Mitchell Pre-Bid Mtg Agenda 22029.pdf

PDF 82 KB Posted

Attached to
751/22209. JAN; Mitchell SP - South T/S Building Replacement
Solicitation number
RFQ 171 220000000521 4
Issued by
Wexford County, Burt CDP, Michigan

About this file

This is a Mandatory Pre-Bid Conference Agenda issued by the State of Michigan Department of Technology, Management & Budget, Design & Construction Division, in coordination with the Department of Natural Resources, Parks & Recreation Division for the Mitchell State Park Campground South Toilet Shower Building Replacement project. The project, identified as File No. 751/22029.JAN (Index No. 5126), requires bidders to submit proposals electronically through the SIGMA website by Wednesday, September 14, 2022, at 2:00 PM local time; hard copy submissions will not be accepted. The pre-bid conference was scheduled for Wednesday, August 31, 2022, at 11:00 AM, with a site tour included. The contract duration is 206 calendar days from the Notice-to-Proceed or by May 12, 2023. Interviews with bidders are scheduled for September 16, 2022, following the bid submission deadline. Questions regarding the project must be submitted to the architect no later than 5:00 PM on September 7, 2022, and any addenda will be issued no later than 5:00 PM on September 9, 2022.

Bid submissions must include a signed Bid Summary Form, Bid Schedule, proof of Michigan-based business status (for projects over $100,000), bid security equal to 5% of the Base Bid Price, and documentation of Qualified Disabled Veteran (QDV) Business Representation if applicable. The project includes a $50,000 Owner's Provisional Allowance incorporated into the base bid, with two alternates addressing flooring and roofing material modifications. Prevailing wage rates apply to this project. Bid evaluation will be based on best value criteria using price and qualitative components among the three lowest responsive and responsible bidders. A Qualified Disabled Veteran Preference is available to eligible bidders. Upon award, payment and performance bonds will be required. Liquidated damages are set at $2,000 per day. The project includes a hazardous materials report addressing PCB, asbestos, and paint, with materials testing to be conducted by the owner.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRETCHEN WHITMER

GOVERNOR

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT & BUDGET

LANSING

BROM STIBITZ

ACTING DIRECTOR

DESIGN & CONSTRUCTION DIVISION

3111 W. ST. JOSEPH STREET ● LANSING, MICHIGAN 48917

www.michigan.gov/dtmb ● 517-284-7910

State Facilities Administration - Design & Construction Division Mandatory Pre-Bid Conference Agenda

Date: Wednesday, August 31, 2022 @ 11:00 AM

Department of Natural Resources, Parks & Recreation Division Mitchell State Park Campground – South Toilet Shower Building Replacement

File No. 751/22029.JAN – Index No. 5126

1. Introductions / Sign-in Sheet

2. Bid Submission - bids must be submitted electronically through the SIGMA website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService no later than Wednesday, Sept. 14, 2022 @ 2:00 pm local time. Hard copy bids will not be accepted.

3. Bid to include, refer to Section 00100 – Instructions to Bidders

• Signed and completed Bid Summary Form

• Bid Schedule

• Qualified Disabled Veteran (QDV) Business Representation, if applicable

• Signed Certification of a Michigan Based Business (projects over $100,000.00)

• Bid Security in the amount of 5% of Base Bid Price

• Signature Authorization or copy of the partnership agreement if signed by all partners

• Post-Bid Submittals will be requested by the professional (projects over $250,000.00) from the apparent low bidder, within one business day after receipt of the request. Interview(s) will be scheduled for September 16, 2022.

4. Modification of bid – the entire bid must be resubmitted on the SIGMA website.

5. Payment and Performance Bonds will be required upon issuing Notice of Award.

6. Qualified Disabled Veteran Preference is in effect, make sure to check the box on the

Bid Summary Form.

7. Best Value Bidder – bids will be evaluated for best value based on price and qualitative components by comparing the three lowest responsive and responsible bidders.

8. Prevailing Wage Rates

9. Contract Time – 206 calendar days from the Notice-to-Proceed or by May 12, 2023.

10. Liquidated Damages - $2,000.00 per day

11. Alternate 1 – Delete labor & materials to change polished concrete floors to sealed.

Alternate 2 – Delete labor & materials to change sheet metal roofing to asphalt shingle.

12. Allowances - $50,000 Owner’s Provisional Allowance, to be included in base bid

13. Hazardous Materials Report – PCB, asbestos, and paint

14. Materials Testing – By owner

15. Schedule

• Questions to akindt@cornerstone-arch.com no later than 5:00 pm, Sept. 7, 2022.

• Addenda issued no later than 5:00 pm, Sept. 9, 2022

• Bids due Sept. 14, 2022 @ 2:00 pm local time

16. Project Description – Cornerstone Architects

17. Site Tour