TOWING, SALVAGE, AND RESCUE SHIP (T-ATS)
GOVERNMENT COMMUNICATIONS SUITE
TURNKEY APPROACH
18 November 2016
N00024-17-R-2207
ATTACHMENT J-3
DEPARTMENT OF THE NAVY
PROGRAM EXECUTIVE OFFICE, SHIPS
WASHINGTON, DC 20376
N00024-17-R-2207 Attachment J-3 Government Communications Suite Turnkey Approach
1.0 Introduction
This document describes the work to be performed by the Contractor and the Government in support of the Government Communications Suite Turnkey process.
The installation of the Government’s communications equipment will be done under a turnkey approach performed by the Contractor and Government. The majority of the Government’s communications equipment will be located within the dedicated Communications Suite and topside, with a small number of equipment located in remote spaces. The Government will provide drawings for envelopes within the shipboard communications space and topside arrangements required for the installation of the communication equipment. The main role of the Contractor is to design, construct, and prepare the Communication Suite and topside locations, and also to provide other related ships services for installation of Government’s communication equipment. The Government will coordinate the electromagnetic environmental effects (E3) compatibility certification between T-ATS contractor-furnished communication equipment and the government furnished communication suite. The Contractor shall participate in a C4I Working Group with the Government to coordinate the installation of the C4I systems, to schedule contractor-supplied services, resolve issues associated with the C4I system installation and testing, and installation schedules for C4I equipment and scheduling of shipyard-required services to support equipment installation.
2.0 Definitions
Communications Suite – Refers to the space that the Contractor shall provide to house the Government communications equipment, as defined in the Circular of Requirements (COR), Attachment J-1, sections 3.401 and 3.441. Also referred to as the Naval Communications Center.
C4I Equipment or Communications Equipment – Refers to the Command, Control, Communications, Computers, and Intelligence (C4I) equipment that will be provided by the Government.
Remote Space – Refers to any space that contains Command, Control, Communications, Computers, and Intelligence (C4I) Government Furnished Equipment (GFE) that is external to the Communications Suite. An example of a remote space is the Pilothouse.
Topside – Refers to all systems and structures that are installed on the external portion of the ship. Topside also includes space and weight reservations for the installation of topside antennas, with associated foundations, cabling, Radio Frequency switching and coupling hardware and components, and associated inter-dependent systems.
C4I Cabling – Refers to cabling that serves C4I equipment located within Communications Suite, remote space, and topside.
Inter-Compartment Cabling – Refers to C4I cabling that terminates one or both ends external to Communications Suite.
Intra-Compartment Cabling – Refers to C4I cabling that terminates both ends within the Communications Suite.
Government Furnished Government Installed (GFGI) – Refers to a subset of C4I GFE consisting of equipment that will be installed by the Government.
Government Furnished Contractor Installed (GFCI) – Refers to a subset of C4I GFE consisting of equipment that shall be installed by the Contractor.
3.0 General
The C4I system consists of equipment located within the Communications Suite, remote space, and topside. The work required to deliver a fully operational C4I system will be done under a turnkey approach whereby the work will be performed by both the Contractor and the Government. Section 6.0, Government Furnished Information (GFI), will provide not-to-exceed values for equipment dimensions and access envelope, weight, Heating, Ventilation, and Air Conditioning (HVAC) load, electrical load, and foundation requirements for the C4I systems.
The Contractor shall keep access envelopes free of any structure, piping, ventilation ductwork, or any other obstruction that will interfere with the installation, operation, or maintenance access to the C4I equipment. Updated GFI will include antenna locations, layout of the Communications Suite, and Center of Gravity (CG) specified at the envelope and cabinet levels, and will be provided during detail design 120 days after contract award. Remote spaces that contain C4I GFE shall have envelopes for that equipment provided with not-to-exceed values.
4.0 General Scope of Work
The Contractor shall: The Government will:
Design and construct the Communications Suite, remote space, and topside in accordance with the Statement of Work; this attachment;
the GFI listed in Section 6.2; and the other requirements of the contract.
Provide updates to this attachment and the GFI listed in Section 6.2, as required for detail design.
4.1 General Shipyard Support Requirements
4.1.1 Equipment Handling
The Contractor shall: The Government will:
Provide material handling services to include but not limited to: lifting, rigging, uncrating, unpacking, moving, and load out of the C4I equipment from the Government’s transport vehicle or Contractor temporary climate controlled storage to the Communications Suite, remote space, or topside.
Anticipate twenty six (26) lifts (20 on load, 6 off load). Heaviest on load is estimated at 459 kg.
4.1.2 GFE Load Out
The Contractor shall: The Government will:
Load out the GFE from the Government’s transport vehicle to the ship’s Communications Suite or from the contractor’s climate controlled storage facility as per schedule agreed upon between government and contractor as part of the C4I Working Group.
Provide the C4I GFCI and GFGI equipment for load out as per schedule agreed upon between government and contractor.
4.2 C4I Shipboard Requirements
4.2.1 Cabling
The Contractor shall: The Government will:
Provide, install, test, but not terminate C4I inter-compartment non-fiber cables in accordance with the GFI listed in section 6.2
Terminate all cable ends and connect the inter-compartment C4I cables to the C4I equipment.
Provide, install, test, but not terminate the C4I inter-compartment fiber cables in accordance with the GFI listed in Section 6.2
Terminate all cable ends and connect the inter-compartment C4I fiber cables to the C4I equipment.
Provide 1.5 meters of excess cable length on each cable end to be terminated by the Government Installation Team.
N/A
Seal and coil all non-terminated cable ends upon completion of installation and resealing and coil after completion of testing.
N/A
Install all Classified cables routed external to the Communications Suite as listed in the GFI listed in section 6.2 in a hardened carrier.
Physically inspect, test and terminate each of the classified cables.
4.2.2 Cable Hangers and Cable Banding
Design, provide, and install cable hangers to support all C4I cabling. This includes hangers for all inter- and intra-compartment cables.
Provide documents referenced in section 6.2
Band all C4I inter-compartment cables. Band all C4I intra-compartment cables.
4.2.3 Deck Covering
Install high voltage deck covering after completion of the Government’s installation but prior to Builder’s Dock Trials (BDT).
N/A
4.2.4 Foundations and Sway Bracing
Design, fabricate, and install foundations and sway bracing for all C4I equipment in accordance with the GFI listed in section 6.2.
This includes all topside, remote space, and Communications Suite equipment locations.
Provide in the GFI the weight and CG, of each individual equipment racks, or item to be installed on a foundation.
Drill mounting holes for Contractor-installed C4I equipment in accordance with the GFI listed in Section 6.2. This includes topside, remote space, and Communications Suite equipment locations.
4.2.5 Painting and Insulation
Complete the insulation and paint out of Communications Suite prior to the Government installation.
N/A
Cover and mask equipment to affect repairs to damaged insulation and damaged paint after completion of the Government installation but prior to BT.
4.2.6 Support Systems
The Contractor shall: The Government will:
Design, install, and test the HVAC, lighting, and convenience receptacle systems for the C4I Suite in accordance with the GFI listed in Section 6.2 and the other requirements of the contract.
Provide GFI values required for detail design.
4.2.7 Power System Requirements
Design, install, and test the power distribution systems for the C4I equipment per the GFI listed in Section 6.2.
N/A
Provide ten (10) percent spare circuit breakers within each power panel installed.
Specify in the GFI the compartment level not-to-exceed electrical power loads, quantities, and ratings of power panels and the number of circuits per power panel required in C4I Suite.
Install and feed all C4I power panels. Terminate the GFE from space power panel circuit breakers to the equipment.
4.2.8 Labels
Provide and install the necessary labels for all C4I equipment and cabling in accordance with Section 6.2.24 T-ATS Inter-Compartment Cabling List and to include but not be limited to C4I antennas, remote compartment equipment and power panels.
4.2.9 Gyrocompass System
Provide Gyrocompass information to the Communication Suite in accordance with the requirements of the contract.
4.2.10 Communication Suite Outfitting
The Contractor shall provide and install the items listed below as initial space outfitting.
Specific locations for these items will be agreed to by the C4I Working Group based on the C4I Communications Suite space layout to be provided by the Contractor.
The Government will adjust Section 6.2.6 GFI once Communications Suite dimensions and outfitting equipment dimension identified
GSA approved Class 6-S security container, Four (4) Drawer – Legal Size (H x W x D):
62.5 inches x 20.875 inches x 28 inches, NSN:
7110-01-606-5836
N/A
High Security (classified up to Top Secret) Cross Cut Shredder from NSA Evaluated Products List: Notional shredder is Capital Shredder Corporation Model K-16 Destroyer (H x W x D): 37 inches x 24 inches x 19 inches
N/A
Single Workbench (H x W x D): Notional
62.25 inches x 52 inches x 29 inches
N/A
VIDMAR Storage Locker (H x W x D):
Notional 70 inches x 36 inches x 15 inches
4.3 Communications Suite Completion, Inspection, and Turnover
4.3.1 Completion
The Contractor shall: The Government will:
Complete the Communications Suite and ship’s services to these spaces as specified in this attachment no later than 150 calendar days prior to Builder’s Dock Trials (BDT).
Conduct inspections to ensure compartment completion prior to Government acceptance of the C4I spaces.
Turn the Communications Suite space over to the Government and make services available on a continuing basis from the date 150 calendar days prior to BDT.
4.3.2 Communications Suite Acceptance Requirements
Complete the installation and testing of doors, door locks, door alarms, alarm panels, hatches, safes, hot work, and joiner work prior to turnover of the Communications Suite to the Government.
N/A
Complete the installation and testing of cabling for power distribution systems prior to turnover of the Communications Suite to the Government.
N/A
Ensure the power distribution systems remain in operable condition during the Government installation phases.
N/A
Complete the installation and testing of lighting panels, cables, fixtures, and switches prior to turnover of the Communications Suite to the Government.
N/A
Demonstrate that the lighting system is operable prior to turnover of the Communications Suite to the Government.
N/A
Ensure the lighting system remains in a continuous operable condition during the Government installation phases.
N/A
Complete the installation and testing of the HVAC system prior to turnover of the Communications Suite to the Government.
N/A
Demonstrate the HVAC system is operational 24 hours prior to the C4I equipment load out.
N/A
Ensure the HVAC system remains operational 24 hours a day until ship delivery. This shall include all ducting, alarms, and other components included in the system.
If necessary to meet the 24 hour operational requirement, the Government will accept HVAC provided by portable units, on a temporary basis, provided that the portable units are external to the Communications Suite and ducted through the normal system ducting.
Complete the installation and testing of piping, wiring, ductwork, cable-ways, and other systems that either serve or traverse the
Communications Suite prior to turnover of the Communications Suite to the Government.
Complete the installation and testing of all Contractor furnished items prior to turnover of the Communications Suite to the Government.
N/A
Complete all insulation and painting prior to turnover of the Communications Suite to the Government.
N/A
Complete the installation of all topside C4I hardware, to include antennas and associated couplers or tuners, matching networks enclosures, no later than 30 days after turnover of the Communications Suite to the Government.
N/A
Complete the installation and measurements of all C4I foundations prior to turnover of the Communications Suite to the Government.
N/A
Complete the bonding of all C4I GFCI equipment of the Communications Suite to the Government.
N/A
Complete the installation and testing of all inter-compartment cables prior to turnover of the Communications Suite to the Government.
N/A
Complete the installation and testing of power for remote C4I equipment prior to turnover of the Communications Suite to the Government.
N/A
Comply with the security requirements and other requirements for secure electronic information processing systems required by the contract.
4.4 Installation
4.4.1 C4I GFE
The Contractor shall: The Government will:
Install C4I GFCI equipment. Install C4I GFGI equipment. Deliver all GFCI antennas and other topside equipment to the Contractor for installation 180 days prior to
Builder’s Dock Trials. Deliver all other C4I equipment for the Communications Suite 150 days prior to Builder’s Dock Trials.
Install foundations, brackets, and mounts per the Outline and Mounting or Outline and Installation drawings listed in Section 6.2.
Provide outline and mounting drawings for C4I
GFE.
Provide, install, and test all inter-compartment cables in accordance with the C4I Cable list listed in Section 6.2.
Terminate those inter-compartment cables that connect to C4I GFE.
N/A Terminate and connect all intra-compartment cables
Complete the installation and testing of furniture and ancillary items no later than 45 days after turnover of the Communications Suite to the Government, or as coordinated with the C4I Working Group.
5. Government Furnished Equipment.
5.1 Projected List of C4I Systems
System Nomenclature QTY
HF Transmit/Receive System 2
RF-7800H-AD400 HF Transceiver
VHF/UHF Line of Sight (LOS)/SATCOM Voice 2
RF-300M-V250, Dual Multiband Man pack Vehicular Mount Radio
Naval Messaging 1
AN/SYQ-26(V)7 Navy Modular Automated Communications System (NAVMACS)
Next Generation Wideband System 1
Tactical Switching 1
RF-7800I Intercom System
Combined Enterprise Regional Information Exchange System (CENTRIXS) Fly Away Kit
Key Management Infrastructure (KMI) Spiral 2 Tier 3 10
Secure Data/Voice Devices
D3 MGUE Military Receiver 1
AN/APX-123A(V)3 Identification Friend or Foe (IFF) 1
5.2 Projected List of GFCI C4I Equipment
Item Description QTY 1000 HF Transmit/Receive System 1010 AT-100D, Antenna, Vertical Whip 2 1020 RF-382A, Antenna Matching Unit 2 2000 Satellite TV Antenna 2010 MS6011-4, Sea Tel COBHAM Direct to Sailor Antenna w/Radome 1 3000 VHF/UHF LOS System 3010 AV 457-6, VHF/UHF Antenna, Dipole Array 2 4000 UHF SATCOM System (OE-570B/WSC 4100 OE-570B/WSC Antenna (AS-4780/U) 1 4110 Radome 1 4120 AM-7641/U Amplifier/Filter Unit 1 4200 UHF SATCOM Omni-Direction Antenna
4210 GD-2100 MUOS SATCOM ANTENNA 1
4220 SYM 438
5000 Next Generation Wideband System 5010 SeaTel 4410W-33Ku Band Antenna Group Antenna, Parabolic with Radome 1 5020 Sailor 500 Fleet Broadband L Band Antenna Group Antenna, Parabolic with
Radome
5030 SYM 851 1
6000 Identification Friend or Foe System 6010 AS-177B/UPX Antenna, Vertical Whip 1 7000 Tactical Switching 7010 Keyboard Display Unit (RF-7800I-KD200) 6 7020 Tactical Speaker (RF-5980-SA001) 6 7030 DC power supply 1 8000 Quality Monitoring System 8010 AS-390/SRC Antenna, Vertical Stub with Ground Plane 1
9000 MGUE
9010 AS-4617/SRN Advanced Digital Antenna Production (ADAP) Global
Positioning System (GPS) Anti-jamming Antenna
6.0 Government Furnished Information.
6.1 List of Inter-Compartment Cables
6.1.1 Forty-three (43) unclassified LAN Ethernet drops shall be installed by the Contractor.
The Inter-Compartment Cabling List in Section 6.2.6.1 contains the projected compartment name and number of drops per compartment.
6.1.2 Nine (9) secure LAN Ethernet drops shall be installed by the Contractor. The Inter- Compartment Cabling List in Section 6.2.6.1 contains the projected compartment name and number of drops per compartment.
6.2 Provided Government Furnished Information
GFI will be provided and updated per Schedule C.
6.2.1 GOVERNMENT FURNISHED INFORMATION INDEX
6.2.2 TECHNICAL DATA SUMMARY, 023-000-538702 rev ()
6.2.2.1 NCS Equipment SWaP Report, 023-001-538702
6.2.3 FLOOR PLANS AND ELEVATIONS DRAWING, 040-000-538702 rev ()
6.2.3.1 Naval Communications Center Floor Plans and Elevations Drawing 040-001-538702
6.2.4 ANTENNA LAYOUTS AND ELEVATIONS DRAWING, 050-000-538702 rev ()
6.2.4.1 Antenna ADAP AS-4617/SRN, Antenna Elevations Drawing, 050-001-538702
6.2.4.2 Antenna HF AT-100D Antenna Elevations Drawing, 050-002-538702
6.2.4.3 Antenna VHF/UHF AV 457-6 Antenna Elevations Drawing, 050-003-538702
6.2.4.4 Antenna SATCOM Omni-Directional GD-2100 Antenna Elevations Drawing, 050-004- 538702
6.2.4.5 Antenna Filter AM-7641/U Elevations Drawing, 050-005-538702
6.2.4.6 Antenna Unit AS-4780/U Elevations Drawing, 050-006-538702
6.2.4.7 Antenna VHF/UHF AS-390/SRC Antenna Elevations Drawing, 050-007-538702
6.2.4.8 Antenna IFF AS-177B/UPX Antenna Elevations Drawing, 050-008-538702
6.2.4.9 SEATEL 4010W-33, Ku-Band Antenna Elevations Drawing, 050-009-538702
6.2.4.10 SAILOR 500, Fleet Broadband L-Band Antenna Elevations Drawing, 050-010-538702
6.2.4.11 MS-6011-4 Antenna Elevations Drawing, 050-011-538702
6.2.5 MECHANICAL ASSEMBLY and MOUNTING DETAILS 171-000-538702 rev ()
6.2.5.1 72 Inch AJ Rack, Mechanical Assembly and Mounting Details Drawing, 171-001-538702
6.2.5.2 NAVMACS II AN/SYQ-26(V)7 MAD II, Mechanical Assembly and Mounting Details Drawing, 171-002-538702
6.2.5.3 DC Power Supply, Mechanical Assembly and Mounting Details Drawing, 171-003- 538702
6.2.5.4 Keypad Display Unit, RF-7800I- KD200, Mechanical Assembly and Mounting Details Drawing, 171-004-538702
6.2.5.5 Speaker Unit RF-5980-SA001, Mechanical Assembly and Mounting Details Drawing, 171-005-538702
6.2.5.6 SYM-438 Terminal Box Assembly, Mechanical Assembly and Mounting Details Drawing, 171-006-538702
6.2.5.7 Antenna Coupler RF-382A, Mechanical Assembly and Mounting Details Drawing, 171- 007-538702
6.2.5.8 SYM-851 Terminal Box Assembly, Mechanical Assembly and Mounting Details Drawing, 171-008-538702
6.2.6 MISCELLANEOUS SYSTEM CONFIGURATION DETAILS
6.2.6.1 Inter-Compartment Cabling List, 190-000-538702 rev ()
6.3 Projected Topside Emitter Summary (GFE)
SYSTEM (QTY) Transmit
Frequency Receive Frequency Transmit Power Polarization Antenna Type
IFF ANTENNA,
AS-177B/UPX (1)
1030 to 1090 MHz 1030 to 1090 MHz 5 W Mean/ 600 W Peak Envelope
Power
Vertical Dipole with Conical Skirt
UHF QUALITY
MONITORING,
AS-390/SRC (1)
(receive only) 240 to 315 MHz (receive only) Vertical Bent Cross Dipole
VHF/UHF LOS
ANTENNA AV 457-6
30 to 512 MHz 30 to 512 MHz 100 W Vertical Center-Fed Dipole
UHF SATCOM
ANTENNA GROUP,
OE-570B/WSC (1)
280 to 322 MHz
243 to 270.5 MHz 338 to 380 MHz
200 W (rated) 50 watts planned
Right Hand Circular Cross-Dipoles Array
UHF Omni-Directional
SATCOM ANTENNA,
GD-2100
292 to 318 MHz
300-320 MHZ
244 to 270 MHz
360-380 MHZ
200 W (rated) 50 watts planned
Right Hand Circular Omni-Directional
SAILOR 500
FLEETBROADBAND
ANTENNA
1626.5 - 1660.5 MHz (L band)
1525.0 - 1559.0 MHz
(L band)
SEATEL 4010W-33
ANTENNA
10.70-12.75 GHz (Ku band)
13.75 – 14.5 GHZ
(Ku band)
Linear Dish- Parabolic
HF
TRANSMIT/RECEIVE
AT-100D
1.6 to 30 MHz 1.6 to 30 MHz 1500 W rated 400 watts planned
Vertical Vertical Dipole
Sea Tel COBHAM Direct to Sailor
3.625 to 4.200 GHz
10.7 to 12.75 GHz
3.625 to 4.200 GHz
10.7 to 12.75 GHz
C Band Circular, Ku Band
Linear/Circular
| 6.0 Government Furnished Information. |
| 6.1 List of Inter-Compartment Cables |
| 6.3 Projected Topside Emitter Summary (GFE) |