Attachment 10 - Quality Assurance Surveillance Form for Cathodic Protection (CP) Inspection

View the file

Other files

File Type Posted
N0002417C4100_J&A__redacted.pdf PDF
16R4100_Questions_and_Answers__16-17.pdf PDF
N00024-16-R-4100_Amend_0003.pdf PDF
Attachment_21_-_Pricing_Worksheet_(Updated_Amend_0003).xlsx XLSX spreadsheet
16R4100_Questions_and_Answers__10-15.pdf PDF
Attachment_21_-_Pricing_Worksheet_(Updated_Amend_0002).xlsx XLSX spreadsheet
N00024-16-R-4100_Amend_0002.pdf PDF
16R4100_Questions_and_Answers__2 _5-9.pdf PDF
16R4100_Questions_and_Answers__1-4.pdf PDF
N00024-16-R-4100_Amend_0001.pdf PDF
Attachment_17_-_CO2_Fire_Extinguisher_and_Dry_Chemical_Inspection_Log.pdf PDF
Attachment_16_-_Security_Violation_Report.pdf PDF
Exhbt_C_-_Past_Performance_Questionnaire.docx DOCX document
Attachment_18_-_Mooring_and_Security_Inspection_Log.pdf PDF
Attachment_13_-_Integrity_Inspection.pdf PDF
Attachment_14_-_Arrival_Inspection_Check-Off_Sheet.pdf PDF
Attachment_15_-_Inspection_of_Disposal_Vessel.pdf PDF
Attachment_19_-_Strike_Ship_Check-off_List.pdf PDF
Attachment_12_-_Quality_Assurance_Surveillance_Form_for_Fire_and_Flood_(FF)_Inspection.pdf PDF
Attachment_2_-_Safe_Stowage_Check-off_List.pdf PDF
Exhbt_B_-_Past_Performance_Data.docx DOCX document
N00024-16-R-4100.pdf PDF
Attachment_22_-_Contract_Security_Classification_Specification _DD_Form_254.pdf PDF
Attachment_11_-_Quality_Assurance_Surveillance_Form_for_Dehumidification_(DH)_Inspection.pdf PDF
Attachment_5_-_Janitorial_Task_and_Frequency_Chart.pdf PDF
Attachment_3_-_Repair_Request_Work_Order_(RRWO)(sample).pdf PDF
Attachment_20_-_Polychlorinated_Biphenyl_(PCB)_Inventory_Survey.pdf PDF
Attachment_7_-_Government_Furnished_Vehicles.pdf PDF
Attachment_21_-_Pricing_Worksheet.xlsx XLSX spreadsheet
Attachment_23_-_Quality_Assurance_Surveillance_Plan.pdf PDF
Attachment_1_-_List_of_assigned_Vessels.pdf PDF
Attachment_6_-_Government_Furnished_Equipment.pdf PDF
Exhbt_A_-_DD_Form_1423 _Contract_Data_Requirements_List.pdf PDF
Attachment_18_-_Mooring_Report_Diagram.pdf PDF
Attachment_8_-_Government_Furnished_Tools.xls XLS spreadsheet
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 10

Periodicity:Spec Code: Berthed At: Quarter:

NSTM 50 INSPECTION GUIDELINES CP1 Insp Date:

TDLRemarksN/ANOYESDescription Item

1 Power supply readings have been taken and recorded and are satisfactory.

2 System has been checked for shorts and opens and none were found.

3 Have all other discrepancies been reported? If not report them here.

C/P Rectifier

1. Annode Type Installed:

2. Number of Annodes:

3. System Arrangements:

4. Time:

5. Tide:

6. Hull Potential (high):

6a. Hull Potential (low):

7. Power Supply Output (volts):

7a. Power Supply Output (amps):

8. Ag/AgCI Reference Cell Potential: MV:

9. Ships and Floats Moored together have at least 2 Bonding Straps Each:

10. Wetted Area:

FWD Draft: AFT Draft: List:

Comments:

Inspector Inspector Inspection Manager

NSTM 50 INSPECTION GUIDELINES - Descrepancy Listing

Spec Code:

Line Item # Location Discrepancy Discovery Dt Correction Dt

NSTM 50 INSPECTION GUIDELINES CP2 Insp Date:

TDLRemarksN/ANOYESDescription Item

1 Take and record hull potential readings every 50 feet and record. All readings fall within the range of 0.8 to 1.2 volt range.

2 Current readings to each anode have been checked and are normal? Record readings.

3 Are support cords for anodes taking strain off cable?

4 Reference cell has been checked against shop standard cell and is satisfactory.

5 Potentiometer-voltmeter has been checked against a standard Weston cell or a battery with a known voltage and is within specifications or adjustments have been made to bring within specs.

6 Have all other discrepancies been reported? If not report them here.

C/P Potential

1. Annode Type Installed:

2. Number of Annodes:

3. System Arrangements:

4. Time:

5. Tide:

6. Hull Potential (high):

6a. Hull Potential (low):

7. Power Supply Output (volts):

7a. Power Supply Output (amps):

8. Ag/AgCI Reference Cell Potential: MV:

9. Ships and Floats Moored together have at least 2 Bonding Straps Each:

10. Wetted Area:

FWD Draft: AFT Draft: List:

Inspector Inspector Inspection Manager

Cathodic Protection Anode Results

Number

Cathodic Protection Hull Potential Results

Output Number Output Number Output Number Output

Number Hull Reading Number Number Number Hull Reading Hull Reading Hull Reading

NSTM 50 INSPECTION GUIDELINES CP3 Insp Date:

TDLRemarksN/ANOYESDescription Item

1 Check power supply ammeters and voltmeters against a suitable calibrated meter. Were results within specifications ?

2 Remove dust and debris from power supply enclosures. Is the general condition satisfactory ?

3 (Automatic hull potential control only) Check reference electrode on the unit against a standard cell. Is the error

0.05 volts or less compared to standard silver-silver chloride reference cell?

4 Clean all exposed terminal connection, ship bonds, rectifier connections, ground return connections by sandpapering.

Have all listed connections been sandpapered and in good condition?

5 All ships in nest have CP installed.

6 Are there 2 bonding cables installed, one fwd and one aft between ships. (Ships over 400 foot long require a third bonding cable in the middle)

7 Have all other discrepancies been reported? If not report them here.

C/P System Check

1. Annode Type Installed:

2. Number of Annodes:

3. System Arrangements:

4. Time:

5. Tide:

6. Hull Potential (high):

6a. Hull Potential (low):

7. Power Supply Output (volts):

7a. Power Supply Output (amps):

8. Ag/AgCI Reference Cell Potential: MV:

9. Ships and Floats Moored together have at least 2 Bonding Straps Each:

10. Wetted Area:

FWD Draft: AFT Draft: List:

Inspector Inspector Inspection Manager

NSTM 50 INSPECTION GUIDELINES CP4 Insp Date:

TDLRemarksN/ANOYESDescription Item

1 (Automatic hull pontential control only) Record the date the reference electrode was installed. Does the reference electrode require replacement ? (must be replaced every 5 years)

2 Have all other discrepancies been reported? If not report them here.

C/P Electrode (Auto Systems)

1. Annode Type Installed:

2. Number of Annodes:

3. System Arrangements:

4. Time:

5. Tide:

6. Hull Potential (high):

6a. Hull Potential (low):

7. Power Supply Output (volts):

7a. Power Supply Output (amps):

8. Ag/AgCI Reference Cell Potential: MV:

9. Ships and Floats Moored together have at least 2 Bonding Straps Each:

10. Wetted Area:

FWD Draft: AFT Draft: List:

Inspector Inspector Inspection Manager

Cathodic Protection Anode Results

Number

Cathodic Protection Hull Potential Results

Output Number Output Number Output Number Output

Number Hull Reading Number Number Number Hull Reading Hull Reading Hull Reading