QA1
| USS TORTUGA - QUESTIONS AND ANSWERS #1 | |||
| Question # | Work Item | Question | Response |
| 1 | 120-11-017 | PARA 3.6.2 requires clad welding in tanks listed in para 1.2.4 thru 1.2.9. There are no tanks listed in these locations. Please provide the tank numbers that associated with these repairs. | ERRATA TO BE ISSUED |
| 2 | 120-11-013 | Item 120-11-013 has para 3.2.1 which requires 6 square feet of clad welding. This seems to be excessive whereas a 6 sq. foot insert would be more economical to accomplish. Is this requirement a mistake or is this the correct quantity of clad welding? | ERRATA TO BE ISSUED |
| 3 | VARIOUS | The numerical index that was provided has 5 less items than the items provided in the “Sneak Peek” adobe file The following items were also received that were not on the excel numerical index list: 150-90-001, 150-90-002, 168-80-002, 551-90-001 & 651-90-001. Also the 120-11-026 item number was on the numerical index but was not provided with a written spec. Will a new index with titles that match the specification attachment be provided in the future? | Use the posted solicitation for pricing. A second CD was issued on 5 June which is the solicitation package. |
| 4 | 584-41-003 | Paragraph 3.11 states to replace 10 SF of plating as identified in 3.6. Paragraph 3.6 does not have an inspection called out. Should the plate replacement be from the inspection called out in 3.3 and reported in 3.3.1? | ERRATA TO BE ISSUED |
| 5 | 612-90-001 | There is not an example of cable tags provided. Will one be provided? | Use standard work practices as required by NAVSEA STD ITEMS which also refers to Electric Plant Standard Methods. |
| 6 | 651-80-001 | The reference drawing 2.3 (Ovhd Sheathing Mod) is the same as reference 2.2 (Door Mods). Contractor requests a copy of reference 2.3 for Overhead Sheathing Modification Galley Upgrade be provided. | Reference Drawing 2.3 will be made available. ERRATA TO BE ISSUED |
| 7 | 120-11-017 | Paragraph 3.1 states to power tool to bare metal the deck and bulkhead surfaces for the locations listed in 1.2.1 thru 1.2.9. |
1. Is it really the intent to have the very large areas listed in 1.2 to be power tooled to bare metal?
2. If the intent is to power tool areas for the NDT called out in 3.2, could the Government narrow the scope to a better defined area? For example paragraphs 1.2.2 thru 1.2.9 are adjacent spaces and therefore do not require all decks and bulkheads to be power tooled to bare metal.
3. After paragraph 3.1 is accomplished the only preservation remaining in this work item is for the newly installed plates. Will the Government allow all the bare decks and bulkheads to be preserved as new and disturbed surfaces?
| Paragraphs 3.9 and 3.10 provide a 009-32 Table and Line for the newly installed plates. Will the Government clarify which paragraph applies to what area of the newly installed plates? What paint system does the Government wish to apply to paragraph 3.6 thru 3.6.2.3 for the welding? | ERRATA TO BE ISSUED | |||
| 8 | 120-11-013 | Paragraph 3.2.1 which requires 6 square feet of clad welding. This seems to be excessive whereas a 6 sq. foot insert would be more economical to accomplish. Does the contractor have the option to insert vice clad weld these areas? How many areas require repairs? | ERRATA TO BE ISSUED | |
| 9 | 120-11-017 | Paragraph 3.1 calls for power tool cleaning of the entire deck and bulkhead surfaces in the locations listed in 1.2.1 thru 1.2.9. This seems extreme to power tool clean the entire Well Deck deck and bulkheads. Please clarify by listing the square footage required in each space listed in 1.2. | ERRATA TO BE ISSUED | |
| 10 | 120-11-017 | Paragraph 3.6.2 requires clad welding in tanks listed in para 1.2.4 thru 1.2.9. There are no tanks listed in these locations. Please provide the tank numbers that are associated with these repairs. | ERRATA TO BE ISSUED | |
| 11 | 123-11-003 | Para 3.8 directs an MT inspection of the “C” links, however paragraph 3.8.1 requires a report of thickness gauging. I shall assume paragraph 3.8.1 is in error and that MT report is requested. | ERRATA TO BE ISSUED | |
| 12 | 123-16-001 | Paragraph 3.3 tasks Contractor to accomplish an Ultrasonic test inspection of each tank located in 1.2.3, 1.2.6 through 1.2.10 and 1.2.12, at 1000 locations. Is this a total of 1000 locations for all the tanks or 1000 spots in each tank? | A total of 1,000 spots for all tanks listed in 3.3 |
13 J-3 Execution Milestones The Milestone/Key Event on Line 20 is listed as Undocking and has a date of A+218, 14 AUG 18. There currently is not a Milestone/Key Event for the Docking.
Line 42 includes Milestone/Key Event “Dock” states "Offeror to Propose Dock & Undock Dates IAW Specification 997-11-002".
| Does the Government intend to modify the J-3 to add a Docking Milestone/Key Event with “TBD” as the date and change the Undocking Milestone/Key Event to also have a date of “TBD”? | Contractor may propose docking date. Latest undocking date in support of subsequent events is 14 AUG 18. | ||
| 14 | RFP Section C – Scope of Work | Paragraph 3.4 and the subsequent table of reports contain due dates of "D+30" and "A+74", however, these dates do not conform to the availability and docking period durations identified in attachment J-3 Execution Milestones. | |
| Does the Government intend to change "D+30" to read "NLT 20% of Docking Period" and change "A+74" to read "A+97" (20% of 487 day availability duration) in paragraph 3.4 and the subsequent table of reports? | The government is requiring reports noted as A+74 by A+74 and reports required by D+30 as D+30. This is in addition to the NAVSEA STD item requirements. | ||
| 15 | RFP Section C – Scope of Work | Thirteen work items in the Para 3.4 table do not contain report paragraph numbers: 233-11-037, 233-12-012, 233-13-008, 233-13-026, 233-14-012, 242-13-001, 242-13-002, 262-11-001, 262-12-001, 311-90-002, 524-11-003, 562-11-001, & 631-11-005. | |
| If these work items do not contain Required Reports will the Government please remove them from the Table to preclude questions regarding these work items? | 233-11-037, 233-12-012, 233-13-026, 233-14-012, 242-13-001, 242-13-002, 262-11-001, 262-12-001, 311-90-002, 524-11-003, 562-11-001, & 631-11-005 will be removed from Sect C para 3.4 table. 233-13-008 Propulsion Diesel Engine (MPDE) Gieslinger Coupling Sect C para 3.4 table will be corrected to reflect report para number 3.4.4. | ||
| 16 | RFP Section C – Scope of Work | Four work items in the Para 3.4 table were not received in the Solicitation, nor are they on the Work Item Index or the J-4 Pricing Sheet (311-90-003, 311-90-004, 311-90-005, & 311-90-006). | |
| If these work items do not exist will the Government please remove them from the table to preclude questions regarding these work items? | These work items are in addendum one. | ||
| 17 | RFP Section C – Scope of Work | Some work items in the Para 3.4 table contain report paragraph numbers that are not open and inspect reports. The type and amount of work required prior to generating some other reports, make them unlikely to be accomplished prior to the due dates (ex. 243-11-002, para 3.11.1 after equipment repairs, completed before D+30). |
Work Items (report paragraphs):
123-11-003(3.18.1, 3.20.1, 3.21.1), 123-16-001(3.2.1 and 3.3.1), 123-19-002(3.2.1), 123-22-003(3.2.1), 123-22-004(3.2.1), 130-11-001(3.2.1), 233-11-008(3.4.4), 233-12-008(3.4.4), 233-14-008(3.4.4), 233-14-015(3.3.2), 242-11-001(3.3.1.1), 243-10-001(3.3.1, 3.5.2.1), 243-11-002(3.10.5, 3.11.1.1,3.15.1, 3.18.1), 243-11-003(3.10.5, 3.11.1.1,3.15.1, 3.18.1), 244-10-002(3.2.1.3), 245-11-004(3.7.1), 245-12-001(3.7.1), & 320-22-001(3.1.2.1).
| Please remove these reports from the Milestones for Certain Reports table in paragraph 3.4. | The following reports will be removed from section C, para 3.4 table: 123-11-003 report 3.18.1 only, 243-10-001 reports 3.3.1 and 3.5.2.1, 243-11-002 reports 3.15.1 and 3.18.1 only, 244-10-002 report 3.2.1.3 only, 245-11-004 report 3.7.1 only, 245-12-001 report 3.7.1 only. Also, 243-11-003 is incorrectly listed and will be corrected to 243-12-003 Port Propulsion Shafting inspect and repair and reports 3.15.1 and 3.18.1 only will be removed. | |||
| 18 | 120-11-008 | Bulkhead Stiffener and Plating para 3.1 requires a visual inspection of each bulkhead and stiffener listed in paragraph 1.3 for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion in each location in 1.2. There are fourteen locations identified by paragraph 1.3. There could possibly be thermal insulation on areas in some or all of the fourteen location identified in paragraph 1.3. A quantity of repair work is specified for each location, but it is much less than the area shown in each of the referenced details. If there is thermal insulation in each of the 14 areas identified in paragraph 1.2 for the visual inspection, is it the intention to remove all of the insulation in those locations identified by details to perform the visual inspection and to reinstall the thermal insulation as interference to the work item? Please clarify quantity of insulation to be replaced in para 3.4. | NAVSEA STD ITEM 009-11 is referenced in the work specification. Please comply with work specification. | |
| 19 | 130-11-007 | In para 3.7 it is required to accomplish 009-32 line 11, 11A, 12, 13 AND 13A. The contractor is confused as to what line the gov’t actually wants to have accomplished. Also the location of work is not identified for the preservation repairs, para 1.2.1 is the A/C Machinery Room #2 (3-74-1-E). Is the intent to preserve the entire space? | The government requires preservation of the deck, newly installed material, and new and disturbed. Use table and line as applicable. | |
| 20 | Milestone | The 50% conference is scheduled for Saturday September 8, 2018 on the milestone sheet. Are we going to keep that date? | Any change will be considered after award. Proposals to move dates to the left will likely be acceptable at no cost to the government. | |
| 21 | Milestone | The 75% conference is scheduled for Tuesday January 8, 2019 on the milestone sheet. Are we going to keep that date as opposed to Wednesday the 9th? | Any change will be considered after award at no cost to the government. | |
| 22 | 150-11-009 | Para 3.1 requires installation of retained lockers. There is no paragraph to remove any lockers. Para 3.4 states to install equipment and lockers retained in 3.1. Please clarify that all lockers listed in para 1.3.1 are to be removed and reused. | ERRATA TO BE ISSUED | |
| 23 | 167-11-003 | The subject item reads: 3.1.10 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line 25, for each newly installed watertight door listed in 1.3.1 through 1.3.9. This requirement is usually reserved for Powder-coating of Intake Louvers. Please validate the watertight doors listed in 1.3.1 thru 1.3.9 require to be preserved by the Fluidized Bed Method as per 009-32- table 2 line 25 requires. | 009-32, Table 2, line 25 applies to watertight doors. Comply with work specification, per govt. engineering this method provides prolonged life of equipment. | |
| 24 | 150-11-015 | Para 3.6 of the subject item requires 009-17 for supply fan 2-20-1. There is no description or identification on this electric motor repair. The contractor needs a description of the nameplate nomenclature for the supply fan 2-20-1 in order to estimate repairs. | ERRATA TO BE ISSUED | |
| 25 | 150-11-028 | In para 3.1 it is required to replace the materials listed in 1.3. In para 1.3 the identified material is the Work Maintenance Platform itself. Para 3.1.1 goes on to say replace the following with new parts: One each Hose Stowage Rack; 2 each "U" Staples; 8 each Tie Downs (Short); 2 each Tie Downs (Long); and 48 each 3/8-16 UNC 2A Weld Mounting Studs. |
These parts are attached to the Work Maintenance platform. Please clarify that it is the intent to replace the entire platform or only the materials listed in para 3.1.1 that are attached to the platform?
| Also in para 3.1.3 it is required to replace with new the weld base mounting studs. There is no way to estimate this unless there is a quantity of studs to be replaced or level of effort added to accomplish this task. How many studs are to be replaced? | ERRATA TO BE ISSUED | |||
| 26 | 167-11-003 | The subject item reads: 3.1.10 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line 25, for each newly installed watertight door listed in 1.3.1 through 1.3.9. This requirement is usually reserved for Powder-coating of Intake Louvers. Please validate the watertight doors listed in 1.3.1 thru 1.3.9 require to be preserved by the Fluidized Bed Method as per 009-32- table 2 line 25 requires. | 009-32, Table 2, line 25 applies to watertight doors. Comply with work specification, per govt. engineering this method provides prolonged life of equipment. | |
| 27 | 233-10-009 | Is the location for Main 2 in paragraph 1.2.2 incorrectly called out for this work item? (Only the heaters for 1A and 1B are identified for work per this specification in paragraph 1.3.) | ERRATA TO BE ISSUED | |
| 28 | 150-90-001 | Para 3.1.2 states to Accomplish the requirement of 009-90. Provided the services of qualified Technical Representative. The Representative recommended in 4.1 is a SPAWAR person that works for the Government. Please confirm the Government will provide this representative. | ERRATA TO BE ISSUED 009-90 is not required and will be deleted. The Government will provide an on site representative to oversee / assist with removal and relocation of antenna. | |
| 29 | 233-11-002 | 233-11-002 MPDE Lube Oil and Jacket Water Thermostatic Valve; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The government has determined 009-09 is not required for this work. | |
| 30 | 233-11-002 | Para. 3.2.2.1 refers to the requirements of para. 3.3.2. Contractor recommends changing it to the correct para. 3.2.2. | ERRATA TO BE ISSUED | |
| 31 | 233-11-005 | 233-11-005 MPDE Air Start Distributor & Main Air Start Control Valve; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The government has determined 009-09 is not required for this work. | |
| 32 | 233-11-005 | 1. Para. 3.2.1.1 refers to the requirements of para. 3.3.1. Contractor recommends changing it to the correct para. 3.2.1. | ||
| 2. Para. 3.3.1.1 refers to the requirements of para. 3.4.1. Contractor recommends changing it to the correct para. 3.3.1. | ERRATA TO BE ISSUED | |||
| 33 | 233-13-015 | 233-13-015 MPDE Cylinder Head and Component; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard. The 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 34 | 233-11-011 | Para. 3.13 refers to the equipment listed in para. 1.3.1.3. Contractor recommends changing it to the correct para. 1.3.1.2. (Enclosure 9, Section 4 of 2.2 is the Fuel Oil Leak Off System para. 1.3.1.2) | ERRATA TO BE ISSUED | |
| 35 | 233-12-002 | 233-12-002 MPDE Lube Oil and Jacket Water Thermostatic Valve; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The government has determined 009-09 is not required for this work. | |
| 36 | 233-12-005 | 233-12-005 MPDE Air Start Distributor & Main Air Start Control Valve; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The government has determined 009-09 is not required for this work. | |
| 37 | 233-12-031 | 233-12-031 MPDE Post Lube Oil Flush; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard. The 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 38 | 233-12-037 | 233-12-037 MPDE Crankcase Vacuum System; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard. The 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 39 | 233-13-002 | 233-13-002 MPDE Lube Oil and Jacket Water Thermostatic Valve; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The government has determined 009-09 is not required for this work. | |
| 40 | 233-13-015 | 233-13-015 MPDE Cylinder Head and Component; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard. The 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 41 | 233-13-026 | 233-13-026 MPDE Camshaft Bearings, Lobes and Flex Drive; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard. The 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 42 | 233-14-004 | 233-14-004 MPDE Turbocharger Air Intercooler; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard. The 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 43 | 233-14-005 | 233-14-005 MPDE Air Start Distributor & Main Air Start Control Valve; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The government has determined 009-09 is not required for this work. | |
| 44 | 233-14-012 | 233-14-012 (2B MPDE Overhaul); the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard the 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 45 | 233-14-016 | 233-14-016 MPDE Jacket Water Cooling Water Elbow; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | The work item is to be accomplished IAW an approved NAVSEA Maintenance Standard the 009-09 SI is not required because the Maintenance Standard (MS) provides the appropriate guidance for the KTR to accomplish the task | |
| 46 | 241-10-001 | The subject item calls for para 3.3 to Remove and retain system oil from equipment listed in 1.3.2 and located in 1.2.1. Para 3.8 states to remove and dispose of systems fluids from the equipment listed in 1.3.3 and located in 1.2.1. Para 3.6 requires the stored oil be used to refill the equipment. It is more cost effective to dispose of the residual oil than it is to store the oil. Please verify that we are to store the oil from the Lube Oil Purifier heater for reuse. | ERRATA TO BE ISSUED | |
| 47 | 241-10-002 | The subject item calls for para 3.2 to Remove and retain system oil from equipment listed in 1.3.2 and located in 1.2.1. Para 3.5 requires the stored oil be used to refill the equipment. It is more cost effective to dispose of the residual oil than it is to store the oil. Please verify that we are to store the oil from the Lube Oil Purifier heater for reuse. | ERRATA TO BE ISSUED | |
| 48 | 311-21-030 | Item 311-21-030 Ship Service Diesel Generator Engine (SSDG) Cylinder Relief Valve; repair; the government has included the requirements of 009-90 in other similar items, however that requirement is not included for this item. Please confirm that 009-90 is not to be included as a requirement for this item. Also the item para 1.3.1.1 calls for 1 Safety Relief Valve vice 12 that are in similar items (i.e. 311-22-032, 311-24-029). | The determination was made to exclude 009-90 in this WI. Para 1.3.1.1 calling for 1 Safety Relief Valve vice 12 is a typo and ERRATA will be issued, the correct quantity of the relief valves is 12. | |
| 49 | 311-22-032 | Item 311-22-032 Ship Service Diesel Generator Engine (SSDG) Air Start Piston and Cylinder Safety Relief Valve; repair; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | 009-09 will be required since the work is not to be accomplished IAW an approved maintenance standard but IAW various sections of the technical manual. ERRATA TO BE ISSUED. | |
| 50 | 311-23-026 | Item 311-23-026 Ship Service Diesel Generator Engine (SSDG) Cylinder Relief Valve; repair; the government has included the requirements of 009-90 in other similar items, however that requirement is not included for this item. Please confirm that 009-90 is not to be included as a requirement for this item. Also the item para 1.3.1.1 calls for 1 Safety Relief Valve vice 12 that are in similar items (i.e. 311-22-032, 311-24-029). | The determination was made to exclude 009-90 in this WI. Para 1.3.1.1 calling for 1 Safety Relief Valve vice 12 is a typo and ERRATA will be issued, the correct quantity of the relief valves is 12. | |
| 51 | 311-24-029 | Item 311-24-029 Ship Service Diesel Generator Engine (SSDG) Air Start Piston and Cylinder Safety Relief Valve; repair; the government has included the requirements of 009-09 in other similar items, however that requirement is not included for this item. Please confirm that 009-09 is not to be included as a requirement for this item. | 009-09 will be required since the work is not to be accomplished IAW an approved maintenance standard but IAW various sections of the technical manual. ERRATA TO BE ISSUED. | |
| 52 | 320-22-001 | Paragraph 3.1.2.1 states to submit one legible copy, in hard copy or approved transferrable media, of a list of new parts installed, excluding parts specifically listed to be removed in this Work Item or invoked Standard Item, in place of those identified to be missing or defective, with documenting invoices or other substantiating data, to the SUPERVISOR. Is this report referring to Paragraph 3.1, 3.1.1 or 3.1.2? | Paragraph 3.1 | |
| 53 | 512-11-003 | Para 3.1 requires that each fan assembly in 1.3 be cleaned. Para 3.1.3 states to clean each inlet and outlet duct, however para 3.2 and 3.3 states to clean only 1.3.1 thru 1.3.45. There are 155 vent systems listed in 1.3. It appears that the systems referenced in 3.2 and 3.3 should be 1.3.1 thru 1.3.155. Please clarify and revise specification. | ERRATA TO BE ISSUED | |
| 54 | 311-23-023 | Paragraph 3.15 reads, “provide 21% mandays of labor and….” Please clarify that the Contractor is to provide 21 mandays of labor. | ERRATA TO BE ISSUED | |
| 55 | 321-80-001 | Paragraph 3.11 calls out 009-32 Table 5, Line 18 for new and disturbed piping. This Table and Line is for a SSPC-SP-10 Blast. Will the Government consider changing this work item to Table 5, Line 1 and review the other SHIPALTs for the same change? | This piping is for elevated temperatures, no change will be processed. | |
| 56 | 512-11-013 | Paragraph 3.1.3 provides direction to accomplish the requirements of 009-32 of 2.1, including Table 3, Line 15, for interior surfaces of new equipment in 3.1. This preservation is for steel surfaces using SSPC-SP-10 of vent plenums. Is it the Government’s intent for the Contractor to sandblast to near white metal and apply 30 Mils of paint to the interior only of the NEW steel and aluminum diffusers listed in 3.1? Please clarify. | ERRATA TO BE ISSUED | |
| 57 | 512-11-020 | Paragraph 3.4 provides direction to accomplish the requirements of 009-32 of 2.1, including Table 2, Line One, for exterior surfaces of natural supply duct, and Table 3, Line 14 for interior surfaces. This Table and Line is for steel surfaces; the replacement duct VD-03 is 050 aluminum. |
Please clarify:
1) Does the Government want the exterior of the duct preserved using the system for the exterior surfaces above the boot-top per Table 2, Line one or the same system for interior surfaces because the duct is in a fan room? If the later, what Aluminum Table and Line should the Contractor use?
| 2) Does the Government want the interior of the duct preserved using the vent plenum system called out in Table 3, Line 14? If so what Aluminum Table and Line should the Contractor use? | ERRATA TO BE ISSUED | |||
| 58 | 130-11-002 | Paragraph 3.4 calls out Table 3, Line 22 which is preservation for under AFFF stations. Is this the preservation system the Government wishes to use or should the paragraph be changed to Table 3, Line 20 which is for Fan Rooms per 009-32 FY-17 (CH-1)? Please advise. | ERRATA TO BE ISSUED | |
| 59 | 130-11-006 | Paragraph 3.4 calls out Table 3, Line 22 which is preservation for under AFFF stations. Is this the preservation system the Government wishes to use or should the paragraph be changed to systems for Interior Surfaces for 2.1 and another table and line for the critical coated tanks on the adjacent sides of the repairs? Please advise. | ERRATA TO BE ISSUED | |
| 60 | 150-11-009 | Paragraph 3.1 states to install retained lockers using new fasteners, paragraph 3.1.1 removes the mounting bracket and paragraph 3.4 installs the equipment and lockers retained in 3.1. Contractor requests paragraph 3.1 be re-worded to remove and retain vice install retained. | ERRATA TO BE ISSUED | |
| 61 | 167-11-003 | The watertight doors listed in paragraphs 3.1.10, 3.2.2.16 and 3.3.4 have Table 2, Line 25 as the preservation paragraphs. This system is the fluidized bed method. Will the Government consider Table 5, Line 26 or 27 for standard powder coat as the coating method? The standard powder coat method can be done locally and will result in cost savings to the Government. | 009-32, Table 2, line 25 applies to watertight doors. Comply with work specification, per govt. engineering this method provides prolonged life of equipment. | |
| 62 | 150-90-001 | The specification shows reference 2.4 533-8621580 Power System Signal Shelter Removal. After looking at the drawing, the title is COLD POTABLE WATER MODS SIGNAL SHELTER REMOVAL 06 & 07 LEVEL, FRAM 34-38. The Power System Drawing is listed under 2.10. Recommend 2.4 be changed to Cold Potable Water Signal Shelter. | ERRATA TO BE ISSUED |
&"-,Bold"&18N00024-17-R-4403