Attachment S-8_Pier_and_Drydock_Graphical_Representation_Template.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
N00024-20-R-4400 USS PREBLE (DDG 88) FY20 DEPOT MODERNIZATION PERIOD (DMP)
Solicitation number
N00024-20-R-4400
Issued by

About this file

This solicitation seeks proposals for the USS PREBLE (DDG 88) FY20 Depot Modernization Period availability. The Naval Sea Systems Command will make a single award by June 2020 for maintenance, modernization, and repair work beginning in September 2020. The contractor must have a DDG-51 class capable pier and resources to complete, coordinate, and integrate multiple areas of ship maintenance, repair, and modernization. The availability is competed on a coast-wide basis and will not be set aside for small businesses. Interested parties must register in SAM and monitor beta.SAM.gov for solicitation release and amendments. Attachments on work packages, J-documents and CDRLs are available by request. The contractor must deliver the USS PREBLE by March 2022.

View the file

Other files

File Type Posted
CDRL A012 Enclosure (1) MAR20.pdf PDF
N00024-20-R-4400_A0004_Conformed.pdf PDF
CDRL A015 Enclosure 2 (Template) MAR20.xlsx XLSX spreadsheet
CDRL A015 Performance Report MAR20.pdf PDF
N00024-20-R-4400_A0004_SF 30.pdf PDF
CDRL A015 Enclosure 1 (BLK 16) MAR20.pdf PDF
N00024-20-R-4400_A0003_SF 30.pdf PDF
Attachment S-6__VATEP - Rev1.xlsx XLSX spreadsheet
Attachment J-3 PREBLE Milestones (INSERT OFFEROR NAME) rev5 20200114.xlsx XLSX spreadsheet
N00024-20-R-4400 QA3_05MAR20.pdf PDF
Attachment J-4 PREBLE Pricing Workbook Rev 2 (INSERT OFFEROR NAME) 20200210.xlsx XLSX spreadsheet
Attachment S-4 Manpower Performance_clp (reduced).xlsx XLSX spreadsheet
N00024-20-R-4400-0002 (CONFORMED).pdf PDF
Attachment J-4 PREBLE Pricing Workbook Rev 1 (INSERT OFFEROR NAME) 20200210.xlsx XLSX spreadsheet
N00024-20-R-4400-0002.pdf PDF
N00024-20-R-4400 Q&A#2_20FEB20.pdf PDF
N00024-20-R-4400 Q&A#1_30JAN20.pdf PDF
Attachment S-5_Eligibility_Criteria_Data_Sheet Rev 1.docx DOCX document
N00024-20-R-4400-0001.pdf PDF
N00024-20-R-4400-0001 (CONFORMED).pdf PDF
Attachment S-3_BQ_PPI.xlsx XLSX spreadsheet
Attachment S-6__VATEP.xlsx XLSX spreadsheet
Attachment S-2_PP_CPARS_Reference_List.docx DOCX document
Attachment S-9_Past_Performance_Questionnaire.docx DOCX document
Attachment S-4 Manpower Performance.xlsx XLSX spreadsheet
Attachment J-7 Schedule Model Review.docx DOCX document
Attachment S-5_Eligibility_Criteria_Data_Sheet.docx DOCX document
N00024-20-R-4400.pdf PDF
Attachment S-1_Manpower_Utilization_Data_Sheet.xlsx XLSX spreadsheet
Attachment S-7 Proposal Assessment PRB.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHURCHILL Template

Name of Offeror:Ship:
LEGENDApr-19May-19Jun-19Jul-19Aug-19Sep-19Oct-19Nov-19Dec-19Jan-20Feb-20Mar-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21
CURRENTLY AWARDED WORK
OTHER PROPOSED WORK
THIS PROPOSAL
Offeror's Pier(s)
Pier X
Pier Y
Pier Z
Add Additional as needed
Subcontracted Pier(s)
Add if required
Government Owned Pier(s)
Add if required
Offeror's Drydock(s)
Drydock 1
Drydock 2
Add Additional as needed
Subcontracted Drydock(s)
Add if required
Government Owned Drydock(s)
Add if required
Provide the pierside, dock and undock dates for each requirement, in accordance with the applicable Execution Milestones and Key Events attachment

CARNEY Template

Name of Offeror:Ship:
LEGENDApr-19May-19Jun-19Jul-19Aug-19Sep-19Oct-19Nov-19Dec-19Jan-20Feb-20Mar-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21
CURRENTLY AWARDED WORK
OTHER PROPOSED WORK
THIS PROPOSAL
Offeror's Pier(s)
Pier X
Pier Y
Pier Z
Add Additional as needed
Subcontracted Pier(s)
Add if required
Government Owned Pier(s)
Add if required
Offeror's Drydock(s)
Drydock 1
Drydock 2
Add Additional as needed
Subcontracted Drydock(s)
Add if required
Government Owned Drydock(s)
Add if required
Provide the pierside, dock and undock dates for each requirement, in accordance with the applicable Execution Milestones and Key Events attachment

Example and Notes

Name of Offeror:Ship(s) and Scenario:
LEGENDApr-19May-19Jun-19Jul-19Aug-19Sep-19Oct-19Nov-19Dec-19Jan-20Feb-20Mar-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21<Note 1
CURRENTLY AWARDED WORK
OUTSTANDING PROPOSED WORK
THIS PROPOSAL
Offeror's Pier(s)
Pier X
Pier YUSS CURRENTLY AWARDED (15AUG19 - 10APR20) NOTE 6
Pier ZUSS THIS PROPOSAL (01JUN19 - 25SEP19) NOTE 8USS THIS PROPOSAL (15DEC19 - 10JUL20) NOTE 8
Add Additional as needed
Subcontracted Pier(s)
Add if required<Note 2
Government Owned Pier(s)
Add if required<Note 3
Offeror's Drydock(s)
Drydock 1
Drydock 2USS THIS PROPOSAL (25SEP19 - 15DEC19) NOTE 8
USS PROPOSED WORK (01JUN19 - 15SEP19) NOTE 7
Add Additional as needed
Subcontracted Drydock(s)
Add if required<Note 4
Government Owned Drydock(s)
Add if required<Note 5
Note 1: Chart must display time from proposal submission through end of period of performance
Note 2: Required if any current awarded work, proposed work, or this proposal utilize subcontracted pier(s). Add additional rows if required.
Note 3: Required if any current awarded work, proposed work, or this proposal utilize government owned pier(s). Add additional rows if required.
Note 4: Required if any current awarded work, proposed work, or this proposal utilize subcontracted pier(s)drydock(s). Add additional rows if required.
Note 5: Required if any current awarded work, proposed work, or this proposal utilize government owned pier(s)drydock(s). Add additional rows if required.
Note 6: This bar represents a currently awarded ship utilizing Pier Y from 15AUG19 - 10APR20.
Note 7: This bar represents an outstanding proposal in which the offeror proposes to utilize drydock 2 from 01JUN19 - 15SEP19.
Note 8: These bars represent this proposal in which the offeror proposes to utilize Pier Z from 01JUN19 - 25SEP19, drydock 2 from 25SEP19 - 15DEC19 and Pier Z from 15DEC19 - 10JUL20.
Note 9: Use notes section to explain any apparent conflicts/ mitigations.

DATES ARE FOR EXAMPLE PURPOSES ONLY

File details come from the government source that posted it. Updated .