Sheet2 Pre-Proposal Information (PPI) Question and Government Responses #7
| Solicitation #: | |||
| TPPC | TPPC-LSD47-SWRMC19-CN01 | Michael Ravnitzky & LT Michelle Wogu, Contract Specialists, michael.ravnitzky@navy.mil & michelle.wogu@navy.mil | |
| Martha Bello, Contracting Officer, martha.bello@navy.mil | |||
| The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation. |
| Q # | Work Item No. | Document Number/ | |
| Title | Question | Government Response | |
| 161 | RFP |
Pages 125 and 135 of N0002418R4410 lists dollar value of $17,982 for Differential Reduction for “Fewer Dock Days Proposed”.
Shouldn’t this dollar value be a negative number?
| Section L annd M have been revised to show a negative number. | ||
| 162 | RFP | 1. Please advise what impact the Government shutdown has on this solicitation. |
2. Is there any movement on a due date extension?
| 3. Will there be anyone to receive quotes on due date of 01/07/19? | The U.S. Navy is not shutdown and is operating as usual. Proposals are still due on Janaury 7, 2019. | |||
| 163 | J-4 | Cell C4 in Labor & Material Rates Tab is behaving like a dollar entry vice a percentage entry. Please correct. | J-4 has been revised to represent a percent. |