ATT_9_-_FPM_Delivery_Schedule.XLS

XLS spreadsheet 33 KB Posted

Attached to
U. S. Navy Force Protection Medium (FPM) Boats
Solicitation number
N00024-19-R-2222
Issued by

About this file

This document provides details for a five-year indefinite delivery/indefinite quantity contract to acquire approximately 113 Force Protection Medium boats for the U.S. Navy. The Naval Sea Systems Command intends to issue a total small business set-aside Request for Proposal in the first quarter of fiscal year 2019. The boats will provide anti-terrorism and force protection for naval installations worldwide, conducting patrols, vessel escorts, and security operations in all weather and water conditions. The attachment outlines notional delivery schedules over five ordering periods, specifying delivery timelines for initial and follow-on orders with and without breaks in production. It also includes definitions distinguishing scenarios involving breaks from those without breaks in boat production.

Attachment 9- FPM Delivery Schedule

View the file

Other files

File Type Posted
Att_8_-_CLIN_Pricing_Chart_RevA.xls XLS spreadsheet
N0002419F2222-0004.pdf PDF
N0002419F2222-0003.pdf PDF
Att_2_FPM_Specification_Response_Matrix_Rev_A_7Mar2019.xlsx XLSX spreadsheet
Att_1_FPM_Specification_Rev_A_20190305.pdf PDF
N0002419R2222-0002.pdf PDF
N0002419R2222-0001.pdf PDF
FP_MED_SIGNED_JA_REDACTED.pdf PDF
Att_1_FPM_Specification_Rev-_20Nov2018.PDF PDF
Att_12_Determination_of_Contractor_Responsibility.pdf PDF
Att_5_-_Past_Performance_Information_(fillable).pdf PDF
Att_6_-_Techncial_Data_Rights_Assertion.pdf PDF
Att_3_FPM_Spares_6Dec2018.xlsx XLSX spreadsheet
Att_10_-_Warranty_Terms_(fillable).pdf PDF
N0002419R2222.pdf PDF
Att_11_Past_Performance_Questionnaire.doc DOC document
Att_4_-_Unique_Item_Identification_(UID).pdf PDF
Att_2_FPM_Specification_Response_Matrix.xlsx XLSX spreadsheet
Att_8_-_CLIN_Pricing_Chart.xls XLS spreadsheet
Att_13_Question_Submittal_Form.doc DOC document
010819_Q&A_19R2222_Presol.pdf PDF
112718_Q&A_19R2222_Presol.pdf PDF
111918_Q&A_19R2222_PreSol.pdf PDF
101618_Q&A_19R2222_PreSol.pdf PDF
101018_Q&A_19R2222_PreSol.pdf PDF
Rev2_100918_19R2222_Draft_CLINs_and_SOW_Posted.docx DOCX document
Rev_100918_19R2222_Draft_CLINs_and_SOW_Posted.docx DOCX document
19R2222_Notional_Cabin_Sketch_FPM.PPT PPT presentation
19R2222_Draft_CLINs_and_SOW_Posted.docx DOCX document
Att_1_FPM_Specification_DRAFT_24AUG.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Delivery Schedule

ATTACHMENT 9
Proposed Delivery Schedule Form
ORDERING PERIOD 1
DELIVERY ORDER 1
Craft No.DestinationNotional Delivery ScheduleProposed Delivery Schedule
Boat 1TBD300 DAYS AFTER ORDER
Boat 2TBD60 DAYS AFTER LAST BOAT
Boat 3+TBD30 DAYS AFTER LAST BOAT
DELIVERY ORDER 2+
Craft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule

NO BREAK in Production

Boat 1+TBD30 DAYS AFTER LAST BOAT
DELIVERY ORDER 2+
Craft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule

BREAK in Production

Boat 1TBD300 DAYS AFTER ORDER
Boat 2TBD60 DAYS AFTER LAST BOAT
Boat 3+TBD30 DAYS AFTER LAST BOAT
ORDERING PERIOD 2
Craft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule

NO BREAK in Production

Boat 1+TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule

BREAK in Production

Boat 1TBD300 DAYS AFTER ORDER
Boat 2TBD60 DAYS AFTER LAST BOAT
Boat 3+TBD30 DAYS AFTER LAST BOAT
ORDERING PERIOD 3
Craft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule

NO BREAK in Production

Boat 1+TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule

BREAK in Production

Boat 1TBD300 DAYS AFTER ORDER
Boat 2TBD60 DAYS AFTER LAST BOAT
Boat 3+TBD30 DAYS AFTER LAST BOAT
ORDERING PERIOD 4
Craft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule

NO BREAK in Production

Boat 1+TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule

BREAK in Production

Boat 1TBD300 DAYS AFTER ORDER
Boat 2TBD60 DAYS AFTER LAST BOAT
Boat 3+TBD30 DAYS AFTER LAST BOAT
ORDERING PERIOD 5
Craft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule

NO BREAK in Production

Boat 1+TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule

BREAK in Production

Boat 1TBD300 DAYS AFTER ORDER
Boat 2TBD60 DAYS AFTER LAST BOAT
Boat 3+TBD30 DAYS AFTER LAST BOAT
DEFINITIONS:
BREAK in Production: If a Delivery Order is issued after 120 days from the date of delivery of the last boat on order. (Example: Last boat on current order delivery date: 15 July 2019, new order placed any time after 15 April 2019 would be defined as a BREAK in production. Boat 1 of the new Delivery Order would have a delivery date of 300 days after placement of new Delivery Order)
NO BREAK in Production: If a Delivery Order is issued before 120 days from delivery of last boat on order. (Example: Last boat on current order delivery date 15 July 2019, new order placed any time before 14 April 2019 would be defined as NO BREAK in production. Boat 1 on the new Delivery Order would have a delivery date of 15 August 2019)