Attachment 01 - CLIN Structure _ Milestones.docx
DOCX document 37 KB Posted
- Attached to
- IX527 and IX528 BARGE PRESERVATION, INSPECTION, REPAIR, AND MAINTENANCE (PIRM) SUPPORT SERVICES
- Solicitation number
- N0016725R1001
About this file
This document is an attachment detailing the Contract Line Item Number (CLIN) Structure and Milestones for the IX527 Barge Preservation, Inspection, Repair, and Maintenance (PIRM) Support Services contract. The base CLIN (CLIN0001) includes a detailed payment schedule with nine milestone events, ranging from a post-award conference to final vessel undocking, with payment percentages tied to specific work item completions. The contract includes multiple option CLINs (CLIN0002-CLIN0017) for various services such as tug delivery, tank sounding tube installation, electric power distribution upgrades, and numerous structural and safety modifications to the vessel.
The contract is for the Naval Surface Warfare Center Carderock Division's Southeast Alaska Acoustic Measurement Facility (SEAFAC), focusing on preservation and maintenance of Service Craft IX527 and IX528. Each option CLIN will be paid in full upon government approval of specific work items, with performance periods extending to 9/1/2026. The document emphasizes that offerors must incorporate pricing for all data in accordance with CDRLs A001-A016 within the base work item CLINs, indicating a comprehensive and detailed approach to contract pricing and deliverables.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION H SPECIAL CONTRACT REQUIREMENTS
CLIN Structure and Milestones for IX527 Barge Preservation, Inspection, Repair, and Maintenance (PIRM) Support Services
CLIN0001 – Base Requirements Payments shall be made in accordance with the following payment schedule:
| Event Number |
| Milestone |
| Event % Value |
| % of Task Completed |
| 1 |
| Post Award Conference Completion |
| 5% |
| 5% |
| 2 |
| Project Planning Report |
| 5% |
| 10% |
| 3 |
| Work Item 5, 6 – Initial Drydocking Completion |
| 10% |
| 20% |
| 4 |
| Work Items 28, 30 Completion |
| 10% |
| 30% |
| 5 |
| Work Items 10, 17, 22 Completion |
| 15% |
| 45% |
| 6 |
| Work Items 12, 15 Completion |
| 15% |
| 60% |
| 7 |
| Work Items 9, 24 Completion |
| 15% |
| 75% |
| 8 |
| Work Items 25, 31 Completion |
| 15% |
| 90% |
| 9 |
| Work Item 6, Final Undocking Completion |
| 10% |
| 100% |
EVENT 1 – Post Award Kickoff Meeting Government will provide payment of 5% of the CLIN value upon completion of the Post Award Kickoff meeting.
EVENT 2 – Project Planning Report The Government will provide payment of 5% of the CLIN value upon completion of the initial Project Planning submission within 60 days of contract award and approval from the Government.
EVENT 3 – Work Item 5, 6 – Initial Drydocking Completion The Government will provide payment of 10% of the CLIN value upon completion and Government approval of the IX527 initial dry-docking and docking report submitted to the Government.
EVENT 4 – Work Items 28, 30 The Government will provide payment of 10% of the CLIN value upon completion and Government approval for IX527 Work Item 28 (Machinery Room Acoustic Enclosure) and Work Item 30 (Clean Keel Coolers).
EVENT 5 – Work Items 10, 17, 22 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 10 (Fuel Systems Modifications), Work Item 17 (Egress and Hatch Modifications), and Work Item 22 (Firemain System Removal).
EVENT 6 – Work Items 12, 15 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 12 (Handrail Modifications) and Work Item 15 (Bilge Strainer Modifications).
EVENT 7 – Work Items 9, 24 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 9 (Preparations) and Work Item 24 (UT Testing and Steel Repairs).
EVENT 8 – Work Items 25, 31 The Government will provide payment of 15% of the CLIN value upon completion and Government approval for IX527 Work Item 25 (Zinc Replacement) and Work Item 31 (Painting).
EVENT 9 – Work Item 6, Final Undocking Completion Upon completion of the IX527 final undocking, the Government will provide payment of 10% of the CLIN value.
CLIN0002 (Option CLIN for Tug Delivery Services, Line Handling, and Mooring to Contractor Site) The Government will provide payment of the full CLIN value upon completion and approval from Government of Work Item 3 for the Contractor to provide tug services to tow or transport the IX527 from SEAFAC to the Contractor’s facility.
POP is from date exercised to 5/21/2026.
CLIN0003 - (Option CLIN for TANK SOUNDING TUBE INSTALL) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0004 - (Option CLIN for ELECTRIC POWER DISTRIBUTION UPGRADES) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0005 - (Option CLIN for CONVERT VOID 6 AND BILGE PIPING MODIFICATIONS) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0006 - (Option CLIN for RAKE ROOM PERSONNEL SAFETY MODIFICATIONS) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0007 - (Option CLIN for NEW DECK CLEAT INSTALLATION) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0008 - (Option CLIN for DECK DRAIN SYSTEM INSTALLATION) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0009 - (Option CLIN for DECKHOUSE STRUCTURAL MODIFICATIONS) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0010 - (Option CLIN for SUSPENSION WINCHES AND WINCH FOUNDATIONS) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0011 - (Option CLIN for CABLE WAY IMPROVEMENTS) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0012 - (Option CLIN for BUTLER BUILDING EXTERIOR REPLACEMENT AND VENT CLOSURE) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0013 - (Option CLIN for EXTERIOR WATERTIGHT DOOR REPLACEMENT) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0014 - (Option CLIN for PLATE REPAIR) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0015 - (Option CLIN for PIT REPAIR) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0016 - (Option CLIN for WELD REPLACEMENT) The Government will provide payment of the full CLIN value upon completion and approval from Government for each IX527 Work Item Option.
POP is from date exercised to 9/1/2026.
CLIN0017 (Option) – Tug Delivery Services, Line Handling, and Mooring to SEAFAC The Government will provide payment of the full CLIN value upon completion and approval from Government of Work Item 3 for the Contractor to provide tug services to tow or transport the IX527 from Contractor facility to SEAFAC.
POP is from date exercised to 9/1/2026.
Please note that Offerors MUST incorporate the pricing for all data in accordance with CDRLs A001 – A016 within the base work item CLINs.