N00024-18-R-2400_Amendment_0007.docx
DOCX document 48 KB Posted
- Solicitation number
- N0002418R2400
About this file
N00024-18-R-2400 Amendment 0007
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0002418R2400
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
The purpose of this amendment to solicitation N00024-18-R-2400 is to:
a) Respond to questions submitted by potential Offerors;
b) Revise SECTION A – SOLICITATION/CONTRACT FORM;
c) Revise SECTION B – SUPPLIES OR SERVICES AND PRICES;
d) Revise SECTION F – DELIVERIES OR PERFORMANCE;
e) Revise SECTION G – CONTRACT ADMINISTRATION DATA;
f) Revise SECTION I – CONTRACT CLAUSES;
g) Revise SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS;
h) Revise SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS; and
i) Revise SECTION M – EVALUATION FACTORS FOR AWARD
1. The following questions were submitted by potential Offerors. The Government’s response follows each question. Questions and Answers 045 through 047 are provided in this Amendment 0007. Questions and Answers 001 to 044 were provided in previous amendments.
Question 045: Section A of the revised RFP indicates the SLEP proposal due date as 6/22/18.
In Amendment 0006, question 43 answer, the Government extended the proposal due date to 7/13/18. What is the correct proposal due date?
Answer 045: The correct proposal due date is 13 July 2018. Section A of the RFP has been modified as shown below in paragraph 2.
Question 046: Since ITEM 0014 (Pre-SLEP) and ITEM 0022 (Pre-SLEP) prices are not option items and not are included in the Total Government Evaluated Price (TGEP) calculation if the work is performed at ACU5, it is recommended that the Government include these Items in the calculation of the TGEP for work accomplished at ACU 5.
Answer 046: The assumption in the question is not correct. If the work is to be performed at a Contractor-Owned facility, Pre-SLEP shipping by the Contractor is to be proposed under OPTION ITEM 0014. If the work is to be performed at ACU5, Pre-SLEP shipping by the Contractor is to be proposed under OPTION ITEM 0022. If the work is to be performed at ACU4, there is no Pre-SLEP shipping order or option.
If the work is to be performed at a Contractor-Owned facility, Post-SLEP shipping by the Contractor may occur under Order ITEM 0021. If the work is to be performed at ACU4, Post-SLEP shipping by the Contractor may occur under Order ITEM 0020. If the work is to be performed at ACU5, there is no Post-SLEP shipping order or option.
Regardless of the place of performance, the craft will have to be transported to ACU 5 at some point in time. To include OPTION ITEM 0022 in the TGEP and to not include Order ITEM 0020 in the TGEP results in an unequitable weighting of the two scenarios. The “Post-SLEP” transportation from ACU4 to ACU5 was converted from an “option” to an “order” via Amendment 0005 due to the difficulty of pricing shipping costs in the out-years. The calculation of the TGEP will not be changed.
Question 047: Paragraph L.3.5.2.3.1.1 states that for pricing evaluations purposes, Offerors shall assume a contract award date of 12/7/18. Paragraph F.1.1, Table F-1 has the LCAC 86 induction date of 12/4/18. Can the Government please clarify this inconsistency?
Answer 047: The RFP has been modified to account for this inconsistency as shown below in paragraph 2.
2. As a result of the questions and answers above, modifications to the subject solicitation are hereby incorporated as follows:
a. SECTION A – SOLICITATION/CONTRACT FORM is hereby revised as follows:
The required response date has changed from 22 June 2018 to 13 July 2018.
b. SECTION F – DELIVERIES OR PERFORMANCE is hereby revised as follows:
i. F.1.1, Table F-1, is hereby deleted in its entirety and replaced with the following:
“TABLE F-1
| ITEM |
| Craft |
| MILESTONES DATES |
Craft Induction (Note 1)
| Fuel On Load |
| Production Work Complete |
| Craft Delivery |
| LCAC 86 |
| 8 Jan 2019 |
| * |
| * |
| 10 Apr 2020 |
| LCAC 87 |
| 11 Jun 2019 |
| * |
| * |
| 11 Sep 2020 |
| LCAC 77 |
| 5 Nov 2019 |
| * |
| * |
| 5 Feb 2021 |
0010 (Option)
| LCAC 50 |
| 7 Apr 2020 |
| * |
| * |
| 5 Nov 2021” |
ii. F.2.1, Table F-3, is hereby deleted in its entirety and replaced with the following:
“TABLE F-3
| ITEM |
| Craft |
| MILESTONES DATES |
Craft Induction
| Fuel On Load |
| Production Work Complete |
| Craft Delivery |
| LCAC 86 |
| 26 Feb 2019 |
| * |
| * |
| 29 May 2020 |
| LCAC 87 |
| 30 Ju1 2019 |
| * |
| * |
| 30 Oct 2020 |
| LCAC 77 |
| 7 Jan 2020 |
| * |
| * |
| 9 Apr 2021 |
0010 (Option)
| LCAC 50 |
| 26 May 2020 |
| * |
| * |
| 24 Dec 2021” |
iii. F.2.2, Table F-4, is hereby deleted in its entirety and replaced with the following:
“TABLE F-4
ITEM
| Craft |
| MILESTONES DATES |
| Period of Performance Start Date |
| Contractor Pickup Date |
| Craft Arrival At Contractor Owned Facility |
Craft Induction
0014AA
| LCAC 86 |
| Option Exercise |
| * |
| ** |
| 26 Feb 2019 |
0014AA
| LCAC 87 |
| Option Exercise |
| * |
| ** |
| 30 Jul 2019 |
0014AB
| LCAC 77 |
| Option Exercise |
| * |
| ** |
| 7 Jan 2020 |
0014AB
| LCAC 50 |
| Option Exercise |
| * |
| ** |
| 26 May 2020 |
| 0014AC |
| LCAC 77 |
| Option Exercise |
| * |
| ** |
| 7 Jan 2020” |
iv. F.3.1, Table F-6, is hereby deleted in its entirety and replaced with the following:
“TABLE F-6
| ITEM |
| Craft |
| MILESTONES DATES |
Craft Induction (Note 1)
| Fuel On Load |
| Production Work Complete |
| Craft Delivery |
| LCAC 86 |
| 26 Feb 2019 |
| * |
| * |
| 29 May 2020 |
| LCAC 87 |
| 30 Jul 2019 |
| * |
| * |
| 30 Oct 2020 |
| LCAC 77 |
| 7 Jan 2020 |
| * |
| * |
| 9 Apr 2021 |
0010 (Option)
| LCAC 50 |
| 26 May 2020 |
| * |
| * |
| 24 Dec 2021” |
v. F.3.2, Table F-7, is hereby deleted in its entirety and replaced with the following:
“TABLE F-7
ITEM
| Craft |
| MILESTONES DATES |
| Period of Performance Start Date |
| Contractor Pickup Date |
Craft Arrival at ACU 5
Craft Induction
0022AA
| LCAC 86 |
| Option Exercise |
| * |
| ** |
| 26 Feb 2019 |
0022AA
| LCAC 87 |
| Option Exercise |
| * |
| ** |
| 30 Ju1 2019 |
0022AB
| LCAC 77 |
| Option Exercise |
| * |
| ** |
| 7 Jan 2020 |
0022AB
| LCAC 50 |
| Option Exercise |
| * |
| ** |
| 26 May 2020 |
| 0022AC |
| LCAC 77 |
| Option Exercise |
| * |
| ** |
| 7 Jan 2020” |
3. SECTION B – SUPPLIES OR SERVICES AND PRICES is hereby revised as follows:
B.2 “CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)” is hereby deleted in its entirety and marked as “RESERVED”.
4. SECTION G – CONTRACT ADMINISTRATION DATA is hereby revised as follows:
G.6 “G-232-H002 PAYMENT INSTRUCTIONS AND CONTRACT TYPE SUMMARY FOR PAYMENT OFFICE (NAVSEA) (JUN 2018)” is hereby added to the RFP. The full text is found in the conformed copy of the solicitation.
5. SECTION I – CONTRACT CLAUSES is hereby revised as follows:
a. 52.230-2 “COST ACCOUNTING STANDARDS (OCT 2015)” is hereby deleted in its entirety and replaced with 52.230-2 “COST ACCOUNTING STANDARDS (Deviation 2018-O0012)(APR 2018)”. The full text is found in the conformed copy of the solicitation.
b. 52.230-3 “DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES (OCT 2015)” is hereby deleted in its entirety and replaced with 52.230-3 “DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES (Deviation 2018-O0012)(APR 2018)”. The full text is found in the conformed copy of the solicitation.
c. 252.204-7004 “ALTERNATE A, SYSTEM FOR AWARD MANAGEMENT (FEB 2014)” is hereby deleted in its entirety.
6. SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS is hereby revised as follows:
52.230-1 “COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION (Deviation 2018-O0012)(APR 2018)” is hereby added to the RFP. The full text is found in the conformed copy of the solicitation.
7. SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS is hereby revised as follows:
a. 252.225-7003 “Supplies and Services Provided by Nontraditional Defense Contractors (JAN 2018)” is hereby deleted in its entirety and replaced with 252.215-7013 “Supplies and Services Provided by Nontraditional Defense Contractors (JAN 2018)”.
b. L.3.5.2.3.1.2.2 is hereby deleted in its entirety and replaced with the following:
“L.3.5.2.3.1.2.2 For all Work Items for each craft, as designated in the TDP, under ITEMS 0001, 0004, 0007, and 0010, Offerors shall provide a breakdown of the proposed price by Work Item using the format shown in Addendum L-2 and shall label this as “Figure L.1”. The Offeror shall make no additions or alterations to the data requested in Addendum L-2. Figure L.1 shall be submitted in Microsoft Office 2010 Excel. All calculations shall performed by formulas in the spreadsheet. Offerors shall round dollar amounts to two (2) decimal places to the right of the decimal point. However, the final dollar amount per Contract Line Item Number in Section B of the offer shall be rounded to the nearest dollar. Offerors shall provide a narrative or description in sufficient detail to substantiate price reasonableness. These may be supporting explanations, rationale or assumptions.”
c. L.3.5.2.3.1.3.1 is hereby deleted in its entirety and replaced with the following:
“L.3.5.2.3.1.3.1 Offeror shall provide a Fully Loaded Man-hour Labor Rate in Section B, Note E, Table B-1 and Note I, Table B-2, inclusive of prime and subcontractor efforts, (including profit and all indirect costs). Labor Dollars ($) equals the Man-hours listed in Section B, Table B-1, times the Fully Loaded Man-hour Rate. Offerors shall present this information in this section as “Figure L.2”. Offerors shall round the Fully Loaded Man-hour Rate to two (2) decimal places to the right of the decimal point. However, the final dollar amount per Contract Line Item Number in Section B of the offer shall be rounded to the nearest dollar. Offerors shall provide a narrative or description in sufficient detail to substantiate price reasonableness. These may be supporting explanations, rationale or assumptions.”
8. SECTION M – EVALUATION FACTORS FOR AWARD is hereby revised as follows:
a. M.6.4, Table M-4, is hereby deleted in its entirety and replaced with the following:
“TABLE M-4
TGEP CALCULATION FOR LCAC SLEP AVAILABILITY AT ACU 4 OR ACU 5
FIRM FIXED PRICED ITEMS
| Step |
| Input |
| Result |
| 1 |
| Offeror Proposed Price for ITEM 0001 |
| 2 |
| Offeror Proposed Price for ITEM 0004 |
| 3 |
| Offeror Proposed Price for ITEM 0007 |
| 4 |
| Offeror Proposed Price for ITEM 0010 |
| 5 |
| Sum of Results under Steps 1 through 4 |
| Firm Fixed Price Total |
ADDITIONAL LABOR REQUIREMENT ORDER ITEMS
| Step |
| Input |
| Result |
| 6 |
| Offeror Proposed Fully Loaded Man-Hour Labor Rate x 26,250 Man-Hours for ITEM 0002 |
| Additional Labor Requirement Ceiling for ITEM 0002 |
| 7 |
| Offeror Proposed Fully Loaded Man-Hour Labor Rate x 26,250 Man-Hours for ITEM 0005 |
| Additional Labor Requirement Ceiling for ITEM 0005 |
| 8 |
| Offeror Proposed Fully Loaded Man-Hour Labor Rate x 26,250 Man-Hours for ITEM 0008 |
| Additional Labor Requirement Ceiling for ITEM 0008 |
| 9 |
| Offeror Proposed Fully Loaded Man-Hour Labor Rate x 30,000 Man-Hours for ITEM 0011 |
| Additional Labor Requirement Ceiling for ITEM 0011 |
| 10 |
| Sum of Results under Steps 6 through 9 |
| Total Additional Labor Requirement Ceiling |
| 11 |
| Normalization for performance at ACU 4/5 per FAR 45.301 “USE AND RENTAL” and FAR 52.245-9, “USE AND CHARGES” |
For ACU 4 use $1,193,933.
For ACU 5 use $1,234,414.
$1,193,933 or
$1,234,414
| 12 |
| Sum of Results under Step 5, Step 10, and Step 11 |
| TGEP” |
b. M.6.4.1 is hereby deleted in its entirety and replaced with the following:
“M.6.4.1 ITEMS 0001, 0004, 0007, and 0010 are Firm Fixed Price items and will be used in the calculation of the TGEP. The pricing provided will be evaluated for price reasonableness and completeness. The breakdown of price by Work Item, as described in Section L.3.5.2.3.1.2.2, will assist the evaluators in determining the Offeror’s understanding of the requirements of the solicitation.”
c. M.6.4.3 is hereby deleted in its entirety and replaced with the following:
“M.6.4.3 ITEMS 0002, 0005, 0008, and 0011 will be evaluated for price reasonableness and completeness by considering the Offeror's proposed fully loaded man-hour labor rate in light of information available to the Contracting Officer.”
d. M.6.4.5 is hereby deleted in its entirety and replaced with the following:
“M.6.4.5 ITEMS 0014, 0016, 0017, and 0022 will be evaluated for price reasonableness and completeness. The Offeror shall provide pricing for all sub-ITEMS thereunder.”
9. Except as provided herein, all other terms and conditions of solicitation N00024-18-R-2400 remain unchanged.
image1.wmf
File details come from the government source that posted it.