Attachment J-3 PREBLE Milestones (INSERT OFFEROR NAME) rev5 20200114.xlsx

XLSX spreadsheet 764 KB Posted

Attached to
N00024-20-R-4400 USS PREBLE (DDG 88) FY20 DEPOT MODERNIZATION PERIOD (DMP)
Solicitation number
N00024-20-R-4400
Issued by

About this file

This solicitation seeks proposals for the USS PREBLE (DDG 88) FY20 Depot Modernization Period (DMP) availability. The Naval Sea Systems Command will execute maintenance, modernization, and repair work at a contractor's facility with DDG-51 capabilities. Interested offerors must register in SAM and monitor beta.SAM.gov for release of the solicitation and amendments. Attachments S-5 Enclosure (1), J-1 through J-5, J-8, and CDRLs are available by request. The contractor must complete all work by March 2022. Proposals are due in June 2020 and award is expected around then as well. The availability start is slated for September 2020.

View the file

Other files

File Type Posted
CDRL A012 Enclosure (1) MAR20.pdf PDF
N00024-20-R-4400_A0004_Conformed.pdf PDF
CDRL A015 Enclosure 2 (Template) MAR20.xlsx XLSX spreadsheet
CDRL A015 Performance Report MAR20.pdf PDF
N00024-20-R-4400_A0004_SF 30.pdf PDF
CDRL A015 Enclosure 1 (BLK 16) MAR20.pdf PDF
N00024-20-R-4400_A0003_SF 30.pdf PDF
Attachment S-6__VATEP - Rev1.xlsx XLSX spreadsheet
N00024-20-R-4400 QA3_05MAR20.pdf PDF
Attachment J-4 PREBLE Pricing Workbook Rev 2 (INSERT OFFEROR NAME) 20200210.xlsx XLSX spreadsheet
Attachment S-4 Manpower Performance_clp (reduced).xlsx XLSX spreadsheet
N00024-20-R-4400-0002 (CONFORMED).pdf PDF
Attachment J-4 PREBLE Pricing Workbook Rev 1 (INSERT OFFEROR NAME) 20200210.xlsx XLSX spreadsheet
N00024-20-R-4400-0002.pdf PDF
N00024-20-R-4400 Q&A#2_20FEB20.pdf PDF
N00024-20-R-4400 Q&A#1_30JAN20.pdf PDF
Attachment S-5_Eligibility_Criteria_Data_Sheet Rev 1.docx DOCX document
N00024-20-R-4400-0001.pdf PDF
N00024-20-R-4400-0001 (CONFORMED).pdf PDF
Attachment S-3_BQ_PPI.xlsx XLSX spreadsheet
Attachment S-6__VATEP.xlsx XLSX spreadsheet
Attachment S-2_PP_CPARS_Reference_List.docx DOCX document
Attachment S-9_Past_Performance_Questionnaire.docx DOCX document
Attachment S-8_Pier_and_Drydock_Graphical_Representation_Template.xlsx XLSX spreadsheet
Attachment S-4 Manpower Performance.xlsx XLSX spreadsheet
Attachment J-7 Schedule Model Review.docx DOCX document
Attachment S-5_Eligibility_Criteria_Data_Sheet.docx DOCX document
N00024-20-R-4400.pdf PDF
Attachment S-1_Manpower_Utilization_Data_Sheet.xlsx XLSX spreadsheet
Attachment S-7 Proposal Assessment PRB.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exec Milestones (Contractural)

USS PREBLE DDG88 DMPOfferors are not to propose milestones highlighted in Orange. These milestones are calculated or fixed
Offerors are to propose values highlighted in Blue in accordance with "Notes". Entering values into the blue highlighted cells will allow the milestone spreadsheet to calculated the remaining interim milestones.
SystemMilestones (Calculated or Proposed)Work Days Prior to "Proposed Contractor Complete" MilestoneNotes
Avail Start at KTR FacilityMonday, September 14, 2020
DOCKOfferor to Propose Dock Dates IAW Specification 997-11-001
Dry Dock Reports Due (No Later Than)Sunday, December 31, 1899Reports due on the date in Column C or, if the date in Column C is on a weekend or Government holiday, due on the next Government business day following the date in Column C
2 F/O groups closed & readyERROR:#NUM!30
2 F/O groups closed & readyERROR:#NUM!20
ALL FO TANKS TURNED OVERERROR:#NUM!10
UNDOCKOfferor to Propose Undock Dates IAW Specification 997-11-001
20% Open and Inspect CFRs dueMonday, December 28, 2020Reports due on the date in Column C or, if the date in Column C is on a weekend or Government holiday, due on the next Government business day following the date in Column C
225% CONFERENCEFriday, January 29, 2021Conference to be held on the next Wednesday following the date in Column C
4050% CONFERENCEMonday, June 14, 2021Conference to be held on the next Wednesday following the date in Column C
75% CONFERENCEWednesday, October 27, 2021Conference to be held on the next Wednesday following the date in Column C
13HM&E AIT starts CTM install and connections in SWBDs, SF SWBDs and Load Centers (30 days)Tuesday, December 01, 2020338
13HM&E T/O 1 to AITMonday, February 01, 2021294
HM&E AIT work complete Turnover 1- GEDMS MG and Mesh B (includes cabling) all AITMonday, February 01, 2021294
HM&E T/O 2 to AITMonday, February 08, 2021289
HM&E AIT work complete Turnover 2Monday, March 01, 2021274
39HM&E T/O 3 to AITMonday, March 01, 2021274
HM&E AIT work complete Turnover 3Monday, March 22, 2021259
HM&E T/O 4 to AITMonday, March 22, 2021259
HM&E AIT work complete Turnover 4Monday, April 12, 2021244
HM&E T/O 5 to AITMonday, April 12, 2021244
HM&E AIT work complete Turnover 5Monday, May 03, 2021229
42HM&E T/O 6 to AITMonday, May 03, 2021229
HM&E AIT work complete Turnover 6Monday, May 24, 2021214
HM&E T/O 7 to AITMonday, May 24, 2021214-297
HM&E AIT work complete Turnover 7Wednesday, June 16, 2021197
Complete Shipyard Combat Systems Space Release Turnover #1Friday, October 22, 2021105
Complete Shipyard Combat Systems Space Release Turnover #2Friday, October 29, 2021100
Complete Shipyard Combat Systems Space Release Turnover #3Friday, November 05, 202195
21Complete Shipyard Combat Systems Space Release Turnover #4Friday, November 12, 202190
21Complete Shipyard Combat Systems Space Release Turnover #5Friday, November 19, 202185
AWS - MMSP/WDRC Cabinets for Radar Room # 3Friday, April 09, 2021245
AWS - MMSP/WDRC Cabinets for Radar Room #2Friday, April 23, 2021235
AWS - MMSP/WDRC Cabinets for CSER #2Friday, May 07, 2021225
DISCONNECT SHIP'S POWER (DEAD ELECTRIC)Monday, November 30, 2020339
RESTORE SHIP'S POWERMonday, February 22, 2021279
START SYSTEM RESTORATIONTuesday, April 20, 2021238
MCS/EC GROUND ISOLATION & SIGNAL VERIFICATION (10 WKS)Wednesday, July 28, 2021167
All Systems Restoration CompleteFriday, August 20, 2021150
EOSS VERIFICATION VISIT # 1Tuesday, September 28, 2021123
START DVSS TESTINGWednesday, September 29, 2021122
SPS -73 SAOP INSTALL (TO AIT)Monday, October 11, 2021114
MCS COMMAND & CONTROL TESTING (6 WKS)Monday, November 01, 202199
START DC SENSOR TESTINGWednesday, November 10, 202192
AHSS VENT VELOCITY TESTING Commence (2 WKS) (MSR)Wednesday, November 10, 202192
CSSE HOT CHECKS ISO/ALOTuesday, November 23, 202183
Engineering Plant Production Completion Date (PCD)Wednesday, November 24, 202182
42Combat Systems AEGIS Light Off (ALO)Tuesday, November 30, 202178-107
CANES POWER UP, SOFTWARE LOAD, AND TESTING COMMENCESTuesday, November 30, 202178
Fuel shipWednesday, December 01, 202177
CANES MIGRATION FROM BARGE TO SHIP COMPLETEMonday, December 06, 202174
Habitability Work CompleteTuesday, December 07, 202173
Commence Crew Move AboardTuesday, December 07, 202173
NAVSSI/67/73 RADAR AVAILABLE FOR IBNS TESTINGWednesday, December 08, 202172
Commence Hot Plant TestingMonday, December 13, 202169
RUDDER SWING CHECKSTuesday, December 14, 202168
DCMA (W/I 30 DAYS OF LOA)Monday, January 24, 202239
Complete Hot Plant TestingFriday, January 28, 202235
Begin LOA PrepFriday, January 28, 202235
CANES POWER UP, SOFTWARE LOAD, AND TESTING COMPLETETuesday, February 08, 202228
LOA StartTuesday, February 22, 202218
Dock TrialsTuesday, March 01, 202213
51Fast CruiseThursday, March 03, 202211
HM&E SEA TRIALS (CSST 1)Friday, March 11, 20225
Proposed Contract CompleteThursday, March 17, 2022- Offeror to Propose "Proposed Contract Complete" milestone date no later than 17 March 2022 or the 'Derived KTR Contract Complete No Later than Date', whichever is earlier.

- Proposed date must be a Government Work Day

"Proposed Contract Complete" No Later than DateThursday, March 17, 2022
"Days Completed Early" for use in the Value Adjusted Total Evaluated Price Tradeoff (VATEP) Schedule Adjustment0

CS Turnovers

USS PREBLE (DDG 88)SUPPORT SERVICES
SPACE NO.SPACE NAME60 Hz400 HzA/CECWChill WaterFM SWSDry AirHP AirLP AirRelease Date
TURNOVER 1
4-94-0-CIC & Gyro Rm #1YYYYALO -38
3-300-0-CIC & Gyro Rm #2YYYYALO -38
3-126-2-QPower Supply/Conversion RoomYYYYALO -38
3-319-0-QPower Conversion RmYYYYALO -38
4-126-0-EAuxiliary Machinery Rm #1YYYYSWSYALO -38
4-42-0-QSonar Cooling Equip RmYYYYYALO -38
03-142-2-QElectric Load Center #1YYALO -38
01-110-3-QFan Room PZ #1YYALO -38
01-126-3-QFan Room PZ #2YYALO -38
01-158-0-QFan RoomYYALO -38
01-240-01-QFan Room PZ #3YYALO -38
01-300-2-QFan RoomYYALO -38
01-338-3-QFan RoomYYALO -38
01-338-4-QFan RoomYYALO -38
03-142-3-QFan RoomYYALO -38
03-142-4-QFan RoomYYALO -38
1-78-1-QFan RoomYYALO -38
1-78-2-QFan RoomYYALO -38
2-42-2-QFan Room (SNR CONT-CSER1)YYALO -38
3-164-2-QFan RoomYYALO -38
3-362-0-QFan RoomYYALO -38
01-130-0-QCSMCYYYALO -38
TURNOVER 2
05-131-0-QDirector Equip Rm #1YYYYYALO -31
04-272-0-QDirector Equip Rm #2YYYYALO -31
03-282-0-QDirector Equip Rm #3YYYYYALO -31
06-157-0-TMast Access/Wiring TrunkYALO -31
1-126-0-CCICYYYALO -31
1-268-0-CCCS (VLS Alarms)YYALO -31
2-53-1-CCSER #1YYYYALO -31
2-126-2-CCSER #2YYYYALO -31
1-300-0-CCSER #3YYYALO -31
1-314-0-CCSER 3 AnnexYYALO -31
03-142-1-CCSER Rm #4YYYYALO -31
TURNOVER 3
03-128-0-CRadar Rm #1YYYYYYALO -24
03-142-0-CRadar Rm #2YYYYYALO -24
01-274-1-CRadar Rm #3YYYYYALO -24
03-128-1-QArray Rm #1 (Fwd Stbd)YYYYALO -24
03-128-2-QArray Rm #2 (Fwd Port)YYYYALO -24
03-158-3-QArray Rm #3/Elect WS #1AYYYYALO -24
03-158-2-QArray Rm #4/ Elect WS #1BYYYYALO -24
2-126-1-CCommunications CenterYYYALO -24
2-157-1-CRadio Transmitter RoomYYYALO -24
2-220-1-QSnap III Computer RoomYYALO -24
01-130-2-CShip Signal Exploitation SpaceYYYALO -24
2-153-2-CTomahawk Equip RmYYALO -24
04-130-0-CPilot HouseYYYYALO -24
04-150-0-CChart RoomYYALO -24
TURNOVER 4
02-299-0-CCIWS Control Rm #2YYFMALO -17
01-300-0-QCIWS Wep & Avi Ord Eqpt WSYYFMALO -17
02-(300-316) DECKCIWS MT 22ALO -17
FWD/AFT 03-05AN/SPY Arrays 5-3 A, B, C, DALO -17
06 (130-160) DECKFCS Director #1/Optical SightALO -17
05 (272-285) DECKFCS Director #2ALO -17
04 (285-297) DECKFCS Director #3ALO -31
01-(46-78) DECKWthr Deck 5" Gun MNT 51ALO -17
1-46-0-M5" Cal Ldr Drum & F/ RmYYYFMYYALO -17
2-50-2-CSonar Control RmYYYALO -17
1-18-0-QSonar Equip Rm #1YYYYYALO -17
2-18-0-QSonar Equip Rm #2YYYALO -17
3-18-0-QSonar Equip Rm #3YYYYALO -17
2-450-1-QNixie RmYYALO -17
2-458-0-QMulti Function Towed Array Winch RoomYYYALO -17
01-(78-110) DECKVLS Deck (FWD)ALO -17
2.5-78-0-MVLS Magazine #1(FWD, 32 cell)YYYFMALO -17
1-97-2-QVLS Service Interface Rm (FWD)YYFMYYALO -17
3-97-2-TVLS Access TrunkYALO -17
1-100-2-QVLS Security Station (FWD)YYALO -17
02-(335-370) DECKVLS Deck (Aft)ALO -17
2-338-0-MVLS Magazine #2 (AFT, 64 cell)YYYFMALO -17
01-330-0-QVLS (AFT) Service Interface RmYYFMYYALO -17
1-335-2-TVLS Access TrunkYALO -17
01-330-2-QVLS Security Station (Aft)YYALO -17
TURNOVER 5
02-(195-220 ) DECKSRBOC Launcher (PORT)YALO -10
02-(195-220 ) DECKSRBOC Launcher (STBD)YALO -10
03-(142-158) DECKEW Array SLQ-32 (PORT)YYYYYALO -10
03-(142-158) DECKEW Array SLQ-32 (STBD)YYYYYALO -10
02-(220-237) DECKNULKA Launchers (PORT)YALO -10
02-(220-237) DECKNULKA Launchers (STBD)YALO -10
01-(240-260) DECKSVTT (PORT)YYYALO -10
01-(240-260) DECKSVTT (STBD)YYYALO -10

HM&E Turnovers

USS PREBLE DDG88 DMP

Hull/Mechanical and Electrical (HM&E) Turnovers

EquipmentDate Contractor turnover to AITDate AIT turnover to test teamEquipment
Contractor Responsible14-Sep-20AIT Responsible
09-Nov-20SA 71726- SPS-73 ISEA Disconnect Stand Alone Operating Panel (SAOP) for relocation and engineering/field changes. ISEA to disconnect prior to Contractor rigging.
05-Nov-20SA 73091- Remove al FODMS IOUs (29 total) and ship as directed by drawing Ripout 12,13,52,73,81 and 91 foundations.
SA 71604- Start CTM install and Swbd Connections in Swbds, SF Swbds, Load Centers (SA71604) (30 days)
MSR Fuel Bank TurnoverAIT Fuel Bank Turnover
2 Fuel banks closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRsERROR:#NUM!ERROR:#NUM!Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections)
2 Fuel banks closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRsERROR:#NUM!ERROR:#NUM!Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections)
2 Fuel banks closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRsERROR:#NUM!20-Apr-21Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections)
MSR HM&E T/O 101-Feb-2101-Feb-21AIT T/O 1 GEDMS Mesh B and MG
SA 70403- Ripout Fuel Storage & Receiver Tanks Monitor Panel from Oil Lab01-Feb-21SA 73091K- All Power Sources and Terminal Boxes for Equipment in TO 1, TO 2 and TO 3 to also include new and upgraded sources.*
01-Feb-21SA 73091K-GEDMS Mesh B (BSE B1-B10) and power cables at least one power source has to be available*
01-Feb-21SA 73091K- Install GEDMS Maintenance Group. Removed MG will be shipped as directed by drawing. Install while access cut to Aft IC is open
MSR HM&E T/O 2 (Aft Strng, Repair 3 & #3 GTG)08-Feb-2101-Mar-21AIT T/O 2 (Aft Strng, Repair 3 & #3 GTG)
SA 71726- Aft Steering Unit (ASU)01-Mar-21(Power/Network/Shipside Cabling)
Repair 3 Equipment , Misc Stowages and painted iaw spec 438-90-00201-Mar-21SA 71604- RSC Repair 3, C/O SW, Speaker. Hold Keyboard for later installation per SMR direction.
SA 71726- Local Control Steering Units (LCUs 1 - 4)01-Mar-21(Power/Network/Shipside Cabling)
SA 71604- Electric Plant DIU 301-Mar-21(Power/Network/Shipside Cabling)
01-Mar-21All Power Sources & Terminal Boxes for Equipment in TO 4, TO 5 and TO 6 as per SIDs.
01-Mar-21FADC #3 (Power/Network/Shipside Cabling)
01-Mar-21SA 73091- Install IOUs: 21, 22, 23 and 62. IIUs 122, 162. C-DR 122, 141 and 162. USE-162B. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
MSR T/O 3 (CCS & Repair 5)01-Mar-2122-Mar-21AIT T/O 3 (CCS & Repair 5)
SA 71604-UCCs 1 & 201-Mar-2122-Mar-21Complete SA 71604 wiring in CCS, including vent control panels, RSC DCC, C/O SW & Speaker. Hold Keyboard, 40" Monitor & Printer for later installation per SMR direction.
SA 77419 Textile Ducting WI 512-90-002 complete01-Mar-21
CCS and Repair 5 Equipment and Misc Stowages. Painted and deck complete iaw spec 438-90-00201-Mar-2122-Mar-21SA 71604-RSC Repair 5, UPS, C/O SW and Speaker. Hold Keyboard for later installation per SMR direction.
22-Mar-21SA 70403K complete in Oil Lab, includes all cabling, connections for Oil Lab PC
22-Mar-21SA 71604- TIWS (CCS) LAN Drop & Power Outlet
22-Mar-21SA 73091- Install IOUs 32, 33, 72. IIUs 132, 172 and 173. C-DRs 132,172 and 172. USE 132B. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
MSR T/O 4 (MER 1, AUX 1 & Repair 2)22-Mar-2112-Apr-21AIT T/O 4 (MER 1, AUX 1 & Repair 2)
SA 71604-Electric Plant DIU 1 AUX 122-Mar-2112-Apr-21(Power/Network/Shipside Cabling)
SA 71604- Propulsion DIU 4 MER 122-Mar-2112-Apr-21(Power/Network/Shipside Cabling)
SA 71604- UCC 3 MER 122-Mar-2112-Apr-21(Power/Network/Shipside Cabling)
SA 71604- ECU 1A and 1B MER 122-Mar-2112-Apr-21(Power/Network/Shipside Cabling)
Repair 2 Equipment, Misc Stowages and painted iaw spec 438-90-00222-Mar-21
F/O, L/O & CRP valves associated with SA71604K in MER1. 1A/1B F/O Filt/Sep Outlet, #1MRG Pur Suct/Fill, #1CRP Pur Suct/Fill22-Mar-2112-Apr-21Electrical hook-up of valves associated with SA 71604K in MER 1
31-Dec-99FADC #1 (Power/Network/Shipside Cabling)
SA 71605 Galley foundations, piping and electrical complete that impact MER 1 overhead22-Mar-2112-Apr-21SA 71604- RSC Repair 2, C/O SW, Speaker. Hold Keyboard for later installation per SMR direction.
31-Dec-99SA 73091- Install IOUs 74, 82, 83 and 84. IIUs 174, 182 and 183. USEs 174B and 183B. C-DRs 174, 182 and 183. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
MSR T/O 5 (MER 2)12-Apr-2103-May-21AIT T/O 5 (MER 2)21
SA 71604- Electric Plant DIU 2 MER 212-Apr-2103-May-21AIT (Power/Network/Shipside Cabling)
SA 71604- Propulsion DIU 5 MER 212-Apr-2103-May-21AIT (Power/Network/Shipside Cabling)
SA 71604-UCC 4 MER212-Apr-2103-May-21AIT (Power/Network/Shipside Cabling)
SA 71604- ECU 2A, 2B MER212-Apr-2103-May-21AIT (Power/Network/Shipside Cabling)
F/O, L/O & CRP valves associated with SCD 71604K in MER2. 2A/2B F/O Filt/Sep Outlet, #2MRG Pur Suct/Fill, #2CRP Pur Suct/Fill12-Apr-2103-May-21AIT (Power/Network/Shipside Cabling)
03-May-21Install IOU 31, IIU 131 and 134, C-DR 131 and 134, USE 131B.All associated work related to these IOUs/IIUs/USEs/C-DR boxes
03-May-21FADC # 2 (Power/Network/Shipside Cabling)
SA 71604- ADACS Foundation MER 212-Apr-2103-May-21ADACS unit in MER2, including power and all hook-ups
MSR T/O 6 (71604 Potable Water)3-May-2124-May-21AIT T/O 621
Complete following under SA 71604; Potable Water System, incl Tanks, TBs, MOVs, TLIs & Modified Pump Controllers24-May-21AIT (Power/Network/Shipside Cabling)
24-May-21GEDMS Mesh A BSEs (A1-A10) and power cables at least one power source has to be available*
24-May-21Install IOUs 53, 93 and 94. IIU 194. C-DR 194. All associated work related to these IOUs/IIUs/USEs/C-DR boxes
24-May-21SA 77829K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) and associated TBs, JP-5, all electrical work complete
MSR T/O 7 (70403K, 76253K, 71604 AHSS Vent Mod)24-May-2116-Jun-21AIT T/O 7 (AHSS, DVSS, Dig Indicators)
LO Filter Separator Purifier (SA 76253K) complete24-May-21
AHSS Vent Mod SA 71604 dwg 500-8659958 complete24-May-2116-Jun-21AHSS Install Complete
Digital Fuel Control SA 70403 complete24-May-2116-Jun-21SA71615 DVSS Complete - ALL VIROEs, CJBs, Cables (*)
16-Jun-21SA 77829K 70403K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) and associated TBs, JP-5, all electrical work complete
16-Jun-21Digital Indicators SA 77427 complete except CS spaces
16-Jun-21SA 71615- Install all DVSS Cameras as directed by SMR (week prior to PCD)
16-Jun-21SA 73091-Install IOUs 14, IIUs 114, C-DRs 114. Complete all associated work related to these IOUs/IIUs/USEs/C-DR boxes
HM&E SHIPALT Equipment in Combat Systems MOD Spaces, dates are CS Turnover dates
Contractor CompleteDateDateAIT Complete
RADAR 1- SA71726 work complete05-Nov-2126-Nov-21RADAR 1- SA 71726 working complete. IBNS Rack 2 wiring including HS Firewall, UPS & C/O Switches
CIC- SA 71604 work complete29-Oct-2119-Nov-21RADAR 2- SA71726 Trigger/Video Amp installed and wired
CIC- SA71726 work complete29-Oct-2119-Nov-21CIC- SA77427 and SA71726 work complete
Array Room #1- SA71726 mods complete05-Nov-2126-Nov-21Array Room 1- SA71726 work complete
CSMC- SA 71604 work complete22-Oct-2112-Nov-21CSMC- SA73091K (BSE A5), SA 84226K and SA 71604K work complete. Hold Keyboard for later installation per SMR direction.
Pilot House- all SA 71604 mods complete05-Nov-2126-Nov-21Pilot House- all SA71604, SA77427 work complete
Pilot House- SA 71726 SPS-73 SAOP install. (ISEA deliver to SY)05-Nov-2126-Nov-21Pilot House- SA71726, SPS-73 ISEA Connectorize SAOP Ethernet SW, C/O SW & UPS
Pilot House- SA 71726 work complete05-Nov-2126-Nov-21Pilot House- SA71726 work complete. Hold Keyboard, Training Monitors, Joystick & Cables for later installation per SMR direction.
Pilot House- SA 77419 Textile ducting work complete05-Nov-2126-Nov-21Pilot House- complete all SA 77427 mods
Pilot House- Painted and deck complete iaw work item 438-90-00117-Dec-21
22-Oct-21Aft IC Gyro 3-300-0-C, SA 73091(IOU41, IIU141, CDR 17/141 and MG) and SA77427 complete.
22-Oct-21Power Supply / Conversion Rm 3-126-2-Q, SA 73091 complete
22-Oct-21Fwd IC Gyro 4-94-0-C, SA 73091(IOU51, IIU151, CDR1/151) and SA 77427 complete
29-Oct-21CSER 1 2-53-1-C, SA 73091(IOU93, CDR4) and SA 77427 complete
29-Oct-21CSER 3 1-300-0-C, SA 73091 complete (IOU42, IIU142, CDR 24/142)
29-Oct-21CSER 2 2-126-2-C, SA 73091 complete (CDR10)
05-Nov-21CIC- SA 71604 work complete including RSC, UPS & C/O Switch. Hold Keyboard for later installation per SMR direction.
12-Nov-21SONAR Control 2-50-2-C, SA 77427 complete
12-Nov-21SONAR 3 3-18-0-Q, SA 73091 complete (IOU92, CDR2/2A)
12-Nov-21SONAR 1 1-18-0-Q, SA 73091 complete (BSE A7)
05-Nov-21Communications Center 2-126-1-C, SA 73091(IOU71, CDR9) and SA 77427 complete
29-Oct-21CSER 4 03-142-1-C, SA 73091 complete (IOU 11, IIU 111, CDR 29,30, 111)
05-Nov-21Chart Room- SA 77427 and SA 71726 complete, IBNS NAV 2 computer
22-Oct-21Electric Load Center 03-142-2-Q, SA73091 complete (CDR28)
12-Nov-21XO Cabin- SA 77427 complete
12-Nov-21CO Cabin- SA 77427, 71726 complete; IBNS NAV 4 computer (CO's Laptop), install prior to HAB Turnover

PERL

USS PREBLE (DDG 88) FY 20 DMP

Planning - Event Readiness List Legend: "I" = Open & Inspect (CFR), "P" = Production Complete, "T" = Testing Complete, "C" = Certification Complete.

Work Item No. / Title GOV EST START OF AVAIL MOVE TO KTR/DOCK DOCK +30 REPORTS AVAIL 20% (O&I) 25% CONFERENCE 50% CONFERENCE UNDOCK SYSTEM RESTORATION COMP PCD ALO/STO/REFUEL 75 % CONFERENCE COMMENCE HOT PLANT TESTING HAB COMPLETE COMPLETE HOT PLANT TEST SHIP PREP LOA LOA DOCK TRAILS/FAST CRUISE HM&E and TYCOM SEA TRIALS CONTRACTOR CONTRACT COMPLETE COMBAT SYSTEM SEA TRIAL #1 COMBAT SYSTEM SEA TRIAL #2 AVAIL COMPLETE Kongdara, Tick CIV SWRMC, 321: Kongdara, Tick CIV SWRMC, 321:

Annotate Critical Path WI, Controlling WI, PCP, RTR…
WORK ITEM NO.WORK ITEM TITLEComments
042-11-001Accountability of Manhour and Material Reservation; accomplishC
042-11-002Work Package Execution Review (WPER); accomplishC
042-11-003Conditions Found Report (CFR); provide and manageC
077-11-001Fire Drill Service; provideORVIS, JAMESC
110-11-001Underwater Hull; inspect and repairIP/C
110-11-003Padeye Remnant; removeIP/C
110-11-004Damage Control Dewatering Overboard Discharge Connection; replaceLOPEZ, CHRISTOPHERIP/C
110-21-002Freeboard Plating and Appendage; inspectIP/C
113-11-001Machinery Space Bilge Drain Well; repair and preserveIP/C
115-90-001ShipAlt DDG51-82746K, Stanchion Cracking Foundation; accomplishIP/C
120-11-001Machinery Room Structural Repair; accomplishIP/C
120-11-007Structural Repair; accomplish (CANCELED)IP/C
122-20-001Bulkhead Vertical Stiffener; repairIP/C
122-21-001Auxiliary Machinery Room Number One Transverse Bulkhead; inspect and repairIP/C
123-10-001Tank and Void Cleaning and Pumping; accomplishIP/CPCP
123-11-001Compensated Fuel Tank Group One; preserve (touch up)IP/CAccess cut
123-11-002Compensated Fuel Tank Group 2; preserve (touch up)IP/CAccess cut
123-11-003Compensated Fuel Tank Group 6; repairIP/C
123-11-004Compensated Fuel Tank Group 5; preserveIP/CAccess cut
123-11-005Compensated Fuel Tank Group 6; preserve (touch up)IP/CAccess cut
123-11-006Fuel Oil Service Tank; preserveIP/CAccess cut
123-11-007Compensated Fuel Tank Group 2; preserveIP/CAccess cut
123-11-008Compensated Fuel Tank Group 5; repairIP/C
123-11-009Compensated Fuel Tank Group 4; preserveIP/CAccess cut
123-11-010Compensated Fuel Tank Group 4; repairIP/C
123-11-011Compensated Fuel Tank Group 5; preserve (touch up)IP/CAccess cut
123-11-012Compensated Fuel Tank Group One; preserveIP/CAccess cut
123-11-013Compensated Fuel Tank Group 3; preserveIP/CAccess Cut
123-11-014Compensated Fuel Tank Group One; repairIP/C
123-11-015Compensated Fuel Tank Group 2; repairIP/C
123-11-016Compensated Fuel Tank Group 3; repairROBERTS, JAMESIP/C
123-11-017Fuel Expansion Seawater Overflow Tank Group 6; preserveIP/CAccess Cut
123-11-018Tank Top Plating; preserveIP/C
123-11-019Fuel Oil Service and Gravity Head Tank; repairIP/CPCP
123-11-020Fuel Oil Gravity Head Tank; preserveIP/C
123-11-021Manhole Cover; preserveIP/C
123-12-001JP-5 Tank; preserveIP/CAccess Cut
123-12-002JP-5 Tank; repairIP/C
123-14-001Potable Water Tank; preserveIP/CAccess Cut
123-14-002Potable Water Tank; repairIP/C
123-15-001Lube Oil Tank and Sump; repairROBERTS, JAMESIP/CPCP
123-17-001Contaminated Oil Tank; repairIP/C
123-17-002Contaminated Oil Tank; preserve (touch up)IP/CAccess Cut
123-17-003Contaminated Oil Tank; preserveIP/CAccess Cut
123-19-001Waste Water Tank; preserveIP/CAccess Cut
123-19-003Waste Water Tank; repairIP/C
123-19-004Vacuum, Collection, Holding and Transfer (VCHT) Tank; preserveROBERTS, JAMESIP/CPCP, Access Cut
123-19-005Vacuum, Collection, Holding and Transfer (VCHT) Tank; repairROBERTS, JAMESIP/CPCP
123-21-001Accessible Void; repairSAMPAN, RYANIP/C
123-21-002Accessible Void; preserveIP/CAccess Cut
123-22-001Chain Locker and Chain Locker Sump; repairIP/C
123-22-002Chain Locker and Chain Locker Sump; preserveIP/CAccess Cut
123-22-003Exhaust Trunk; repair (CANCELED)IP/C
123-22-004Deck Plating; repair and preserveIP/C
123-43-001Overhead Longitudinal; repairIP/C
130-11-001Aircraft Securing Fitting; replaceIP/C
130-11-003Weapons Magazine Structure Repair; accomplishIP/C
131-11-001Overhead Structural; repairIP/C
131-11-003Deck Plating; replaceIP/C
132-11-001Deck Plating; repair and preserveIP/C
137-11-00102 Level Weather Deck; preserveIP/C
139-11-00105 Level Deck Edge Coaming; repairIP/C
142-11-001Second Platform Deck Plate; repairIP/C
150-11-00106 Level Deck Edge Plating and Mast Platform; repairIP/C
150-11-00205 Level Bliss Cap Foundation and Deck; repairIP/C
150-11-003Deck Repair; accomplishIP/C
150-11-004Weather Deck Edge Drain Trough; repairIP/C
150-11-005Auto Tilt Antenna Platform; repair and preserveIP/C
150-11-006Forward Stack 03 Level Structural Bulkhead; repairIP/C
150-11-007Helicopter Control Station Window Washer Pipe and Bulkhead; repair (OPTION ITEM)IP/C
150-11-008Deck and Bulkhead Plate; replaceP/C
150-11-00902 Level Deck; repairIP/C
150-11-010Lighting Fixture; repairIP/C
150-11-011Antenna Foundation; removeP/C
150-80-001AER DDG51-83007D, Increase Deck Plate Thickness; accomplish (partial)IP/C
152-11-001Pallet Truck Stowage/Battery Charging Room; repairP/C
153-11-002Super Rapid Blooming Off-Board Chaff (SRBOC) Launcher Deck Plate; repairIP/C
157-11-00206 Level Platform Structure and Grating; repairIP/C
161-11-001Strut; repairIP/C
161-11-002Strut; repairIP/C
163-11-001Sea Chest; inspect and repairIP/C
163-11-002Waster Sleeve; replaceIP/C
165-11-001Sonar Dome Rubber Window (SDRW); inspect and repair (OPTION ITEM)IP/C
165-11-002Sonar Dome Pressurization System Valve; replaceIP/C
167-11-001Watertight Scuttle; repairP/C
167-11-002Bolted Equipment Removal Plate (BERP); repairIP/C
167-11-004Structural Closure; repairIP/C
167-11-005Scuttle Lower Sonar Dome; repairFLETES, CARLOSIP/C
167-11-006Hatch; replaceP/C
167-11-007Watertight Closure; replaceP/C
167-11-008Cross Flooding Duct Cover Stud; installIP/CAccess Cut
167-11-009Hatch; repairIP/C
167-11-010Watertight Scuttle; replaceP/C
167-11-012Blowout Hatch; overhaul and preserveIP/C
167-80-001ShipAlt DDG51-72424D, MAFO-Holtkamp Door Installation; accomplish (partial)P/C
168-11-002Cargo Door; inspect and repairIP/C
168-11-003Structural Door; replaceP/C
168-11-004Door, Watertight, Individually Dogged; replaceP/C
168-11-005Hatch, Watertight, Raised, Quick-Acting; replaceP/C
168-12-002Pallet Truck Stowage/Battery Door; inspect and repairIP/C
171-11-001Tactical Air Navigation (TACAN) Antenna Foundation; repairIP/C
180-11-001Force Protection .50 Caliber Gun Mount and Kevlar Shield Mounting Pad; replaceP/C
234-14-001Gas Turbine Module 2B Base Enclosure; repairIP/C
234-80-001DDG-51 Class AER 66051D, Main Gas Turbine (MGT) and Gas Turbine Generator (GTG) Louver Foreign Object Damage (FOD) Screen Removal; accomplishP/CPCP
241-11-001Main Reduction Gear (MRG) Resistance Temperature Detector (RTD); replaceP/CPCP
242-11-0011A and 1B Gas Turbine Main (GTM) Synchro Self-Shifting (SSS) Turbine Clutch Assembly; replaceIP/CPCP
242-12-0012A and 2B Gas Turbine Main (GTM) Synchro Self-Shifting (SSS) Turbine Clutch Assembly; replaceIP/CPCP
243-11-001Bulkhead Shaft Seal Emergency Clamp Ring; repair (CANCELED)IP/C
243-11-002Starboard Waterborne Propulsion Shafting; install (OPTION ITEM)IP/CAccess Cut
243-11-003Starboard Propulsion Shafting; inspect and repairIP/CAccess Cut
243-11-004Starboard Stern Tube Shaft Seal; overhaulIP/C
243-12-001Port Propulsion Shafting; inspect and repairIP/CAccess Cut
243-12-002Port Stern Tube Shaft Seal; overhaulIP/C
243-12-003Port Waterborne Propulsion Shafting; install (OPTION ITEM)IP/CAccess Cut
244-11-001Starboard Outboard Propulsion Shafting Bearing Clearance Measurement; accomplishIP/CPCP
244-12-001Port Outboard Propulsion Shafting, Bearing Clearance Measurement; accomplishIP/C
245-11-001Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Starboard; repairIP/CRTR, PCP
245-11-002Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box; replaceP/CRTR
245-11-003Controllable Pitch Propeller (CPP) Starboard Hub; replaceIP/CPCP
245-11-004Controllable Pitch Propeller (CPP) Propeller Blade (Starboard); assess and repairIP/CPCP
245-11-005Number One Controllable Pitch Propeller (CPP) Standby Hydraulic Pump and Motor; overhaulIP/C
245-11-006Controllable Reversible Pitch (CRP) Flexible Hose Assembly; replaceP/C
245-12-001Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Port; repairIP/CPCP
245-12-002Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box; replaceP/C
245-12-003Controllable Pitch Propeller (CPP) Port Hub; replaceIP/CPCP
245-12-004Controllable Pitch Propeller (CPP) System Propeller Blade (Port); assess and repairIP/CPCP
245-12-005Controllable Pitch Propeller (CPP) Sump Tank; repairIP/C
251-30-001Propulsion Gas Turbine (GTRB) Air Intake Number One; repair and preserveIP/C
251-30-002Number 2A and 2B Gas Turbine Module (GTM) Clean Air Intake; inspect and repairIP/CPCP
251-31-001Air Intake and Exhaust Louver; clean and preserveIP/C
251-32-001Propulsion Gas Turbine (GTRB) Intake Number 2 and Ships Service Gas Turbine Generator (SSGTG) Intake Trunk Number 2 and 3; repair and preserveIP/C
251-32-002Gas Turbine Intake Number One; repairIP/C
256-11-001Seawater Service Butterfly Valve; replaceP/C
256-11-002Sea Water Cooling Gage Line; replaceP/C
256-61-001Number 2 Main Reduction Gear Lube Oil Cooler Drain Piping; replaceP/C
256-72-001Seawater Service Pump Resilient Mount; replaceP/C
256-80-001ShipAlt DDG51-64250D, Ship Service Gas Turbine Generator (SSGTG) Emergency Seawater Cooling System Modification; accomplishP/C
259-10-001Number 2 Gas Turbine Mixing Room, Uptake; repair and preserveIP/C
259-10-002Number One Gas Turbine Mixing Room, Uptake and Boundary Layer Infra-Red Suppression System (BLISS) Cap; repair and preserveIP/C
259-11-001Gas Turbine (GTRB) Exhaust Duct Collector; repair and preserveP/C
259-11-002Uptake Engine Room and Number 3 Ship Service Gas Turbine Generator (SSGTG) Exhaust Flange Fastener; replaceIP/C
259-13-001Gas Turbine Exhaust Duct Lagging and Insulation; replaceIP/C
259-80-001ShipAlt DDG51-76087D, Gas Turbine (GTRB) and Ship Service Gas Turbine Generator (SSGTG) Boundary Layer Infrared Suppression System (BLISS) Cap Modification; accomplishIP/C
262-10-002Main Reduction Gear (MRG) Lube Oil Flexible Hose Assembly; replaceP/C
262-11-002Lube Oil Pump Hose; replaceP/C
262-11-003Lubricating Oil System Flexible Hose; replaceP/C
262-11-005Lube Oil Temperature Regulating Valve; repairIP/C
262-12-001Lube Oil Temperature Regulating Valve; repairIP/C
262-41-001Number One Main Reduction Gear (MRG) Lube Oil Cooler; clean and inspectIP/CPCP
262-42-001Number 2 Main Reduction Gear (MRG) Lube Oil Cooler; clean and inspectIP/CPCP
262-80-001ShipAlt DDG-51-76501D Replace Engine Room Number One Reduction Gear Lube Oil Flexible Hose; accomplishP/C
262-90-001ShipAlt DDG51-76253K, Install Lube Oil Coalescing Filter; accomplishP/CPCP, RTR
264-10-001Lube Oil Purifier Flexible Hose; replaceP/C
264-31-001Lube Oil Purifier Heater Number One; clean and inspectIP/C
264-32-001Lube Oil Purifier Heater Number 2; clean and inspectIP/C
311-32-001Number 2 Ships Service Gas Turbine Generator (SSGTG) Air Inlet Duct Flexible Seal; replaceP/C
313-80-001ShipAlt DDG51-86517D, Material Handling Equipment (MHE) Battery Charger Replacement; accomplishP/C
314-31-001400 Hertz Remote Control Panel Gauge; calibrateP/CRTR
321-11-001Cableway Hanger; replaceIP/C
321-11-002Chafing Ring; reseal
321-23-001Flexible Conduit; replaceP/C
331-11-001Waterline Security Light Bracket; replace
331-11-002Lighting Distribution Box Cable; replaceP/C
343-13-001Foreign Object Damage (FOD) Screen; replaceP/C
411-11-001Cable; replace (OPTION ITEM)P/C
411-90-001ShipAlt DDG51-89804K, ACB16/TI16 OA Computing Plant; accomplishP/CCritical Path, PCP, Access Cut
411-90-002ShipAlt DDG51-89925K, AWS ACB16/TI16 CIC Display Upgrade; accomplishP/CCritical Path, PCP, Access Cut
432-11-001Sound Powered Telephone System Cable; replaceP/C
432-11-002Integrated Voice Communication System (IVCS) Cable; replaceP/C
432-14-001Integrated Voice Communication System (IVCS) Cable; replaceP/C
433-11-001General Announcing System Circuit 1MC; repairP/C
437-21-001Fuel Oil Storage Tank Level Indicating (TLI) Systems Transmitter; replaceP/C
437-21-002Tank Level Indicating (TLI) Stuffing Tube; repairP/C
437-90-001ShipAlt DDG51-77829K, Installation of Radar and Time Domain Reflectometer (TDR) Tank Level Indicator (TLI) for Diesel Fuel Marine (DFM), Jet Propellant-5 (JP-5) and Potable Water Tank; accomplish (partial)P/CRTR
438-90-001ShipAlt DDG51-71604K, DDG Mod MCS/DCS Upgrades, Single Central Control Station (CCS) Watchstander; accomplishP/CControlling Work Item, PCP, RTR, Access Cut
438-90-002ShipAlt DDG51-71726K, DDG Mod Full IBS Upgrade, Single Bridge Watchstander; accomplishP/CControlling Work Item, PCP, Access Cut
438-90-003ShipAlt DDG51-88260K, Enterprise Remote Monitor Hardware Installation; accomplishP/C
441-11-001Antenna Coupler Bolt; replaceP/C
456-90-001ShipAlt DDG51-91754K, AWS ACB16/TI16 MMSP Upgrade; accomplishP/CCritical Path, PCP, Access Cut
456-90-002ShipAlt DDG51-89769K, ACB16/TI16 Kill Assessment System (KAS) Warhead Data Receiver Cabinet (WDRC) Upgrade; accomplishP/CCritical Path, RTR, Access Cut
462-08-001DT-513/BQA-8 Hydrophone and Cable Assembly; replaceIP/C
463-89-001AN/SQQ-89 Sonar Transducer and Stave Cable Connectorized; replaceIP/C
472-90-001ShipAlt DDG51-80156K, AN/SLQ-32 (V)6 Surface Electronic Warfare Improvement Program (SEWIP) Block 2 Upgrade; accomplishP/CPCP, Access Cut
482-00-001OrdAlt 80831, BMD-MK99 KAS DDG Illuminator RAM Material; accomplishP/C
482-11-001MK 82 Mod 0, Director; replaceP/C
482-90-001ShipAlt DDG-51-81961K and DDG-51-85114K, Tactical Tomahawk Weapons Control System (TTWCS) V5.4.0.2 and TMPC 5.0.1 Upgrade; accomplishP/CAccess Cut
484-90-001ShipAlt DDG51-92831K, SNLWS Increment 1 (HELIOS); accomplishP/CPCP, Access Cut
492-60-001Visual Landing Aids Line-up Light Fixture; replaceIP/C
508-11-001Lagging and Insulation; replaceIP/C
508-11-002Auxiliary Machinery Room Number One Lagging and Insulation; replaceP/C
508-11-003Lagging and Insulation; replaceP/C
508-11-004Lagging and Insulation; replaceP/C
508-11-005Gas Turbine Exhaust Trunk Insulation and Lagging; replaceIP/C
508-11-006Insulation and Lagging Outside Machinery Space; replaceIP/CRTR
508-11-007Lagging and Insulation, Outside Machinery Space; replaceIP/CRTR
508-11-008Lagging and Insulation, Inside Machinery Space; replaceP/CRTR
508-11-009Redundant Independent Mechanical Start System (RIMSS) Exhaust Assembly Insulation and Lagging; replaceP/C
508-11-010Lagging and Insulation; replaceP/C
512-11-001Cooling Coil Unit; replace (OPTION ITEM)P/C
512-11-003Cooling Coil Unit; replaceP/C
512-11-004Supply Ventilation; replaceP/C
512-11-007Ventilation Cleaning; accomplishP/C
512-11-008Cooling Coil Unit; replaceP/C
512-11-010Exhaust Ventilation Ducting; replace
512-11-011Fan Coil Unit Differential Pressure Gauge; installP/C
512-11-012Ventilation Closure Teleflex Remote Operator; replaceP/C
512-11-014Cooling Coil Unit; replaceP/C
512-11-016Ventilation; replaceP/C
512-11-018Ventilation Watertight Closure; repairP/C
512-11-019Remote Valve Operator Teleflex Cable; replaceP/C
512-90-001ShipAlt DDG51-74012K, VLS Magazine Ventilation Upgrade; accomplishP/CRTR, Access Cut
512-90-002ShipAlt DDG51-77419K, Textile Duct Installation; accomplishP/CRTR
512-90-003ShipAlt DDG51-71655K, Ventilation System Zone 4 Intake Modification; accomplishP/C
514-11-001Resilient Mount; replaceP/C
514-11-002Cooling Coil Air Flow Differential Pressure Gage; installP/C
514-20-001Air Conditioning Plant Condenser Water Control Valve (CWCV); replaceP/C
514-21-001Air Conditioning (AC) Plant Condenser; mechanically cleanIP/C
514-22-001Number 2 Air Conditioning (A/C) Plant Compressor; overhaulIP/C
516-10-001Refrigeration Compressor; overhaulIP/C
520-11-001Sea Valve; repair and replaceIP/C
521-11-001Firemain Pressure Control Valve (PCV); replaceP/C
521-11-002Firemain Piping; replaceP/C
521-11-003Seawater Fuel Oil Compensating Piping; replaceP/C
521-11-004Decontamination Station Number One Firemain Valve; replaceP/C
521-11-005Firemain Piping; replaceP/C
521-11-006Firemain Piping; repairP/C
522-11-001Magazine Sprinkling System Transmission Tubing; replaceP/C
522-11-002Magazine Sprinkling System Transmission Tubing; replaceP/C
522-11-003Magazine Sprinkling System Transmission Tubing; replaceP/C
523-11-001Countermeasure Washdown (CMWD) Valve; replaceP/C
526-10-001T-Wrench Stowage Bracket, Deck Drain; installP/C
526-11-001Deck Drain; replaceP/C
526-80-001ShipAlt DDG51-64270D, 02 Level Aft Weather Deck Drain Modification; accomplishP/C
528-11-001Plumbing Valve Remote Operator Welded Deck Box; replaceP/C
528-11-002Deck Box; replaceP/C
528-11-004Plumbing Drain Piping; replaceP/C
529-11-001Main Drainage Valve Teleflex Cable; replaceP/C
529-11-002Valve Teleflex Cable; replaceP/C
529-11-003Secondary Drainage Eductor Valve Remote Operator Teleflex; replaceP/C
533-11-001Potable Water Valve; replaceP/C
534-11-001Machinery Drain Piping; replaceP/C
541-11-001MORPAC Valve and Actuator Overhaul; accomplishIP/C
541-12-001Fuel Oil Compensating System Pressure Switch Gauge Valve and Tubing; replaceP/C
541-90-001ShipAlt DDG51-70403K, Digital Fuel Control System Installation; accomplishP/CRTR
551-21-00101 Level Weatherdeck Low Pressure Air Piping; repairP/C
551-53-001Low Pressure Air Compressor (LPAC) Class B Overhaul; accomplish (OPTION ITEM)IP/C
551-60-001Bleed Air Regulating Valve; repairP/C
551-64-001Anti-Icing Pipe Hanger; replaceP/C
561-11-001Main Steering Hydraulic Power Unit (HPU) Resilient Mount; replaceP/C
561-11-002Fill and Drain Pump Assembly Isolator Mount; replaceP/C
562-11-001Starboard Rudder Bearing Seal and Rudderstock Seal; overhaulIP/C
562-11-002Port Rudder Bearing Seal and Rudderstock Seal; overhaulIP/C
562-11-003Rudder Stock Bearing; install (OPTION ITEM)IP/C
562-11-004Port Rudder; inspect and repairIP/C
562-11-005Starboard Rudder; inspect and repairIP/C
581-11-001Anchor and Anchor Chain; inspect and preserveIP/C
582-11-001Retractable Chock and Bitt; preserveIP/C
583-11-002Boat Handling System; repair (OPTION ITEM)P/C
583-11-003Liferaft Cradle; repair and preserveP/C
583-90-001ShipAlt DDG51-83894K, Navy Standard Slewing Arm Davit (SLAD) Installation; accomplishP/CPCP, RTR
588-21-001Flight Deck and Recovery Assist, Securing and Traversing (RAST) System Track and Plate; clean and preserveIP/C
588-21-003Naval Air Warfare Center, Aviation Facility Assist Visit Discrepancy; correctP/CRTR
588-90-001ShipAlt DDG51-73212K, Helo Hanger Door Control System Upgrade; accomplishP/CRTR
593-11-002Vacuum, Collection, Holding and Transfer (VCHT) Piping System; chemically cleanP/CPCP
593-11-003Remote Mechanical Valve Actuator; repairP/C
593-11-004Vacuum, Collection, Holding and Transfer (VCHT) Ejector Pump and Motor; replaceP/CPCP
593-25-001Oily Water Separator; repairP/C
593-31-001Metal and Solid Waste Shredder Catch Tray; replaceIP/C
593-90-001ShipAlt DDG51-73622K, VCHT Room H2S Detector Install; accomplishP/C
611-11-001J-Bar Davit Stowage Strap Assembly; replace
612-11-001Reversible Deck Bolt and Deck Socket; repairP/C
612-11-002Stanchion; repairP/C
612-11-003Kevlar Lifeline Assembly; installP/C
612-21-002Helo Safety Net and Frame; repair (OPTION ITEM)IP/C
621-11-001Joiner Bulkhead and Coaming; repairP/C
622-12-001Nomex Deck Panel; replaceP/C
622-12-003Nomex Deck Panel; replaceP/C
622-12-004Nomex Deck Panel; replaceP/C
623-11-001Boatswain Storeroom Ladder; repairP/C
624-11-001Balanced Joiner Door; replaceP/C
631-10-001Main Mast Interior; preserveP/C
631-10-002Boatswain Storeroom Number 2; preserveP/C
631-10-003CBR and DC Storeroom; preserveP/C
631-10-015Shore Power Station Deck and Bulkhead; preserveP/C
631-11-002Machinery Space Bilge; preserveIP/C
631-11-003Fan Room; preserveP/C
631-11-004Auxiliary Machinery Room Number 2; repair and preserveIP/C
631-11-008Generator Room Bilge; repair and preserveIP/C
631-11-009Machinery Room Structural Repair; accomplishIP/C
631-11-011Engine Room Number 2; repair and preserveIP/C
631-11-012Escape Trunk; repair and preserveIP/C
631-11-014Fan Room Deck; repair and preserveIP/C
631-11-015Engine Room Number One; repair and preserveIP/C
631-11-016Auxiliary Machinery Room Number One Repair and Preserve; accomplishIP/C
631-12-001Bulkhead; preserveP/C
631-12-002Corroded Stringer; preserveIP/C
631-12-003Engine Room Number 2; preserveIP/C
631-13-001Collective Protection System (CPS) Zone 2 Fan Room; repair and preserveIP/C
631-13-002Passage; repair and preserveIP/C
631-13-003Collective Protection System (CPS) Zone 4 Fan Room; repair and preserveIP/C
631-13-004Collective Protection System (CPS) Zone One Fan Room; repair and preserveIP/C
631-13-005Collective Protection System (CPS) Zone 3 Fan Room; repair and preserveIP/C
631-13-006Supply Storeroom Number 4; preserveP/C
631-13-009Access Trunk; preserveP/C
631-13-011Fan Room; repair and preserveP/C
631-13-013Fan Room Deck; preserveP/C
631-13-015Exhaust Trunk Deck Plate; preserveIP/C
631-21-001Mast Preservation; accomplishIP/C
631-21-00205 Level Antenna Platform; repair and preserveIP/C
631-21-004Antenna Platform; inspect and preserveIP/C
631-21-00505 Level Nonskid; replaceP/C
631-21-006Visual Landing Aid (VLA) Protective Shield and Foundation; preserveP/C
631-21-007Antenna Platform; inspect and preserveIP/C
631-31-001Underwater Hull; preserveIP/CPCP
631-41-001Freeboard; preserveIP/C
633-21-001Impressed Current Cathodic Protection (ICCP) System; repairIP/C
633-21-002Shaft Grounding Assembly; repairIP/C
634-11-001Chemical - Resistant Floor Covering System; install
634-11-002Nixie Room Nonskid; replaceP/C
634-11-003Electrical Grade Matting Deck Covering System; replaceP/C
634-11-004Electrical Grade Matting Deck Covering System; installP/C
634-11-00502 Level Chemical - Resistant Floor Covering System; installP/C
634-11-006Chemical Resistant Deck Covering System (Zone One); repairP/C
634-11-007Chemical - Resistant Floor Covering System (Zone One); installP/C
634-11-008Chemical - Resistant Floor Covering; resurfaceP/C
634-11-009Deck Covering System; installP/C
634-11-010Chemical - Resistant Floor Covering System; installP/C
634-11-01101 Level Deck Covering (Forward); replaceP/C
634-11-012Chemical Resistant Floor Covering System (01 Level Aft); installP/C
634-11-015Electrical Grade Matting Deck Covering System; replaceP/C
634-11-016Chemical - Resistant Floor Covering System; replaceP/C
634-11-017Chemical - Resistant Floor Covering System; installP/C
634-11-018Chemical - Resistant Floor Covering; resurfaceP/C
634-11-020Porcelain Tile Deck Covering System; replaceP/C
634-11-021Helicopter Control Station Nonskid; replaceP/C
634-11-022Porcelain Tile Deck Covering System; replaceP/C
634-21-001Flight Deck Nonskid; replaceP/C
634-21-002Forecastle Nonskid; replaceP/C
634-21-00402 Level Nonskid; replaceP/C
634-21-00501 Level Amidship Nonskid; replaceP/C
635-11-001Hull Insulation; repairP/CRTR
643-11-001Berthing Habitability Project Installation; accomplishP/C
644-11-002Shower Stall; replaceP/C
644-11-003Sanitary Habitability Project Installation; accomplishP/C
644-90-001ShipAlt DDG51-86821K, Women at Sea Berthing Modification, Crew Living Space Number 2; accomplishP/CPCP
651-90-001ShipAlt DDG51-71605K, DDGM Advanced Galley Modification; accomplishP/CControlling Work Item, Access Cut
652-11-001Medical Exam Table; replaceP/C
654-11-001Vending Machine Foundation; replaceP/C
655-11-001Washer-Extractor; replaceP/C
660-11-001Work Desk; replaceP/C
670-12-001Ship Store Storeroom Grating; installP/C
712-11-0015 Inch Ammunition Strikedown Elevator System Operability Test (SOT), Level III; accomplishP/C
721-31-001Vertical Launch System (VLS) Valve Repair and Flush; accomplishP/C
721-31-003Vertical Launch System (VLS), MK 41 Launcher Top and Uptake Hatch; replace and preserveP/C
721-31-004MK 41 Vertical Launching System (VLS), Cell Hatch; remove and replaceP/C
721-90-001ShipAlt DDG51-85964K, MK 41 Vertical Launching System Block V; accomplishP/C
837-11-001Antenna Photographs; provideP/C
844-31-001Combat Systems Discrepancy Correction; accomplishP/CRTR
857-11-001Temporary Duty Section Berthing Off-Ship; provideP/CRTR
857-11-002Temporary Galley and Messing Facility; provide (OPTION ITEM) (CANCELED)P/CRTR
863-50-001Local Area Network (LAN) Support Service; provideP/C
897-10-001Availability Program Management AIT Integrator; provide (OPTION ITEM)P/C
980-00-001OrdAlt DDG51-78778K, 79024K, and 85473K, AWS: MMSP Transmitter Modification, BMD SPY Coherent Combiner for DDG, and SPY-1D Solid State Switch, Alteration Installation Team (AIT) Support Service; provideP/CRTR
980-00-002OrdAlt DDG51-85224K, MK41 VLS BL BMD 5.1, OrdAlt DDG51-79353K, Ablative upgrade, and OrdAlt DDG51-83746K, HSD Relocation, Alteration Installation Team (AIT) Support Service; provideP/CRTR
980-00-004OrdAlt DDG51-74588K, MK 99 FCS KAS, Alteration Installation Team (AIT) Support Service; provideP/C