16R4100_Questions_and_Answers__10-15.pdf

PDF 125 KB Posted

Attached to
Operation and Maintenance of Philadelphia Inactive Vessels and CG/LSD Modernization
Solicitation number
N00024-16-R-4100
Issued by

About this file

Questions and Answers 10-15

View the file

Other files

File Type Posted
N0002417C4100_J&A__redacted.pdf PDF
16R4100_Questions_and_Answers__16-17.pdf PDF
N00024-16-R-4100_Amend_0003.pdf PDF
Attachment_21_-_Pricing_Worksheet_(Updated_Amend_0003).xlsx XLSX spreadsheet
Attachment_21_-_Pricing_Worksheet_(Updated_Amend_0002).xlsx XLSX spreadsheet
N00024-16-R-4100_Amend_0002.pdf PDF
16R4100_Questions_and_Answers__2 _5-9.pdf PDF
16R4100_Questions_and_Answers__1-4.pdf PDF
N00024-16-R-4100_Amend_0001.pdf PDF
Attachment_17_-_CO2_Fire_Extinguisher_and_Dry_Chemical_Inspection_Log.pdf PDF
Attachment_16_-_Security_Violation_Report.pdf PDF
Exhbt_C_-_Past_Performance_Questionnaire.docx DOCX document
Attachment_18_-_Mooring_and_Security_Inspection_Log.pdf PDF
Attachment_13_-_Integrity_Inspection.pdf PDF
Attachment_14_-_Arrival_Inspection_Check-Off_Sheet.pdf PDF
Attachment_15_-_Inspection_of_Disposal_Vessel.pdf PDF
Attachment_19_-_Strike_Ship_Check-off_List.pdf PDF
Attachment_12_-_Quality_Assurance_Surveillance_Form_for_Fire_and_Flood_(FF)_Inspection.pdf PDF
Attachment_2_-_Safe_Stowage_Check-off_List.pdf PDF
Exhbt_B_-_Past_Performance_Data.docx DOCX document
Attachment_10_-_Quality_Assurance_Surveillance_Form_for_Cathodic_Protection__(CP)_Inspection.pdf PDF
N00024-16-R-4100.pdf PDF
Attachment_22_-_Contract_Security_Classification_Specification _DD_Form_254.pdf PDF
Attachment_11_-_Quality_Assurance_Surveillance_Form_for_Dehumidification_(DH)_Inspection.pdf PDF
Attachment_5_-_Janitorial_Task_and_Frequency_Chart.pdf PDF
Attachment_3_-_Repair_Request_Work_Order_(RRWO)(sample).pdf PDF
Attachment_20_-_Polychlorinated_Biphenyl_(PCB)_Inventory_Survey.pdf PDF
Attachment_7_-_Government_Furnished_Vehicles.pdf PDF
Attachment_21_-_Pricing_Worksheet.xlsx XLSX spreadsheet
Attachment_23_-_Quality_Assurance_Surveillance_Plan.pdf PDF
Attachment_1_-_List_of_assigned_Vessels.pdf PDF
Attachment_6_-_Government_Furnished_Equipment.pdf PDF
Exhbt_A_-_DD_Form_1423 _Contract_Data_Requirements_List.pdf PDF
Attachment_18_-_Mooring_Report_Diagram.pdf PDF
Attachment_8_-_Government_Furnished_Tools.xls XLS spreadsheet
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVAL SEA SYSTEMS COMMAND

N00024-16-R-4100

QUESTIONS AND ANSWERS #10-15

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

10. Q: In case the Contractor performs the entire level of effort on its own there will be no subcontractor assigned to any portion of the level of effort. Please confirm that the requirement for data submittal as described in Section L-3

Subcontractor Costs, will not be applicable.

a. Please also clarify how the specialized reimbursable subcontracted services (e.g. security/guard services) will be structured into the total cost?

b. Historically these type of costs were summarized in a designated ODC item (“Subcontractor”) as a plug number provided by the RFP.

A: If subcontractor costs are not associated, than data submittal as described in Section L-3 is not required .

Subcontractor costs shall be identified in the tabs in Attachment 21 under “Subcontracts” along with subcontractor cost proposal information. Plug in numbers for subcontractor costs are not provided.

11. On Attachment 21 provided, on the Philly pages, the line titled " Total Estimated Cost " has the formula: Subtotal Cost plus Total FCOM cost. On the Norfolk pages, the line titled "Total Estimated Cost" has the formula: Subtotal Cost only

(this ceil does not include the FCOM cost.) Therefore the FCOM is not in the " Total Estimated Costs Plus Fixed Fee " amount for each Norfolk page. The Summary Page is correct , just the individual Norfolk Pages are off.

A: The Norfolk tabs have been updated to include the “Total Cost of Money” to the "Total Estimated Cost." See revised Attachment 21 via Amendment 0003.

12. If the plan is to employ individuals for many of the positions on a salary basis, what justification is allowed for this situation?

A: Employment and terms of compensation are at the discretion of the Offeror. The requirement in Section L-2 Labor

Rates shall apply as stated: “The Offeror shall provide the unburdened direct labor rates for all personnel proposed. The proposed labor rates should be arrived at by utilizing the actual labor rates for personnel proposed. Provide escalation rates for out years and basis. The Offeror shall substantiate all labor rates in the Offeror’s proposal by providing, e.g., payroll data, job offer letters, DCAA approved rates etc.”

13. What is to be included in uncompensated overtime? If it is uncompensated, why is it included in the bid? Will it in fact be compensated if it is identified in the bid?

A: Proposing uncompensated effort/overtime is at the discretion of the Offeror. If applicable and proposed, see RFP

Section L-2 Labor Rates, which states “If the Offeror proposes uncompensated overtime it shall be clearly identified and shall comply with the requirements of FAR 52.237-10 “Identification of Uncompensated Overtime.” Additionally, Offerors shall provide data to substantiate uncompensated overtime, e.g., by providing decremented rates of preceding year for the individual for whom the uncompensated overtime is proposed, signed letter of agreement for uncompensated overtime from the individual proposed, etc.”

14. Please clarify the satellite office vs. main office requirement. Is there a limitation on the location of the main office? Is there a limit on the number of main offices if the bid effort is split between a prime and subcontractor?

NAVAL SEA SYSTEMS COMMAND

N00024-16-R-4100

A: There is no limitation on the location of the prime and subcontractor offices.

15. Is the page limit 50 one sided pages or 50 printed on both sides?

A: Per Section L-II, the page limit for Volume I is fifty (50) pages total. One (1) single sided printed page equals one (1) page. One double sided printed page equals two (2) pages.