N00024-20-R-4400 QA3_05MAR20.pdf

PDF 333 KB Posted

Attached to
N00024-20-R-4400 USS PREBLE (DDG 88) FY20 DEPOT MODERNIZATION PERIOD (DMP)
Solicitation number
N00024-20-R-4400
Issued by

About this file

This solicitation requests proposals for the USS PREBLE (DDG 88) FY20 Depot Modernization Period availability. The Naval Sea Systems Command seeks a contractor capable of maintenance, modernization, and repair work for the DDG-51 class ship. The availability includes a combination of tasks over an 18-month period from September 2020 to March 2022 at the contractor's facility. Interested offerors must be registered in the System for Award Management and monitor the beta.SAM.gov site for solicitation documents. Proposals are due in June 2020 and award is expected by that same month. The solicitation is competed on a coast-wide basis and is not set aside for small businesses.

View the file

Other files

File Type Posted
CDRL A012 Enclosure (1) MAR20.pdf PDF
N00024-20-R-4400_A0004_Conformed.pdf PDF
CDRL A015 Enclosure 2 (Template) MAR20.xlsx XLSX spreadsheet
CDRL A015 Performance Report MAR20.pdf PDF
N00024-20-R-4400_A0004_SF 30.pdf PDF
CDRL A015 Enclosure 1 (BLK 16) MAR20.pdf PDF
N00024-20-R-4400_A0003_SF 30.pdf PDF
Attachment S-6__VATEP - Rev1.xlsx XLSX spreadsheet
Attachment J-3 PREBLE Milestones (INSERT OFFEROR NAME) rev5 20200114.xlsx XLSX spreadsheet
Attachment J-4 PREBLE Pricing Workbook Rev 2 (INSERT OFFEROR NAME) 20200210.xlsx XLSX spreadsheet
Attachment S-4 Manpower Performance_clp (reduced).xlsx XLSX spreadsheet
N00024-20-R-4400-0002 (CONFORMED).pdf PDF
Attachment J-4 PREBLE Pricing Workbook Rev 1 (INSERT OFFEROR NAME) 20200210.xlsx XLSX spreadsheet
N00024-20-R-4400-0002.pdf PDF
N00024-20-R-4400 Q&A#2_20FEB20.pdf PDF
N00024-20-R-4400 Q&A#1_30JAN20.pdf PDF
Attachment S-5_Eligibility_Criteria_Data_Sheet Rev 1.docx DOCX document
N00024-20-R-4400-0001.pdf PDF
N00024-20-R-4400-0001 (CONFORMED).pdf PDF
Attachment S-3_BQ_PPI.xlsx XLSX spreadsheet
Attachment S-6__VATEP.xlsx XLSX spreadsheet
Attachment S-2_PP_CPARS_Reference_List.docx DOCX document
Attachment S-9_Past_Performance_Questionnaire.docx DOCX document
Attachment S-8_Pier_and_Drydock_Graphical_Representation_Template.xlsx XLSX spreadsheet
Attachment S-4 Manpower Performance.xlsx XLSX spreadsheet
Attachment J-7 Schedule Model Review.docx DOCX document
Attachment S-5_Eligibility_Criteria_Data_Sheet.docx DOCX document
N00024-20-R-4400.pdf PDF
Attachment S-1_Manpower_Utilization_Data_Sheet.xlsx XLSX spreadsheet
Attachment S-7 Proposal Assessment PRB.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: N00024-20-R-4400 Phone TPPC USS PREBLE (DDG 88) Zachary Tucker, Contract Specialist, zachary.m.tucker@navy.mil 202-781-4234

Erica Fetter, Contracting Officer, erica.fetter@navy.mil 202-781-3421

Q # Work Item No. Document Number/Title Question Government Response Solicitation ∆

66 482-00-001

Ref 2.2 472-7498087 Rev Q, DDG 51 Class Baseline

Configuration 1-2 Installation Details

Special Coating Materials

Paragraph 3.1 states, "Accomplish the requirements of 009-78 of 2.1 for installation of Passive Countermeasure System (PCMS) for the location listed in 1.2, using 2.2 for guidance, and material listed in 5.3.

Note 4.2 states, "Reference 2.2 is a Controlled Drawing. The pertinent portions for the equipment being worked are sheet 5 of 21 Tiles R,S,T sheet 11 of 21 Tiles AP,AR,AS and sheet 12 of 21 Tiles AU,AW,AX. The applicable portions of the drawing for the equipment being worked are available upon request from the Point of Contact:

Allen A. Smith

Email: allen.a.smith@navy.mil" The contractor reviewed Attachment J-2 Reference CD -ROMs (2 EA) received on Thu

01/23/20 @ 0948 noting that reference 2.2 file "7498087_Q.pdf" was provided, but when trying to open the document it was found that it is protected and requires a Document Open

Password.

1) Will an unlocked copy of file 7498087_Q.pdf be provided?

- or -

2) Must the contractor request the unlocked copy of reference 2.2 directly from Allen A.

Smith as detailed in Note 4.2?

Correct POC will be added in Errata 8. The POCs below for PCMS on the West Coast are as follows. Request references from them:

San Diego area:

Jose Aguayosantiago, SWRMC Code242

Phone: (619) 519-2737 Email: jose.aguayosantiago@navy.mil

James Hardy, SWRMC Code 242 Phone: (619) 556-0125

Email: james.g.hardy.ctr@navy.mil

Seattle/Portland area:

Jeff Kirk, IMF Everett, WA, Code 210.2 Phone: (425) 304-5421

Email: jeffery.kirk@navy.mil

Errata 8

Pre-Proposal Information (PPI) Question and Government Responses #3

The following are answers to questions received from potential offerors.

The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

To request references, drawings, RLARs, and Erratas being provided under this Solicitation Question & Answer Set, please contact Zachary Tucker at zachary.m.tucker@navy.mil and Erica Fetter, erica.fetter@navy.mil.

65 N/A Solicitation #: N00024-20- R-4400-0001

• Page 116 of 228, Section C, Paragraph 1.11, states, "For all generated RCCs and GMRs the contractor shall provide a Change Order Price Analysis (COPA) proposal to the ACO within three (3) calendar days (See CDRL A002).”

• Page 209 of 228, Section L, V. Proposal Content, B. Volume II, 2. Factor 2 - Resource

Capacity & Schedule, Paragraph (4)(b)(i), states, “The Government considers the use of overtime to increase the risk of unsuccessful contract performance.”

To meet the 3 calendar day COPA requirement, Contractors will be forced to expend overtime, and in some cases, double time to comply with the requirement as written; yet the Government considers the use of overtime to increase the risk of unsuccessful contract performance. The Contractor also wishes to note that Subcontractors, many small businesses, operate with limited resources but will be subject to overtime and double time impacts from such a swift turnaround. This includes impacts to support during multiple holidays within the 550 day availability duration

1) In order to depressurize COPA turnaround, the Contractor requests the requirement be changed from “(3) calendar days” to “(3) business days”. Doing so will mitigate risk by reducing usage of overtime, limit delays, and still allow the Government sufficient time to appropriately adjudicate COPAs.

Contractor's request acknowledged. The requirement will remain unchanged.

67 980-90-004 Ship Alt AIT Support Service; Proivde

The GFM ship alt kit listed in paragraph 5.3 does not detail what material is going to be delivered to contractor's facility via paragraph 3.24.

Please provide the GFM information so contractor knows extent of support needed for paragraph 3.24.

Please contact Zachary.M.Tucker@navy.mil for 4720/3-DDG88-FY20-A-7.

68 243-11-001 Bulkhead Shaft Seal

Emergency Clamp Ring;

repair

The OEM listed in 1.3 for the requirements of paragraph 3.1 responded the contractor with a "no bid", stating "Mide will not be bidding on 243-11-001 in its current state, as we do not want to be bound by an inaccurate work item since the costs associated with the stated work will likely not match what is actually required at this seal location. With that being said, I fully expect the Project Manager, Mr. Casey Bressem, to issue a new work item, 243- 11-002, that better reflects the required work associated with the bulkhead seal at frame

254 on the STBD shaft aboard the PREBLE."

Will a new item be issued? if not please provide direction.

Work item 243-11-001 is cancelled via errata 6. No new work item will be issued as scope of work will be accomplished during upcoming CMAV.

69 631-41-001 N/A

Paragraph 3.6 states, "Accomplish the requirements to manufacture, fit, and install with new the deck+D82:D111+D82:D84 scuppers removed as interference in 1.2 using 2.5 for material and manufacturing requirements."

Paragraph 1.2 does not provide a quantity, size, or type (A, B, C, D, E, F, G, and Rubber) of scuppers to be removed as interference and paragraph 2.5 only identifies the types of scuppers and associated parts list but does not include per ship quantities.

1) Please provide the quantity, size, and type of each scupper to be manufactured as directed by paragraph 3.6.

Approx. 25 EA rubber type scuppers to be used for bidding purposes. Template exact size, configuration, and location from existing shipboard conditions.

70 512-90-002 N/A

Paragraph 3.1.1 states, "Work to be completed in accordance with schedule provided in Attachment A."

Contractor has reviewed ALL received documentation and is unable to locate the referenced Attachment A.

1) Please provide Attachment A referenced in paragraph 3.1.1.

This is a work spec error.

Paragraph 3.1.1 has been deleted via Errata 10 Errata 10

71 482-90-001 (E1) N/A

Paragraph 3.1 states, "Accomplish the requirements of 2.2 through 2.6, using 2.28 guidance and material provided in 5.3. (E1)

Paragraph 2.5 identifies, "482-8826003 Rev A, ShipAlt DDG-51-81961 TTWCS V5.4.0.2 Consolidated Elec Dwg and ML" (E1)

Paragraph 2.29 identifies, "4720-DDG88-FY20, Ship Alteration Material Summary (4720/3)"

Contractor has reviewed reference 2.5 noting that the Material List has (26 EA) items listed as HSC (HARDWARE SYSTEMS COMMAND) for sourcing, but they are not found on reference

2.29 (Kitted Material for ShipAlt 81961K and ShipAlt 85114K) as identified in paragraph 5.3.

1) Is the material identified in reference 2.5 Material List which show HSC (HARDWARE SYSTEMS COMMAND) in the source column to be provided as GFM?

4720/3 has been released at A-7 (14FEB). All material listed as GFM/ HSC in reference drawings to be provided.

Please contact Zachary.M.Tucker@navy.mil for 4720/3-DDG88-FY20-A-7.

72 N/A Solicitation #: N00024-20- R-4400-0001

Page 206 of 228, Factor 2, Sub-factor A, Paragraph 1(a) – Attachment S-4

The requirement is for the Attachment S-4 data to be completed for all discrete commercial, ship repair and new construction projects that are on-going or completed within the proposed shipyard and within the local Naval Station, if the shipyard is within the homeport area or fleet concentration area between 22 April 2019 and 27 December 2019.

1) There is no requirement to submit or retain all the required S-4 data for non-U.S. Navy CNO Availabilities. Please clarify if there was no requirement for this data to be generated during the contract execution, these projects are not required to be captured on the Attachment S-4, such as CMAVs.

All projects includes all "non-U.S. Navy CNO Availabilities" and CMAVs. There are three components to this requirement,

1) Actual Manning,

2) Planned Manning and

3) Planned Manning.

The Government assumes that the offeror has record of Actual Manning provided in support of projects between 22 April and 27 December 2019. As such, the Government interprets this question as focused on planned and earned manning requirements of Attachment S-4. For availabilities in which no planned manning schedules were developed by ther offeror, future manning plans may be estimated by the offeror. The offeror shall explain any assumptions in this estimating process. In this context, "future manning" is defined as availability requirements to be completed after the release date of the subject solicitation. Historical planned and earned manning requirements for "non-US Navy CNO Availabilities" and CMAVs may be assumed to be equivalent to Actual Manning on the S-4, if no plan was developed in the execution of the availability.

73 N/A Solicitation #: N00024-20- R-4400-0001

Page 206 of 228, Factor 2, Sub-factor A, Paragraph 1(a) – Attachment S-4

The requirement is for the Attachment S-4 data to be completed for all discrete commercial, ship repair and new construction projects that are on-going or completed within the proposed shipyard and within the local Naval Station, if the shipyard is within the homeport area or fleet concentration area between 22 April 2019 and 27 December 2019.

1) Please confirm that the data reporting period for the Attachment S-4 commences on 22 April 2019 and extends to the latest forecasted completion date for any projects that were on-going or completed between 22 April 2019 and 27 December 2019. Therefore, no data prior to 22 April 2019 is required.

The offeror shall provide information for all projects, including all discrete commercial, ship repair and new construction projects, that are completed, awarded, on-going, or proposed (including the proposal for the USS PREBLE DMP) between the week ending 26 April 2019 and the Contract Complete date of this solicitation, from the Contract Start and Actual / Forecast Start Dates to the Contract Completion and

Actual / Forecast Completion Dates for each project.

74 N/A Solicitation #: N00024-20- R-4400-0001

Page 206 and 207 of 228, Factor 2, Sub-factor A, Paragraph 2, 2(b), 2(c) – Total Manpower Curves

The Paragraph 2 requirement states “All curves provided shall span the date of this solicitation [17 Jan 2020] through the “Contract Complete” date…”

The Paragraph 2(b) and 2(c) requirements state “This chart shall commence at the start of the earliest project included in the offeror’s S-4 and continue through the completion of this solicitation’s “Contract Complete” date.”

1) These requirements seem to be in conflict. Please clarify if the curves shall commence on the date of the solicitation (17 Jan 2020), the start of the evaluation period (22 April 2019), or the start of the earliest project included in the offeror’s Attachment S-4.

Section L has been revised. The offeror shall provide the Manpower Curves representing the EAC and Actual / Forecasted Start & Completion Dates of each project as presented in attachment S-4 A0003

75 N/A Solicitation #: N00024-20- R-4400-0001

Page 206 of 228, Factor 2, Sub-factor A, Paragraph 2– Total Manpower Curves

The requirement states that the curves “shall show correlated manning values across all curves.”

1) Please define what is required for “correlated manning values across all curves.”

Section L has been revised to remove this sentence. A0003

76 N/A Solicitation #: N00024-20- R-4400-0001

Page 206 and 207 of 228, Factor 2, Sub-factor A, Paragraph 2, 2(a), 2(b), 2(c) – Total Manpower Curves

The Paragraph 2 requirement states “The Offer shall provide three (3) Manpower Curves (Total) in accordance with the requirements detailed in CDRL A012 that graphically delineate the resources tied to each individual ship availability in men-per-day.

The Paragraph 2(a), 2(b), and 2(c) requirements state the curves shall show the “total FTE resources.”

1) These requirements seem to be in conflict, as individuals may accomplish >1.0 FTEs per day. Please clarify if the curves shall be represented in “men-per-day” or “FTEs-per-day.”

Section L has been revised to remove all references to men per day. The S-4 and manpower curves shall be provided in FTE.

A0003

77 N/A Solicitation #: N00024-20- R-4400-0001

Page 207 of 228, Factor 2, Sub-factor A, Paragraph 2(c)* – Total Manpower Curves

The requirement states, “Provide a calculations translation as part of the required excel tables.”

1) Please define what “calculations translation” is required.

Section L has been revised to remove this sentence. A0003

78 N/A Solicitation #: N00024-20- R-4400-0001

Page 207 and 208 of 228, Factor 2, Sub-factor A, Paragraph 3, 3(b), 3(c) – Trade Manpower Curves

The Paragraph 3 requirement states “All curves provided shall span the date of this solicitation [17 Jan 2020] through the “Contract Complete” date…”

The Paragraph 3(b), 3(c), and 3(d) requirements state “This chart shall commence at the start of the earliest project included in the offeror’s S-4 and continue through the completion of this solicitation’s “Contract Complete” date.”

1) These requirements seem to be in conflict. Please clarify if the curves shall commence on the date of the solicitation (17 Jan 2020), the start of the evaluation period (22 April 2019), or the start of the earliest project included in the offeror’s Attachment S-4.

Section L has been revised. The offeror shall provide the Manpower Curves representing the EAC and Actual / Forecasted Start & Completion Dates of each project as presented in attachment S-4 A0003

79 N/A Solicitation #: N00024-20- R-4400-0001

Page 207 of 228, Factor 2, Sub-factor A, Paragraph 3 – Trade Manpower Curves

The requirement states that the curves “shall show correlated manning values…across all curves.”

1) Please define what is required for “correlated manning values… across all curves.”

Section L has been revised to remove this sentence. A0003

80 N/A Solicitation #: N00024-20- R-4400-0001

Page 207 and 208 of 228, Factor 2, Sub-factor A, Paragraph 3, 3(a), 3(b), 3(c) – Trade Manpower Curves

The Paragraph 2 requirement states “The Offer shall provide three (3) Manpower Curves (Trade) in accordance with the requirements detailed in CDRL A012 which graphically delineates the resources tied to each trade in men-per-day.

The Paragraph 3(a), 3(b), 3(c), and 3(d) requirements state the curves shall show the “trade FTE resources.”

1) These requirements seem to be in conflict, as individuals may accomplish >1.0 FTEs per day. Please clarify if the curves shall be represented in “men-per-day” or “FTEs-per-day.”

Section L has been revised to remove all references to men per day. The S-4 and manpower curves shall be provided in FTE.

A0003

81 N/A Solicitation #: N00024-20- R-4400-0001

Page 208 of 228, Factor 2, Sub-factor A, Paragraph 3(d)* – Total Manpower Curves

The requirement states, “Provide a calculations translation as part of the required excel tables.”

1) Please define what “calculations translation” is required.

Section L has been revised to remove this sentence. A0003

82 N/A Solicitation #: N00024-20- R-4400-0001

Page 208 of 228, Factor 2, Sub-factor A, Paragraph 4(a)(i) – Narrative

The RFP states, “Inefficiencies” are defined as cumulative actual man days completed (ACWP) less than the cumulative baseline man day budget for that work completed (BCWP).

1) This definition seems to be in error; an ACWP less than the BCWP would be reflective of efficient work accomplishment. Please clarify.

The Offeror is correct. The Government has revised this sentence to say:

“Inefficiencies” are defined as cumulative actual man days completed (ACWP) greater than the cumulative baseline man day budget for that work completed

(BCWP).

via Amendment 0003.

A0003

83 N/A Solicitation #: N00024-20- R-4400-0001

Page 209 of 228, Factor 2, Sub-factor A, Paragraph 4(b)(i) – Overtime

The RFP states, “The Government considers the use of overtime to increase the risk of unsuccessful contract performance.

1) Please provide the percentage of overtime use that demonstrates increased risk of unsuccessful contract performance to the Government.

The Government has deleted the sentence "The Government considers the use of overtime to increase the risk of unsuccessful contract performance." via Amendment

0003.

A0003

84 N/A Solicitation #: N00024-20- R-4400-0001

Page 210 of 228, Factor 2, Sub-factor C, Paragraph c(1) – IPS

The RFP states, “The format in CDRL A012 shall be used as the template for IPS submissions.”

CDRL A012 outlines the requirements for IPS submissions at 30 days after the contract award.

1) Please confirm that the IPS for this proposal submission does not require BCWS and BCWP columns, a holiday calendar, nor the IPS native software format.

The IPS for this proposal submission does not require BCWP and ACWP columns.

BCWS, holiday calendar, and IPS native software format are requirements of the proposal submission. BCWS is already required to in order to provide the Manpower Curves of Sub-factor A, Para 3.

85 N/A Solicitation #: N00024-20- R-4400-0001

Page 211 of 228, Factor 2, Sub-factor C, Paragraph 2(b) – IPS

The RFP states, “Review their schedule in accordance with the Schedule Metrics provided in Defense Contract Management Agency (DCMA) Earned Value Management System (EVMS)

Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1, October 2012, Section 4.0. In accordance with the DCMA instruction, the Contractor shall calculate the 14 required metrics and explain any flags or areas of concern.

1) Late erratas and amendments will hinder the completion of this requirement. The offeror requests time extensions to be granted with errartas and amendment that affect the IPS.

The proposal due date has been extended to 23 March 2020, 1900 local time, Washington DC via Amendment 0003.

A0003

86 115-90-001 (BQ-012) 4720-DDG88-

FY20-A11 dated 10.21.19

There is no 4720 identified in paragraph 2. REFERENCES, there is no GFM Kitted Material identified in paragraph 5.3, but reference 2.6 "RLAR 82746/DDG88/1175224, Revise Sourcing

From GFM to IAF" dated 04.11.19 is identified.

Review of reference 2.6 notes that only Item No. 301 was changed from GFM to IAF

Review of (BQ-012) 4720-DDG88-FY20-A11 dated 10.21.19 provided with Amendment 0001 on 01.30.20 notes that pages 146 thru 148 of 259 identifies numerous items for ShipAlt

DDG51-82746K, Reference 2.2 115-8570330 Rev D to be provided as GFM.

1) Will the specification be revised through an Errata to add reference 4720-DDG88-FY20-A11 dated 10.21.19 to paragraph 2.# and will the Kitted Material for Shipalt 82746K be added to paragraph 5.3?

Reference 4720-DDG88-FY20 has been added to work item via Errata 10 Errata 10

87 N/A Specification Package

TPPC-DDG88-SWRMC20-

CN01

• Addendum 01 added (2 EA) new work items: 643-11-001 and 644-11-003.

• Errata 01 revised (25 EA) work items: 113-11-001, 163-11-002, 243-11-004, 243-12-002, 251- 30-001, 256-11-001, 262-90-001, 411-90-001, 411-90-002, 437-90-001, 438-90-001, 438-90-002, 456-90-001, 456-90-002, 472-90-001, 482-90-001, 484-90-001, 512-90-001, 520-11-001, 541-90-

001, 583-90-001, 651-90-001, 721-90-001, 857-11-001, and 992-11-014.

• Errata 02 cancelled (1 EA) work item: 857-11-002

• Errata 04 revised (4 EA) work items: 472-90-001, 634-11-001, 980-90-021, and 992-11-018.

But, the contractor notes that Errata 03 has not yet been provided.

1) Please provide Errata 03 documentation to the specification package.

Please contact Zachary.M.Tucker@navy.mil for Errata 3.

88 N/A Attachment J-3 Execution

Milestones and Key Event Dates R3 01.14.20

The contractor has reviewed Attachment J-3 Execution Milestones and Key Event Dates R3

01.14.20 (PERL tab) and notes that only lists (417 EA) but the J-1 Specification Package TPPC- DDG88-SWRMC20-CN01 with Addendum 01, Errata 01, Errata 02, and Errata 04 lists (420 EA) work items.

The following (3 EA) work items are missing from the J-3:

• 643-11-001 “Berthing Habitability Project Installation; accomplish”, Added by Addendum

• 644-11-003 “Sanitary Habitability Project Installation; accomplish”, Added by Addendum

• 857-11-001 “Temporary Duty Section Berthing and Messing Off-Ship; provide”, Provided with the Basic and the title was revised by Errata 01

1) Will a revised Attachment J-3 Execution Milestones and Key Event Dates be issued which includes the (3 EA) missing work items identified above on the (PERL tab)?

Attachment J-3 has been revised via Amendment 0003.

Please contact Zachary.M.Tucker@navy.mil for attachment.

89 N/A Attachment J-4 Pricing Workbook 01.15.20

The contractor has reviewed Attachment J-4 Pricing Workbook 01.15.20 and notes that only lists (417 EA) but the J-1 Specification Package TPPC-DDG88-SWRMC20-CN01 with

Addendum 01, Errata 01, Errata 02, and Errata 04 lists (420 EA) work items.

The following (3 EA) work items are missing from the J-4:

• 643-11-001 “Berthing Habitability Project Installation; accomplish”, Added by Addendum

• 644-11-003 “Sanitary Habitability Project Installation; accomplish”, Added by Addendum

• 857-11-001 “Temporary Duty Section Berthing and Messing Off-Ship; provide”, Provided with the Basic and the title was revised by Errata 01

1) Will a revised J-4 Pricing Workbook 01.15.20 be issued which includes the (3 EA) missing work items identified above?

Attachment J-4 was revised via Amendment 0002 to include referenced work items.

Please contact Zachary.M.Tucker@navy.mil for attachment.

A0002

91 492-60-001 Visual Landing Aids Line-up Light Fixture; replace

Para 3.2.3.1. states "Accomplish nondestructive testing in accordance with Line 8."

Is (RT) a typo? (UT) will satisfy the installation requirements.

Please advise

Concur with Contractor.

Work Item has been revised via Errata 10 to change language in Para. 3.2.3.1 to read the following:

"Accomplish nondestructive testing in accordance with Line 10."

Errata 10

92 980-90-002 Ship Alt AIT Support Service; Proivde

The GFM ship alt kit listed in paragraph 5.3 does not detail what material is going to be delivered to contractor's facility via paragraph 3.13.

Please provide the GFM information so contractor knows extent of support needed for paragraph 3.13.

All material listed in 5.3 will be delivered to contactor's facility per 3.13.

634-11-010 and 634-11-016

N/A

• Paragraph 3.2 states, "Accomplish the requirements of 009-26 of 2.1, including Attachment C, for the entire space located in 1.2.2."

• Paragraph 3.2.1 states, "Accomplish the requirements of 009-32 of 2.1, including Table 3, Line One, Columns A and D for each deck surface location listed in 1.2.2, including up each adjacent vertical surface intersecting the deck up to one inch above the complete deck covering system level."

• Paragraph 1.2.2 states, "Barber Shop (3-346-2-Q)"

• Paragraph 3.1 states, "Accomplish the requirements of 009-26 of 2.1, including Attachment C, for removal of existing and installation of new deck covering system in each location listed in 1.2."

• Paragraph 3.1.1 states, "Accomplish the requirements of 009-32 of 2.1, including Table 3, Line 6, Columns A and B for surface preparation of each deck surface located in 1.2, including up each adjacent vertical surface intersecting the deck up to one inch above the complete deck covering system level."

• Paragraph 1.2.3 states, "Barber Shop (3-346-2-Q)"

1) Barber Shop (3-346-2-Q) has 009-26 being accomplished by (2 EA) work items, will an Errata be issued to correct this duplication of effort? The contractor recommends that work items 634-11-016 be revised to delete paragraph 1.2.3.

Concur with Contractor on duplicate scope of work and recommendation.

Work Item has been revised via Errata 10 to remove 1.2.3 from 634-11-016.

Errata 10

93 482-90-001 Ship Alt DDG- 51-81961K and DDG-51-85114K

Paragraph 3.1 states “Accomplish the requirements of 2.2 through 2.6, using 2.27 for guidance and material provided in 5.3.”

Contractor has reviewed the 4720 GFM ship alt kit in paragraph 5.3 and it states, “NO DRAWINGS FOUND FOR DDG 88 ALT SA 85114K.”And “NO DRAWINGS FOUND FOR DDG 88

ALT SA 81961K."

Reference 2.3 and 2.5 contain material on the BOM, which states it is GFM source.

Please clarify if any material is going to be provided GFM on this ship alt.

Please contact Zachary.M.Tucker@navy.mil for 4720-DDG88-FY20 A-7.

94 581-11-001 Anchor and Anchor Chain (inspect and preserve)

Paragraph 3.10 is directing to replace each detachable link in place of those found defective as a result of measurements and tests of 3.6.3 then it continues indicating specific quantities and parts (8 each detachable links; 3 each chain, stud links; 2 each shackles).

Is the customer directing us to purchase and replace those parts prior to accomplishing 3.6.3?

Please advise

Materials purchased per 3.10 will be installed based on conditions found in 3.6.3, parts not required will be turned over to SUPERVISOR for the ship.

95 120-11-007, 123-43-001

Structural Repair;

accomplish

Overhead Longitudinal;

repair

Both items have similar scope of work in the approximate same location. Is this duplicate

SOW.

Please advise

Concur with Contractor, duplicate scope of work.

Work item 120-11-007 has been cancelled via Errata 10.

Errata 10

96 721-31-001 Reference: 2.4 VLS-5982374. Contractor was unable to open this drawing.

Please provide readable copy.

Please contact Zachary.M.Tucker@navy.mil for reference.

97 721-31-001 Identification: 1.3.4.1, 1.3.5, 1.3.6, 1.3.7.

Please provide what type of gaskets and quantity needed.

IAW Para 3.10.1 gaskets shall conform to category D-2 of 2.4. Quantity of gaskets to coincide with quantity of valves being replaced in 1.3.4.1, 1.3.5, 1.3.6 and 1.3.7.

98 721-31-001 Para: 3.11.3 through 3.11.3.1.

Please provide quantity needed.

Please contact Zachary.M.Tucker@navy.mil for reference.

One EA filter.

99 256-80-001 Ship Alt DDG-51-64250D

Paragraph 3.1 states “Accomplish the requirements of 2.2 through 2.6, using material provided in 5.1.”

Contractor has reviewed the 4720 GFM ship alt kit in paragraph 5.3 and it states, “NO

DRAWINGS FOUND FOR DDG 88 ALT SA 64250.”

Reference 2.2 contain material on the BOM, which states it is GFM source.

Please clarify if any material is going to be provided GFM on this ship alt.

Please contact Zachary.M.Tucker@navy.mil for 4720-DDG88-FY20 A-7.

100 484-90-001 Ship Alt DDG-51-92831K

Paragraph 3.4 states “Accomplish the requirements of 2.2 through 2.6, using 2.7 for guidance and material provided in 5.3.”

Contractor has reviewed the 4720 GFM ship alt kit in paragraph 5.3 and there is no GFM listed in the reference.

References to be acomplished contain material on the BOM, which states it is GFM source.

Please clarify if any material is going to be provided GFM on this ship alt.

Please contact Zachary.M.Tucker@navy.mil for 4720-DDG88-FY20 A-7.

Solicitation Section L, V, B, 2, a)

The solicitation for this fixed priced contract calls for offerors to submit proprietary performance information including ACWP and ETC from both Navy and non-Navy fixed priced contracts not associated with this solicitation. Please amend the proposal instructions to remove this instruction or provide clarification on what basis this is considered an appropriate request.

This information is a requirement of the contract.

101 721-90-001 Ship Alt DDG-51-85964K

PART 1:

Paragraph 3.2 states “Accomplish the requirements of sheet 10 through 13 of 2.2 in each loaction listed in 1.2. using material provided in 5.3.”

Contractor has reviewed the 4720 GFM ship alt kit in paragraph 5.3 and there is no GFM listed in the reference.

References to be acomplished contain material on the BOM, which states it is GFM source.

Please clarify if any material is going to be provided GFM on this ship alt.

PART 2:

The GFM ship alt kit listed in paragraph 5.3 does not detail what material is going to be delivered to contractor's facility via paragraph 3.5.

Please provide the GFM information so contractor knows extent of support needed for paragraph 3.5.

Part 1 - Please contact Zachary.M.Tucker@navy.mil for 4720-DDG88-FY20 A-7.

Part 2 -All material listed in 5.3 will be delivered to contactor's facility per 3.13.

Solicitation Section L, V, B, 2, a)

The proposal instructions include highly burdensome requests for manpower data for a time period not associated with performance of this solicitation. Please amend the proposal instructions to remove this instruction or provide clarification on what basis this is considered an appropriate request.

This information is a requirement of the contract.

104 CDRL A012

CDRL A012 calls for offerors to submit proprietary performance information including ACWP and ETC. Please amend the CDRL to remove this instruction or provide clarification on what basis this is considered an appropriate request.

This information is a requirement of the contract.

Solicitation Section C, para 1.4.3, CDRL A012, and CDRL A015

The requirements in paragraphs 1.4.3.1, 1.4.3.1.1, CDRL A012, and CDRL A015 to constrain production budgets to the J-4 values and only report production hours as defined by Section

B, Note B represent an irreconcilable conflict with the contractor’s existing performance management system and cost accounting system. In order to produce the reports the

Government desires, an entirely new and separate reporting process must be developed and staffed at a significant expense. Given that these reports are solely for the Government and of no value or utility to the contractor in the actual performance of the work, please remove these requirements from the solicitation.

The Government has revised the SOW to remove section 1.4.3 in its entirety via Amendment 0003.

A0003

106 CDRL A015

Please remove CDRL A015 from the solicitation as it is both highly burdensome and inappropriate for this type of contract This information is a requirement of the contract.

107 CDRL A015

This report is highly burdensome to produce yet calls for a weekly submittal whereas on cost-type contracts it is only a monthly submittal. Please remove CDRL A015 from the solicitation.

This information is a requirement of the contract.

Solicitation Section C, paragraph 1.11

Paragraph 1.11 calls for contractors to provide COPAs within 3 calendar days. As this paragraph also requires contractors to provide material pricing and subcontractor quotes with the COPA, it will be substantially impossible for contractors to comply with the three calendar day requirement, particularly when the RCC/GMR is issued on a Friday or prior to a holiday. Please amend the solicitation to revise the requirements to be seven calendar days to conform with the requirements of prior solicitations.

This information is a requirement of the contract.

Section C, paragraph 3.6 and CDRL A016

Despite claiming otherwise, by requiring reporting of actual manhours and actual material cost data, this CDRL is effectively requiring contractors to inappropriately report proprietary financial data on a fixed price contract. While contractors may report the BCWP values and negotiated material amounts, since the Government already knows the negotiated contract values for the work performed, this report imposes a new burden to report data the Government already possesses. Please remove paragraph 3.6 and CDRL A016 from the solicitation.

This information is a requirement of the contract.

110 Section L, Volume 2

At numerous locations in the solicitation offerors are directed to provide manning plans and narratives discussing staffing for currently contracted work, the work in this solicitation, and “ALL outstanding proposals”. Given the uncertain nature of the competitive bidding process contractors will out of business necessity have more proposals outstanding than they expect to be awarded. Consequently, this requirement unreasonably demands offerors provide a plan to accomplish work at a level of staffing that will never be realized. Please remove this requirement from the solicitation.

This information is a requirement of the contract.

112 CDRL A015

This CDRL is clearly derived from reporting that is only appropriate on cost type contracts and contains numerous elements which are inappropriate for a fixed priced contract, such as:

i. ESTIMATED PRODUCTION HOURS FOR AUTHORIZED, UNPRICED WORK

ii. ESTIMATED PRODUCTION HOURS

iii. OVER TARGET BASELINE (OTB)/OVER TARGET

SCHEDULE (OTS)

iv ESTIMATED PRODUCTION HOURS AT COMPLETION

This information is a requirement of the contract

Solicitation Section L, V, B, 2, c), (2), (a) and Section B, Note F

Subfactor C requires offerors to “Demonstrate how the Offeror has scheduled the performance of all work items included in the Availability work package (including both Base and Option items) so as to permit the contract scope increases described in Section B, Note F (all new and growth work identified in this solicitation) without causing delay or disruption to the work required by the aforementioned work items, to any other Government contract, or to any other work in progress for the Government.” Since growth work, by its very definition, is work which must be completed in order to finish the basic scope of work, it is physically and logically impossible to complete growth work requirements without impacted to basic work requirements. Additionally, since the Government is allotting themselves 14 calendar days to review COPAs and put growth work on contract, there will at a minimum be a 14 calendar day impact to the basic work schedule regardless of the magnitude of the requirements changed by the growth work. Likewise, as new work is wholly undefined, it is logically impossible to affirm that it may be incorporated without causing delay or disruption regardless of magnitude, scope, timing, or affect upon the critical path. Finally, as at this point there is no defined scope for these growth or new work requirements, it is technically and logically impossible to determine the schedule relationships and resource requirements necessary to integrate them into the schedule. Please remove from the solicitation the demand to accomplish what is clearly impossible to affirm or perform.

The Key Events & Milestones provided in Attachment J-3 reflect the no later than milestones that must be achieved to return the vessel to the Fleet in a timely basis.

These milestones include duration margin for expected new and growth work.

The Government expects the the Offeror to schedule performance of all work items included in the Availability work package (including both Base and Option items) in their initial IMS with sufficient duration margin to absorb new and growth work without delay or disruption to the Attachment J-3 Key Events & Milestones.

113 651-90-001 (E1) N/A

• Paragraph 3.3 states, "Remove existing and install new 10 EA, (4 Foot by 8 Foot) sheet, CRES, honeycomb sheathing panels located in 1.2.1 - Crew/CPO Galley (1-191-0-Q) as designated by the SUPERVISOR."

The contractor has found that installation of CRES honeycomb (Nomex core) sheathing panels in wet spaces, as is directed by paragraph 3.3, has led to wicking of fluids into the

(Nomex core), delamination of the core from the CRES sheathing, and has a high probability of generating black mold within the panels themselves. As a "Lessons Learned" the contractor has worked with the customer to install CRES (aluminum core) sheathing panels in lieu of the (Nomex core) panels, this alleviates the risk of wicking and the subsequent delamination and mold growth potential.

1) Will the customer revise the work item thru the issuance of an Errata to replace the CRES (Nomex core) panels identified in paragraph 3.3 with CRES (Aluminum core) panels?

Work item will not be modified. Material to be as provided.

115 259-13-001 N/A

The contractor has reviewed Work Item 259-13-001 and notes that:

• Paragraph 3.1.2 states, "Schedule work to ensure that a minimum of one SSGTG is operational and available for Ship's Force use at all times during the availability."

This is a 18 month Docking availability, the contractor suspects that paragraph 3.1.2 was inadvertently copied from a CMAV availability work item template.

Bidder's Question:

1) Will the customer issue an errata to delete paragraph 3.1.2 as not required for this availability?

Work item has been revised via Errata 10 to delete Para 3.1.2 Errata 10

114 484-90-001 (E1) N/A

• Paragraph 3.4 states, "Accomplish the requirements of 2.2 through 2.6, using 2.7 for guidance and material provided in 5.3. Work to be completed in accordance with the schedule provided in Attachment A."

Attachment A is on page 7 of 7 of this work item, but it is NOT a schedule it is the list of planners who developed the work item.

• Paragraph 2.6 identifies, "512-8808795 Rev A, ShipAlt DDG-51-92831 SNLWS Incr 1 (HELIOS) HVAC Mods & ML"

The drawing is an Initial Issue it is only 3 pages long (Sheet 1, 1A, and 2) and contains (46 EA) General, (1 EA) Ripout, (1 EA) Special, and (1 EA) Test Notes but NO work requirements.

Bidder's Questions:

1) Will the customer issue an errata to revise paragraph 3.4 of the work item to delete

"Work to be completed in accordance with the schedule provided in Attachment A." or will Attachment A work item schedule be provided?

2) Will a revised reference 2.6 be issued that actually contains work scope for contractor accomplishment?

Errata 10 has removed the requirements of " Work to be completed in accordance with the schedule provided in Attachment A."

In regards to ref 2.6, currently revision B is pending. Once this drawing revision is released it will be encorporated via RCC.

112 CDRL A015

iv. ESTIMATED PRODUCTION HOURS AT COMPLETION

v. ACTUAL COST - WORK PERFORMED

vi. VARIANCE – COST

vii. AT COMPLETION – ESTIMATED

viii. AT COMPLETION – VARIANCE

Please remove CDRL A015 from the solicitation as it is both highly burdensome and inappropriate for this type of contract

This information is a requirement of the contract.

116 123-22-003 N/A

• Paragraph 1.2.1 identifies location of work as, "SS GTRB GEN Exhaust TRK (1-254-1-Q)"

• Paragraph 1.3.1 states, "Quantity (10 SF), Deck Plating Corrosion, .438 Inch Plate, MIL-S-

22698 Gr DH-36, Sheet 3-2, Detail 3-2-5A of 2.2"

• Paragraph 3.1 states, "Accomplish the requirements of 009-32 of 2.1, including Table 3, Line 22, Column A, for surface preparation of deck listed in 1.3 and located in 1.2."

The contractor notes that paragraph 3.1 directs to accomplish a "Near White Metal Blast, NACE 2/SSPC-SP 10" on (10 SF) of deck plating. The contractor suspects that the effort to accomplish a Near White Metal Blast of only (10 SF) in the confined space identified in 1.2.1 may be more efficiently accomplished as a "Power Tool Clean to Bare Metal, SSPC-SP 11

(DECKS). This could be accomplished if paragraph 3.1 referenced Table 3, Line 20, Column A.

1) Will the customer issue an errata to revise paragraph 3.1 to Line 20 as recommended above?

Work item 123-22-003 has been deleted via Errata 10. Errata 10

118 857-11-001 (E1) N/A

With the incorporated Errata 01 changes this work item is no longer identified as an (OPTION ITEM) and is not listed in Attachment J-4 dated 01/15/20, but upon review of its work scope it appears to be exclusively for bidder's outside of San Diego, CA. All requirements on this work item (Berthing and Messing) are captured under work item 992-

11-006 "Temporary Service, Equipment and Systems Test, Inspection and Repair in Contractor Plant, Barge; accomplish".

The contractor recommends that this item be annotated either within the work item and/or Attachment J-4 that it is to ONLY be priced by bidders outside of San Diego, CA.

1) Does the customer concur with the above recommendation and will an Errata be issued to revise the specification and/or will a revised Attachment J-4 be issued?

Attachment J-4 was revised via Amendment 0003.

Please contact Zachary.M.Tucker@navy.mil for attachment.

A0003

117 992-11-006 N/A

• Paragraph 1.3.1 states, "Living Barge for USS Preble (DDG-88)"

• Paragraph 3.1.3.3 states, "Install a relief valve in the supply line before the barge supply piping and set as follows: Steam at 125 PSIG."

• Paragraph 3.1.8 states, "Provide 5,000 pounds per hour of steam at 100 PSIG to the shore steam connection."

• Paragraph 3.1.8.1 states, "Install a steam pressure gauge and strainer at each shore steam connection."

• Paragraph 3.1.8.2 states, "Install an emergency cut-off valve in each steam supply line at dockside within 50 feet of the nearest gangway."

• Paragraph 3.1.8.3 states, "Each steam hose must conform to MIL-DTL-29210 or MIL-H- 18160, metal hose assemblies, for transferring steam from shore to vessel and must be insulated to prevent personnel injury.

The contractor is aware that most of the berthing barges available for use in San Diego have had the all-electric conversion accomplished and that for planning purposes the berthing barges are assigned and reserved well in advance of the availability start date.

1) Will the Personnel Berthing Barge assigned for USS Preble (DDG 88) DMP require steam services or is it all-electric?

Concur with Contractor, steam services not required.

Work item has been revised via Errata 8 to remove steam services requirements.

Errata 8

119 N/A Solicitation #: N00024-20-

R-4400-0001

Page 112 of 228, paragraph 1.1 states, "Category II NSIs are applicable when invoked and/or referenced in individual work items specified in Attachment J-1."

Attachment J-1 Specification Package No. TPPC-DDG88-SWRMC20-CN01, INDEX, CATEGORY

II. FY-20 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB

ORDER lists, “009-32 Cleaning and Painting Requirements; accomplish.”

1) Since the ship was last painted in a US Shipyard, has there been any paint applied outside of the United States?

2) If so, verify that all paint applied outside of the United States met NAVSEA Standard Item FY20 Change 2, 009-32, table 1 thru 8 requirements?

Since last being painted in US shipyard, no paint has been applied outside of US.

121 N/A Solicitation #: N00024-20- R-4400-0001

On page 129 of 228 of the RFP the Contractor notes the Governments inclusion of C-211-

H016 SPECIFICATION AND STANDARDS (NAVSEA) (OCT 20181994):

(a) Definitions.

(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).

(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.

(b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below.

None.

(End of text)

It is the Contractors understanding that all required references listed in paragraph 2 of a zero-tier specification (work item) are "first tier" references. However, when a zero-tier specification directs to use a first-tier reference as "guidance", bidders should not estimate

It is unclear what "estimate the reference" means in this context, given that the solicitation requires the pricing of work items. In accordance with the solicitation, the Government will assess price proposals in accordance with FAR 15.404 to determine reasonableness of proposed pricing based on the information contained in the Pricing Workbook.

120 N/A Solicitation #: N00024-20-

R-4400-0001

The contractor has reviewed the conformed RFP with Amendment 0001 and notes the following:

RFP Page 118 of 228, IAW Section C - Descriptions and Specifications, SCOPE OF WORK, 2.

LOCATION: paragraph 2.1 states, "The required place of performance for the Availabilities shall be the contractor’s facility." Additionally, Attachment J-3 Execution Milestones and Key Event Date R3 also identifies the first milestone as, "Avail Start at Contractor Facility." These appear to be generalized statements prepared for a coast wide bid for out of homeport (San

Diego) bidders.

The contractor has reviewed previously awarded contracts, both Coast wide and SDMAC, and notes that availabilities accomplished in the Port of San Diego start pierside at NAVSTA 32nd Street for the first 14 Calendar days. This allows the customer and ship's force time to prepare the ship to enter contractor’s facility. Activities listed are not all inclusive: Ship's Force movement to Berthing Barge and Ship's Force off-load of stores, material, and portable equipment. This also allows the contractor an opportunity to set-up temporary services; installation of staging, drain, disposal, and dewatering of specific water systems;

installation of the AN/SPY-1D Antenna Protective Covers and installation of deck protection prior to arrival in the contractor’s facility.

Bidder’s Question:

1) Can bidder's assume that if the contract is awarded to a bidder for accomplishment in the Port of San Diego, than the first 14 Calendar days will be accomplished pierside at NAVSTA 32nd Street prior to movement of the ship and berthing barge to the contractors facility?

Concur with Contractor's assumption.

122 N/A Solicitation #: N00024-20-

R-4400-0001

On page 7 of 228 the RFP states, NOTE E: SPECIAL AGREEMENT FOR CHANGES WITH A PRICE OF $25,000 OR LESS

To make administration of small dollar value growth more efficient and less costly, both parties (Government and Contractor) agree to a pre-priced value for individual growth items with an estimated price of $25,000 or less. The Contract will include a firm fixed price for growth valued at $25,000.00 or less. Zero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures, but will follow the change process.

1) In NOTE e, will the Government clearly identify changes in drawings when they have determined that "no additional work is required"?

In accordance with Note E, paragraph 1, Drawing revisions where no additional work is required is defined as an administrative or zero dollar change. Each instance of these changes will be authorized/executed by the Administering Contracting Officer following the change process.

123 Various N/A

482-90-001 (E1) “ShipAlt DDG-51-81961K and DDG-51-85114K, Tactical Tomahawk Weapons Control System (TTWCS) V5.4.0.2 and TMPC 5.0.1 Upgrade; accomplish”

Paragraph 3.7 states, “Provide a secure warehouse for 30 days prior to the start of Industrial Installation (05 Oct 2020) to end of Industrial Installation (29 Jan 2021), for storing approximately 200 Sq. ft. of Government Furnished Equipment (GFE) and Government- Furnished Material (GFM).”

980-00-002 “OrdAlt DDG51-85224K, MK41 VLS BL BMD 5.1, OrdAlt DDG51-79353K, Ablative upgrade, and OrdAlt DDG51-83746K, HSD Relocation, Alteration Installation Team (AIT)

Support Service; provide” Paragraph 3.12.1 states, “500 square feet of usable floor space.”

980-90-002 “OrdAlt DDG51-85224K, MK41 VLS BL BMD 5.1, OrdAlt DDG51-79353K, Ablative upgrade, and OrdAlt DDG51-83746K, HSD Relocation, Alteration Installation Team (AIT)

Support Service; provide” Paragraph 3.12 states, “Provide a 5,000 square feet covered, weather proof, secure/lockable warehouse facility within close proximity to the ship, for shipping and receiving, receipt inspection, crating and uncrating, asset recovery and temporary storage of AIT tools, materials and removed/relocated equipment."

980-90-024 “ShipAlt DDG51-89920K and 86222K, AN/SQQ-89A(V)15 Tech Refresh with TI-16 HW and AN/UQN-10 Next Gen Fathometer, Alteration Installation Team (AIT) Support

Service; provide” Paragraph 3.17 states, “Provide 1600 square feet of storage and transportation to and from ship/warehouse."

Paragraph 3.23 states, “Contractor must warehouse equipment until pickup/disposition.”

993-11-002 “Ship's Force Warehouse Storage Space; provide (OPTION ITEM)”

Per Section C paragraph 1.2: "The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for receipt, storage and installation of Government Furnished Material as identified in work item specifications, and for accomplishment of production work." The Contractor is responsible for storage of GFM. Specific storage requirements listed in the bidders question refer to AIT and Ships force required storage space and not GFM required by referenced drawings.

p g , the reference and only use it to aid in the development of an estimate of references that are to be accomplished.

1) Please concur or advise on this interpretation.

124 992-21-001 N/A

The contractor has reviewed Work Item 992-21-001 and all identified references noting that:

The intent of this items work scope appears to be for out of home port (San Diego) bidders.

Historically, in the port of San Diego naval vessels are typically defueled prior to arrival at the Contractors facility and are typically refueled after departing the Contractor facility.

Bidder’s Question:

1) Is this work item to be priced only by OUT of homeport (San Diego) bidders and is it be accomplished only if the contract is awarded outside of San Diego?

Concur with Contractor that this item is for out of homeport bidders.

126 992-11-012 USS Preble Q&A No. 01

(BQ-001 thru 022) 01.30.20@1229

The contractor has reviewed USS Preble Q&A No. 01 (BQ-001) received 01.30.20@1229 which questioned, "Please identify which Option items are not to be bid by out of home port

Offerors." and was answered, "Work item 992-11-012 is for in port bidders only." The contractor has reviewed Work Item 992-11-012 and notes that:

Paragraph 3.4 through 3.7 appear to direct the contractor to perform actions to prepare and move the barge out of San Diego Bay into Deep Water for an At Sea Tow and do not appear to be required for in bay movement from Naval Base San Diego to the contractors facility as directed by paragraph 3.1.

1) Does the customer concur with the contractors assessment and will an errata be issued to delete the requirements in paragraphs 3.4 through 3.7 as not required within San Diego Bay?

Para 3.5 through 3.5.3 have been deleted in Errata 10 as these are for open water towing. All other paragraphs will apply.

Errata 10

125 077-11-001

J-3 Execution Milestones and Key Event Dates R3

J-4 Pricing Workbook 01.15.20

In the port of San Diego, the South West Regional Maintenance Center (SWRMC) has historically accomplished and coordinated all facets of this work requirement with the

Contractor only…