This document provides details regarding solicitation number N00024-22-R-4412 issued by the Naval Sea Systems Command for the USS NITZE (DDG 94) FY23 DEPOT MODERNIZATION PERIOD availability. The solicitation seeks a contractor to perform a combination of maintenance, modernization, and repair services for the USS NITZE from July 2023 through April 2025. Interested parties must register in the System for Award Management and monitor the SAM.gov website for release of the solicitation and any amendments. The solicitation is issued on a coast-wide basis for the East Coast under a single award contract. Based on the complexity, magnitude and duration of the requirement, the procurement will not be set aside for small business. The Navy anticipates making a single award for this solicitation in or around January 2023.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PPI FORM
| USS NITZE (DDG 94) DMP N00024-22-R-4412 | RFP | |||||
| Attachment S-3 Pre-Proposal Information (PPI) Form | Attachment J-1 | |||||
| NAVSEA POC: | CDR Jonathan Pagnucco; jonathan.pagnucco@navy.mil | Attachment J-2 | ||||
| Nelimar Munoz; nelimar.munoz-martin@navy.mil | Attachment J-3 | |||||
| Attachment J-4 | ||||||
| Question # | Question Area | Work Iem (if applicable) | Section/Para | Contractor Question | Government Response | Attachment J-5 |
| 96 | RFP | Several large solicitations prior to this one have created a very large backlog for subcontractors and we are still without pricing from several fixed price subcontractors in support of this proposal. Please extend the proposal due date one week to October 10th so offerors can include pricing from small business subcontractors who are interested in working on this contract. | Amendment 0004 extended the proposal submission date to 11 October 2022. | |||
| 97 | Attachment J-1 | 837-11-001 | 3.1 | Errata 3 removed Attachment A from the specification. However, Errata 3 para 3.1 still states " Accomplish the requirements of Attachment A………" Please confirm Attachment A remains part of this item and provide updated specification with Attachment A. | Attachment A is still part of WI 837-11-001 and was not removed as part of Errata 3. | |
| 98 | Attachment J-1 | 588-90-001 | 2.7, 2.8 and 3.1 | Errata 3 Ref. 2.7, 2.8 & 2.9 was added to that package. First issue.... Ref. 2.7 and 2.8 is a duplicate of 2.5 and 2.6. Second issue..... para 3.1 still states to accomplish the requirements of 2.2 through 2.6. This should be changed to "2.2 through 2.9". | Follow the requirements of Para 3.1 as written. |