MtHome Chapel BID Specifications 10.28.2021.pdf

PDF 6 MB Posted

Attached to
Z2DZ--36C249-21-AP-3989 - Project 621-20-101 Correct FCA Deficiencies w Historical Chapel Building 13
Solicitation number
36C24921B0017
Issued by

About this file

This federal presolicitation notice describes a requirement for construction services. The James H. Quillen VA Medical Center in Mountain Home, Tennessee seeks to correct all facility condition assessment deficiencies in the Historical Chapel Building 13. Work includes selective demolition, abatement of environmental hazards, modification, restoration and new construction of interior and exterior features such as roofing, walls, stairs, sidewalks, and mechanical, electrical and plumbing systems. The estimated value is between $2-5 million. The solicitation will be issued on October 15th, closing on November 16th, and will be a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. The NAICS code is 236220 and size standard is $39.5 million. Questions must be submitted in writing by email to the listed contracting specialist by the solicitation date. Only SDVOSBs verified in the CVE database and registered in SAM may respond. The awardee must also enroll in VETS-4212.

View the file

Other files

File Type Posted
36C24921B0017 0007.pdf PDF
36C24921B0017 0006.pdf PDF
36C24921B0017 0005.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part2.pdf PDF
070150.74 Rehabilitation of EPDM Roofing.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part1.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part4.pdf PDF
000110 - Table of Contents.pdf PDF
RFI Bldg 13 Chapel.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part3.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part5.pdf PDF
36C24921B0017 0004.docx DOCX document
36C24921B0017 0003.docx DOCX document
36C24921B0017 0002.pdf PDF
Pre-Bid Sign-In Sheet Bldg. 13 Chapel 11-29-2021.pdf PDF
ACM LBP Survey Report.pdf PDF
Lead-Based Paint Removal Plan.pdf PDF
VA Church Report.pdf PDF
Organ Evaluation Report.pdf PDF
Site Investigation Report.pdf PDF
36C24921B0017 0001.docx DOCX document
Asbestos Removal Plan.pdf PDF
Mt Home Chapel B13 - Bid Documents_Part1.pdf PDF
WD TN20210111 1-1-2021.pdf PDF
Mt Home Chapel B13 - Bid Documents_Part3.pdf PDF
Mt Home Chapel B13 - Bid Documents_Part4.pdf PDF
36C24921B0017_1.docx DOCX document
Contractor EMR Certification Form.docx DOCX document
VHA Supp Contract Req Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.pdf PDF
RFI Form - Mt. Home Chapel B13.docx DOCX document
Mt Home Chapel B13 - Bid Documents_Part2.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF VETERANS AFFAIRS

James H. Quillen VA Medical Center

Mt. Home, Tennessee

Veterans Way Mt. Home, TN 37604

Correct FCA Deficiencies w/Historical Chapel Bldg 13

Project No.: #621-20-101

Bid Documents

Prepared By:

July 2021

James H. Quillen VA Medical Center, Project 621-20-101 AE Correct FCA Deficiencies with Historical Chapel Bldg 13

11-01-20

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 00b Quality Control Reports 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-21 01 74 19 Construction Waste Management 01-21 01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 82 11 Traditional Asbestos Abatement 05-21 02 83 33.13 Lead-Based Paint Removal and Disposal 05-21

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 01 00 Maintenance of Masonry 01-21 04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 01-21 04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 31 00 Steel Decking 02-16 05 40 00 Cold-Formed Metal Framing 05-16 05 50 00 Metal Fabrications 08-18 05 50 01 Metal Cross 05 50 02 Chapel Bell Restoration

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

11-01-20

00 01 10-2

SECTION NO. DIVISION AND SECTION TITLES DATE

06 10 00 Rough Carpentry 10-17 06 20 00 Finish Carpentry 01-21 06 00 02 Wood Restoration 08-16

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 11 13 Bituminous Dampproofing 01-21 07 12 00 Built-Up Bituminous Waterproofing 01-21 07 21 13 Thermal Insulation 01-21 07 22 00 Roof and Deck Insulation 01-21 07 31 26 Slate Shingles 01-21 07 51 00 Built-Up Bituminous Roofing 08-18 07 60 00 Flashing and Sheet Metal 01-21 07 72 00 Roof Accessories 01-21 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 51 13 Aluminum Windows 04-20 08 71 00 Door Hardware 04-20 08 71 00b Door Hardware Attachment 1 08 88 00 Glazing 01-21

DIVISION 09 – FINISHES

09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 06-18 09 24 00 Portland Cement Plastering 01-21 09 26 00 Veneer Plastering 01-21 09 29 00 Gypsum Board 04-20 09 30 13 Ceramic/Porcelain Tiling 01-21 09 66 16 Terrazzo Floor Tile 10-15 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21 10 28 00 Toilet, Bath, and Laundry Accessories 01-21 10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 12 – FURNISHINGS

12 17 00 Leaded Stained-Glass Windows - Restoration

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components 01-14

11-01-20

00 01 10-3

DIVISION 21 - FIRE SUPPRESSION

21 13 16 Dry-Pipe Sprinkler Systems 01-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20 22 05 19 Meters and Gages for Plumbing Piping 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 11 00 Facility Water Distribution 11-19 22 13 00 Facility Sanitary and Vent Piping 09-20 22 14 00 Facility Storm Drainage 09-15 22 33 00 Electric Domestic Water Heaters 09-20 22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 09 23 Direct-Digital Control System for HVAC 08-20 23 21 13 Hydronic Piping 02-20 23 21 23 Hydronic Pumps 02-20 23 22 13 Steam and Condensate Heating Piping 02-20 23 25 00 HVAC Water Treatment 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 37 00 Air Outlets and Inlets 02-20 23 81 00 Decentralized Unitary HVAC Equipment 03-20 23 82 00 Convection Heating and Cooling Units 03-20 23 82 16 Air Coils 03-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 41 00 Facility Lightning Protection 01-17 26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 01-18

11-01-20

00 01 10-4

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 10 00 Control, Communication and Signal Wiring 06-15 27 11 00 Communications Equipment Room Fittings 06-15 27 15 00 Communications Structured Cabling 01-16

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12 31 31 16 Termite Control

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 17 23 Pavement Markings 08-16

DIVISION 33 – UTILITIES

33 46 13 Foundation Drainage 10-11

05-01-20

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G000 COVER SHEET

G001 GENERAL NOTES, ABBREVIATIONS, AND SYMBOLS

GI002 CODE PLAN, CODE NOTES

CIVIL

CD100 DEMOLITION PLAN

CS100 SITE PLAN

CG100 GRADING AND SWPP PLAN

CG101 STORM WATER MANAGEMENT PLAN

CU100 UTILITY PLAN

CS500 DETAILS AND EROSION CONTROL GENERAL NOTES

STRUCTURAL

SD101 STRUCTURAL DEMOLITION PLAN

SS101 ENLARGED STRUCTURAL PLANS

SS201 STRUCTURAL ELEVATIONS

SS501 STRUCTURAL SECTIONS

SS601 STRUCTURAL DETAILS

ARCHITECTURAL

AD101 DEMOLITION FLOOR PLAN - BASEMENT

AD102 DEMOLITION FLOOR PLAN – FIRST FLOOR

AD103 DEMOLITION FLOOR PLAN – BALCONY AND TOWER

AD141 DEMOLITION REFLECTED CEILING PLAN

AE101 FLOOR PLAN - BASEMENT

AE102 FLOOR PLAN – FIRST FLOOR

AE103 FLOOR PLAN – BALCONY AND TOWER

AE131 ROOF PLANS

AC141 REFLECTED CEILING PLAN

AE201 ELEVATIONS

05-01-20

00 01 15 - 2

AE202 ELEVATIONS

AE203 ELEVATIONS

AE204 ELEVATIONS

AE301 WEST CHAPEL – SECTIONS

AE302 NORTH CHAPEL – SECTIONS

AE311 WALL SECTIONS

AE401 ENLARGED RESTROOM PLANS, ELEVATIONS, AND

DETAILS

AE402 ENLARGED ORGAN & BELL PLANS, ELEVATIONS AND

DETAILS

AS431 ENLARGED RAMP – SECTIONS, ELEVATIONS, AND

DETAILS

AS432 ENLARGED STAIR – SECTIONS, ELEVATIONS, AND

DETAILS

AE441 ENLARGED INTERIOR SECTIONS AND ELEVATIONS

AS501 EXTERIOR DETAILS

AS502 INTERIOR DETAILS

AE601 DOOR SCHEDULE AND DETAILS

AE602 WINDOW SCHEDULE AND DETAILS

AE611 SIGNAGE PLAN AND SCHEDULE

AF801 FINISH SCHEDULE, LEGEND AND GENERAL DETAILS

FIRE PROTECTION

FD101 BASEMENT FIRE PROTECTION DEMOLITION PLAN

FX101 BASEMENT & FIRST FLOOR FIRE SUPPRESSION PLANS

FX102 SECOND FLOOR & BELL TOWER FIRE SUPPRESSION

PLANS

PLUMBING

P001 PLUMBING LEGEND SHEET

PD101 BASEMENT & FIRST FLOOR PLUMBING DEMOLITION

PLANS

PL101 BASEMENT & FIRST FLOOR PLUMBING NEW WORK PLANS

PL501 PLUMBING SCHEDULES & DETAILS

PL901 PLUMBING ISOMETRIC DIAGRAMS

MECHANICAL

M001 MECHANICAL LEGEND

05-01-20

00 01 15 - 3

MD101 BASEMENT MECHANICAL DEMOLITION PLAN

MD102 FIRST FLOOR MECHANICAL DEMOLITION PLAN

MH101 BASEMENT MECHANICAL NEW WORK PLAN

MH102 FIRST FLOOR MECHANICAL NEW WORK PLAN

MP101 BASEMENT MECHANICAL PIPING NEW WORK PLAN

MP102 FIRST FLOOR MECHANICAL PIPING NEW WORK PLAN

M501 MECHANICAL DETAILS I

M502 MECHANICAL DETAILS II

M601 MECHANICAL SCHEDULES I

M602 MECHANICAL SCHEDULES II

M701 MECHANICAL CONTROLS I

M702 MECHANICAL CONTROLS II

ELECTRICAL

E001 LEGEND & ABBREVIATIONS

ED101 BASEMENT & FIRST FLOOR DEMOLITION PLAN

ED102 SECOND FLOOR DEMOLITION PLAN

EL101 BASEMENT & FIRST FLOOR LIGHTING PLAN

EL102 SECOND FLOOR LIGHTING PLAN

EP101 BASEMENT & FIRST FLOOR POWER AND TECHNOLOGY

PLAN

EP102 SECOND FLOOR POWER AND TECHNOLOGY PLAN

ELP101 LIGHTNING PROTECTION PLAN

ES100 ELECTRICAL SITE PLAN

E501 ELECTRICAL DETAILS

E502 TECHNOLOGY DETAILS

E601 SINGLE-LINE DIAGRAM

E602 SCHEDULES

- - - END - - -

01-01-21

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for AE Correct FCA Deficiencies with Historical Chapel Building 13 as required by drawings and specifications.

B. A single one-time site visit for all Bidders will be scheduled.

C. Offices of FFE Inc. 110 Boggs Lane, Suite 170, Springdale, OH 45246 as

Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the

Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting

Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. BID ITEM 1, BASE BID: Work includes general construction, alterations, walks, grading, drainage, construction and certain other items. The building includes approximately 6,352 square feet of existing space on the first floor, second floor, and basement with crawl space including utilities. Work includes selective demolition, abatement of environmental hazards including mold, LBP, and ACM, modification, restoration, and new construction of existing interior and exterior features such as: roof, exterior walls, stairs, ramps, handrails, VHAMOULopezJ Line

01-01-21

01 00 00 -2 concrete sidewalks, landscaping, accent lighting, building-mounted lighting, and signage; interior walls, floors, ceilings; doors and frames, and signage; floors, walls and ceiling finishes; finished carpentry; Chapel organ restorations, mechanical HVAC including air handling units, electrical power and lighting systems; plumbing systems including domestic water, data and communications systems; fire suppression. The number of Days for the project is 365 days.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

B. Hazardous Material Reports, Roof Investigation Report, Site Investigation report and Chapel Organ Evaluation Report are available for review as Reference Documents.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

B. BID ITEM 2: All work in BID ITEM 1, BASE BID , except all standard glazing is installed in lieu of laminated glazing. This item is referred to as Alternate #2 in the Drawings. The number of Days for the project is 350 days.

C. BID ITEM 3: All work in BID ITEM 2, except DELETE all labor and materials associated with the reinstallation and restor ation of the Chapel organs.

The organ will still be removed and stored on-campus in this Bid

Item. Provide proper containers to transport and house organ parts in humidity-controlled environments for an extended period as recommended by Organ Restoration Contractor. The VA will refurbish and re install the organs in a separate bid package. The number of Days for the project is 320 days.

01-01-21

01 00 00 -3

2. Before starting work the General Contractor shall give three weeks’ notice to the Contracting Officer so that security arrangements can be provided for the contractor’s employees and all subconsultant employees. The names of any new employee(s) added to any of the contractor’s or subconsultant’s teams during the project duration shall be provided to the Contracting Officer three weeks before they are allow on site. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation . See Section 08 71

00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

01-01-21

01 00 00 -4

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2) permits shall be issued for General Contractor and its employees for parking in designated areas only.

Contractor to coordinate with VA Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

01-01-21

01 00 00 -5

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways when and as authorized by the

Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any

Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as shown on the drawings and as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment, and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR. All such actions shall be coordinated with the COR or Utility Company involved:

01-01-21

01 00 00 -6

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and

Contractor. Contractor is responsible to submit to the COR a phasing plan with schedules prior to the start of construction.

J. Building No. 13 will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to

Proceed and turned over to Contractor.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area for the entire perimeter of project work zone. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Fence fabric to be installed on all perimeter fencing. Fabric to be green with 85% visual blockage HDPE UV protected material. Provide solid brass grommets every 24” o.c. top and bottom on all perimeter fencing.

01-01-21

01 00 00 -7

Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by the COR.

L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to the COR, in writing, 7 days in advance of proposed interruption.

Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least

01-01-21

01 00 00 -8 inconvenience to operations of the Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

01-01-21

01 00 00 -9

1.7 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.8 IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

01-01-21

01 00 00 -10

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge

Elimination System (NPDES) permit is required for this project. The

Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.

Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the

Contractor's method of operations and operations planning and the

Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall

01-01-21

01 00 00 -11 conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SOIL CONDITIONS

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Terracon, Raleigh, NC.

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.

C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical

Center, and shall be considered part of the contract documents.

D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make

01-01-21

01 00 00 -12 their bids accordingly. Upon proper application to Department of

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.

The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The

Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.

If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey

01-01-21

01 00 00 -13 shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

E. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of

Article "Professional Surveying Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit two copies of the warranty management plan. Include within the warranty

01-01-21

01 00 00 -14 management plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4-month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty

01-01-21

01 00 00 -15 of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect

01-01-21

01 00 00 -16 to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.

Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

Fire suppression systems.

Fire alarm system(s).

01-01-21

01 00 00 -17

b) Code 1-Air Conditioning Systems

Air conditioning leak in part of the building, if causing damage.

Air conditioning system not cooling properly.

c) Code 1 Doors

Overhead doors not operational, causing a security, fire or safety problem.

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

Overhead doors not operational.

Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

Power failure (entire area or any building operational after

1600 hours).

Security lights.

Smoke detectors.

f) Code 2-Electrical

Power failure (no power to a room or part of building).

Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical Exterior lights not operational.

h) Code 1-Gas

Leaks and pipeline breaks.

i) Code 1-Heat

Power failure affecting heat.

j) Code 1-Plumbing

Hot water heater failure.

2) Leaking water supply pipes

k) Code 2-Plumbing

Flush valves not operating properly Fixture drain, supply line or any water pipe leaking.

Toilet leaking at base.

l) Code 3- Plumbing Leaky faucets.

01-01-21

01 00 00 -18

m) Code 3-Interior

Floors damaged.

Paint chipping or peeling.

Casework damaged.

n) Code 1-Roof Leaks

Damage to property is occurring.

o) Code 2-Water (Exterior) No water to facility.

p) Code 2-Water (Hot) No hot water in portion of building listed.

q) Code 3

All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting

Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

01-01-21

01 00 00 -19

1.16 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR. When necessary, to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges. Grass areas damaged by construction activities must be replaced with healthy sod.

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used

01-01-21

01 00 00 -20 in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used…