About this file

This presolicitation notice is for a construction project to correct all facility condition assessment deficiencies at the Historical Chapel building at the James H. Quillen VA Medical Center in Mountain Home, Tennessee. The project includes general construction, alterations, abatement of environmental hazards including mold, lead-based paint and asbestos-containing materials, restoration, and new construction of exterior features such as roofing, walls, stairs and ramps; and interior features such as walls, floors, ceilings, doors, mechanical and electrical systems, and plumbing. The estimated value is between $2-5 million. Responses are due between October 15th and November 16th, 2021. This opportunity is a 100% set-aside for service-disabled veteran-owned small businesses. The NAICS code is 236220 and the small business size standard is $39.5 million. Questions must be submitted in writing by email and reference the project number, name, and solicitation number. The Department of Veterans Affairs Veterans Health Administration is the contracting agency.

View the file

Other files

File Type Posted
36C24921B0017 0007.pdf PDF
36C24921B0017 0006.pdf PDF
36C24921B0017 0005.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part2.pdf PDF
070150.74 Rehabilitation of EPDM Roofing.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part1.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part4.pdf PDF
000110 - Table of Contents.pdf PDF
RFI Bldg 13 Chapel.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part3.pdf PDF
Mt Home Chapel B13 - Amendment 0005_Part5.pdf PDF
36C24921B0017 0004.docx DOCX document
36C24921B0017 0003.docx DOCX document
36C24921B0017 0002.pdf PDF
Pre-Bid Sign-In Sheet Bldg. 13 Chapel 11-29-2021.pdf PDF
ACM LBP Survey Report.pdf PDF
Lead-Based Paint Removal Plan.pdf PDF
VA Church Report.pdf PDF
Organ Evaluation Report.pdf PDF
Site Investigation Report.pdf PDF
36C24921B0017 0001.docx DOCX document
Mt Home Chapel B13 - Bid Documents_Part1.pdf PDF
WD TN20210111 1-1-2021.pdf PDF
Mt Home Chapel B13 - Bid Documents_Part3.pdf PDF
Mt Home Chapel B13 - Bid Documents_Part4.pdf PDF
36C24921B0017_1.docx DOCX document
Contractor EMR Certification Form.docx DOCX document
MtHome Chapel BID Specifications 10.28.2021.pdf PDF
VHA Supp Contract Req Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.pdf PDF
RFI Form - Mt. Home Chapel B13.docx DOCX document
Mt Home Chapel B13 - Bid Documents_Part2.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building 13 Renovations VA Project No. 621-20-101

Asbestos Removal Section 02 82 11 -1

Asbestos-Containing Materials Section 02 82 11

1.0 GENERAL REQUIREMENTS

1.1. General Information

Building 13 will undergo extensive renovations. Asbestos-containing materials have been identified and will require abatement to facilitate renovations. The following plan outlines work practices required at this site. This work will be contracted under a single contract and other specifications, drawings, and general provisions of the contract referenced under other specifications provided by Architect shall apply.

The Owner for this project is James H. Quillen VA Medical Center. The Architect for this project is FFE, Inc. and is referred to throughout this Plan as “Architect.” The Owner’s authorized representative for the purposes of asbestos abatement is referred to as Engineer, Designer, or Air Monitoring Firm throughout the Plan. The Engineer, Designer, or Air Monitoring Firm will advise and consult with the Owner and Architect.

The Contractor is the person or entity identified as such in the Owner-Contractor Agreement and is referred to throughout the Plan as “Contractor.” The term Contractor means the Asbestos Abatement Contractor for the purposes of this Plan. The Owner will contract with a qualified abatement Contractor.

1.2. Scope of Work

1.2.1. The scope of work includes the cleaning, removal, and disposal of asbestos-containing materials (ACM) in the building structure as identified on the drawings in the specifications. A summary of the asbestos-testing results is provided at the end of this section.

1.2.2. The following removal work practices are required for the identified ACM.

Additional requirements are provided in Section 3.0.

Asbestos Removal Section 02 82 11 -2

Material Full Containment

Non- Friable

Removal Notes

TSI Contaminated Debris

See Notes No Due to the limited amount of this material (30 square feet), a full containment is not required. A “mini-enclosure” can be utilized during the removal/abatement process.

Silver Duct Mastic No See Notes

While this material is listed as being in a friable state, it can be removed intact with the ductwork so long as both materials are wrapped in poly sheeting and sealed prior to the removal.

Exterior Door Caulking No See Notes

While this material is listed as being in a friable state, the removal will occur outdoors and will follow standard outdoor removal practices i.e.; use of a drop cloth, PPE, barricade tape, signage, etc.

Gray Mortar Joint Caulking

No Yes

Black Mastic on Downspout Connections

No Yes

Residual Flashing Mastic

No Yes

Brown/Gold Stair Tread Mastic

No Yes

Please note the above materials were materials found during the January 12th and 13th, 2021 survey. The Architect and Owner shall designate which materials are to be removed during the renovations and which are to remain. Those that are to remain must be put into the management plan and handled according to Veteran’s Administration practices.

1.2.3. The Contractor shall be prepared to provide temporary power and water.

Temporary power and water piping shall be secured so that it does not present a hazard to onsite workers and authorized visitors. The Contractor shall also be responsible for providing electrical power to the air monitoring firm for air sample collection.

1.2.4. Air filtration devices are required to run continuously during a regulated abatement project. The work area shall be sealed and locked to prevent access during non-working hours.

1.2.5. Authorized workers: All workers performing work within asbestos work areas at this site must be licensed by Tennessee with an appropriate asbestos credential.

1.2.6. Asbestos-containing material found to extend from the designated areas into, through, above, or below walls, ceilings, roofs, behind paneling, above ceilings, or other barriers is also included in this specification.

Asbestos Removal Section 02 82 11 -3

1.2.7. Discovery of other hazardous materials. If hazardous materials other than asbestos debris, such as stored chemicals, are discovered during the course of the work, the Contractor shall cease work in the affected area and immediately assess the area. The Owner shall be notified within the work shift of discovery.

1.2.8. The Contractor shall assume full responsibility and liability for the compliance with all applicable federal, state and local regulations pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor is responsible for providing medical examinations and maintaining medical records of personnel as required by the applicable federal, state, and local regulations. The Contractor shall hold the Owner, Architect, and Engineer/Air Monitoring Firm harmless for failure to comply with any applicable work, hauling, disposal, safety, health or other regulation on the part of itself, its employees, or its subcontractors.

1.2.9. Contractor must furnish all permits, labor, material, services, insurance, tools, equipment (including, but not limited to, power and water), and notifications in accordance with EPA, OSHA, State, and all other applicable agencies to complete removal of asbestos containing materials from the structure. It is the Contractor’s responsibility to be aware of and obtain all permits necessary to complete the scope of work.

1.2.10. The Contractor shall prepare a work plan to address means and methods for the asbestos removal. Include in the plan location and layout of phased work areas, sequencing of work, detailed description of the work methods, and methods to endure safety of building occupants and visitors to the site. The Plan shall be presented to the Architect and Engineer at least 10 days prior to the planned beginning of abatement for review and comment.

1.2.11. Where in the performance of the Work, workers, supervisory personnel, subcontractors, or consultants may encounter, disturb, or otherwise function in the immediate vicinity of any identified asbestos-containing materials, take appropriate continuous measures as necessary to protect all building occupants from the potential hazard of exposure to airborne asbestos. Such measures will include the procedures and methods described herein, and compliance with regulations of applicable federal, state and local agencies.

1.2.12. The Contractor is responsible for all costs, including additional visits, should the Air Monitoring Firm determine that the Contractor failed a final inspection.

Notification and scheduling of the final inspection during the project is the responsibility of the Contractor. The Contractor will allow a minimum notice of twenty-four (24) hours unless the Air Monitoring Firm / Engineer and the Contractor agree upon a different timeframe.

Asbestos Removal Section 02 82 11 -4

1.2.13. In event of any apparent conflict among codes, standards, or this Plan, the Contractor shall refer the conflict to the Architect or Engineer for written resolution.

1.3. Contractor Use of Premises

1.3.1. The Contractor shall limit their use of the premises to the work indicated. The Contractor is responsible for securing all points of ingress/egress to the building.

1.3.2. Use of Site: Confine operations at the site to the areas permitted under contract.

Portions of the site beyond areas on which work is indicated are not to be disturbed. Conform to site rules and regulations affecting the work while engaged in project construction. The Contractor shall notify the Owner at least seven (7) days in advance of a proposed time for shutting down or interrupting any utilities, services or facilities which may affect the operation of other portions of the building or of other buildings, services or facilities of the Owner. In no case may any shutdown or interruption of any utilities, services or facilities be made without the approval and authorization of the Owner.

1.3.3. Driveways and Entrances: Keep driveways and entrances adjacent to the premises clear and available to the general public. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. All vehicles must be parked in areas approved by the Owner.

1.3.4. Partial Owner Occupancy: The Owner reserves the right to occupy and to place and install equipment in completed areas prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placing of equipment and partial occupancy shall not constitute acceptance of the total Work.

1.3.5. Smoking: Smoking or open fires will not be permitted within the building enclosure or on the premises.

1.3.6. Temporary Toilet Rooms: The Contractor must provide self-contained, single-occupant toilet units of the chemical, aerated recirculation, or combustion type.

Provide units properly vented and fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material. Comply with regulations and health codes for the type, number, location, operation, and maintenance of fixtures and facilities. Install where facilities will best serve the Project's needs. Provide temporary hand washing facilities maintained with soap and disposable towels in an area adjacent to the toilet rooms.

Asbestos Removal Section 02 82 11 -5

1.3.7. The Contractor at all times shall keep the premises free from accumulation of waste materials or rubbish caused by its operations. At the completion of the work the Contractor shall leave the Project in a clean and orderly condition, including removing all its waste materials and rubbish from and about the Project as well as all its tools, construction equipment, machinery, and surplus materials.

1.3.8. Title to Materials: All materials resulting from demolition work, except as specified otherwise, shall become the property of the Contractor and shall be disposed of as specified herein.

1.3.9. The Contractor is responsible for the behavior of workers within its employment. If at any time during the contracted work, any of its employees are judged to exhibit behavior unfitting for the area or judged to be a nuisance by the Owner, Architect, or Engineer, the Contractor shall remove them immediately from the project.

1.3.10. Under no circumstances are alcohol, firearms, drugs, or any other type of controlled substances permitted on the work site property.

1.3.11. All workers must conform to the following basic dress code when in public areas of the project confines: long pants, shirts, no tank tops, no shorts, no bare backs.

1.4. Coordination

1.4.1. Coordinate construction operations included in various Sections of these Specifications to assure efficient and orderly completion of each part of the Work.

Coordinate construction operations included under different Sections that depend on each other for proper installation, connection, and operation.

1.4.2. Develop a directory of all entities involved in the project. Include the Contractor's principal staff assignments, including the Superintendent and other personnel in attendance at the site. Identify individuals, their duties and responsibilities. List business name, contact person, normal business and emergency telephone, pager and fax numbers and addresses.

1.4.2.1. Supervisor. All supervisors on the project shall have a minimum of two years of experience in the administration and supervision of asbestos abatement projects including work practices, protective measures for building and personnel, disposal procedures, etc. One supervisor shall be provided for every 10 workers inside each containment. A minimum of one supervisor shall be provided per asbestos abatement work area.

Asbestos Removal Section 02 82 11 -6

1.4.2.2. The Contractor shall have at least one employee on the jobsite in either a foreman, supervisor, and/or competent person position that is fluent in English and any necessary language(s) to effectively communicate with abatement personnel who do not fluently speak English. That person must be on site at all times as long as non-English speaking personnel are working on site.

1.4.2.3. A competent person, as defined in the OSHA asbestos standard 29 CFR 1926.1101, employed by the Contractor must be outside each work area at all times to monitor activity, ensure containment security, provide information to visitors, and provide access to the work area. The competent person, employed by the Contractor, shall be multilingual in the appropriate languages when employing workers who do not speak fluent English.

1.4.3. Notify other entities at the job site of the nature of the asbestos abatement activities, location of asbestos-containing materials (ACM), requirements relative to asbestos set forth in these specifications and applicable regulations. Advance notification will be made to: the Owner; employees who will perform asbestos abatement work or related activities or who will be in the work area during the course of the work of this contract; and, employers of employees who work and/or will be working in adjacent areas during the course of the work of this contract.

1.4.4. Notify emergency service agencies (not less than 10 days prior to start) including fire, ambulance, police or other agency that may service the abatement work site in case of an emergency. Notification is to include methods of entering work area, emergency entry and exit locations, modifications to fire notification or fire-fighting equipment, and other information needed by agencies providing emergency services.

1.4.5. Contingency Plan: Prepare a contingency plan for emergencies or any other event that may require breaching of work area containment or modification or abridgement of decontamination or work area isolation procedures. Include in this plan procedures for performing electrical and mechanical repairs inside containment after abatement work has begun. Include in plan specific procedures for decontamination or work area isolation. Note that nothing in this specification should impede safe exiting or providing of adequate medical attention in the event of an emergency. Items to be addressed in the plan include, but are not limited to the following:

1. Fire

2. Accident

3. Life threatening injury

4. Non-life threatening injury

5. Rescue

Asbestos Removal Section 02 82 11 -7

6. Power Failure

7. Pressure differential system failure

8. Breach of containment

9. Electrical faults or shock

10. Excessive heat / cold (if/when such limits are specified)

11. Supplied air system failure

12. Water leaks

13. Waste spills

14. Unauthorized entry into work area

15. Elevated air samples outside of containment

16. Repairs inside containment

17. Toxic releases

1.5. Pre-Construction Conference

1.5.1. An initial progress meeting, recognized as "Pre-Construction Conference" will be conducted prior to start of any work. The preconstruction conference will be scheduled before start of construction, at a time convenient to the Owner, Architect and the Designer, but no later than 15 days after execution of the Agreement.

Meet at the project site, or as otherwise directed, with General Superintendent, Owner, Architect, Designer, Project Administrator, and other entities concerned with the asbestos abatement work. Seventy-two (72) hours advance notice will be provided to all participants prior to convening Pre-Construction Conference.

1.5.2. Attendees: Authorized representatives of the Owner, Architect, Designer, and their consultants will be in attendance. An authorized representative of the Contractor and its superintendent; major subcontractors; manufacturers; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

1.5.3. Agenda: This is an organizational meeting, to review responsibilities and personnel assignments, to locate regulated areas and temporary facilities including power, light, water, etc. Items of significance that could affect progress will be discussed, including the following:

1. Tentative construction schedule.

2. Critical work sequencing.

3. Designation of responsible personnel.

4. Procedures for processing field decisions and Change Orders.

5. Procedures for processing Applications for Payment.

6. Distribution of Contract Documents.

7. Submittal of Shop Drawings, Product Data, and Samples.

8. Preparation of record documents.

Asbestos Removal Section 02 82 11 -8

9. Use of the premises.

10. Parking availability.

11. Office, work, and storage areas.

12. Equipment deliveries and priorities.

13. Safety procedures.

14. First aid.

15. Security.

16. Working hours.

1.6. References

1.6.1. Except to the extent that more explicit or more stringent requirements are written directly into the contract documents, all applicable codes, regulations, and standards have the same force and effect (and are made a part of the central documents by reference) as if copied directly into the contract documents, or as if published copies are bound herewith.

1.6.2. The current issue of each regulation, code and standard shall govern. Where conflict among requirements or with these specifications exists, the more stringent requirements shall apply.

1.6.3. U.S. Department of Labor, Occupational Safety and Health Administration, (OSHA), including but not limited to:

1. Occupational Exposure to Asbestos, Tremolite, Anthophyllite, and Actinolite:

Final Rules Title 29, Part 1910, Section 1001 and Part 1926, Section 1101, of the Code of Federal Regulations.

2. Respiratory Protection: Title 29, Part 1910, Section 134 and Title 29, Part 1926, Section 103 of the Code of Federal Regulations.

3. Construction Industry: Title 29, Part 1926, of the Code of Federal Regulations.

4. Access of Employee Exposure and Medical Records: Title 29, Part 1910, Section 20 and Title 29, Part 1926, Section 33 of the Code of Federal Regulations.

5. Specifications for Accident Prevention Signs and Tags: Title 29, Part 1910, Section 145 of the Code of Federal Regulations.

6. Personal Protective Equipment: Title 29, Part 1910, Section 132 and Title 29, Part 1926, Sections 95 through 107 of the Code of Federal Regulations.

7. Hazard Communication: Title 29, Part 1910, Section 1200 and Title 29, Part 1926, Section 59 of the Code of Federal Regulations.

8. Lead in Construction; Title 29, Part 1926, Section 62.

1.6.4. U.S. Environmental Protection Agency (EPA) including but not limited to:

1. Asbestos Abatement Project Rule: 40 CFR Part 763 Subpart G; as of July 1, 1991.

Asbestos Removal Section 02 82 11 -9

2. Regulations for Asbestos: Title 40, Part 61, Subpart A of the Code of Federal Regulations.

3. National Emissions Standard for Asbestos: Title 40, Part 61, Subpart M (Revised Subpart B); Code of Federal Regulations.

4. Hazardous Wastes: Title 40, Part 260-265.

1.6.5. American National Standards Institute (ANSI):

1. ASTM D1331 - 1989: Surface and Interfacial Tension of Solution of Surface-

Active Agents.

2. American National Standard for Respiratory Protection - Respirator Use-

Physical Qualifications for Personnel, Publication Z88.6-1984

3. Practices for Respiratory Protection - Publication Z88.2-1992

1.6.6. American Society for Testing and Materials (ASTM):

1. ASTM D-1331 - 1989: Surface and Interfacial Tension of Solution of Surface

Active Agents.

1.6.7. Underwriters Laboratories, Inc. (UL):

1. UL 586 - 1985 (Rev 1988): High-Efficiency Particulate, Air Filter Units.

2. E1368-90: Standard Practice for Visual Inspection of Asbestos Abatement Projects

1.6.8. Tennessee Department of Environment and Conservation (TDEC)

1. Regulation 1200-01.

1.7. Definitions

1.7.1. Air Filtration Units: A local exhaust unit, utilizing high-efficiency particulate air (HEPA) filtration and capable of maintaining a minimum negative pressure differential of 0.02 inches of water within the containment barrier with respect to that of the environment surrounding the containment barrier. The unit also cleans recirculated air or generates a constant air flow from adjacent areas into the abatement work area through the decontamination enclosure.

1.7.2. Air Pressure Monitoring: The process of measuring the air pressure differential between the containment barrier and the surrounding area using inches of water unit.

1.7.3. Amended Water: Water to which a surfactant (wetting agent) has been added to increase the ability of the liquid to penetrate asbestos-containing materials (ACM).

Asbestos Removal Section 02 82 11 -10

1.7.4. Area Monitoring: Sampling of asbestos fiber concentrations within the asbestos control area and outside the asbestos control area which is representative of the airborne concentrations of asbestos fibers that may reach the breathing zone of personnel potentially exposed to asbestos.

1.7.5. Asbestos: A group of naturally occurring minerals that separate into fibers. There are six asbestos minerals used commercially: chrysotile; amosite; crocidolite;

tremolite; anthophyllite; and actinolite.

1.7.6. Asbestos Control Area: An area where asbestos removal operations are performed which is isolated by physical boundaries to prevent unauthorized entry of personnel and to prevent the spread of asbestos dust, fibers, or debris.

1.7.7. Asbestos-Containing Material (ACM): Any material containing more than 1% asbestos by volume of any type or mixture of types.

1.7.8. Asbestos Fibers: Asbestos fibers having a length to diameter ratio of at least 3:1 and is 5 micrometers long or longer, as analyzed by Phase Contrast Microscopy utilizing NIOSH Method 7400.

1.7.9. Asbestos Permissible Exposure Limit: The limit is 0.1 fibers per cubic centimeter of air as an 8-hour time weighted average as determined by 29 CFR 1926.1101.

1.7.10. Competent Person: One who is capable of identifying existing asbestos, tremolite, anthophyllite, or actinolite hazards in the work place and who has the authority to take prompt corrective measures to eliminate them.

1.7.11. Critical Barrier: Those portions of the containment barrier which represent the minimum structural components necessary to maintain the asbestos removal area in airtight isolation from the surrounding areas. Critical barriers shall be placed at floors, windows, ventilation louvers and other openings as necessary to achieve abatement work area isolation before putting up the double-layer plastic sheeting containment enclosure within which abatement work is performed. If a temporary plastic sheeting/stud wall must be erected, it shall be treated as a critical barrier.

The double-layer plastic sheeting containment enclosure shall then be erected on that wall. Wrappings on lights, control boxes, etc., do not constitute part of the critical barrier.

1.7.12. Encapsulant: A material applied after the removal of ACM or to the ACM-edges of partially abated substrates which surrounds or embeds residual asbestos fibers in an adhesive matrix to prevent their release into the atmosphere.

Asbestos Removal Section 02 82 11 -11

1.7.13. Equipment Decontamination and Waste Load Out System: A decontamination area for waste materials and equipment, typically consisting of a designated area of work area for HEPA vacuuming and wet wiping.

1.7.14. Friable Asbestos Material: Material that contains more than one percent asbestos as determined using the method specified in Appendix A, Subpart F, 40 CFR Part 763 Section 1, Polarized Light Microscopy, that when dry can be crumbled, pulverized, or reduced to powder by hand pressure.

1.7.15. Glove Bag: A pouch, typically constructed of a minimum 6 mil thick, 45 inches x 45 inches, transparent polyethylene or polyvinylchloride plastic, with inward projecting sleeve gloves to abate ACM in a sealed micro-environment with designated inlets for amended water and sealant application, and a HEPA filtered vacuum unit attachment. The pouch has capacity for tool storage and to hold removed ACM.

1.7.16. GFCI (Ground Fault Circuit Interrupter): A type of ground fault protection in areas where personnel are at high risk of receiving electrical shocks (for example, in damp locations); makes use of a device designed to trip at a ground current in the milliampere range, i.e., very much below currents that are normally harmful.

1.7.17. HEPA Vacuum Equipment: High efficiency particulate air (HEPA) filtered vacuuming equipment with a UL 586 filter system capable of collecting and retaining asbestos fibers. Filters shall be of 99.97 percent efficiency for retaining fibers of 0.3 micrometers or larger.

1.7.18. Impermeable Waste-Disposal Containers: Suitable to receive and retain any asbestos-containing or contaminated material until disposal at an approved site.

The containers shall be labeled in accordance with OSHA Regulation 29 CFR

1910.1001 and 29 CFR 1926.1101. Containers must be both water-tight and air-tight.

1.7.19. Lockdown: Lockdown is the procedure of applying a protective coating or sealant to a surface from which asbestos-containing material has been removed. Its primary function is to control and minimize airborne asbestos fiber generation that might result from any asbestos-containing residue on the substrate.

1.7.20. Negative Pressure System: A system in which static pressure in an enclosed control area is lower than that of the environment outside the control area, as specified herein.

1.7.21. Non-friable Asbestos Material: Material that contains more than one percent asbestos as determined by the method specified in Appendix A, Subpart F, 40

Asbestos Removal Section 02 82 11 -12

CFR Part 763 Section 1, in which the fibers have been locked in by a bonding agent, coating, binder, or other material so that the asbestos is well bound and may not release fibers in excess of the asbestos permissible exposure limit during any appropriate use, handling, storing, transporting, or processing. Non-friable asbestos material may be hazardous and rendered friable during removal and disposal procedures. Cutting, crushing, grinding and sanding will render non-friable materials into a friable state.

1.7.22. Personnel Decontamination Unit System: A decontamination unit consisting of a clean room, shower room, and equipment room separated by airlocks, thus making a 5-stage system. This unit is attached to the regulated area.

1.7.23. Personal Monitoring: Sampling of asbestos fiber concentrations within the breathing zone of an employee to determine the 8-hour time weighted average in accordance with Appendix A of 29 CFR 1926.1101. The samples shall be representative of the employee's work tasks. The breathing zone shall be considered an area within 12 inches of the nose or mouth of an employee.

1.7.24. Regulated Area: An area established to demarcate areas where airborne concentrations of asbestos, tremolite, anthophyllite, actinolite, or a combination of these minerals exceed or can be expected to exceed the permissible exposure limits. The regulated area may take the form of an enclosed control area or an area demarcated to prohibit occupants from the vicinity of the area and prevent potential exposure to asbestos, tremolite, anthophyllite, or actinolite.

1.7.25. Surfactant (Wetting Agent): A chemical wetting agent added to water to improve penetration. The surfactant shall be a 50/50 mixture of polyoxyethylene ether and polyoxyethylene ester, or equivalent, mixed in a proportion of one fluid ounce to 5 gallons of water or as specified by the manufacturer. An equivalent surfactant shall be understood to mean a material with a surface tension of 29 dynes/cm as tested in accordance with ASTM D 1331.

1.7.26. Time Weighted Average (TWA): The TWA is an 8-hour time weighted average of airborne concentration of fibers (5 micrometers or longer) per cubic centimeter of air which represents the employee's 8-hour workday exposure as determined by Appendix A of 29 CFR 1926.1101.

Asbestos Removal Section 02 82 11 -13

1.8. Submittals

1.8.1. The Contractor shall be responsible for obtaining and maintaining all permits and certifications for the work. All permits and certifications shall be maintained onsite.

The Contractor shall submit permits and certifications to the Owner for recordkeeping prior to final payment. Final payment will not be made until all requested submittals have been reviewed and approved by the Owner.

1.8.2. Affidavits: Contractor’s affidavit of payment of debts and claims, affidavit of release of liens, and consent of surety company to final payment.

1.8.3. Notification: Notify the appropriate regulatory body for asbestos removal. Obtain and post the asbestos removal permit onsite. Notification is also required for any changes in work schedule. Submit notification and permit copies to the Architect and Designer not less than 10 days prior to commencing any work. Contractor is responsible for obtaining any work practice variances.

1.8.4. All work practice variances must be approved in writing by both the Designer and TDEC. Contractor shall submit written variances for review. Allow one week for initial review.

1.8.5. Hazard Communication Program: The Contractor will submit evidence, if requested, of a written Hazard Communication Program as required by 29 CFR 1910.1200.

1.8.6. Respirator Program: Establish and implement a respirator program as required by ANSI Z88.2, 29 CFR 1910.134, and 29 CFR 1926.1101. Submit evidence of program, if requested.

1.8.7. Training: Submit to the Owner not less than 10 days prior to commencing any work documentation that the required EPA, OSHA and State training has been conducted. Prior to or at time of initial assignment to asbestos work, and at least annually thereafter, each employee shall be instructed with regard to the hazards of asbestos, safety and health precautions, the use and requirements for protective clothing, equipment, and respirators, and the association of cigarette smoking and asbestos-related disease, and the additional requirements of 29 CFR 1926.1101.

Training shall fully cover engineering and other hazard control techniques and procedures.

1.8.8. Logs: Submit to the Owner a daily sign in sheet, a record of all employees and visitors who enter the asbestos control area, daily reports of the abatement activity compiled by the onsite abatement supervisor, reports of unusual events, and accident reports.

Asbestos Removal Section 02 82 11 -14

1.8.9. Landfill Receipts: Submit to the Owner receipts from the approved landfill and transport manifest recording the transportation and disposal of the asbestos and demolition waste. Submit detailed delivery tickets, prepared signed, and dated by an agent of the landfill, certifying the amount of asbestos materials delivered to the landfill. All asbestos waste shall be disposed of in accordance with federal, state, and local regulations.

1.8.10. Air Monitoring Firm Submittals

1.8.10.1. Submit the license of the of the air monitoring professional 10 days prior to the start of monitoring for review by the Architect and Designer.

1.8.10.2. Submittal of firms Quality Assurance program to meet the requirements of NIOSH Method 7400, Asbestos and Other Fibers by PCM 10 days prior to the start of monitoring for review by the Architect and Designer.

1.8.10.3. Submit current calibration certificates for air calibration devices used onsite 10 days prior to the start of monitoring for review by the Architect and Designer.

1.8.10.4. On a weekly basis submit air monitoring data and quality assurance data via email to the Owner, Architect, and Designer.

1.9. Daily Reports

1.9.1. The Contractor shall maintain daily logs and reports of job-site activities and personnel exposure monitoring at the site and shall provide copies to the Architect prior to final payment.

1.9.2. Reporting Unusual Events: When an event of unusual and significant nature occurs at site (examples: failure of pressure differential system, rupture of temporary enclosures, equipment or power failure, high airborne fiber reading), prepare and submit a special report listing chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information.

Asbestos Removal Section 02 82 11 -15

1.9.3. Accident Reporting: Report all accidents to onsite safety representative. Prepare reports of significant accidents, at site and anywhere else work is in progress.

Record and document data and actions; comply with industry standards. For this purpose, a significant accident is defined to include events where personal injury is sustained, property loss of substance is sustained, or where the event posed a significant threat of loss or personal injury. Contractor shall be responsible for the investigation of accidents, the generation of documentation, and the resolution of issues within its control.

Asbestos Removal Section 02 82 11 -16

2.0 PRODUCTS

2.1. Materials

2.1.1. Encapsulant: Product shall be rated as acceptable for use intended when field tested in accordance with ASTM Proposed Specification P-189 “Specification for Encapsulants for Friable Asbestos Containing Building Materials". Use only materials that have a flame spread index of 25 or less when dry, when tested in accordance with ASTM E-84.

2.1.2. Glove-Bag: Transparent polyethylene or polyvinylchloride plastic with long sleeve gloves, designated inlets for HEPA vacuum attachment, and storage pouch. Use in accordance with manufacturer’s instructions.

2.1.3. Impermeable Waste-Disposal Containers: Suitable to receive and retain any asbestos-containing or contaminated material until disposal at an approved site.

The containers shall be labeled in accordance with OSHA Regulation 29 CFR

1910.1001 and 29 CFR 1926.1101. Containers must be both water-tight and air-tight.

2.1.4. Plastic Sheeting: Polyethylene plastic sheeting material typically 6-mil thickness for covering floors and walls, providing air locks, and sealing doors and windows;

supply in appropriate widths to minimize seams.

2.1.5. Surfactant (Wetting Agent): 50% polyoxyethylene ester and 50% polyoxyethylene ether, or approved equal, shall be mixed with water to provide a concentration of 2 ml surfactant to 1 liters of water, or manufacturer's recommended concentration.

2.1.6. Tape: Glass fiber or other tape capable of sealing joints of adjacent sheets of plastic sheeting and for attachment of plastic sheets to finished or unfinished surfaces of dissimilar materials under both dry and wet conditions, including use of amended water.

2.1.7. Warning Signs and Labels: Provide caution signs printed in English at approaches to asbestos control areas. Locate signs at such a distance that personnel may read the sign and take the necessary precautions before entering the area.

Provide caution labels printed in English. Affix labels to asbestos materials, scrap, waste, debris, sealed impermeable bags, asbestos waste drums, and other asbestos-contaminated products.

Asbestos Removal Section 02 82 11 -17

1. Warning Signs: The warning signs required by 29 CFR 1926.1101, paragraph (k)(7), shall bear the following information:

DANGER

ASBESTOS

MAY CAUSE CANCER

CAUSES DAMAGE TO LUNGS

AUTHORIZED PERSONNEL ONLY

In addition, where the use of respirators and protective clothing is required in the regulated areas, the warning signs shall include the following:

WEAR RESPIRATORY PROTECTION AND PROTECTIVE CLOTHING

IN THIS AREA

2. Warning Labels: Provide label with sufficient print size to be clearly legible with bold print on a contrasting background, displaying the following legend:

DANGER

CONTAINS ASBESTOS FIBERS

MAY CAUSE CANCER

CAUSES DAMAGE TO LUNGS

DO NOT BREATHE DUST

AVOID CREATING DUST

2.2. Equipment

2.2.1. The Contractor shall make available three complete sets of personal protective equipment daily, as required herein, for entry to and inspection of the asbestos control area by the Owner's Representative or other appointed authorized safety or health personnel. The items furnished by the Contractor shall include disposable protective whole body covering, head covering, gloves, foot coverings, eye protection, and use of the Contractor's staging/decontamination area. The personal protective equipment shall remain the property of the Contractor.

2.2.2. Respirators: Select respirators approved by the National Institute for Occupational Safety and Health (NIOSH), Department of Health and Human Services, for use in atmospheres containing asbestos fibers. Respirator selection shall be in accordance with OSHA Regulation 29 CRF 1910.134.

Asbestos Removal Section 02 82 11 -18

2.2.3. Eye Protection: Furnish eye protection for personnel engaged in asbestos operations when the use of a full-face respirator is not required.

2.2.4. Protective Clothing: Personnel exposed to airborne concentrations of asbestos fibers shall wear disposable protective whole body clothing, head coverings, gloves, and foot coverings. Cloth gloves may be worn for comfort, but shall not be used alone. Secure sleeves at the wrists and secure foot coverings at the ankles with duct tape.

2.2.5. Work Clothing: Cloth or nylon undergarments may be worn under the disposable protective coveralls.

2.2.6. Decontamination Systems: Provide a personnel 5-stage decontamination staging area and an equipment decontamination staging area as described herein.

Personnel entry/exit procedures shall be located adjacent to the regulated area as described in 29 CFR 1926.1101. Wastewater shall be disposed of as asbestos waste or shall be filtered through a filter of at least 0.5-micron particle size collection capability before disposal into the sanitary sewer system. Handle and dispose of filters as asbestos contaminated waste.

2.2.7. Tools and Exhaust Systems: Provide the local exhaust in accordance with ANSI Z9.2 and as specified herein. Filters on vacuums and exhaust equipment shall be absolute HEPA filters and UL 586 labeled. Replace filters as required to maintain the efficiency of the system.

2.2.8. Scaffolding: Provide scaffolding, ladders and/or staging, etc. as necessary to accomplish the work of this contract. Scaffolding may be of suspension type or standing type such as metal tube and coupler, tubular welded frame, pole or outrigger type or cantilever type. The type, erection and use of scaffolding shall comply with applicable OSHA provisions.

2.2.9. Temporary Water Service Connection: Connections to any Owner or municipal water system shall include backflow protection, as required. Valves shall be temperature and pressure rated for operation of the temperatures and pressures encountered. After completion of use, connections and fittings shall be removed without damage or alteration to existing water piping and equipment. Leaking or dripping valves shall be piped to the nearest drain or located over an existing sink or grade where water will not damage existing finishes or equipment. Provide separate hoses and/or/ pumps for shower water and amended water, without the possibility of cross connection.

Asbestos Removal Section 02 82 11 -19

2.2.10. Electrical Power Cords: Provide grounded extension cords. Use hard-service cords where exposed to abrasion and traffic. Provide waterproof connectors to connect separate lengths of electric cords if single lengths will not reach areas where construction activities are in progress. Do not exceed safe length-voltage ratio.

2.2.11. Lamps and Light Fixtures: Provide general service incandescent lamps or fluorescent lamps of wattage indicated or required for adequate illumination as required by the work or this section. Protect lamps with guard cages or tempered glass enclosures, where fixtures are exposed to breakage by construction operations. Provide vapor tight fixtures in work area and decontamination units.

Provide exterior fixtures where fixtures are exposed to the weather or moisture.

2.2.12. First Aid Supplies: Comply with governing regulations and recognized recommendations within the construction industry.

2.2.13. Fire Extinguishers: Provide hand-carried, portable, UL-rated, Class A fire extinguishers for temporary offices and similar spaces. In other locations, provide hand-carried, portable, UL-rated, Class ABC, dry-chemical extinguishers or a combination of extinguishers of NFPA-recommended classes for the exposures.

Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and size required by location and class of fire exposure.

Asbestos Removal Section 02 82 11 -20

3.0 EXECUTION

3.1. Construction of Worker/Equipment Decontamination Systems

3.1.1. An adequate decontamination area consists of a serial arrangement of connected rooms/spaces. All persons shall pass through this decontamination area during entry to and exit from the work area for any purpose except in case of emergencies.

The decontamination unit shall be place adjacent to the work area and the outer shell constructed of hard materials and shall be lockable. Containment set-up and specific location shall be discussed in the pre-construction meeting.

3.1.2. The general construction of the unit is illustrated in Figure 1 below:

3.1.3. If the decontamination unit becomes contaminated or its integrity diminished through use, no employee shall use the unit until corrective steps are taken.

3.1.4. The Contractor shall construct a worker/equipment decontamination enclosure consisting of at least a clean room, a shower room, and an equipment room, each separated by air locks as described below.

3.1.4.1. All rooms shall be constructed of non-porous materials than can be easily cleaned and decontaminated. A minimum of 6-mil polyethylene shall be used. Damp wipe all surfaces twice after each shift change with a disinfectant solution.

Asbestos Removal Section 02 82 11 -21

3.1.4.2. Provide GFCI protection for all electrical equipment.

3.1.4.3. Provide temporary lighting inside the decontamination enclosure facility.

3.1.4.4. Clean Room: In this room the workers shall leave all street clothes and don clean working clothes (usually disposable coveralls). Respiratory protection equipment shall be kept in this area. No asbestos-contaminated items shall enter this room. Workers enter this room either from outside the structure dressed in street clothes or directly from the showers. This room shall be reasonably heated or cooled. This room shall be separated from the outside by poly barriers (Z flaps) or a door (lockable, if located outside the building).

3.1.4.5. Shower Room: This is a separate room used for transit by cleanly dressed workers entering the job from the clean room or by workers showering after undressing in the equipment room. The shower stall shall have two open sides and be set up to allow a single pass through between the clean room and equipment room and be built with rigid sides and top. Shower water shall be filtered. No leakage of shower water to the outside of the shower is allowed. Shower drain water shall be filtered with a 5 micron filter. Any leakage to the outside is to be considered contaminated. This room shall be separated from the clean room and equipment room by an airlock using by poly barriers (Z flaps). The shower room shall provide hot and cold running water and soap and towels.

3.1.4.5.1. Shower Stall: Provide leak tight shower enclosure unit with integrated drain pan fabricated from fiberglass or other durable waterproof material. Equip with hose bibs for hot and cold water. Arrange water shut off and drain pump operation controls so that a single individual can shower without assistance from either inside or outside of the abatement work area. Provide splash proof entrances. Provide back flow prevention device and vacuum breaker, where required. Connect drain to a reservoir, pump water from reservoir through filters to a drain.

Mount filters inside shower stall in manner that allows for access for filters to be changed from inside the shower. Change filters daily or more often if necessary. Locate filters inside shower unit so that water lost during filter changes is caught by shower pan. Hot and cold water shall be available at a minimum of 3 gallons of water per minute per worker. There shall be 1 shower for every 10 workers. Hot and cold water shall be available and controlled within the shower. This assembly is to be setup as a permanent fixture for the duration of the project. A water hose and bucket is not an acceptable shower.

Asbestos Removal Section 02 82 11 -22

3.1.4.5.2. Filtered Waste Water Drainage: Provide cascaded disposable HEPA filter units on drain lines from showers or any other fluid source carrying ACM. Connect so that discharged water passes primary filter and output of primary (particles 20 microns and smaller) filter passes through secondary (particles 5 microns and smaller) filter. Filtered water shall be discharged into a sanitary sewer. The Contractor shall not place water in storm drains, onto lawns, or into ditches, creeks, streams, rivers or oceans.

3.1.4.6. The Equipment Room shall have two airlocks, one adjacent to the abatement work area and one adjacent to the shower room. The room shall be of sufficient size so as to accommodate at least one worker to change clothes, and temporarily house any equipment which the Contractor wishes to store when not in use. The area shall have facilities for decontaminating material and equipment, and a container lined with

0.15 mm polyethylene bag for collection of disposable coveralls and foot coverings.

3.1.5. Equipment Decontamination / Load out Area. Construct a separate 2-stage load out unit. The unit shall be place adjacent to the work area and the outer shell constructed of hard materials and shall be lockable.

3.2. Asbestos Work Area Preparation (General)

The Work Area is the location where asbestos abatement work occurs. It is a variable of the extent of Work of the contract. For this project a "Work Area" is defined as the area in which asbestos removal is being performed. A "Work Area" is considered contaminated during the Work, and must be isolated from the balance of the building, and decontaminated at the completion of the asbestos-abatement work.

3.2.1. Completely isolate the Work Area from the outside so as to prevent asbestos containing dust or debris from passing beyond the isolated area. Should the area beyond the Work Area(s) become contaminated with asbestos containing dust or debris as a consequence of the Work, immediately stop all abatement work and clean those areas. Perform all such required cleaning or decontamination at no additional cost to Owner.

3.2.2. Prior to any asbestos related activities, the Contractor shall have a locked waste container on site.

Asbestos Removal Section 02 82 11 -23

3.3. Asbestos Work Area Preparation (Non-Friable Materials)

3.3.1. Post Warning signs and barrier tape in and around work area as required by all applicable regulatory agencies and restrict access to work area to personnel approved by Contractor or Owner’s Representative.

3.3.2. Contractor shall establish an equipment room or area that is adjacent to the work area for the decontamination of workers and equipment contaminated with asbestos. The decontamination area shall consist of an area covered by an impermeable drop cloth on the floor or horizontal working surface, and be of sufficient size as to accommodate cleaning of equipment and removing personal protective equipment without spreading contamination beyond the area when acceptable by OSHA asbestos regulations.

3.3.3. For interior work, seal off all openings with critical barriers. Critical barriers must be placed on penetrations that include but are not limited to; heating and ventilation ducts, doorways, corridors, and windows, with plastic sheeting taped securely in place. Clean and cover fixed surfaces in the proposed work area with polyethylene sheeting. A polyethylene splash guard shall be placed on all walls or other surfaces adjacent to where floor tile mastic are being removed. The splash guard shall extend up the wall a minimum of three feet from the floor. Install HEPA-filtered exhaust units in work area. A pressure differential is not required.

Entrances and exits from the work area will have flap barriers of plastic sheeting.

3.3.4. All building ventilation air systems connected to the work area shall remain off and sealed during preparation and until the area has passed final visual inspection and final air sampling when required.

3.3.5. The Contractor shall implement an electrical practice protocol that includes, but is not limited to, lockout and GFCI shutdown as described in OSHA Construction Standard 29 CFR 1926.417. All electrical powered equipment utilized during the project shall have ground-fault protection as described in OSHA Construction Standards. All equipment and wiring shall be in compliance with National Fire Protection Association Standard 70, and the National Electrical Code.

3.4. Asbestos Work Area Preparation (Mini Enclosure)

The Work Area is a variable of the extent of Work of the contract. For this project a "Work Area" is defined as the area in which asbestos removal is being performed. A "Work Area" is considered contaminated during the Work, and must be isolated from the balance of the building, and decontaminated at the completion of the asbestos-abatement work.

Asbestos Removal Section 02 82 11 -24

3.4.1. Post Warning signs and barrier tape in and around work area as required by all applicable regulatory agencies and restrict access to work area to personnel approved by Contractor or Consultant.

3.4.2. Construct a mini enclosure. A mini enclosure is a small walk-in enclosure which accommodates no more than two persons. Provide a fabricated or job-made enclosure constructed of 6 mil plastic or equivalent. Place the enclosure under negative pressure by means of a HEPA filtered vacuum or similar HEPA filtered ventilation unit.

3.4.3. Change Room: Provide an approximately 3 feet by 3 feet Change Room, with additional space as required for storage, attached to each Work Room. Fabricate Change Room from 6 mil sheet plastic in the same manner as a Primary Barrier.

Locate so that access to Work Area is though Change Room.

3.4.4. Step Off Area: Cover floor in front of entry to Change…