Text version
_TWSM Copy of Segment UID
_TWSM
OBS
Name % Complete
Duration Start Finish
4 TMPC 5.0.2 94% 1169 daysMon 5/20/13 Fri 3/23/18
2063 5.0.2 Events/Major Milestones 99% 908 d Tue 10/8/13 Fri 7/14/17
2070 Prog Mgmt
5.0.2 FOC complete 0% 0 d Fri 7/14/17 Fri 7/14/17
2071 5.0.2 Requirements Definition 99% 851 d Mon 5/20/13
Wed 11/16/16
2458 5.0.2 Statement of Functionality (SOF) (3900/167)
89% 892 d Tue 9/24/13 Tue 6/6/17
7148 5.0.2 SOF DT Assist Updates Received 0% 0 d Mon 4/24/17 Mon 4/24/17
3125 Engineering 5.0.2 Final SOF Resolve comments from routing (3900/167) & Incorporate DT Results
92% 26 d Mon 3/20/17 Mon 4/24/17
5131 Formal Qualification Test 99% 451 d Mon 8/31/15
Fri 7/14/17
1436 5.0.2 Testing & FIB 99% 644 d Wed 9/17/14
Fri 5/19/17
2428 DT Assist 99% 128 d Tue 10/4/16 Fri 4/21/17
2435 T&E Test Reporting of DT Assist 93% 15 d Mon 4/3/17 Fri 4/21/17
2436 Fleet Release Activities 73% 110 d Thu 12/1/16 Fri 5/19/17
6892 5.0.2 Cybersecurity Accreditation 99% 471 d Tue 5/12/15 Mon 4/24/17
7089 5.0.2 IATT Recertification 99% 257 d Fri 4/1/16 Mon 4/24/17
7/14
4/24
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Project: TMPCShell Date: Wed 5/3/17
DRAFT
OBS
Name % Complete
Duration Start Finish
7134 TMPOC 5.0.2 IATT NAO Expires 0% 0 d Mon 4/24/17 Mon 4/24/17
7150 5.0.2 Logistics 23% 297 d Tue 1/3/17 Fri 3/23/18
7176 TMPC 5.0.2 IWTC/CMSA LANT
Curriculum Pilot Course Support Activities
0% 48 d Tue 1/16/18 Fri 3/23/18
7178 Conduct TMPC 5.0.2 Mission Planner Course
0% 48 d Tue 1/16/18 Fri 3/23/18
7177 Conduct TMPC 5.0.2 TLAM Geopositioning Analyst Course
0% 48 d Tue 1/16/18 Fri 3/23/18
7171 TMPC 5.0.2 MDS Users Handbook & QRG Activities
8% 167 d Mon 4/3/17 Thu 11/30/17
7175 Completion of Initial Updates to 5.0.2 MDS Users Handbook & QRG
11% 127 d Mon 4/3/17 Fri 9/29/17
7174 Receive Feedback from Users for 5.0.2 MDS Users Handbook & QRG Updates
0% 19 d Mon 10/2/17 Fri 10/27/17
7173 Completion of Final Updates to 5.0.2 MDS Users Handbook & QRG Updates
0% 19 d Mon 10/30/17
Tue 11/28/17
7172 Delivery of 5.0.2 MDS Users Handbook & QRG
0% 2 d Wed 11/29/17
Thu 11/30/17
7167 TMPC 5.0.2 CSCS/CMSA LANT
Curriculum Update Activities
14% 146 d Mon 4/3/17 Fri 10/27/17
4/24 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Project: TMPCShell
OBS
Name % Complete
Duration Start Finish
7170 Update TMPC 5.0.2 TLAM Geopositioning Analyst Course Materials (CMSA LANT)
11% 127 d Mon 4/3/17 Fri 9/29/17
7169 Update TMPC 5.0.2 Mission Planner Course Materials (CMSA LANT)
10% 146 d Mon 4/3/17 Fri 10/27/17
7168 Development of TNT 5.0.2 Functional Task List
70% 20 d Mon 4/3/17 Fri 4/28/17
7159 5.0.2 ULSS 46% 166 d Tue 1/3/17 Mon 8/28/17
7160 5.02 ULSS Final Copy Posted & Delivered to Install Team for FRCB Process
0% 0 d Mon 8/28/17 Mon 8/28/17
7161 5.02 ULSS Final Delivery to PMA-281 0% 1 d Mon 8/28/17 Mon 8/28/17
7162 5.02 ULSS Initial Draft Received at
PMA-281
0% 1 d Thu 6/1/17 Thu 6/1/17
7163 5.02 ULSS PMA-281 comments Incorporated
0% 39 d Mon 7/3/17 Fri 8/25/17
7164 5.02 ULSS Initial Draft Comments from PMA-281 back to Leidos
0% 0 d Fri 6/30/17 Fri 6/30/17
8/28
6/30
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7165 5.02 ULSS Initial Draft PMA-281 Review
0% 21 d Fri 6/2/17 Fri 6/30/17
7166 5.0.2 ULSS Initial Draft Development & Developer Input
73% 104 d Tue 1/3/17 Wed 5/31/17
7152 5.0.2 LCSP 46% 166 d Tue 1/3/17 Mon 8/28/17
7158 5.02 LCSP Final Copy Posted & Delivered to Install Team for FRCB Process
0% 0 d Mon 8/28/17 Mon 8/28/17
7157 5.02 LCSP Final Delivery to PMA-281 0% 1 d Mon 8/28/17 Mon 8/28/17
7154 5.02 LCSP Initial Draft Received at
PMA-281
0% 1 d Thu 6/1/17 Thu 6/1/17
7156 5.02 LCSP PMA-281 comments Incorporated
0% 42 d Wed 6/28/17 Fri 8/25/17
7155 5.02 LCSP Initial Draft Comments from PMA-281 back to Leidos
0% 0 d Tue 6/27/17 Tue 6/27/17
7153 5.02 LCSP Initial Draft PMA-281 Review
0% 18 d Fri 6/2/17 Tue 6/27/17
8/28
6/27
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7151 5.0.2 LCSP Initial Draft Development & Developer Input
73% 104 d Tue 1/3/17 Wed 5/31/17
#ERROR TMPC 6 0 Schedule 67% 2118 daysMon 4/8/13 Tue 12/14/21
1062 TMPC
6.0
TMPC 6.0 67% 2118d Mon 4/8/13 Tue 12/14/21
7944 TMPC
6.0
TMPC 6.0 User Events 54% 176d Mon 9/26/16
Fri 6/16/17
8498 TMPC
6.0
TMS User Event 9% 44d Mon 4/17/17
Fri 6/16/17
8499 TMPC
6.0
TMS User Event 0% 3d Tue 5/23/17 Thu 5/25/17
8523 TMPC
6.0
TMS User Event Preps (Vencore) 15% 26d Mon 4/17/17 Mon 5/22/17
8501 TMPC
6.0
TMS User Event Report 0% 15d Fri 5/26/17 Fri 6/16/17
7945 TMPC
6.0
MDS 58% 159d Mon 9/26/16
Tue 5/23/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7953 TMPC
6.0
User Event Build Ready (SVT) (MDS User Event)
0% 0d Mon 4/10/17 Mon 4/10/17
7955 TMPC
6.0
User Event Scenario Package Completed (MDS User Event)
93% 15d Mon 4/3/17 Fri 4/21/17
7956 TMPC
6.0
MDS User Event 0% 3d Mon 4/24/17 Wed 4/26/17
7957 TMPC
6.0
MDS User Event Report Complete 0% 14d Thu 4/27/17 Tue 5/16/17
7958 TMPC
6.0
MDS User Event Actions Distributed/Added as Necessary
0% 5d Wed 5/17/17 Tue 5/23/17
7136 TMPC
6.0
TWS Touch Points 99% 1284d Mon 9/14/15
Fri 12/18/20
7139 TMPC
6.0
Deliveries/Dependencies From Other Segments to TMPC
99% 1068d Mon 4/11/16
Thu 8/20/20
8122 OUT: Formal Build Integration (D) Complete
0% 0d Thu 11/30/17
Thu 11/30/17
8535 OUT: NSP Ready to Support TMPC/TTWCS Integration Event C1 Event
0% 1d? Tue 10/1/13 Tue 10/1/13
4/10
4/26
11/3011/30
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8519 TMPC
6.0
IN: NSP Ready to Participate in C1 0% 0d Mon 5/15/17 Mon 5/15/17
7917 TMPC
6.0
IN: Formal Integration Build Event D Complete (Milestone For Visibility)
0% 0d Thu 11/30/17
Thu 11/30/17
8175 OUT: OT Report - A2AD Comms to
TMPC
0% 0d Thu 8/20/20 Thu 8/20/20
7137 TMPC
6.0
IN: TWS Modernization Operational Test Report Completed - from Engineering
0% 0d Thu 8/20/20 Thu 8/20/20
8119 OUT: TTWCS Ready for Second Modernized Interface Test (C1)
0% 0d Thu 3/2/17 Thu 3/2/17
8531 TMPC
6.0
IN: Second Modernized Interface Test (C1) NSP Test Point Build from
TTWCS
0% 0d Wed 5/24/17 Wed 5/24/17
8562 TMPC
6.0
IN: Projected Start Date of Raytheon Final GNC Assessments
0% 0d Mon 11/13/17
Mon 11/13/17
7204 TMPC
6.0
IN: Second Modernized Interface Test (C1) B2 Fixes from TTWCS
0% 0d Thu 4/27/17 Thu 4/27/17
5/15
11/30
8/208/20
8/20
3/23/2
5/24
11/13
4/27
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8120 OUT: Fully Functional Integration Test Complete (C2)
0% 0d Thu 7/20/17 Thu 7/20/17
7526 TMPC
6.0
IN: Fully Functional Integration Test Complete (C2) from TTWCS
0% 0d Thu 7/20/17 Thu 7/20/17
8121 OUT: Fully Functional Integration Test Anomaly Resolution Complete (C2)
0% 0d Thu 8/17/17 Thu 8/17/17
7223 TMPC
6.0
IN: Fully Functional Integration Test Anomaly Resolution Complete (C2) from TTWCS
0% 0d Thu 8/17/17 Thu 8/17/17
7140 TMPC
6.0
Deliveries/Dependencies To Other Segments from TMPC
99% 1284d Mon 9/14/15
Fri 12/18/20
8278 TMPC
6.0
OUT: Tech Concurrence 3900/114E
TSN IRS ICN-E6, DDG-1000
Transition to TMPC 6.0
0% 0d Tue 5/16/17 Tue 5/16/17
8143 TMPC
6.0
OUT: TMPC 6.0 Technical Concurrence 3900/146C TTWCS IRS Rev C Final
0% 0d Wed 5/24/17 Wed 5/24/17
8159 IN: 3900/146C Rev C Tech Concurrence (TMPC UID: 8143)
0% 0d Wed 5/24/17 Wed 5/24/17
7/207/20
7/20
8/178/17
8/17
5/16
5/24
5/245/24
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8142 TMPC
6.0
OUT: TMPC 6.0 Program/Signature Approval 3900/146C TTWCS IRS Rev C Final
0% 0d Fri 6/9/17 Fri 6/9/17
8161 IN: 3900/146B Rev C Final Sig CCB
(TMPC UID: 8142)
0% 0d Fri 6/9/17 Fri 6/9/17
8170 TMPC
6.0
OUT: TMPC 6.0 Product Acceptance Test (PAT) Started
0% 0d Fri 1/26/18 Fri 1/26/18
8172 IN: TMPC 6.0 Product Acceptance Testing (PAT) Started
0% 0d Fri 1/26/18 Fri 1/26/18
8237 TMPC
6.0
OUT: TMPC 6.0 Ready to Deliver IMMMs to Support Raytheon Parking Lot Test
0% 0d Tue 12/5/17 Tue 12/5/17
7145 TMPC
6.0
OUT: TMPC 6.0 Product Acceptance Test (PAT) Completed
0% 0d Fri 5/4/18 Fri 5/4/18
7928 IN: TMPC 6.0 Product Acceptance Testing (PAT) Completed
0% 0d Fri 5/4/18 Fri 5/4/18
7181 IN: TMPC 6 0 PAT Completed 0% 0d Tue 2/27/18 Tue 2/27/18
6/9
6/96/9
1/26
1/261/26
12/5
5/4
5/45/4
2/272/27
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8558 TMPC
6.0
OUT: TMPC 6.0 Initial Build Delivered to WPC
0% 0d Wed 10/4/17 Wed 10/4/17
8559 IN: TMPC Initial Build Delivered to
WPC
0% 1d? Thu 10/5/17 Thu 10/5/17
8557 TMPC
6.0
OUT: TMPC 6.0 Fix-it Build #1 Delivered to WPC
0% 0d Fri 5/25/18 Fri 5/25/18
8560 IN: TMPC Fix It Build 1 Delivered to
WPC
0% 1d? Tue 5/29/18 Tue 5/29/18
8556 TMPC
6.0
OUT: TMPC 6.0 Fix-it Build #2 Delivered to WPC
0% 0d Wed 9/5/18 Wed 9/5/18
8561 IN: TMPC Fix It Build 2 Delivered to
WPC
0% 1d? Thu 9/6/18 Thu 9/6/18
7144 TMPC
6.0
OUT: TMPC 6.0 Fix-it Build (FIB #1) Completed
0% 0d Tue 8/14/18 Tue 8/14/18
8176 IN: TMPC Fix It Build 1 PAT Complete
0% 0d Tue 8/14/18 Tue 8/14/18
7188 IN: TMPC 6 0 FIB 1 Completed 0% 0d Tue 8/14/18 Tue 8/14/18
10/4
5/25
9/5
8/14
8/148/14
8/148/14
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7141 TMPC
6.0
OUT: TMPC 6.0 Fix-it Build (FIB #2) Completed
0% 0d Thu 12/13/18
Thu 12/13/18
8075 IN: TMPC 6 0 FIB 2 Completed 0% 0d Thu 12/13/18
Thu 12/13/18
7197 TMPC
6.0
OUT: TMPC 6.0 Authorization to Operate (ATO) Accreditation Received
0% 0d Wed 11/21/18
Wed 11/21/18
7501 TMPC
6.0
OUT: TMPC 6.0 NAV Integration Mission 3 - FQT Final to AUR (Block
IV)
0% 0d Thu 8/10/17 Thu 8/10/17
8074 IN: TMPC 6.0 NAV Integration Mission 3 - FQT Final to AUR (Block
IV)
0% 0d Thu 8/10/17 Thu 8/10/17
7931 IN: TMPC 6.0 NAV Integration Mission 3 - FQT Final to AUR (Block
IV)
0% 0d Thu 8/10/17 Thu 8/10/17
8532 TMPC
6.0
OUT: Second Modernized Interface Test Complete (C1) Virtual
0% 0d Mon 5/8/17 Mon 5/8/17
7216 TMPC
6.0
OUT: Second Modernized Interface Test Complete (C1) NSP Test Points
0% 0d Wed 6/7/17 Wed 6/7/17
7985 IN: Second Modernized Interface Test Complete (C1)
0% 0d Wed 6/7/17 Wed 6/7/17
12/13
12/1312/13
11/21
8/10
8/108/10
8/108/10
5/8
6/7
6/76/7
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7217 TMPC
6.0
OUT: Second Modernized Interface Test Anomaly Resolution Complete (C1)
0% 0d Thu 7/6/17 Thu 7/6/17
7986 IN: Second Modernized Interface Test Anomaly Resolution Complete (C1)
0% 0d Thu 7/6/17 Thu 7/6/17
7205 TMPC
6.0
OUT: TMPC Code for Fully Functional Integration Test (C2)
0% 0d Fri 5/5/17 Fri 5/5/17
7987 IN: TMPC Code for Fully Functional Integration Test (C2)
0% 0d Fri 5/19/17 Fri 5/19/17
7201 TMPC
6.0
OUT: Formal Build Integration (D) 0% 0d Mon 8/28/17 Mon 8/28/17
8280 TMPC
6.0
OUT: TMPC 6.0 IOC 0% 0d Fri 12/18/20 Fri 12/18/20
8283 IN: TMPC 6.0 IOC 0% 0d Mon 4/12/21 Mon 4/12/21
7222 IN: Formal Build Integration Support from TMPC 6.0 (D)
0% 0d Mon 8/28/17 Mon 8/28/17
7198 IN: TMPC 6.0 Accreditations Received
0% 0d Wed 11/21/18
Wed 11/21/18
7/6
7/67/6
5/5
5/195/19
8/28
12/18
4/124/12
8/288/28
11/2111/21
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7196 IN: TMPC Fix It Build 2 PAT Complete
0% 0d Thu 12/13/18
Thu 12/13/18
6560 TMPC
6.0
6.0 System Engineering (Requirements) 94% 987d Fri 6/28/13 Thu 7/20/17
8203 TMPC
6.0
DDG 1000 & Post Phase III SCNs & ICNs
77% 324d Thu 2/11/16 Fri 6/2/17
8465 TMPC
6.0
DDG 1000 & Post Phase III SCNs 79% 319d Thu 2/11/16 Thu 5/25/17
7290 TMPC
6.0
3900/133E TMPC 6.0 Phase II/III SEC SS SCN-D5/Rev E
99% 296d Thu 2/11/16 Mon 4/24/17
7940 TMPC
6.0
3900/133E 6.0 Phase II/III SEC SS Rev E (update) - CCB/System Release
0% 1d Mon 4/24/17 Mon 4/24/17
8343 TMPC
6.0
3900/13F SCN-F7 MDS SSS DDG
79% 62d Fri 2/10/17 Tue 5/9/17
8346 TMPC
6.0
3900/13F SCN-F7
Create/Update Signature Brief/QA
96% 23d Wed 3/22/17 Fri 4/21/17
8347 TMPC
6.0
3900/13F SCN-F7 - Delivery to
PMA281
0% 1d Mon 4/24/17 Mon 4/24/17
12/1312/13 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8348 TMPC
6.0
3900/13F SCN-F7 - Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8349 TMPC
6.0
3900/13F SCN-F7 - Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8350 TMPC
6.0
3900/13F SCN-F7 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8311 TMPC
6.0
3900/2K TMPC SS SCN-K8 DDG
77% 62d Fri 2/10/17 Tue 5/9/17
8316 TMPC
6.0
3900/2K TMPC SS SCN-K8 -
Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8317 TMPC
6.0
3900/2K TMPC SS SCN-K8 -
Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8318 TMPC
6.0
3900/2K TMPC SS SCN-K8 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8351 TMPC
6.0
3900/110H SCN-H6 TPS SSS DDG
74% 60d Tue 2/14/17 Tue 5/9/17
8539 TMPC
6.0
3900/110H SCN-H6 - QA of Additional Updates & Re-Deliver to PMA 281
50% 2d Thu 4/20/17 Fri 4/21/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8356 TMPC
6.0
3900/110H SCN-H6 - Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8357 TMPC
6.0
3900/110H SCN-H6 - Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8358 TMPC
6.0
3900/110H SCN-H6 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8359 TMPC
6.0
3900/127A SCN-A5 TCOMMS
SSS DDG 1000
69% 57d Fri 2/17/17 Tue 5/9/17
8363 TMPC
6.0
3900/127A SCN-A5 - Delivery to PMA281
0% 1d Fri 4/21/17 Fri 4/21/17
8364 TMPC
6.0
3900/127A SCN-A5 - Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8365 TMPC
6.0
3900/127A SCN-A5 - Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8366 TMPC
6.0
3900/127A SCN-A5 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8367 TMPC
6.0
3900/186A SCN-A7 TNT SSS
DDG 1000
72% 56d Mon 2/20/17
Tue 5/9/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8372 TMPC
6.0
3900/186A SCN-A7 - Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8373 TMPC
6.0
3900/186A SCN-A7 - Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8374 TMPC
6.0
3900/186A SCN-A7 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8335 TMPC
6.0
3900/205 SCN-6 HW SS
DDG-1000
67% 56d Mon 2/20/17
Tue 5/9/17
8340 TMPC
6.0
3900/205 SCN-6 - Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8341 TMPC
6.0
3900/205 SCN-6 - Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8342 TMPC
6.0
3900/205 SCN-6 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8383 TMPC
6.0
3900/208 SCN-7 TEI SSS 75% 55d Wed 2/22/17
Tue 5/9/17
8541 TMPC
6.0
3900/208 SCN-7 TEI SSS - QA
of Additional Updates
80% 5d Mon 4/17/17 Fri 4/21/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8387 TMPC
6.0
3900/208 SCN-7 TEI SSS -
Delivery to PMA281
0% 1d Mon 4/24/17 Mon 4/24/17
8388 TMPC
6.0
3900/208 SCN-7 TEI SSS -
Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8389 TMPC
6.0
3900/208 SCN-7 TEI SSS -
Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8390 TMPC
6.0
3900/208 SCN-7 TEI SSS -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8375 TMPC
6.0
3900/206 SCN-3 PL SSS
DDG-1000
69% 52d Mon 2/27/17
Tue 5/9/17
8380 TMPC
6.0
3900/206 SCN-3 - Conduct Tabletop Review
0% 5d Tue 4/25/17 Mon 5/1/17
8381 TMPC
6.0
3900/206 SCN-3 - Route for Signatures
0% 5d Tue 5/2/17 Mon 5/8/17
8382 TMPC
6.0
3900/206 SCN-3 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8327 TMPC
6.0
3900/168 Rev H Computing Environments DDG 1000
60% 65d Fri 2/24/17 Thu 5/25/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8332 TMPC
6.0
3900/168 Rev H - PMA 281 Acceptance
17% 30d Fri 4/14/17 Thu 5/25/17
8319 TMPC
6.0
3900/133E SEC SS SCN-E1 DDG
73% 57d Mon 2/20/17
Wed 5/10/17
8323 TMPC
6.0
3900/133E SEC SS SCN-E1 -
Delivery to PMA281
0% 1d Tue 4/25/17 Tue 4/25/17
8324 TMPC
6.0
3900/133E SEC SS SCN-E1 -
Conduct Tabletop Review
0% 5d Wed 4/26/17 Tue 5/2/17
8325 TMPC
6.0
3900/133E SEC SS SCN-E1 -
Route for Signatures
0% 5d Wed 5/3/17 Tue 5/9/17
8326 TMPC
6.0
3900/133E SEC SS SCN-E1 -
CCB/Signature Approval
0% 1d Wed 5/10/17 Wed 5/10/17
8466 TMPC
6.0
DDG 1000 & Post Phase III ICNs 72% 88d Mon 1/30/17
Fri 6/2/17
8204 TMPC
6.0
3900/114E TSN IRS ICN-E6,
DDG-1000 Transition to TMPC 6.0
32% 49d Mon 3/27/17
Fri 6/2/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8209 TMPC
6.0
3900/114E TSN IRS ICN-E6-
SVT(Develop & Distribute to Interface Community)
95% 20d Mon 3/27/17 Fri 4/21/17
8210 TMPC
6.0
3900/114E TSN IRC ICN-E6
Technical Concurrence Review and Received
0% 10d Mon 4/24/17 Fri 5/5/17
8211 TMPC
6.0
3900/114E TSN IRC ICN-E6
Create/Update Signature Brief & Get SEI Approval
0% 17d Mon 4/24/17 Tue 5/16/17
8212 TMPC
6.0
3900/114E TSN IRS ICN-E6 -
Delivery to PMA281
0% 1d Wed 5/17/17 Wed 5/17/17
8213 TMPC
6.0
3900/114E TSN IRS ICN-E6 -
Conduct Tabletop Review
0% 5d Thu 5/18/17 Wed 5/24/17
8214 TMPC
6.0
3900/114E TSN IRS ICN-E6 -
Route for Signatures
0% 5d Thu 5/25/17 Thu 6/1/17
8215 TMPC
6.0
3900/114E TSN IRS ICN-E6 -
CCB/Signature Approval
0% 1d Fri 6/2/17 Fri 6/2/17
8261 TMPC
6.0
3900/183C TED IRS ICN-C4,
DDG-1000 Transistion to TMPC 6.0
81% 46d Tue 3/7/17 Tue 5/9/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8266 TMPC
6.0
3900/183C TED IRS ICN-C4 -
Conduct Tabletop Review
0% 5d Wed 4/26/17 Tue 5/2/17
8267 TMPC
6.0
3900/183C TED IRS ICN-C4 -
Route for Signatures
0% 4d Wed 5/3/17 Mon 5/8/17
8268 TMPC
6.0
3900/183C TED IRS ICN-C4 -
CCB/Signature Approval
0% 1d Tue 5/9/17 Tue 5/9/17
8244 TMPC
6.0
3900/146B TTWCS IRS ICN-B11
DDG-1000 Missile Cell Location Backward Compatability
87% 65d Mon 1/30/17
Mon 5/1/17
8547 TMPC
6.0
3900/146B ICN-B11A Review of Adjudication & Signature Recommendations
0% 2d Fri 4/21/17 Mon 4/24/17
8250 TMPC
6.0
3900/146B ICN-B11A Route for Signatures
0% 4d Tue 4/25/17 Fri 4/28/17
8251 TMPC
6.0
3900/146B ICN-B11A
CCB/Signature Approval
0% 1d Mon 5/1/17 Mon 5/1/17
8218 TMPC
6.0
3900/146B TTWCS IRS ICN-B14,
Expand Frequency Lookup Range
81% 68d Mon 1/30/17
Thu 5/4/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8545 TMPC
6.0
3900/146B ICN-B14 Review of Adjudication and Signature Recommendations
0% 5d Fri 4/21/17 Thu 4/27/17
8221 TMPC
6.0
3900/146B ICN-B14 Route for Signatures
0% 4d Fri 4/28/17 Wed 5/3/17
8220 TMPC
6.0
3900/146B ICN-B14
CCB/Signature Approval
0% 1d Thu 5/4/17 Thu 5/4/17
8252 TMPC
6.0
3900/114E TSN IRS ICN-E5,
Expand Frequency Lookup Range
84% 63d Wed 2/1/17 Mon 5/1/17
8543 TMPC
6.0
3900/114E TSN IRS ICN-E5 -
Review of Adjudication and Signature Recommendations
0% 2d Fri 4/21/17 Mon 4/24/17
8258 TMPC
6.0
3900/114E TSN IRS ICN-E5 -
Route for Signatures
0% 4d Tue 4/25/17 Fri 4/28/17
8259 TMPC
6.0
3900/114E TSN IRS ICN-E5 -
CCB/Signature Approval
0% 1d Mon 5/1/17 Mon 5/1/17
8467 TMPC
6.0
Specification and Interface Document Revisions
0% 57d Mon 5/1/17 Thu 7/20/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8428 TMPC
6.0
3900/13G MDS SSS Rev. G 0% 47d Wed 5/10/17
Mon 7/17/17
8429 TMPC
6.0
3900/13G MDS SSS Rev. G (SVT - Export, Initial Review, Distribute)
0% 12d Wed 5/10/17 Thu 5/25/17
8430 TMPC
6.0
3900/13G MDS SSS Rev. G Review, Comments, Adjudication
0% 12d Fri 5/26/17 Tue 6/13/17
8431 TMPC
6.0
3900/13G MDS SSS Rev. G Create CCB Brief/QA
0% 2d Wed 6/14/17 Thu 6/15/17
8432 TMPC
6.0
3900/13G MDS SSS Rev. G - Delivery to PMA281
0% 1d Fri 6/16/17 Fri 6/16/17
8433 TMPC
6.0
3900/13G MDS SSS Rev. G - Route for Signatures
0% 19d Mon 6/19/17 Fri 7/14/17
8434 TMPC
6.0
3900/13G MDS SSS Rev. G - CCB/Signature Approval
0% 1d Mon 7/17/17 Mon 7/17/17
8391 TMPC
6.0
3900/2L TMPC SS Rev. L 0% 50d Wed 5/10/17
Thu 7/20/17
8392 TMPC
6.0
3900/2L TMPC SS Rev. L (SVT - Export, Initial Review, Distribute)
0% 12d Wed 5/10/17 Thu 5/25/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8393 TMPC
6.0
3900/2L TMPC SS Rev. L Review, Comments, Adjudication
0% 12d Fri 5/26/17 Tue 6/13/17
8394 TMPC
6.0
3900/2L TMPC SS Rev. L Create CCB Brief/QA
0% 3d Wed 6/14/17 Fri 6/16/17
8395 TMPC
6.0
3900/2L TMPC SS Rev. L - Delivery to PMA281
0% 1d Mon 6/19/17 Mon 6/19/17
8397 TMPC
6.0
3900/2L TMPC SS Rev. L - Route for Signatures
0% 21d Tue 6/20/17 Wed 7/19/17
8398 TMPC
6.0
3900/2L TMPC SS Rev. L - CCB/Signature Approval
0% 1d Thu 7/20/17 Thu 7/20/17
8442 TMPC
6.0
3900/127B TCOMMS SSS Rev. B 0% 49d Wed 5/10/17
Wed 7/19/17
8443 TMPC
6.0
3900/127B TCOMMS SSS Rev. B (SVT - Export, Initial Review, Distribute)
0% 12d Wed 5/10/17 Thu 5/25/17
8444 TMPC
6.0
3900/127B TCOMMS SSS Rev. B Review, Comments, Adjudication
0% 12d Fri 5/26/17 Tue 6/13/17
8445 TMPC
6.0
3900/127B TCOMMS SSS Rev. B Create CCB Brief/QA
0% 2d Wed 6/14/17 Thu 6/15/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8446 TMPC
6.0
3900/127B TCOMMS SSS Rev. B - Delivery to PMA281
0% 1d Fri 6/16/17 Fri 6/16/17
8447 TMPC
6.0
3900/127B TCOMMS SSS Rev. B - Route for Signatures
0% 21d Mon 6/19/17 Tue 7/18/17
8448 TMPC
6.0
3900/127B TCOMMS SSS Rev. B - CCB/Signature Approval
0% 1d Wed 7/19/17 Wed 7/19/17
8456 TMPC
6.0
3900/208 TEI SSS Rev. A 0% 47d Wed 5/10/17
Mon 7/17/17
8457 TMPC
6.0
3900/208 TEI SSS Rev. A (SVT - Export, Initial Review, Distribute)
0% 12d Wed 5/10/17 Thu 5/25/17
8458 TMPC
6.0
3900/208 TEI SSS Rev. A Review, Comments, Adjudication
0% 12d Fri 5/26/17 Tue 6/13/17
8459 TMPC
6.0
3900/208 TEI SSS Rev. A Create CCB Brief/QA
0% 2d Wed 6/14/17 Thu 6/15/17
8460 TMPC
6.0
3900/208 TEI SSS Rev. A - Delivery to PMA281
0% 1d Fri 6/16/17 Fri 6/16/17
8461 TMPC
6.0
3900/208 TEI SSS Rev. A - Route for Signatures
0% 19d Mon 6/19/17 Fri 7/14/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8462 TMPC
6.0
3900/208 TEI SSS Rev. A - CCB/Signature Approval
0% 1d Mon 7/17/17 Mon 7/17/17
8414 TMPC
6.0
3900/205A HW SS Rev. A 0% 49d Wed 5/10/17
Wed 7/19/17
8415 TMPC
6.0
3900/205A HW SS Rev. A (SVT - Export, Initial Review, Distribute)
0% 12d Wed 5/10/17 Thu 5/25/17
8416 TMPC
6.0
3900/205A HW SS Rev. A Review, Comments, Adjudication
0% 12d Fri 5/26/17 Tue 6/13/17
8417 TMPC
6.0
3900/205A HW SS Rev. A Create CCB Brief/QA
0% 4d Wed 6/14/17 Mon 6/19/17
8418 TMPC
6.0
3900/205A HW SS Rev. A - Delivery to PMA281
0% 1d Tue 6/20/17 Tue 6/20/17
8419 TMPC
6.0
3900/205A HW SS Rev. A - Route for Signatures
0% 19d Wed 6/21/17 Tue 7/18/17
8420 TMPC
6.0
3900/205A HW SS Rev. A - CCB/Signature Approval
0% 1d Wed 7/19/17 Wed 7/19/17
8449 TMPC
6.0
3900/186B TNT SSS Rev. B 0% 49d Wed 5/10/17
Wed 7/19/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8450 TMPC
6.0
3900/186B TNT SSS Rev. B (SVT - Export, Initial Review, Distribute)
0% 12d Wed 5/10/17 Thu 5/25/17
8451 TMPC
6.0
3900/186B TNT SSS Rev. B Review, Comments, Adjudication
0% 12d Fri 5/26/17 Tue 6/13/17
8452 TMPC
6.0
3900/186B TNT SSS Rev. B Create CCB Brief/QA
0% 2d Wed 6/14/17 Thu 6/15/17
8453 TMPC
6.0
3900/186B TNT SSS Rev. B - Delivery to PMA281
0% 1d Fri 6/16/17 Fri 6/16/17
8454 TMPC
6.0
3900/186B TNT SSS Rev. B - Route for Signatures
0% 21d Mon 6/19/17 Tue 7/18/17
8455 TMPC
6.0
3900/186B TNT SSS Rev. B - CCB/Signature Approval
0% 1d Wed 7/19/17 Wed 7/19/17
8435 TMPC
6.0
3900/110I TPS SSS Rev. I 0% 49d Wed 5/10/17
Wed 7/19/17
8436 TMPC
6.0
3900/110I TPS SSS Rev. I (SVT - Export, Initial Review, Distribute)
0% 12d Wed 5/10/17 Thu 5/25/17
8437 TMPC
6.0
3900/110I TPS SSS Rev. I Review, Comments, Adjudication
0% 12d Fri 5/26/17 Tue 6/13/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8438 TMPC
6.0
3900/110I TPS SSS Rev. I Create CCB Brief/QA
0% 2d Wed 6/14/17 Thu 6/15/17
8439 TMPC
6.0
3900/110I TPS SSS Rev. I - Delivery to PMA281
0% 1d Fri 6/16/17 Fri 6/16/17
8440 TMPC
6.0
3900/110I TPS SSS Rev. I - Route for Signatures
0% 21d Mon 6/19/17 Tue 7/18/17
8441 TMPC
6.0
3900/110I TPS SSS Rev. I - CCB/Signature Approval
0% 1d Wed 7/19/17 Wed 7/19/17
8421 TMPC
6.0
3900/133F SEC SS Rev. F 0% 49d Thu 5/11/17 Thu 7/20/17
8422 TMPC
6.0
3900/133F SEC SS Rev. F (SVT-Export, Initial Review, Distribute)
0% 12d Thu 5/11/17 Fri 5/26/17
8423 TMPC
6.0
3900/133F SEC SS Rev. F Review, Comments, Adjudication
0% 12d Tue 5/30/17 Wed 6/14/17
8424 TMPC
6.0
3900/133F SEC SS Rev. F Create CCB Brief/QA
0% 4d Thu 6/15/17 Tue 6/20/17
8425 TMPC
6.0
3900/133F SEC SS Rev. F - Delivery to PMA281
0% 1d Wed 6/21/17 Wed 6/21/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8426 TMPC
6.0
3900/133F SEC SS Rev. F - Route for Signatures
0% 19d Thu 6/22/17 Wed 7/19/17
8427 TMPC
6.0
3900/133F SEC SS Rev. F - CCB/Signature Approval
0% 1d Thu 7/20/17 Thu 7/20/17
8126 TMPC
6.0
3900/146 IRS REV C TMPC 6.0
Phase II/III TTWCS IRS
0% 29d Mon 5/1/17 Fri 6/9/17
8127 TMPC
6.0
3900/146C 6.0 Ph.II/III TTWCS IRS Rev C - SVT (Develop, QA, Distribute to Interface)
0% 8d Mon 5/1/17 Wed 5/10/17
8147 TMPC
6.0
3900/146C 6.0 Ph.II/III TTWCS IRS Rev C- Technical Concurrence & Meetings
0% 10d Thu 5/11/17 Wed 5/24/17
8148 TMPC
6.0
3900/146C 6.0 Ph.II/III TTWCS IRS Rev C- Adjudication & Incorporation of Interface Review Comments
0% 3d Thu 5/25/17 Tue 5/30/17
8129 TMPC
6.0
3900/146C 6.0 Ph.II/III TTWCS IRS Rev C- Deliver to PMA 281/280
0% 3d Wed 5/31/17 Fri 6/2/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8130 TMPC
6.0
3900/146C 6.0 Ph.II/III TTWCS IRS Rev C - CCB/System Release
0% 5d Mon 6/5/17 Fri 6/9/17
6038 TMPC
6.0
6.0 TNT Activities (BAE Systems) 94% 819d Mon 6/2/14 Thu 10/5/17
6081 TMPC
6.0
TNT 6.0 Phase III (Other CRs) 90% 445d Fri 12/11/15 Thu 10/5/17
6106 TMPC
6.0
TNT 6.0 Phase III Engineering & Development
89% 366d Fri 12/11/15 Wed 6/14/17
6091 TMPC
6.0
TNT 6.0 Integration and Testing 68% 120d Thu 12/15/16
Wed 6/14/17
6107 TMPC
6.0
CDRLs TNT 6.0 Phase III 90% 394d Tue 3/8/16 Thu 10/5/17
6140 TMPC
6.0
SDD - TNT 6.0 Phase III 87% 394d Tue 3/8/16 Thu 10/5/17
6145 TMPC
6.0
Produce/deliver Final As-built
SDD
0% 19d Mon 9/11/17 Thu 10/5/17
6146 TMPC
6.0
IDD - TNT 6.0 Phase III 87% 394d Tue 3/8/16 Thu 10/5/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
6151 TMPC
6.0
Produce/deliver Final As-Built
IDD
0% 19d Mon 9/11/17 Thu 10/5/17
6152 TMPC
6.0
DBDD - TNT 6.0 Phase III 87% 394d Tue 3/8/16 Thu 10/5/17
6157 TMPC
6.0
Produce/deliver Final As-Built
DBDD
0% 19d Mon 9/11/17 Thu 10/5/17
6162 TMPC
6.0
STD -TNT 6.0 Phase III 85% 338d Wed 5/25/16
Thu 10/5/17
6165 TMPC
6.0
Produce/deliver Final As-Built
STD
0% 19d Mon 9/11/17 Thu 10/5/17
6241 TMPC
6.0
6.0 MDS TED TCIP TMS ISAT Activities
(Vencore)
95% 780d Tue 5/20/14 Mon 7/31/17
4615 TMPC
6.0
TCIP Drops to PMA 280 (NRO/Aur) 99% 704d Thu 8/28/14 Fri 7/21/17
7161 TMPC
6.0
TCIP 6 Eng Build - Receive AUR Feedback/Test Set Development (TMPC Task)
0% 0d Mon 5/22/17 Mon 5/22/17
7163 TMPC
6.0
TCIP 6 Final Build - Delivery to
PMA280
0% 0d Fri 7/21/17 Fri 7/21/17
5/22
7/21
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
6288 TMPC
6.0
CDRLs MDS TED TCIP TMS ISAT 6.0 Phase III
80% 336d Wed 3/23/16
Mon 7/31/17
6293 TMPC
6.0
SDD -MDS TED TCIP TMS ISAT 6.0
Phase III
52% 336d Wed 3/23/16
Mon 7/31/17
6298 TMPC
6.0
Produce/deliver Final (Detailed) Post-CDR SDD MDS TED TCIP TMS ISAT 6.0 Phase III
0% 11d Mon 7/17/17 Mon 7/31/17
6299 TMPC
6.0
IDD - MDS TED TCIP TMS ISAT 6.0
Phase III
52% 336d Wed 3/23/16
Mon 7/31/17
6304 TMPC
6.0
Produce/deliver Phase III Final (Detailed) Post-CDR IDD MDS TED TCIP TMS ISAT 6.0 Phase III
0% 11d Mon 7/17/17 Mon 7/31/17
6305 TMPC
6.0
DBDD - MDS TED TCIP TMS ISAT
6.0 Phase III
59% 336d Wed 3/23/16
Mon 7/31/17
6310 TMPC
6.0
Produce/deliver Phase III Final (Detailed) Post-CDR DBDD MDS TED TCIP TMS ISAT 6.0 Phase III
0% 11d Mon 7/17/17 Mon 7/31/17
6315 TMPC
6.0
STD - MDS TED TCIP TMS ISAT 6.0
Phase III
91% 299d Fri 5/13/16 Mon 7/31/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
6318 TMPC
6.0
Produce/deliver Final STD MDS TED TCIP TMS ISAT 6.0 Phase III
0% 11d Mon 7/17/17 Mon 7/31/17
8236 TMPC
6.0
Post Phase III Development & System Integration & Test
52% 140d Tue 1/3/17 Fri 7/21/17
6287 TMPC
6.0
MDS TED TCIP TMS ISAT 6.0 Phase II/III Systems Test/Integration
54% 140d Tue 1/3/17 Fri 7/21/17
8524 TMPC
6.0
Other Post Phase III Code 22% 51d Thu 4/6/17 Fri 6/16/17
8235 TMPC
6.0
Post-Phase III Development (DDG-1000, Misc FY17)
77% 73d Wed 2/1/17 Mon 5/15/17
8516 TMPC
6.0
ISAT MIDB Coding 46% 76d Fri 3/3/17 Mon 6/19/17
8234 TMPC
6.0
Post Phase III Code Complete (All Code Complete)
0% 0d Mon 6/19/17 Mon 6/19/17
7206 TMPC
6.0
6.0 COA2 TTWCS/TMPC Early
Integration Events
64% 223d Mon 8/8/16 Thu 7/6/17
8527 TMPC
6.0
Vencore B2 Fixes Completed, Ready for "Virtual" C1
77% 30d Tue 3/21/17 Mon 5/1/17
8526 TMPC
6.0
Virtualized B2 FIB Event (Confirm B2 Fixes)
0% 5d Tue 5/2/17 Mon 5/8/17
6/19
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7207 TMPC
6.0
Second Modernized Interface Test (C1) NSP Test Points
0% 10d Wed 5/24/17 Wed 6/7/17
8530 TMPC
6.0
Virtual B2 FIB Test Issues Fixed or Deferred (Or there was none)
0% 7d Tue 5/9/17 Wed 5/17/17
7215 TMPC
6.0
NSP C1 Second Modernized Interface Test Issues Fixed or Deferred
0% 20d Thu 6/8/17 Thu 7/6/17
8529 TMPC
6.0
Vencore Build Ready for C2 At Dalhgreen
0% 4d Tue 5/2/17 Fri 5/5/17
6386 TMPC
6.0
6.0 TPS Activities (Tapestry) 94% 780d Mon 6/2/14 Thu 8/10/17
7571 TMPC
6.0
NAV Integration Missions to APL/AUR85% 279d Thu 6/23/16 Thu 8/10/17
8579 TMPC
6.0
TMPC 6.0: NAV Integration Mission 3 - Work with Raytheon Planning the Mission
0% 10d Fri 7/7/17 Thu 7/20/17
7498 TMPC
6.0
TMPC 6.0: NAV Integration Mission 3 - FQT Final to AUR (Block IV)
0% 5d Fri 8/4/17 Thu 8/10/17
6463 TMPC
6.0
TPS 6.0 Phase III (Other CRs) 84% 412d Mon 11/30/15
Mon 8/7/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
6464 TMPC
6.0
TPS 6.0 Phase III Engineering & Development
77% 396d Mon 11/30/15
Fri 7/14/17
6468 TMPC
6.0
TPS 6.0 Phase III Code and Test 85% 210d Tue 7/26/16 Mon 6/5/17
7111 TMPC
6.0
TPS 6.0 Phase III Code Complete 0% 0d Mon 6/5/17 Mon 6/5/17
8269 TMPC
6.0
TPS 6.0 Executable/System Integration Test Planning & Preps
0% 11d Tue 6/6/17 Tue 6/20/17
6469 TMPC
6.0
TPS 6.0 Phase III Executable/System Integration Testing
0% 31d Thu 6/1/17 Fri 7/14/17
6470 TMPC
6.0
CDRLs TPS 6.0 Phase III 88% 367d Tue 2/16/16 Mon 8/7/17
6471 TMPC
6.0
SRS - TPS 6.0 Phase III 86% 253d Wed 7/27/16
Mon 8/7/17
6474 TMPC
6.0
Produce/deliver Final SRR TPS 6.0
0% 10d Tue 7/25/17 Mon 8/7/17
6475 TMPC
6.0
SDD - TPS 6.0 Phase III 86% 253d Wed 7/27/16
Mon 8/7/17
6/5
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
6480 TMPC
6.0
Produce/deliver Final SDD TPS 6.0
0% 10d Tue 7/25/17 Mon 8/7/17
6481 TMPC
6.0
IDD - TPS 6.0 Phase III 86% 253d Wed 7/27/16
Mon 8/7/17
6486 TMPC
6.0
Produce/deliver Final IDD TPS 6.0
0% 10d Tue 7/25/17 Mon 8/7/17
6487 TMPC
6.0
DBDD - TPS 6.0 Phase III 89% 253d Wed 7/27/16
Mon 8/7/17
6492 TMPC
6.0
Produce/deliver Final DBDD
TPS 6.0
0% 10d Tue 7/25/17 Mon 8/7/17
6493 TMPC
6.0
STP - TPS 6.0 Phase III 86% 253d Wed 7/27/16
Mon 8/7/17
6496 TMPC
6.0
Produce/deliver Final STP TPS 6.0
0% 10d Tue 7/25/17 Mon 8/7/17
6090 TMPC
6.0
6.0 TMPC Integration Events (@ BAE) 69% 289d Sun 6/5/16 Mon 8/7/17
8508 TMPC
6.0
TMPC 6.0 Integration Event II.5 72% 100d Thu 1/5/17 Fri 5/26/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8509 TMPC
6.0
Setup/Install Suite with Windows Server 2016 for Event II.5
0% 10d Mon 4/24/17 Fri 5/5/17
8511 TMPC
6.0
Conduct Test Planning For Integration Event II.5
90% 10d Mon 4/10/17 Fri 4/21/17
8512 TMPC
6.0
Conduct 6.0 System Integration Event II.5
0% 10d Mon 5/1/17 Fri 5/12/17
8513 TMPC
6.0
Document/Deliver Integration Event II.5 Test Report
0% 10d Mon 5/15/17 Fri 5/26/17
1726 TMPC
6.0
TMPC 6.0 Integration Event III 0% 54d Mon 5/22/17
Mon 8/7/17
1727 TMPC
6.0
Setup Final Integration Test Suite (Event III)
0% 19d Tue 5/30/17 Fri 6/23/17
7586 TMPC
6.0
Define Final Event III System Integration Objectives
0% 5d Mon 5/22/17 Fri 5/26/17
7587 TMPC
6.0
Conduct Test Planning For Integration Event III
0% 19d Tue 5/30/17 Fri 6/23/17
1728 TMPC
6.0
Conduct 6.0 System Integration Event III
0% 20d Mon 6/26/17 Mon 7/24/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7589 TMPC
6.0
Document/Deliver Integration Event III Test Report
0% 10d Tue 7/25/17 Mon 8/7/17
7556 TMPC
6.0
Vendor Software Initial FQT (Pre PAT and Pre Integration Event D)
0% 50d Mon 7/24/17
Mon 10/2/17
7911 TMPC
6.0
TPS FQT Activities 0% 34d Tue 8/8/17 Mon 9/25/17
4502 TMPC
6.0
TPS 6.0 FQT 0% 20d Tue 8/8/17 Tue 9/5/17
7915 TMPC
6.0
TPS 6.0 FQT & Cyber Cleanup 0% 10d Tue 9/12/17 Mon 9/25/17
7913 TMPC
6.0
TNT FQT Activities 0% 30d Mon 8/21/17
Mon 10/2/17
4501 TMPC
6.0
TNT 6.0 FQT 0% 10d Mon 8/21/17 Fri 9/1/17
7914 TMPC
6.0
TNT 6.0 FQT & Cyber Cleanup 0% 20d Tue 9/5/17 Mon 10/2/17
7912 TMPC
6.0
Vencore FQT Activities (MDS etc.) 0% 47d Mon 7/24/17
Wed 9/27/17
7240 TMPC
6.0
MDS, TCOMMS, TEI, TEN, TMS 6.0
FQT Prep & Dry Run
0% 25d Mon 7/24/17 Fri 8/25/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7916 TMPC
6.0
MDS, TCOMMS, TEI, TEN, TMS 6.0
FQT
0% 14d Mon 8/28/17 Fri 9/15/17
7124 TMPC
6.0
MDS, TCOMMS, TEI, TEN, TMS 6.0
FQT & Cyber Cleanup
0% 8d Mon 9/18/17 Wed 9/27/17
1748 TMPC
6.0
TMPC 6.0 Final Release Activities 0% 81d Fri 8/21/20 Fri 12/18/20
1743 TMPC
6.0
TMPC 6.0 & TWS DT/OT Activities 0% 20d Fri 8/21/20 Fri 9/18/20
3693 TMPC
6.0
TMPC 6.0 JITC/OT Test Report Complete
0% 20d Fri 8/21/20 Fri 9/18/20
1749 TMPC
6.0
6.0 Pre Fleet Release Activities $PP 0% 44d Mon 9/14/20 Mon
11/16/20
7566 TMPC
6.0
6.0 Fleet Release Approval 0% 0d Mon
11/16/20
Mon 11/16/20
1750 TMPC
6.0
6.0 CMSA Install-SAT-IA-Training 0% 22d Tue
11/17/20
Fri 12/18/20
8534 TMPC
6.0
6.0 All Training & Logistics Documents
Complete
0% 0d Fri 12/18/20 Fri 12/18/20
1751 TMPC
6.0
6.0 IOC 0% 0d Fri 12/18/20 Fri 12/18/20
7024 TMPC
6.0
6.0 Cybersecurity 0% 403d Fri 4/21/17 Thu 12/6/18
9/18
11/16
12/18
12/18
12/18
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8242 TMPC
6.0
IATT Test Windows 0% 247d Wed 12/6/17
Thu 12/6/18
7002 TMPC
6.0
IATT ONI Window (High Side) 0% 10d Thu 1/11/18 Thu 1/25/18
6996 TMPC
6.0
IATT NAO Window (Low Side)
PAT-FIB#2 PAT
0% 247d Wed 12/6/17 Thu 12/6/18
6991 TMPC
6.0
6.0 Cybersecurity IATT Accreditation, Navy Approving Office (NAO) (Low Side) PAT - FIB#2 PAT
0% 156d Fri 4/21/17 Tue 12/5/17
6992 TMPC
6.0
IATT NAO - Categorize System for
6.0 Accreditation (Step 1)
0% 66d Fri 4/21/17 Tue 7/25/17
6993 TMPC
6.0
IATT NAO - Select Security Controls for 6.0 Accreditation (Step 2)
0% 10d Wed 7/26/17 Tue 8/8/17
6994 TMPC
6.0
IATT NAO - Implement Security Controls for 6.0 Accreditation (Step 3)
0% 8d Fri 9/22/17 Tue 10/3/17
6995 TMPC
6.0
IATT NAO - Assess Security Controls for 6.0 Accreditation (Step 4)
0% 26d Wed 10/4/17 Thu 11/9/17
8194 TMPC
6.0
IATT NAO - Authorize System for 6.0 Accreditation (Step 5)
0% 15d Mon 11/13/17
Tue 12/5/17
8/8
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
6997 TMPC
6.0
6.0 Cybersecurity IATT Accreditation, Office of Naval Intelligence (ONI) (High Side) PAT
0% 156d Fri 4/21/17 Tue 12/5/17
6998 TMPC
6.0
IATT ONI - Categorize System for 6.0 Accreditation (Step 1)
0% 66d Fri 4/21/17 Tue 7/25/17
6999 TMPC
6.0
IATT ONI - Select Security Controls for 6.0 Accreditation (Step 2)
0% 10d Wed 7/26/17 Tue 8/8/17
7000 TMPC
6.0
IATT ONI - Implement Security Controls for 6.0 Accreditation (Step 3)
0% 8d Fri 9/22/17 Tue 10/3/17
7001 TMPC
6.0
IATT ONI - Assess Security Controls for 6.0 Accreditation (Step 4)
0% 26d Wed 10/4/17 Thu 11/9/17
8195 TMPC
6.0
IATT ONI - Authorize System for 6.0 Accreditation (Step 5)
0% 15d Mon 11/13/17
Tue 12/5/17
7557 TMPC
6.0
Vendor Software Final Fix-it-Build CyberSecurity Scans & Test (For ATO)
0% 4d Thu 9/6/18 Tue 9/11/18
7558 TMPC
6.0
TNT Final Fix-it-Build Cybersecurity IA Scans
0% 2d Thu 9/6/18 Fri 9/7/18
8/8
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7559 TMPC
6.0
TNT Final Fix-it-Build Cybersecurity Test & Evaluation
0% 2d Mon 9/10/18 Tue 9/11/18
7560 TMPC
6.0
TPS Final Fix-it-Build Cybersecurity IA Scans
0% 2d Thu 9/6/18 Fri 9/7/18
7561 TMPC
6.0
TPS Final Fix-it-Build Cybersecurity Test & Evaluation
0% 2d Mon 9/10/18 Tue 9/11/18
7562 TMPC
6.0
MDS TED TCIP TMS ISAT Final Fix-it-Build Cybersecurity IA Scans
0% 2d Thu 9/6/18 Fri 9/7/18
7563 TMPC
6.0
MDS TED TCIP TMS ISAT Final Fix-it-Build Cybersecurity Test & Evaluation
0% 2d Mon 9/10/18 Tue 9/11/18
7003 TMPC
6.0
6.0 Cybersecurity ATO Accreditation, Navy Approving Office (NAO) (Low Side)
0% 138d Mon 5/7/18 Wed 11/21/18
7004 TMPC
6.0
ATO NAO - Categorize System for
6.0 Accreditation (Step 1)
0% 66d Mon 5/7/18 Wed 8/8/18
7005 TMPC
6.0
ATO NAO - Select Security Controls for 6.0 Accreditation (Step 2)
0% 10d Thu 8/9/18 Wed 8/22/18
7006 TMPC
6.0
ATO NAO - Implement Security Controls for 6.0 Accreditation (Step 3)
0% 8d Wed 9/12/18 Fri 9/21/18
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
8188 TMPC
6.0
ATO NAO - Compare FIB#2 FQT IA Scans to FIB#2 IA Scans at Fib #2
PAT
0% 5d Tue 10/9/18 Mon 10/15/18
7007 TMPC
6.0
ATO NAO - Assess Security Controls for 6.0 Accreditation (Step 4)
0% 26d Mon 9/24/18 Tue 10/30/18
7008 TMPC
6.0
ATO NAO - Authorize System for 6.0 Accreditation (Step 5)
0% 15d Wed 10/31/18
Wed 11/21/18
7009 TMPC
6.0
6.0 Cybersecurity ATO Accreditation, Office of Naval Intelligence (ONI)
0% 138d Mon 5/7/18 Wed 11/21/18
7010 TMPC
6.0
ATO ONI - Categorize System for 6.0 Accreditation (Step 1)
0% 66d Mon 5/7/18 Wed 8/8/18
7011 TMPC
6.0
ATO ONI - Select Security Controls for 6.0 Accreditation (Step 2)
0% 10d Thu 8/9/18 Wed 8/22/18
7012 TMPC
6.0
ATO ONI - Implement Security Controls for 6.0 Accreditation (Step 3)
0% 8d Wed 9/12/18 Fri 9/21/18
8189 TMPC
6.0
ATO ONI - Compare FIB#2 FQT IA Scans to FIB#2 IA Scans at Fib #2
PAT
0% 5d Tue 10/9/18 Mon 10/15/18
7013 TMPC
6.0
ATO ONI - Assess Security Controls for 6.0 Accreditation (Step 4)
0% 26d Mon 9/24/18 Tue 10/30/18
10/15
10/30
10/15
10/30
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7014 TMPC
6.0
ATO ONI - Authorize System for 6.0 Accreditation (Step 5)
0% 15d Wed 10/31/18
Wed 11/21/18
8190 TMPC
6.0
Provide Cybersecuirty Input to TWS Level Test Packages
0% 61d Thu 4/5/18 Fri 6/29/18
8193 TMPC
6.0
Provide Latest TMPC IA Scans to TWS Cybersecurity team
0% 2d Thu 6/28/18 Fri 6/29/18
8192 TMPC
6.0
Develop & Update Documents to deliver to TWS Cybersecurity team
0% 22d Thu 4/5/18 Fri 5/4/18
8196 TMPC
6.0
CyberSecurity Early Scans & Categoization
0% 5d Mon 5/1/17 Fri 5/5/17
8197 TMPC
6.0
TPS Cyber Scans & Categorization 0% 5d Mon 5/1/17 Fri 5/5/17
8198 TMPC
6.0
MDS TED TCIP TMS ISAT Cyber Scans & Categorization
0% 5d Mon 5/1/17 Fri 5/5/17
8200 TMPC
6.0
TNT Cyber Scans & Categorization 0% 5d Mon 5/1/17 Fri 5/5/17
7910 TMPC
6.0
CyberSecurity FQT 0% 13d Tue 9/5/17 Thu 9/21/17
7552 TMPC
6.0
TPS FQT Cybersecurity IA Scans 0% 2d Wed 9/6/17 Thu 9/7/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
7555 TMPC
6.0
TNT FQT Cybersecurity Test & Evaluation
0% 2d Thu 9/7/17 Fri 9/8/17
7553 TMPC
6.0
TPS FQT Cybersecurity Test & Evaluation
0% 2d Fri 9/8/17 Mon 9/11/17
7554 TMPC
6.0
TNT FQT Cybersecurity IA Scans 0% 2d Tue 9/5/17 Wed 9/6/17
7549 TMPC
6.0
MDS TED TCIP TMS ISAT FQT
Cybersecurity IA Scans
0% 2d Mon 9/18/17 Tue 9/19/17
7551 TMPC
6.0
MDS TED TCIP TMS ISAT FQT
Cybersecurity Test & Evaluation
0% 2d Wed 9/20/17 Thu 9/21/17
6568 TMPC
6.0
6.0 & TMPC Test & Evaluation (Initial thru FIB #2)
44% 972d Fri 12/19/14 Thu 12/13/18
1731 TMPC
6.0
6.0 Delivery/Installation to WPC for
PAT
0% 47d Tue 8/8/17 Fri 10/13/17
4503 TMPC
6.0
TNT 6.0 Delivery 0% 8d Tue 10/3/17 Fri 10/13/17
4504 TMPC
6.0
TNT 6.0 Delivery to WPC 0% 2d Tue 10/3/17 Wed 10/4/17
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
OBS
Name % Complete
Duration Start Finish
4505 TMPC
6.0
TNT 6.0 Installation, Data Migration, Checkout Testing
0% 6d Thu 10/5/17 Fri 10/13/17
4506 TMPC
6.0
TNT 6.0 Installation Complete 0% 0d Fri 10/13/17 Fri 10/13/17
7918 TMPC
6.0
HW Install? 0% 10d Tue 8/8/17 Mon 8/21/17
7919 TMPC
6.0
HW Install $PP 0% 10d Tue 8/8/17 Mon 8/21/17
4521 TMPC
6.0
MDS, TCOMMS, TEI, TEN, TMS 6.0
Delivery
0% 8d Thu 9/28/17 Tue 10/10/17
4522 TMPC
6.0
MDS, TCOMMS, TEI, TEN, TMS
6.0 Deliv. to WPC
0% 2d Thu 9/28/17 Fri 9/29/17
4523 TMPC
6.0
MDS, TCOMMS, TEI, TEN, TMS
6.0 Installation, Data Migration, Checkout Testing
0% 6d Mon 10/2/17 Tue 10/10/17
4524 TMPC
6.0
MDS, TCOMMS, TEI, TEN, TMS
6.0 Installation Complete
0% 0d Tue 10/10/17
Tue 10/10/17
4493 TMPC
6.0
TPS 6.0 Delivery 0% 8d Tue 9/26/17 Thu 10/5/17
10/13
10/10
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 2017 2018 2019 2020 2021 2022 2023
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .