This document is an Attachment detailing the Contract Line Item Number (CLIN) Structure and Milestones for the IX527 Barge Preservation, Inspection, Repair, and Maintenance (PIRM) Support Services contract. The base CLIN0001 includes a detailed payment schedule with nine milestone events, ranging from a post-award conference (5% payment) to final undocking (10% payment), with incremental payments tied to specific work item completions and government approvals. Additional option CLINs (CLIN0002-CLIN0018) cover services such as tug delivery, various modifications and upgrades to the vessel, including tank sounding tube installation, electric power distribution upgrades, alarm system improvements, structural modifications, and other specific repair and enhancement work, each with full payment upon government approval and performance periods extending to 9/1/2026.

View the file

Other files

File Type Posted
Solicitation Amendment N0016725R10010006 SF 30.pdf PDF
Answers to Prospective Offeror Questions - Round Six.pdf PDF
Solicitation Amendment SF 1449 - N0016725R10010005.pdf PDF
Solicitation Amendment N0016725R1001 SF30 0005.pdf PDF
Answers to Prospective Offeror Questions - Round Five Rev 3.pdf PDF
Solicitation Amendment N0016725R10010004 SF 30.pdf PDF
Answers to Prospective Offeror Questions - Round Five.pdf PDF
Answers to Prospective Offeror Questions - Round Four.pdf PDF
Solicitation Amendment N0016725R10010003 SF 30.pdf PDF
Attachment 05 - Requirements Specification for Task Order 0001 - Barge IX527 (WI-23 and 1.4.9 update).docx DOCX document
Questions and Answers from Industry Day Two.pdf PDF
Solicitation Amendment N0016725R10010002 SF 30.pdf PDF
Answers to Prospective Offeror Questions - Second and Third Rounds.pdf PDF
Answers to Prospective Offerors Questions.pdf PDF
Solicitation Amendment N0016725R10010001 SF 30.pdf PDF
Attachment 09 - IX528 General Specifications.docx DOCX document
UPDATED Attachment 06 - CLIN Pricing Structure.xlsx XLSX spreadsheet
Attachment 04 - IX527 Barge PIRM Support Services GFP Attachment_DRAFT.xlsx XLSX spreadsheet
Exhibit A - CDRLs A001 - A016.pdf PDF
Attachment 02 - Past Performance Reference.docx DOCX document
Attachment 07 - Property Management Questionnaire.docx DOCX document
Attachment 08 - CFR Price Template.xlsx XLSX spreadsheet
SF 1449 - N0016725R1001.pdf PDF
Attachment 03 - Past Performance Questionnaire.docx DOCX document
Attachment 06 - CLIN Pricing Structure.xlsx XLSX spreadsheet
Attachment 01 - CLIN Structure _ Milestones.docx DOCX document
Attachment 05 - Requirements Specification for Task Order 0001 - Barge IX527.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION H SPECIAL CONTRACT REQUIREMENTS

CLIN Structure and Milestones for IX527 Barge Preservation, Inspection, Repair, and Maintenance (PIRM) Support Services

CLIN0001 – Base Requirements Payments shall be made in accordance with the following payment schedule:

Event Number
Milestone
Event % Value
% of Task Completed
1
Post Award Conference Completion
5%
5%
2
Project Planning Report
5%
10%
3
Work Item 5, 6 – Initial Drydocking Completion
10%
20%
4
Work Items 28, 30 Completion
10%
30%
5
Work Items 10, 17, 22 Completion
15%
45%
6
Work Items 12, 15 Completion
15%
60%
7
Work Items 9, 24 Completion
15%
75%
8
Work Items 25, 31 Completion
15%
90%
9
Work Item 6, Final Undocking Completion
10%
100%

EVENT 1 – Post Award Kickoff Meeting Government will provide payment of 5% of the CLIN value upon completion of the Post Award Kickoff meeting.

EVENT 2 – Project Planning Report The Government will provide payment of 5% of the CLIN value upon completion of the initial Project Planning submission within 60 days of contract award and approval from the Government.

EVENT 3 – Work Item 5, 6 – Initial Drydocking Completion The Government will provide payment of 10% of the CLIN value upon completion and Government approval of the IX527 initial dry-docking and docking report submitted to the Government.

EVENT 4 – Work Items 28, 30 The Government will provide payment of 10% of the CLIN value upon completion and Government approval for IX527 Work Item 28 (Machinery Room Acoustic Enclosure) and Work Item 30 (Clean Keel Coolers).

EVENT 5 – Work Items 10, 17, 22 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 10 (Fuel Systems Modifications), Work Item 17 (Egress and Hatch Modifications), and Work Item 22 (Firemain System Removal).

EVENT 6 – Work Items 12, 15 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 12 (Handrail Modifications) and Work Item 15 (Bilge Strainer Modifications).

EVENT 7 – Work Items 9, 24 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 9 (Preparations) and Work Item 24 (UT Testing and Steel Repairs).

EVENT 8 – Work Items 25, 31 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 25 (Zinc Replacement) and Work Item 31 (Painting).

EVENT 9 – Work Item 6, Final Undocking Completion Upon completion of the IX527 final undocking, the Government will provide payment of 10% of the CLIN value.

CLIN0002 (Option CLIN for Tug Delivery Services, Line Handling, and Mooring to Contractor Site) The Government will provide payment of the full CLIN value upon completion and approval from Government of Work Item 3 for the Contractor to provide tug services to tow or transport the IX527 from SEAFAC to the Contractor’s facility.

POP is from date exercised to 5/21/2026.

CLIN0003 - (Option CLIN for Tank Sounding Tube Install) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0004 - (Option CLIN for Electric Power Distribution Upgrades) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0005 - (Option CLIN for Alarm System Upgrades) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0006 - (Option CLIN for Convert Void 6 and Bilge Piping Modifications) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0007 - (Option CLIN for Rake Room Personnel Safety Modifications) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0008 - (Option CLIN for New Deck Cleat Installation) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0009 - (Option CLIN for Deck Drain System Installation) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0010 - (Option CLIN for Deckhouse Structural Modifications) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0011 - (Option CLIN for Suspension Winches and Winch Foundations) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0012 - (Option CLIN for Cable Way Improvements) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0013 - (Option CLIN for Butler Building Exterior Replacement and Vent Closure) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0014 - (Option CLIN for Exterior Watertight Door Replacement) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0015 - (Option CLIN for Plate Repair) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0016 - (Option CLIN for Pit Repair) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0017 - (Option CLIN for Weld Replacement) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.

POP is from date exercised to 9/1/2026.

CLIN0018 (Option) – Tug Delivery Services, Line Handling, and Mooring to SEAFAC The Government will provide payment of the full CLIN value upon completion and approval from Government of Work Item 3 for the Contractor to provide tug services to tow or transport the IX527 from Contractor facility to SEAFAC.

POP is from date exercised to 9/1/2026.

Please note that Offerors MUST incorporate the pricing for all data in accordance with CDRLs A001 – A016 within the base work item CLINs.