This is an electrical panel and load calculation drawing for the Mitchell South Locker Room replacement project, part of a multi-sheet mechanical, electrical, and plumbing (MEP) design package for a state or local facility renovation. The document provides detailed specifications for two electrical panels serving the locker room renovation: Panel #A1 (Mech. Room) with a 150-amp main circuit breaker at 120/240V single-phase, three-wire configuration, and a Subpanel (Loon Cabin) with a 30-amp main circuit breaker. The drawing outlines circuit-by-circuit load calculations for lighting, receptacles, equipment, and specialized fixtures including lights in men's and women's restrooms, shower rooms, mechanical spaces, and exterior areas; receptacles distributed throughout various locker room sections and mechanical rooms; electric hand dryers (EHD) in restroom facilities; and gas water heaters in the mechanical room. Total calculated loads include 1.0 kVA for motors, 4.2 amps for miscellaneous equipment in Panel #A1, and 23.5 kVA for motors with 97.9 amps for miscellaneous equipment in the subpanel, with a comprehensive total calculated load of 11,776 VA across both panels.

The document represents engineering design documentation rather than a procurement solicitation and contains no pricing information, set-asides, funding sources, incumbent contractor details, or contract terms. This is a technical MEP drawing component used during the design and construction phase of a facility improvement project, establishing electrical infrastructure requirements and load calculations necessary for contractor bid preparation and project execution.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

30A MLO, 120/240V‐1PH.‐3W

SQ.D QO ‐ SURFACE MNTD.

CIR. CB/P DESCRIPTION LOAD P LOAD DESCRIPTION CB/P CIR.

1 20/1 LIGHTS ‐ MENS 101 & WOMENS 108 325.5 A 80 LIGHTS ‐ SHOWER ROOMS 103‐106 20/1 2

3 20/1 LIGHTS ‐ MECH. ROOM & EXTERIOR 406 B 191.5 LIGHTS ‐ ALL GENDER FAMILY 107 & LCP‐1 20/1 4

5 ‐‐‐ SPACE ‐‐‐ A ‐‐‐ SPACE ‐‐‐ 6

7 ‐‐‐ SPACE ‐‐‐ B ‐‐‐ SPACE ‐‐‐ 8

LIGHTS VA

RECEPTS. VA TOTAL CALCULATED LOAD:

MOTORS VA 1.0 kVA

MISC VA 4.2 A

PANEL #A1 (MECH. ROOM)

150A MCB, 120/240V‐1PH.‐3W

SQ.D NQ ‐ SURFACE MNTD.

CIR. CB/P DESCRIPTION LOAD P LOAD DESCRIPTION CB/P CIR.

1 20/1 RECEPTACLE ‐ ALL GENDER 107 180 A 360 RECEPTACLES ‐ WOMENS 108 20/1 2

3 20/1 E.H.D. ‐ ALL GENDER 107 1000 B 1000 E.H.D. ‐ WOMENS 108 20/1 4

5 20/1 RECEPTACLES ‐ MECH. RM, SOUTH EXTR. 360 A 1000 E.H.D. ‐ WOMENS 108 20/1 6

7 20/1 RECEPTACLES ‐ MECH. RM, EAST EXTR. 360 B 1000 E.H.D. ‐ WOMENS 108 20/1 8

9 20/1 GAS WATER HEATERS ‐ MECH RM. 102 400 A 360 RECEPTACLES ‐ MENS 101 20/1 10

11 20/1 RECEPTACLES ‐ MECH. RM, NORTH EXTR. 360 B 1000 E.H.D. ‐ MENS 101 20/1 12

13 20/1 E.W.C. ‐ NORTH EXTERIOR 325 A 1000 E.H.D. ‐ MENS 101 20/1 14

15 20/1 RECEPTACLES ‐ WEST EXTR. 180 B 1000 E.H.D. ‐ MENS 101 20/1 16

17 180 A 18

19 180 B 20

21 2208 A 22

23 2208 B 24

25 ‐‐‐ SPACE ‐‐‐ A ‐‐‐ SPACE ‐‐‐ 26

27 ‐‐‐ SPACE ‐‐‐ B ‐‐‐ SPACE ‐‐‐ 28

29 ‐‐‐ SPACE ‐‐‐ A ‐‐‐ SPACE ‐‐‐ 30

31 ‐‐‐ SPACE ‐‐‐ B ‐‐‐ SPACE ‐‐‐ 32

33 ‐‐‐ SPACE ‐‐‐ A ‐‐‐ SPACE ‐‐‐ 34

35 ‐‐‐ SPACE ‐‐‐ B ‐‐‐ SPACE ‐‐‐ 36

37 ‐‐‐ SPACE ‐‐‐ A ‐‐‐ SPACE ‐‐‐ 38

39 ‐‐‐ SPACE ‐‐‐ B 487 40

41 ‐‐‐ SPACE ‐‐‐ A 487 42

LIGHTS VA

RECEPTS. VA TOTAL CALCULATED LOAD:

MOTORS VA 23.5 kVA

MISC VA 97.9 A

100/27820

1003 ATS & PANEL #A1

MTS‐1 30/2

PANEL #A (MECH. ROOM)

15/2 DF‐1

25/2 ERV‐1

30/2

SUB‐PANEL (LOON CABIN)

11776