The document is a CLIN (Contract Line Item Number) Pricing Structure spreadsheet for the IX527 Barge Preservation Inspection, Repair, and Maintenance (PIRM) Support Services contract. The spreadsheet details 17 line items for various services and modifications, all with a unit price of $1 and a quantity of 1 EA (each), with a date of exercise set for 9/1/2026. Specific line items include Tug Delivery Services, Tank Sounding Tube Installation, Electric Power Distribution Upgrades, Personnel Safety Modifications, Deck Cleat Installation, Deck Drain System Installation, Deckhouse Structural Modifications, Suspension Winches and Winch Foundations, Cable Way Improvements, Building Exterior Replacement, and various repair services (plate, pit, and weld repairs).
The contract is associated with the Naval Surface Warfare Center Carderock Division's Signatures Department (Code 70) and relates to maintenance of service craft at the Southeast Alaska Acoustic Measurement Facility (SEAFAC). The two service craft, IX527 and IX528, are permanently moored at the SEAFAC Static Site in Western Behm Canal near Back Island. The primary objective is to provide inspection, repair, maintenance, and preservation support services for these specialized acoustic research vessels, which are modified with features like a moon pool and large deckhouse structure to support naval submarine acoustic testing and evaluation.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| CLIN | Option CLIN | Description | Period of Performance | Unit Price | Quantity | Unit of Measure | Total Price |
| 1 | N | IX527 Barge Preservation Inspection, Repair, and Maintenance (PIRM) Support Services. Payment in accordance with Milestones set forth in Attachment 01. Payment in accordance with Milestones set forth in Attachment 01. Inclusive of Post Award Conference, Project Planning Report, Work Items 5, 6, 28, 30, 10, 17, 22, 12, 15, 9, 24, 25, 31, and 6. Inclusive of Post Award Conference, Project Planning Report, Work Items 5, 6, 28, 30, 10, 17, 22, 12, 15, 9, 24, 25, 31, and 6. | DOA – 9/1/2026 | $ | 1 | EA | $ |
| 2 | Y | Tug Delivery Services, Line Handling and Mooring to Contractor Site Work Item # X. | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 3 | Y | Tank Sounding Tube Install. | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 4 | Y | Electric Power Distribution Upgrades. | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 5 | Y | Convert Void 6 and Bilge Piping Modifications. | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 6 | Y | Rake Room Personnel Safety Modifications. | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 7 | Y | Rake Room Personnel Safety Modifications | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 8 | Y | New Deck Cleat Installation | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 9 | Y | Deck Drain System Installation | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 10 | Y | Deckhouse Structural Modifications | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 11 | Y | Suspension Winches and Winch Foundations | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 12 | Y | Cable Way Improvements | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 13 | Y | Butler Building Exterior Replacement and Vent Closure | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 14 | Y | Plate Repair | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 15 | Y | Pit Repair | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 16 | Y | Weld Replacement | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |
| 17 | Y | Tug Delivery Services, Line Handling, and Mooring to SEAFAC | Date Exercised – 9/1/2026 | $ | 1 | EA | $ |