Atch 11. Repair Roof & Upgrade UPS HVAC Pre Proposal Q&As - C.pdf

PDF 79 KB Posted

Attached to
Repair Roof and Upgrade HVAC and UPS System B328
Solicitation number
MXDP10-A058
Issued by

About this file

This document contains pre-proposal questions and answers regarding a federal contract opportunity to repair the roof and upgrade the HVAC and UPS systems on Building 328 at Laughlin Air Force Base. The scope of work includes replacing the single-ply roofing system with a new white EPDM membrane roof, upgrading controls on the UPS system to enable remote monitoring and alarming, and improving HVAC system serving UPS rooms. Questions addressed specifications for the roof replacement, availability of construction drawings, composition of the existing roof, scope of reinstalling lightning protection, requirements for parapet walls, allowance of TPO roofing in lieu of EPDM, and whether roof drains require replacement. The opportunity is solicited under solicitation number MXDP10-A058 and has an anticipated award as a firm-fixed price contract. This acquisition is set aside only for women-owned small businesses with a NAICS code of 238160 and size standard of $16.5 million.

View the file

Other files

File Type Posted
Solicitation Amendment FA309920R00080008 SF 30.pdf PDF
Atch 13 Repair Roof Upgrade UPS-HVAC Pre-Proposal Questions Answers - D.pdf PDF
Solicitation Amendment FA309920R00080007 SF 30.pdf PDF
Solicitation Amendment FA309920R00080006 SF 30.pdf PDF
Atch 12 - Fire Alarm Panel Photos.pdf PDF
FA309920R00080005 SF 30.pdf PDF
FA309920R00080004 SF 30.pdf PDF
Atch 10. Repair Roof & Upgrade UPS HVAC Pre Proposal Q&As - B.pdf PDF
Solicitation Amendment FA309920R00080003 SF 30.pdf PDF
Atch 9. Repair Roof & Upgrade UPS HVAC Pre Proposal Q&As.pdf PDF
Solicitation Amendment FA309920R00080002 SF 30.pdf PDF
Solicitation Amendment FA309920R00080001 SF 30.pdf PDF
6 - Blank DD Form 1354.pdf PDF
Atch A. FAA Form 7460-1.pdf PDF
Atch D. AF IMT 3000, Material Submittal.pdf PDF
Atch 5. AETC 47.pdf PDF
Atch G. AF IMT 3064 Contract Progress Schedule.pdf PDF
Atch 7. Past Performance Questionnaire.pdf PDF
Atch E. Schedule of Submittals FLight Simulator Bldg 328.xlsx XLSX spreadsheet
Atch F. AF Form 3952-Chemical-Hazardous Material Request.pdf PDF
Atch 3. Wage Determination TX20200186.pdf PDF
Atch C. Division 01 Specifications.pdf PDF
MFR HVAC SOW Atch 5 - Blank Progress Schedule and Report.pdf PDF
2 - Design Drawings B328.pdf PDF
3 - B328 Design Specifications.pdf PDF
Atch H. AF IMT 3065 Contract Progress Report.pdf PDF
Atch I. DD Form 1354 Transfer and Acceptance of DoD Real Property.pdf PDF
Atch B. Environmental Quality Construction Specifications LAFB.pdf PDF
Atch 6. Financial Institution Reference Sheet.pdf PDF
4 - Asbestos Survey Report B328.pdf PDF
Atch J. Photographs Bldg 328 Roof.pdf PDF
Solicitation - FA309920R0008.pdf PDF
Atch 1. SOW MXDP 10-A058 Repair Roof Flight Simulator - B328.pdf PDF
Atch 8. HVAC Chiller System Justification and Approval, 7 Aug 19.pdf PDF
Atch 4. Notification of Compliance with Contract Insurance Requirements.pdf PDF
Atch 2. SOW MXDP 16-1015 Upgrade UPS-HVAC Systems Flight Sim - B328.pdf PDF
7 - Schedule of Material Submittals.xlsx XLSX spreadsheet
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Roof and Upgrade HVAC and UPS System B328 Pre-Bid Questions C

FA309920R0008

14 August 2020

Below are our questions for the above mentioned project.

#1. Will a full set of specifications for the roof replacement requirements (division 7) be included so all bidders are bidding the same roof requirements?

CEN Response: No. Any proven roofing systems meeting all requirements as described in SOW is acceptable. Contractor shall submit roofing specifications for approval.

#2. Is there are set of original construction drawings or Red Line drawings available that show both architectural and structural details that can be provided to help understand the existing roof construction?

CEN Response: No. There are no as-built drawings.

#3. Has there been a core cut done on the existing roof to verify the composition?

CEN Response: No.

#4. What is the scope of work for the existing lightning protection that will need to be removed during the re-roofing process?

CEN Response: Contractor shall remove and re-install the existing lightning protection.

#5. Will the existing parapet walls require a new nailer and a metal coping system or will they be left as is?

CEN Response: Existing parapet walls shall require new nailer and metal coping system.

#6. The scope of work designates a new EPDM roof system. Can a TPO single-ply roof system be installed instead?

CEN Response: No. The Government shall not consider any substitute for the EPDM roofing system.

#7. Will the existing roof drains require replacement and or testing?

CEN Response: Refer to SOW Section 4.4.

#8. The requirement for insulation in the scope of work states to meet R-30 is this an average R- value or a minimum R- value?

CEN Response: R-30 shall be the minimum R-value.