANANANA0 days?Yes
184549906F-18 3.2.0IT.5 Assemble MPE10 days248FS+36 days157,212,213,165,168Tue 8/8/17Mon 8/21/17NANANANA0 days?No
184549905F-18 3.2.0IT.5 Distribute SIlverDisk3 days156,213214SS,275Fri 8/25/17Tue 8/29/17NANANANA0 days?No
184549722F-18 3.2.0OT MMI7 daysTue 5/31/16Wed 6/8/16Tue 5/31/16Wed 6/8/16Fri 6/3/16Wed 6/15/169 daysNo
184549800F-18 3.2.0Create MMI5 days146219,160Tue 5/31/16Mon 6/6/16Tue 5/31/16Mon 6/6/16Fri 6/3/16Thu 6/9/165 daysNo
184549834F-18 3.2.0Smoke Test MMI2 days159218Mon 6/6/16Wed 6/8/16Mon 6/6/16Wed 6/8/16Fri 6/10/16Wed 6/15/164 daysNo
184549844F-18 3.2.0OT MVM9 daysThu 6/23/16Wed 7/6/16Thu 6/23/16Wed 7/6/16Tue 6/14/16Fri 6/24/169 daysNo
184549843F-18 3.2.0Build MVM5 days148163Thu 6/23/16Wed 6/29/16Thu 6/23/16Wed 6/29/16Tue 6/14/16Mon 6/20/165 daysNo
184549842F-18 3.2.0Smoke Test MVM4 days162222Thu 6/30/16Wed 7/6/16Thu 6/30/16Wed 7/6/16Tue 6/21/16Fri 6/24/164 daysNo
184549803F-18 3.2.0MMI Deploy9 daysTue 8/22/17Fri 9/1/17NANAThu 4/13/17Tue 4/25/179 daysNo
184549806F-18 3.2.0Develop MMI (post OT)5 days248,156226,166Tue 8/22/17Mon 8/28/17NANAThu 4/13/17Wed 4/19/175 daysNo
184549835F-18 3.2.0Smoke Test MMI (post OT)4 days165225Tue 8/29/17Fri 9/1/17NANAThu 4/20/17Tue 4/25/174 daysNo
184549847F-18 3.2.0MVM Deploy9 daysTue 8/22/17Fri 9/1/17NANAThu 4/13/17Tue 4/25/179 daysNo
184549846F-18 3.2.0Build MVM (Deploy)5 days248,156169Tue 8/22/17Mon 8/28/17NANAThu 4/13/17Wed 4/19/175 daysNo
184549845F-18 3.2.0Smoke Test MVM (Deploy)4 days168229Tue 8/29/17Fri 9/1/17NANAThu 4/20/17Tue 4/25/174 daysNo
184549501F-18 3.2.0System Test and Evaluation664 daysThu 1/22/15Tue 10/3/17Thu 1/22/15NAWed 11/5/14Wed 5/10/17604 daysNo
184549502F-18 3.2.0Operational Test Risk Assessment Level of Test (OT RALOT) Decision4 daysTue 11/3/15Fri 11/6/15Tue 11/3/15Fri 11/6/15Tue 11/3/15Fri 11/6/154 daysNo
184549503F-18 3.2.0Draft RALOT Recommendation1 day49,50,51,52,53,54,55,47173Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/151 dayNo
184549504F-18 3.2.0Initiate RALOT Recommendation with COTF1 day172,18174,58Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/151 dayNo
184549776F-18 3.2.0Update OT RALOT1 day173,59175Thu 11/5/15Thu 11/5/15Thu 11/5/15Thu 11/5/15Thu 11/5/15Thu 11/5/151 dayNo
184549507F-18 3.2.0Finalize OT RALOT Recommendation1 day17472FFFri 11/6/15Fri 11/6/15Fri 11/6/15Fri 11/6/15Fri 11/6/15Fri 11/6/151 dayNo
184549505F-18 3.2.0Test Planning401 daysThu 1/22/15Fri 9/2/16Thu 1/22/15Fri 9/2/16Wed 11/5/14Fri 8/7/15181 daysNo
184549508F-18 3.2.0Draft Test and Evaluation Master Plan (TEMP) Annex (If Req)312 daysFri 5/29/15Fri 9/2/16Fri 5/29/15Fri 9/2/16Wed 11/5/14Thu 4/23/15107 daysNo
184549509F-18 3.2.0Develop TEMP Annex30 days19192,179Fri 5/29/15Fri 7/10/15Fri 5/29/15Fri 7/10/15Wed 11/5/14Wed 11/26/1415 daysNo
184549880F-18 3.2.0PMA-281 Internal Review20 days178180Mon 7/13/15Fri 8/7/15Mon 7/13/15Fri 8/7/15Mon 12/1/14Fri 12/5/145 daysNo
184549879F-18 3.2.0Update TEMP Annex194 days179181Mon 8/10/15Fri 5/27/16Mon 8/10/15Fri 5/27/16Mon 12/8/14Mon 12/8/141 dayNo
184549878F-18 3.2.0SVT: N98, N84, COTIF O-6 Review7 days180182Sat 5/28/16Wed 6/8/16Sat 5/28/16Wed 6/8/16Tue 12/9/14Tue 2/3/1530 daysNo
184549877F-18 3.2.0Update TEMP Annex15 days181183Wed 6/8/16Wed 6/29/16Wed 6/8/16Wed 6/29/16Wed 2/4/15Wed 2/18/1510 daysNo
184549876F-18 3.2.0PMA-281 TEMP Final Signature20 days182184Thu 6/30/16Thu 7/28/16Thu 6/30/16Thu 7/28/16Thu 2/19/15Wed 2/25/155 daysNo
184549882F-18 3.2.0SVT: Route TEMP Annex for Signature (COTIF, N84, N98)0 days183,77SS186,185Fri 7/29/16Thu 9/1/16Fri 7/29/16Thu 9/1/16Thu 2/26/15Wed 4/22/1540 daysNo
184549904F-18 3.2.0TEMP Approved by PEO (U&W)1 day184186Fri 9/2/16Fri 9/2/16Fri 9/2/16Fri 9/2/16NANA0 days?No
184549511F-18 3.2.0TEMP Annex Published0 days184,185248Fri 9/2/16Fri 9/2/16Fri 9/2/16Fri 9/2/16Thu 4/23/15Thu 4/23/151 dayNo
184549512F-18 3.2.0Draft Developmental Test (DT) Plan32 daysThu 1/22/15Mon 3/9/15Thu 1/22/15Mon 3/9/15Thu 1/22/15Mon 3/9/1532 daysNo
184549711F-18 3.2.0Develop DT Plan0 days59,95189Thu 1/22/15Thu 1/22/15Thu 1/22/15Thu 1/22/15Thu 1/22/15Fri 1/23/150 daysNo
184549514F-18 3.2.0Route DT Plan for Signature20 days188190Mon 1/26/15Mon 2/23/15Mon 1/26/15Mon 2/23/15Mon 1/26/15Mon 2/23/1520 daysNo
184549515F-18 3.2.0DT Plan Published10 days18972FFTue 2/24/15Mon 3/9/15Tue 2/24/15Mon 3/9/15Tue 2/24/15Mon 3/9/1510 daysNo
184549667F-18 3.2.0Draft Operational Test (OT) Plan50 daysFri 5/29/15Fri 8/7/15Fri 5/29/15Fri 8/7/15Fri 5/29/15Fri 8/7/1550 daysNo
184549536F-18 3.2.0Develop OTRR Certification Checklist Complete5 days178,1977FF,193Fri 5/29/15Thu 6/4/15Fri 5/29/15Thu 6/4/15Fri 5/29/15Thu 6/4/155 daysNo
184549665F-18 3.2.0SVT: OT Plan45 days19277FFFri 6/5/15Fri 8/7/15Fri 6/5/15Fri 8/7/15Fri 6/5/15Fri 8/7/1545 daysNo
184549518F-18 3.2.0DT Testing567 daysWed 6/10/15Tue 10/3/17Wed 6/10/15NAWed 6/10/15Wed 5/10/17465 daysNo
184549519F-18 3.2.0Iteration 1 DT Testing77 daysWed 6/10/15Mon 9/28/15Wed 6/10/15Mon 9/28/15Wed 6/10/15Mon 9/28/1577 daysNo
184549389F-18 3.2.0DT. 1: Setup DT Lab1 day131198Wed 6/10/15Wed 6/10/15Wed 6/10/15Wed 6/10/15Wed 6/10/15Wed 6/10/151 dayNo
184549874F-18 3.2.0DT. 135 daysMon 8/3/15Mon 9/21/15Mon 8/3/15Mon 9/21/15Mon 8/3/15Mon 9/21/1535 daysNo
184549829F-18 3.2.0DT. 1: Software Installation5 days22,196199Mon 8/3/15Fri 8/7/15Mon 8/3/15Fri 8/7/15Mon 8/3/15Fri 8/7/155 daysNo
184549831F-18 3.2.0DT. 1: Quick Look5 days198200Mon 8/10/15Fri 8/14/15Mon 8/10/15Fri 8/14/15Mon 8/10/15Fri 8/14/155 daysNo
184549520F-18 3.2.0DT. 1: Test MPE Build25 days199201,61,202,238Mon 8/17/15Mon 9/21/15Mon 8/17/15Mon 9/21/15Mon 8/17/15Mon 9/21/1525 daysNo
184549521F-18 3.2.0DT. 1: Complete Post DT Analysis5 days20024Tue 9/22/15Mon 9/28/15Tue 9/22/15Mon 9/28/15Tue 9/22/15Mon 9/28/155 daysNo
184549753F-18 3.2.0DT. 1: Update Metrics1 day20061Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/151 dayNo
184549886F-18 3.2.0DT.216 daysThu 10/15/15Thu 11/5/15Thu 10/15/15Thu 11/5/15Thu 10/15/15Thu 11/5/1516 daysNo
184549524F-18 3.2.0Iteration 4 DT Testing56 daysMon 5/9/16Thu 7/28/16Mon 5/9/16Thu 7/28/16Tue 5/17/16Tue 7/19/1644 daysNo
184549394F-18 3.2.0DT. 4: Setup DT Lab0 days142207Mon 5/9/16Mon 5/9/16Mon 5/9/16Mon 5/9/16Tue 5/17/16Mon 5/23/165 daysNo
184549875F-18 3.2.0DT. 4: Setup DT Lab26 daysMon 6/20/16Wed 7/27/16Mon 6/20/16Wed 7/27/16Tue 6/14/16Mon 7/18/1624 daysNo
184549830F-18 3.2.0DT. 4: Software Installation2 days27,205208Fri 6/24/16Mon 6/27/16Fri 6/24/16Mon 6/27/16Tue 6/14/16Thu 6/16/163 daysNo
184549839F-18 3.2.0DT. 4: Quick Look0 days207209,232Mon 6/20/16Mon 6/27/16Mon 6/20/16Mon 6/27/16Fri 6/17/16Thu 6/23/165 daysNo
184549525F-18 3.2.0DT. 4: Test MPE Build21 days90,208210,64Tue 6/28/16Wed 7/27/16Tue 6/28/16Wed 7/27/16Fri 6/24/16Mon 7/18/1616 daysNo
184549526F-18 3.2.0DT. 4: Complete Post DT Analysis/Update Metrics1 day20928Thu 7/28/16Thu 7/28/16Thu 7/28/16Thu 7/28/16Tue 7/19/16Tue 7/19/161 dayNo
184549909F-18 3.2.0DT. 523 daysTue 8/22/17Fri 9/22/17NANANANA0 days?No
184549908F-18 3.2.0DT. 5: Software Installation1 day156Tue 8/22/17Tue 8/22/17NANANANA0 days?No
184549911F-18 3.2.0DT.5: Quick Look3 days156157Tue 8/22/17Thu 8/24/17NANANANA0 days?No
184549910F-18 3.2.0DT.5: Test MPE Build20 days157SS215Fri 8/25/17Fri 9/22/17NANANANA0 days?No
184549912F-18 3.2.0Differences Scans7 days21482FFMon 9/25/17Tue 10/3/17NANANANA0 days?No
184549777F-18 3.2.0DT End of Test0 days28,9129,233Tue 8/2/16Tue 8/2/16Tue 8/2/16Tue 8/2/16Wed 7/20/16Wed 7/20/160 daysNo
184549884F-18 3.2.0OT MMI18 daysMon 6/20/16Thu 7/14/16Mon 6/20/16Thu 7/14/16Thu 6/16/16Thu 6/30/1611 daysNo
184549832F-18 3.2.0Quick Look MMI6 days160219Mon 6/20/16Mon 6/27/16Mon 6/20/16Mon 6/27/16Thu 6/16/16Wed 6/22/165 daysNo
184549799F-18 3.2.0Create MMI VDD2 days159,218220Mon 6/27/16Wed 6/29/16Mon 6/27/16Wed 6/29/16Thu 6/23/16Mon 6/27/163 daysNo
184549798F-18 3.2.0Distribute MMI to Developers4 days21930Mon 7/11/16Thu 7/14/16Mon 7/11/16Thu 7/14/16Tue 6/28/16Thu 6/30/163 daysNo
184549808F-18 3.2.0OT MVM21 daysThu 7/7/16Thu 8/4/16Thu 7/7/16Thu 8/4/16Mon 6/27/16Thu 7/7/168 daysNo
184549840F-18 3.2.0Quick Look MVM18 days163223Thu 7/7/16Mon 8/1/16Thu 7/7/16Mon 8/1/16Mon 6/27/16Fri 7/1/165 daysNo
184549811F-18 3.2.0Create MVM Report3 days22234Thu 7/14/16Thu 8/4/16Thu 7/14/16Thu 8/4/16Tue 7/5/16Thu 7/7/163 daysNo
184549883F-18 3.2.0MMI Deploy11 daysTue 9/5/17Tue 9/19/17NANAWed 4/26/17Wed 5/10/1711 daysNo
184549833F-18 3.2.0Quick Look MMI (post OT)5 days166226Tue 9/5/17Mon 9/11/17NANAWed 4/26/17Tue 5/2/175 daysNo
184549805F-18 3.2.0Create MMI VDD (post OT)3 days165,225227Tue 9/12/17Thu 9/14/17NANAWed 5/3/17Fri 5/5/173 daysNo
184549869F-18 3.2.0Distribute MMI to Developers (post OT)3 days22633Fri 9/15/17Tue 9/19/17NANAMon 5/8/17Wed 5/10/173 daysNo
184549853F-18 3.2.0MVM Deploy8 daysTue 9/5/17Thu 9/14/17NANAWed 4/26/17Fri 5/5/178 daysNo
184549852F-18 3.2.0Quick Look MVM5 days169230Tue 9/5/17Mon 9/11/17NANAWed 4/26/17Tue 5/2/175 daysNo
184549851F-18 3.2.0Create MVM Report3 days22933Tue 9/12/17Thu 9/14/17NANAWed 5/3/17Fri 5/5/173 daysNo
184549784F-18 3.2.0DT to OT Transition Report41 daysMon 7/11/16Tue 9/6/16Mon 7/11/16Tue 9/6/16Thu 7/21/16Thu 9/15/1640 daysNo
184549540F-18 3.2.0Develop DT to OT Transition Report38 days208234Mon 7/11/16Wed 8/31/16Mon 7/11/16Wed 8/31/16Thu 7/21/16Wed 8/17/1620 daysNo
184549812F-18 3.2.0Write and Consolidate DRs16 days216234Wed 8/3/16Wed 8/24/16Wed 8/3/16Wed 8/24/16Thu 7/21/16Wed 7/27/165 daysNo
184549813F-18 3.2.0Conduct ERB1 day233,232235Thu 9/1/16Thu 9/1/16Thu 9/1/16Thu 9/1/16Thu 8/18/16Wed 8/24/165 daysNo
184549814F-18 3.2.0Finalize DT to OT transition Report1 day234236,258Thu 9/1/16Mon 9/5/16Thu 9/1/16Mon 9/5/16Thu 8/25/16Wed 8/31/165 daysNo
184549787F-18 3.2.0Staff/Sign DT to OT Transition Report1 day23579Tue 9/6/16Tue 9/6/16Tue 9/6/16Tue 9/6/16Thu 9/1/16Thu 9/15/1610 daysNo
184549529F-18 3.2.0EDT42 daysTue 9/22/15Fri 11/20/15Tue 9/22/15Fri 11/20/15Tue 9/22/15Fri 11/20/1542 daysNo
184549816F-18 3.2.0Develop EDT Plan/scenarios1 day200239Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/151 dayNo
184549837F-18 3.2.0EDT Planning/Go-No-Go0 days238240Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/15Tue 9/22/150 daysNo
184549818F-18 3.2.0Submit EDT invitations1 day239241,242Wed 9/23/15Wed 9/23/15Wed 9/23/15Wed 9/23/15Wed 9/23/15Wed 9/23/151 dayNo
184549530F-18 3.2.0Configure Lab1 day22,240242Thu 9/24/15Thu 9/24/15Thu 9/24/15Thu 9/24/15Thu 9/24/15Thu 9/24/151 dayNo
184549531F-18 3.2.0Execute EDT1 day241,24023,245Fri 9/25/15Fri 9/25/15Fri 9/25/15Fri 9/25/15Fri 9/25/15Fri 9/25/151 dayNo
184549532F-18 3.2.0Complete Post EDT Analysis1 day23244Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/151 dayNo
184549533F-18 3.2.0Complete EDT Out-Brief1 day24390Fri 11/20/15Fri 11/20/15Fri 11/20/15Fri 11/20/15Fri 11/20/15Fri 11/20/151 dayNo
184549815F-18 3.2.0Reconfigure Lab Post UE1 day242285Mon 9/28/15Mon 9/28/15Mon 9/28/15Mon 9/28/15Mon 9/28/15Mon 9/28/151 dayNo
184549755F-18 3.2.0Update Metrics1 day2361Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/15Thu 11/19/151 dayNo
184549535F-18 3.2.0Operational Testing (OT)231 daysWed 10/12/16Fri 9/22/17Wed 10/12/16NAThu 11/3/16Wed 5/10/17120 daysNo
184549537F-18 3.2.0SVT: Conduct OT Testing162 days31,274,30,186,1032,165,275,276,168,279SS-30 days,156FS+36 daysWed 10/12/16Thu 6/15/17Wed 10/12/16NAThu 11/3/16Wed 4/12/17100 daysNo
184549538F-18 3.2.0SVT: H12 OT Data Reduction an Report Production64 days32,13SS250,258Fri 6/16/17Fri 9/15/17NANAThu 4/13/17Wed 4/26/1710 daysNo
184549820F-18 3.2.0OT Anomaly Analysis5 days24982Mon 9/18/17Fri 9/22/17NANAThu 4/27/17Wed 5/3/175 daysNo
184549495F-18 3.2.0Change Management678 daysWed 2/4/15Mon 11/6/17Wed 2/4/15NAWed 2/4/15Thu 10/27/16429 daysNo
184549497F-18 3.2.0ECP678 daysWed 2/4/15Mon 11/6/17Wed 2/4/15NAWed 2/4/15Thu 10/27/16429 daysNo
184549496F-18 3.2.0Preliminary ECP165 daysWed 2/4/15Mon 9/28/15Wed 2/4/15Mon 9/28/15Wed 2/4/15Mon 9/28/15165 daysNo
184549498F-18 3.2.0Develop Preliminary ECP1 day49,50,51,52,53,54,55,47255Wed 2/4/15Wed 2/4/15Wed 2/4/15Wed 2/4/15Wed 2/4/15Wed 2/4/151 dayNo
184549499F-18 3.2.0Conduct Pre-staffing Review and Updates on Preliminary ECP13 days25467FF,256Tue 2/10/15Fri 2/27/15Tue 2/10/15Fri 2/27/15Tue 2/10/15Fri 2/27/1513 daysNo
184549500F-18 3.2.0Staff for Recommendations, Concurrence, and CCB Approval on Preliminary ECP88 days25572FF,258Tue 5/26/15Mon 9/28/15Tue 5/26/15Mon 9/28/15Tue 5/26/15Mon 9/28/1588 daysNo
184549731F-18 3.2.0Final ECP35 daysMon 9/18/17Mon 11/6/17NANAThu 9/1/16Thu 10/27/1639 daysNo
184549732F-18 3.2.0Update based upon Preliminary ECP5 days256,249,235259Mon 9/18/17Fri 9/22/17NANAThu 9/1/16Thu 9/8/165 daysNo
184549733F-18 3.2.0Conduct Pre-staffing Review and Updates on Final ECP5 days258260Mon 9/25/17Fri 9/29/17NANAFri 9/9/16Wed 9/21/169 daysNo
184549734F-18 3.2.0Staff for Recommendations, Concurrence, and CCB Approval on Final ECP25 days25982Mon 10/2/17Mon 11/6/17NANAThu 9/22/16Thu 10/27/1625 daysNo
184549541F-18 3.2.0Training762 daysMon 11/17/14Mon 1/22/18Mon 11/17/14NAMon 11/17/14Fri 7/14/17642 daysNo
184549548F-18 3.2.0Training Package Development Plan3 daysMon 11/17/14Wed 11/19/14Mon 11/17/14Wed 11/19/14Mon 11/17/14Wed 11/19/143 daysNo
184549542F-18 3.2.0Identify Training Requirements1 day106264Mon 11/17/14Mon 11/17/14Mon 11/17/14Mon 11/17/14Mon 11/17/14Mon 11/17/141 dayNo
184549714F-18 3.2.0Update Training Plan1 day263265Tue 11/18/14Tue 11/18/14Tue 11/18/14Tue 11/18/14Tue 11/18/14Tue 11/18/141 dayNo
184549715F-18 3.2.0Publish Training Plan1 day264268Wed 11/19/14Wed 11/19/14Wed 11/19/14Wed 11/19/14Wed 11/19/14Wed 11/19/141 dayNo
184549549F-18 3.2.0User Documentation593 daysMon 8/3/15Mon 1/22/18Mon 8/3/15NAMon 8/3/15Fri 7/14/17473 daysNo
184549756F-18 3.2.0USD Development516 daysMon 8/3/15Wed 9/13/17Mon 8/3/15NAMon 8/3/15Wed 4/26/17418 daysNo
184549862F-18 3.2.0USD Development ~60%30 days137,265269Mon 8/3/15Mon 9/14/15Mon 8/3/15Mon 9/14/15Mon 8/3/15Mon 9/14/1530 daysNo
184549867F-18 3.2.0IPR 1 Prep5 days268270Tue 9/15/15Mon 9/21/15Tue 9/15/15Mon 9/21/15Tue 9/15/15Mon 9/21/155 daysNo
184549865F-18 3.2.0IPR 10 days269271Mon 9/21/15Mon 9/21/15Mon 9/21/15Mon 9/21/15Mon 9/21/15Mon 9/21/150 daysNo
184549864F-18 3.2.0USD Development ~90%12 days148,270272Mon 6/20/16Wed 7/6/16Mon 6/20/16Wed 7/6/16Tue 6/14/16Tue 7/26/1630 daysNo
184549868F-18 3.2.0IPR 2 Prep5 days271273Thu 7/7/16Wed 7/13/16Thu 7/7/16Wed 7/13/16Wed 7/27/16Tue 8/2/165 daysNo
184549866F-18 3.2.0IPR 29 days272274Thu 7/14/16Tue 7/26/16Thu 7/14/16Tue 7/26/16Tue 8/2/16Tue 8/2/160 daysNo
184549762F-18 3.2.0Fleet Verification12 days273248Tue 8/23/16Thu 9/8/16Tue 8/23/16Thu 9/8/16Wed 8/3/16Thu 8/11/167 daysNo
184549769F-18 3.2.0Update and Finalize USD10 days248,157277Wed 8/30/17Wed 9/13/17NANAThu 4/13/17Wed 4/26/1710 daysNo
184549758F-18 3.2.0Create Op Notes1 day248277Fri 6/16/17Fri 6/16/17NANAThu 4/13/17Thu 4/13/171 dayNo
184549727F-18 3.2.0Create USD Disk10 days275,276283,34FS+12 daysThu 9/14/17Wed 9/27/17NANAThu 4/27/17Wed 5/10/1710 daysNo
184549558F-18 3.2.0Conduct Training335 daysTue 8/23/16Mon 1/22/18Tue 8/23/16NAFri 8/12/16Fri 7/14/17222 daysNo
184549560F-18 3.2.0Conduct OT Training0 days248SS-30 days285Tue 8/23/16Thu 8/25/16Tue 8/23/16Thu 8/25/16Fri 8/12/16Thu 8/18/165 daysNo
184549562F-18 3.2.0Conduct Fleet Training5 days28436Tue 1/16/18Mon 1/22/18NANAMon 7/10/17Fri 7/14/175 daysNo
184549718F-18 3.2.0Deploy MPE68 daysWed 9/20/17Fri 1/12/18NANAThu 5/11/17Fri 7/7/1740 daysNo
184549720F-18 3.2.0MMI Delivered to LMCO3 days29,33283Wed 9/20/17Fri 9/22/17NANAThu 5/11/17Mon 5/15/173 daysNo
184549721F-18 3.2.0Develop Binders10 days282,277,35284Fri 12/8/17Fri 1/5/18NANAFri 6/16/17Thu 6/29/1710 daysNo
184549719F-18 3.2.0Ship Binders5 days283280Mon 1/8/18Fri 1/12/18NANAFri 6/30/17Fri 7/7/175 daysNo
184549663F-18 3.2.0MPE End0 days36,245,279Mon 1/22/18Mon 1/22/18NANAFri 7/14/17Fri 7/14/170 daysNo
184549789F-18 3.2.0critical DRR3000 days85Tue 11/21/17Mon 8/27/29NANAThu 6/1/17Tue 3/13/293000 daysNo
16777235F-18 3.3.0F-18 3.3.0803 daysWed 8/31/16Mon 9/30/19Wed 8/31/16NANANA0 days?No
16777234F-18 3.3.0UPC 10 daysTue 11/15/16Tue 11/15/16Tue 11/15/16Tue 11/15/16NANA0 days?Yes
16777233F-18 3.3.0UPC 20 daysMon 5/22/17Mon 5/22/17NANANANA0 days?Yes
16777232F-18 3.3.0UPC 30 daysTue 1/16/18Tue 1/16/18NANANANA0 days?Yes
16777231F-18 3.3.0IRR0 daysWed 8/31/16Wed 8/31/16Wed 8/31/16Wed 8/31/16NANA0 days?Yes
16777230F-18 3.3.0CRR0 daysMon 12/19/16Mon 12/19/16Mon 12/19/16Mon 12/19/16NANA0 days?Yes
16777229F-18 3.3.0OTRR0 daysTue 8/21/18Tue 8/21/18NANANANA0 days?Yes
16777224F-18 3.3.0DRR0 daysFri 9/13/19Fri 9/13/19NANANANA0 days?Yes
16777240F-18 3.3.0FR0 daysMon 9/30/19Mon 9/30/19NANANANA0 days?Yes
16777227F-18 3.3.0IT 145 daysWed 12/14/16Tue 2/14/17Wed 12/14/16Tue 2/14/17NANA0 days?Yes
16777226F-18 3.3.0IT 218 daysWed 5/31/17Fri 6/23/17NANANANA0 days?Yes
16777225F-18 3.3.0IT 317 daysThu 1/25/18Fri 2/16/18NANANANA0 days?Yes
16777238F-18 3.3.0WIPT 10 daysWed 9/28/16Wed 9/28/16Wed 9/28/16Wed 9/28/16NANA0 days?Yes
16777237F-18 3.3.0WIPT 20 daysThu 9/28/17Thu 9/28/17NANANANA0 days?Yes
16777236F-18 3.3.0WIPT 30 daysWed 5/9/18Wed 5/9/18NANANANA0 days?Yes
16777239F-18 3.3.0EDT4 daysTue 9/19/17Fri 9/22/17NANANANA0 days?Yes
16777242F-18 3.3.0MOC11 daysWed 5/30/18Wed 6/13/18NANANANA0 days?No
16777241F-18 3.3.0CSAA19 daysThu 5/3/18Tue 5/29/18NANANANA0 days?No
16777221EA6B 8.0.1EA6B 8.0.13393 daysThu 10/1/15Mon 3/5/29Thu 10/1/15NANANA0 days?No
188743968EA6B 8.0.1MPE Start0 days30,6,7,8,93,92Thu 10/1/15Thu 10/1/15Thu 10/1/15Thu 10/1/15Thu 10/1/15Thu 10/1/150 daysNo
188743933EA6B 8.0.1Platform Milestones (Level One)261 daysMon 11/2/15Thu 12/1/16Mon 11/2/15NAMon 11/2/15Thu 12/1/16261 daysNo
188743934EA6B 8.0.1Platform Requirements Received (External Task)0 daysMon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
188744093EA6B 8.0.1New/Modified Unique Planning Component Delivered from Developer(s) (External Task)0 daysFri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/160 daysNo
188744092EA6B 8.0.1New/Modified Unique Planning Component Delivered from Developer(s) (External Task)0 daysFri 1/8/16Fri 1/8/16Fri 1/8/16Fri 1/8/16Fri 1/8/16Fri 1/8/160 daysNo
188743935EA6B 8.0.1New/Modified Unique Planning Component Delivered from Developer(s) (External Task)0 days115Fri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/16Fri 3/18/160 daysYes
188744091EA6B 8.0.1New/Modified Unique Planning Component Delivered from Developer(s) (External Task)0 days1Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/160 daysNo
188744090EA6B 8.0.1New/Modified Unique Planning Component Delivered from Developer(s) (External Task)0 days119Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/160 daysYes
188743936EA6B 8.0.1New/Modified Common Components Delivered from Developer(s) (External Task)0 daysMon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
188743937EA6B 8.0.1New/Modified Framework Delivered from Developer(s) (External Task)0 daysMon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/150 daysNo
188743939EA6B 8.0.1Training (External Task)0 daysMon 11/2/15Mon 11/2/15NANAMon 11/2/15Mon 11/2/150 daysNo
188743942EA6B 8.0.1Milestones (Level Two)393 daysMon 11/2/15Wed 6/21/17Mon 11/2/15NAWed 11/4/15Thu 5/25/17372 daysNo
188743943EA6B 8.0.1IRR Approval (Milestone A)0 days47199Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/150 daysYes
188743944EA6B 8.0.1CRR Approval (Milestone B)0 days52199Wed 6/15/16Wed 6/15/16Wed 6/15/16Wed 6/15/16Thu 4/7/16Thu 4/7/160 daysYes
188743945EA6B 8.0.1External Deliveries, Iteration 1 Received0 days99,6199Tue 8/2/16Tue 8/2/16Tue 8/2/16Tue 8/2/16Fri 5/13/16Fri 5/13/160 daysNo
188743947EA6B 8.0.1MPE Disk Set 1 Delivered0 days105199Tue 8/30/16Tue 8/30/16Tue 8/30/16Tue 8/30/16Thu 6/23/16Thu 6/23/160 daysNo
188743948EA6B 8.0.1EDT 1 Completed0 days148199Thu 9/15/16Thu 9/15/16Thu 9/15/16Thu 9/15/16Tue 7/19/16Tue 7/19/160 daysYes
188743949EA6B 8.0.1DT Test MPE Build 1 Completed0 days199Mon 11/2/15Mon 11/2/15Mon 11/2/15Mon 11/2/15Fri 8/12/16Fri 8/12/160 daysNo
188743950EA6B 8.0.1External Deliveries, Iteration 2 Received0 days107,8199Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/16Thu 12/1/160 daysNo
188743952EA6B 8.0.1MPE Disk Set 2 Delivered0 days116199Mon 1/30/17Mon 1/30/17Mon 1/30/17Mon 1/30/17Thu 1/12/17Thu 1/12/170 daysNo
188743954EA6B 8.0.1DT Test MPE Build 2 Completed0 days155199Fri 3/17/17Fri 3/17/17NANAFri 2/17/17Fri 2/17/170 daysNo
188744056EA6B 8.0.1DT End of Test0 days156199Mon 3/20/17Mon 3/20/17NANAFri 2/17/17Fri 2/17/170 daysNo
188743958EA6B 8.0.1MMI Disk Completed0 days117199Tue 4/18/17Tue 4/18/17NANAWed 2/8/17Wed 2/8/170 daysNo
188743959EA6B 8.0.1Deployment Readiness Review (DRR) Approval (Milestone C)0 days58199Mon 5/22/17Mon 5/22/17NANAWed 4/26/17Wed 4/26/170 daysYes
188743960EA6B 8.0.1Fleet Release Shipped0 days197199Fri 6/9/17Fri 6/9/17NANAMon 5/15/17Mon 5/15/170 daysYes
188743961EA6B 8.0.1Training Completed0 days194199Wed 6/21/17Wed 6/21/17NANAThu 5/25/17Thu 5/25/170 daysNo
188743681EA6B 8.0.1Internal PMA-2813393 daysThu 10/1/15Mon 3/5/29Thu 10/1/15NAThu 10/1/15Thu 5/25/17396 daysNo
188743747EA6B 8.0.1Program Management396 daysThu 10/1/15Thu 5/25/17Thu 10/1/15NAThu 10/1/15Mon 5/1/17378 daysNo
188743751EA6B 8.0.1MPE Scope Definition10 daysThu 10/1/15Thu 10/15/15Thu 10/1/15Thu 10/15/15Thu 10/1/15Thu 10/15/1510 daysNo
188743752EA6B 8.0.1Define Capability5 days131,34,120Thu 10/1/15Wed 10/7/15Thu 10/1/15Wed 10/7/15Thu 10/1/15Wed 10/7/155 daysNo
188743758EA6B 8.0.1Define Reccommended Versioning Nomenclature5 days3044FFThu 10/8/15Thu 10/15/15Thu 10/8/15Thu 10/15/15Thu 10/8/15Thu 10/15/155 daysNo
188744003EA6B 8.0.1MPE Development Plan30 daysThu 10/1/15Fri 11/13/15Thu 10/1/15Fri 11/13/15Thu 10/1/15Fri 11/13/1530 daysNo
188743759EA6B 8.0.1Draft MPE Development Plan19 daysThu 10/1/15Wed 10/28/15Thu 10/1/15Wed 10/28/15Thu 10/1/15Wed 10/28/1519 daysNo
188743699EA6B 8.0.1MPE Risk Assesment7 days3035Thu 10/1/15Mon 10/12/15Thu 10/1/15Mon 10/12/15Thu 10/1/15Mon 10/12/157 daysNo
188743994EA6B 8.0.1Draft Scope7 days3437,38,39,44,36Thu 10/1/15Wed 10/21/15Thu 10/1/15Wed 10/21/15Thu 10/1/15Wed 10/21/157 daysNo
188743757EA6B 8.0.1Identify Hardware Requirements5 days3544FFWed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/155 daysNo
188743995EA6B 8.0.1Draft Schedule5 days3544FFWed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/155 daysNo
188743996EA6B 8.0.1Draft Budget5 days3544FFWed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/155 daysNo
188743997EA6B 8.0.1Draft Stakeholders5 days3544FFWed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/15Wed 10/21/15Wed 10/28/155 daysNo
188743998EA6B 8.0.1Finalize MPE Development Plan11 daysThu 10/29/15Fri 11/13/15Thu 10/29/15Fri 11/13/15Thu 10/29/15Fri 11/13/1511 daysNo
188743761EA6B 8.0.1Update for Build Content and Test Strategies3 days4742,126Thu 10/29/15Mon 11/9/15Thu 10/29/15Mon 11/9/15Thu 10/29/15Mon 11/9/153 daysNo
188743711EA6B 8.0.1Finalize MPE Development Plan3 days4149FFTue 11/10/15Fri 11/13/15Tue 11/10/15Fri 11/13/15Tue 11/10/15Fri 11/13/153 daysNo
188743762EA6B 8.0.1IRR Brief7 daysMon 10/26/15Wed 11/4/15Mon 10/26/15Wed 11/4/15Mon 10/26/15Wed 11/4/157 daysNo
188743763EA6B 8.0.1Draft IRR Brief0 days31FF,35,37FF,38FF,39FF,36FF45Mon 10/26/15Mon 10/26/15Mon 10/26/15Mon 10/26/15Mon 10/26/15Mon 11/2/155 daysNo
188743764EA6B 8.0.1Provide Read Aheads0 days4446Mon 10/26/15Mon 10/26/15Mon 10/26/15Mon 10/26/15Mon 10/26/15Mon 10/26/150 daysNo
188743765EA6B 8.0.1Conduct IRR0 days4547Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/15Tue 11/3/150 daysNo
188743766EA6B 8.0.1IRR Approval (Milestone A)1 day4613,41,121Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/15Wed 11/4/151 dayNo
188743780EA6B 8.0.1CRR Brief4 daysFri 6/10/16Wed 6/15/16Fri 6/10/16Wed 6/15/16Wed 3/30/16Thu 4/7/167 daysNo
188743781EA6B 8.0.1Draft CRR Brief3 days123FF,130FF,66,42FF50,170Fri 6/10/16Tue 6/14/16Fri 6/10/16Tue 6/14/16Wed 3/30/16Tue 4/5/165 daysNo
188743782EA6B 8.0.1Provide Read Aheads1 day4951Wed 6/15/16Wed 6/15/16Wed 6/15/16Wed 6/15/16Wed 4/6/16Wed 4/6/161 dayNo
188743783EA6B 8.0.1Conduct CRR0 days5052Wed 6/15/16Wed 6/15/16Wed 6/15/16Wed 6/15/16Thu 4/7/16Thu 4/7/161 dayNo
188743784EA6B 8.0.1CRR Approval (Milestone B)0 days5186,87,88,89,91,90,14,83Wed 6/15/16Wed 6/15/16Wed 6/15/16Wed 6/15/16Thu 4/7/16Thu 4/7/160 daysNo
188743793EA6B 8.0.1DRR Brief79 daysTue 1/31/17Mon 5/22/17Tue 1/31/17NAMon 3/27/17Wed 4/26/1723 daysNo
188744116EA6B 8.0.1SVT:Collect UPC Certification Letters18 days11655FFTue 1/31/17Fri 2/24/17Tue 1/31/17Fri 2/24/17Mon 3/27/17Fri 4/14/1715 daysNo
188743794EA6B 8.0.1Draft DRR Brief25 days166FF,172FF,141FF,54FF,83,192FF56Fri 4/7/17Thu 5/11/17Fri 4/7/17NATue 4/18/17Mon 4/24/175 daysNo
188743795EA6B 8.0.1Provide Read Aheads1 day5557Fri 5/12/17Fri 5/12/17NANATue 4/25/17Tue 4/25/171 dayNo
188743796EA6B 8.0.1Conduct DRR1 day56,162FF58Mon 5/22/17Mon 5/22/17NANAWed 4/26/17Wed 4/26/171 dayNo
188743797EA6B 8.0.1DRR Approval (Milestone C)0 days5724,60FF,200Mon 5/22/17Mon 5/22/17NANAWed 4/26/17Wed 4/26/170 daysNo
188743790EA6B 8.0.1Fleet Release Message8 daysTue 5/16/17Thu 5/25/17NANAThu 4/20/17Mon 5/1/178 daysNo
188743791EA6B 8.0.1Draft Fleet Release Message5 days58FF61Tue 5/16/17Mon 5/22/17NANAThu 4/20/17Wed 4/26/175 daysNo