These construction documents outline the HVAC, mechanical, electrical, and plumbing upgrades for the Challenge Academy South Kitchen at the WV Army National Guard facility. The project involves selective demolition and renovation of the second floor, including removing and replacing ductwork, mechanical equipment, electrical systems, and ceiling infrastructure. The design is prepared by Miller Engineering, Inc. and covers comprehensive system upgrades including a new Carrier RTU-1 air handling unit, modifications to existing pumps and piping, electrical panel and circuit adjustments, and reinstallation of lighting, fire alarm, and security systems.
The project appears to be funded by the WV Army National Guard and involves precise mechanical and electrical system replacements to modernize the kitchen and surrounding spaces. The drawings indicate careful coordination between disciplines, with specific notes about maintaining existing infrastructure while upgrading critical systems. The mechanical schedules detail equipment specifications like the RTU-1 with 8,700 CFM air flow, 15 HP fan, and associated heating and cooling coils. Electrical plans show reusing existing electrical panels and carefully routing new conduits and receptacles, suggesting a cost-conscious approach to system upgrades that minimizes new infrastructure while improving overall building performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PENNSYLVANIA OFFICE
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PHONE: (724) 966 - 5655
WEST VIRGINIA OFFICE
54 WEST RUN RD
MORGANTOWN, WV 26508
PHONE: (304) 291 - 2234
CHALLENGE ACADEMY SOUTH KITCHEN HVAC
UPGRADES
MEI PROJECT #24014
DWG TITLE
COVER
G000 COVER PAGE
G001 PROJECT GENERAL NOTES, ABBREVATIONS, AND SYMBOLS
G002 PROJECT SITE
ARCHITECTURAL
A011 DEMO RCP
A101 SECOND FLOOR PLAN
A111 NEW RCP
FIRE PROTECTION
F101 FIRE PROTECTION PLAN
PLUMBING
P000 PLUMBING ABBREVIATIONS
P101 PLUMBING PLAN
P102 PLUMBING PLAN - TEMPORARY FACILITIES - ALT #1
MECHANICAL
M000 MECHANICAL ABBREVIATIONS
M001 MECHANICAL DEMO PLAN
M002 MECHANICAL DEMO PLAN
M003 MECHANICAL PIPING DEMO PLAN
M101 MECHANICAL PLAN
M102 MECHANICAL PIPING PLAN
M201 MECHANICAL PLAN
M501 MECHANICAL DETAILS
M502 MECHANICAL DETAILS
M601 MECHANICAL SCHEDULES
ELECTRICAL
E000 ELECTRICAL ABBREVIATIONS
E001 ELECTRICAL DEMO PLAN
E002 ELECTRICAL DEMO PLAN
E003 ELECTRICAL CEILING DEMO PLAN
E101 ELECTRICAL PLAN
E102 ELECTRICAL CEILING PLAN
E103 ELECTRICAL PLAN - TEMPORARY FACILITIES - ALT #1
E501 ELECTRICAL SCHEDULES & DETAILS
CONCRETE
CLAY UNIT MASONRY
CONCRETE UNIT MASONRY
WOOD FRAMING
PLYWOOD
FINISHED WOOD
BATT INSULATION
RIGID INSULATION
GYPSUM BOARD
SOIL
CRUSHED STONE
MATERIAL HATCH DESCRIPTION
CENTER LINE
HIDDEN LINE
VIEW TITLE
ELEVATION MARKER
SECTION MARKER
DETAIL CALLOUT
ROOM TAG
GRID LINE MARKER
ELEVATION DATUM
SPOT ELEVATION MARK
WALL TAG
DOOR TAG
WINDOW TAG
CALL-OUT SYMBOL DESCRIPTION
View Name 1/8" = 1'-0"
A101
ROOM
NAME
A101
4 2
A101
A101
SIM
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
G001
PROJECT GENERAL
NOTES,
ABBREVATIONS, AND
SYMBOLS
18 JUNE, 2025
TWT
TWT
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
DEFINITIONS
PROVIDE: FURNISH AND INSTALL, COMPLETE AND READY FOR THE INTENDED USE.
FURNISH: SUPPLY AND DELIVER TO PROJECT SITE, READY FOR UNLOADING, UNPACKING, ASSEMBLY, INSTALLATION, AND SIMILAR OPERATIONS.
INSTALL: UNLOAD, TEMPORARILY STORE, UNPACK, ASSEMBLE, ERECT, PLACE, ANCHOR, APPLY, WORK TO DIMENSION, FINISH, CURE, PROTECT, CLEAN, AND SIMILAR
OPERATIONS AT PROJECT SITE.
EXISTING TO REMAIN (OR EXISTING) (OR EX.): LEAVE EXISTING ITEMS THAT ARE NOT TO BE REMOVED AND THAT ARE NOT OTHERWISE INDICATED TO BE SALVAGED OR
REINSTALLED.
REMOVE (OR DEMOLISH) (OR DEMO): DETACH ITEMS FROM EXISTING CONSTRUCTION AND DISPOSE OF THEM OFF-SITE UNLESS INDICATED TO BE SALVAGED OR
REINSTALLED.
REMOVE AND SALVAGE: DETACH ITEMS FROM EXISTING CONSTRUCTION, IN A MANNER TO PREVENT DAMAGE, AND DELIVER TO OWNER READY FOR REUSE.
REMOVE AND REINSTALL (OR REMOVE AND REUSE): DETACH ITEMS FROM EXISTING CONSTRUCTION, IN A MANNER TO PREVENT DAMAGE, PREPARE FOR REUSE, AND
REINSTALL WHERE INDICATED.
DISMANTLE: TO REMOVE BY DISASSEMBLING OR DETACHING AN ITEM FROM A SURFACE, USING GENTLE METHODS AND EQUIPMENT TO PREVENT DAMAGE TO THE ITEM
AND SURFACES; DISPOSING OF ITEMS UNLESS INDICATED TO BE SALVAGED OR REINSTALLED.
DISPOSE: REMOVAL OFF-SITE OF DEMOLITION AND CONSTRUCTION WASTE AND SUBSEQUENT SALE, RECYCLING, REUSE, OR DEPOSIT IN LANDFILL OR INCINERATOR ACCEPTABLE TO AUTHORITIES HAVING JURISDICTION AND IN ACCORDANCE WITH PROJECT REQUIREMENTS.
# Number & And " Inch ' Foot @ At +/- Approximately
ABV Above ACM Aluminum Composite Material ACM Asbestos Containing Material ACT Acoustic Ceiling Tile AD Area Drain ADA Americans with Disabilities Act ADAAG Americans with Disabilities Act Architectural Guidelines ADD Addendum ADJ Adjustable AFF Above Finished Floor AHJ Authority Having Jurisdiction (Code Official, Fire Marshal, Etc.)
ALT Alternate ALUM Aluminum ANOD Anodized APPROX Approximately
BFF Below Finished Floor BIT Bituminous BL Borrowed Lite, Hollow Metal BSMT Basement BYND Beyond BOT Bottom BUR Built-up Roof
C/C Center to Center CB Chalkboard CF Cubic Foot CFCI Contractor Furnished, Contractor Installed CFOI Contractor Furnished, Owner Installed CIP Cast In Place CIRC Circumference or Circulating CJ Control Joint CL Column Line CLG Ceiling CLR Clear CMU Concrete Masonry Unit COL Column COMPRCompressible CONC Concrete CONT Continuous CPT Carpet CT Ceramic Tile
D Deep DBL Double DEG Degree DEMO Demolish or Demolition DIA Diameter DIM Dimension DIMS Dimensions DN Down DS Down Spout DWG Drawing
EA Each EJ Expansion Joint EL Elevation ELEC Electrical ELEV Elevator or Elevation EOS Edge of Slab EPDM Ethylene Propylene Diene Monomer Membrane EQ Equal EX Existing EXIST Existing EXP JT Expansion Joint EXT Exterior EXT GDExterior Grade
FD Floor Drain or Fire Department FE Fire Extinguisher FEC Fire Extinguisher Cabinet FIXT Fixture FLR Floor FO Face Of FR Fire Retardant Treated FRP Fiberglass Reinforced Plastic FT Foot
GA Gauge GALV Galvanized GC General Contractor GFCI Ground Fault Circuit Interrupter GL Glass GWB Gypsum Wall Board
HC Hollow Core HM Hollow Metal HORIZ Horizontal HP High Point HR Hour HVAC Heating, Ventilating, And Air Conditioning
ID Inside Diameter IRGWB Impact Resistant Gypsum Wall Board ILO In Lieu Of INSUL Insulated or Insulation INT Interior JB Junction Box
L Long LAV Lavatory LBS Pounds
MAX Maximum MB Markerboard MO Masonry Opening MECH Mechanical MEMBR Membrane MEZZ Mezzanine MIN Minimum MISC Miscellaneous MRGWB Moisture-Resistant Gypsum Wall Board MTL Metal
NA Not Applicable NIC Not In Contract (See OFOI) NO Number NOM Nominal NTS Not to Scale
OC On Center OD Outside Diameter OFCI Owner Furnished, Contractor Installed OFOI Owner Furnished, Owner Installed OH Overhand OPP Opposite or Opposite Hand OZ Ounce
PCC Pre-Cast Concrete PLAM Plastic Laminate PLUMB Plumbing PLYD Plywood PT Pressure Treated PNT Paint or Painted PVC Polyvinyl Chloride
RBR Rubber RCP Reflected Ceiling Plan RB Rubber (Vinyl) Wall Base RD Roof Drain REBAR Reinforcing Bar REINF Reinforce REQD Required REV Revision RO Rough Opening RM Room
SB Splash Block SD Supplemental Document (Drawing Revision) SFM State Fire Marshal SQFT Square Foot SF Aluminum Storefront Framing SIM Similar SPEC Specified OR Specification SPK Speaker SSTL Stainless Steel STC Sound Transmission Coefficient STL Steel STRUC Structure or Structural
T Tall T&B Top and Bottom T&G Tongue and Groove TB Tackboard TELE Telephone TLT Toilet TME To Match Existing TO Top Of TOC Top Of Concrete TOS Top Of Steel TOW Top Of Wall T/D Telephone/Data TYP Typical
UL Underwriters Laboratory UNO Unless Noted Otherwise U/S Underside
VERT Vertical VIF Verify In Field VP Vision Panel
W Wide W/ With W/o Without WD Wood WP Weatherproof or Waterproof
GENERAL DRAWING SET NOTES
1. WRITTEN SPECIFICATIONS FOR THE PROJECT ARE PROVIDED IN THE PROJECT MANUAL AND REQUIREMENTS ARE COMPLEMENTARY.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CONSTRUCTION METHODS, PROCEDURES AND SEQUENCES TO MAINTAIN AND PROTECT THE STRUCTURAL INTEGRITY OF ALL NEW AND EXISTING CONSTRUCTION AT ALL STAGES.
3. THE CONTRACTOR SHALL ABIDE BY ALL SAFETY RULES AND REGULATIONS IMPOSED BY OSHA AND THE OWNER AT ALL TIMES. IF THERE IS A CONFLICT BETWEEN THE TWO, THE STRICTER REGULATION SHALL APPLY.
4. SPECIFIC REQUIREMENTS SHALL SUPERSEDE GENERAL/GENERIC REQUIREMENTS.
5. DIMENSIONS SHALL SUPERSEDE DRAWINGS. DO NOT SCALE DRAWINGS. WHERE A MISSING OR CONFLICTING DIMENSION OCCURS, THE ARCHITECT SHALL BE CONTACTED IMMEDIATELY TO OBTAIN THE NECESSARY CLARIFICATION.
6. THE CONTRACTOR SHALL NOTIFY THE ARCHITECT OF ANY AND ALL DISCREPANCIES BETWEEN THE DRAWINGS AND ACTUAL FIELD CONDITIONS IMMEDIATELY UPON DISCOVERY.
7. COMMENCEMENT OF THE WORK SHALL SIGNIFY THE CONTRACTOR IS FAMILIAR WITH AND AGREES TO THE SCOPE OF WORK AS OUTLINED IN THE CONTRACT DOCUMENTS.
8. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROPER DISPOSAL OF ALL MATERIALS RESULTING FROM THE WORK OF THIS PROJECT.
WORK REQUIRING GRAVITY DRAINAGE WILL HAVE REASONABLE PRIORITY OF PLACEMENT. TRADES WILL COORDINATE PLACEMENT OF THEIR WORK TO AVOID CONFLICT WITH DRAINAGE LINES.
ABBREVATIONS AND SYMBOLS
N O
D
E S
C R
IP
T
IO
N
D A
T E
07/09/2025 8:01:40 AM
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
G002
PROJECT SITE
18 JUNE, 2025
TWT
TWT
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
N O
D
E S
C R
IP
T
IO
N
D A
T E
1" = 40'-0"
OVERALL PROJECT SITE
MACLIN HALL
TECH CENTER
07/09/2025 8:01:53 AM
C
D
E
F
G
1 2 3 4 5 6
DEMO CEILING TYP
3 3
6 6 6
AREA OF CEILING TILE, GRID, AND BULKHEAD DEMOLITION
AREA OF EXISTING CEILING TILE AND GRID TO REMAIN
AREA OF BULKHEAD, WALL, KITCHEN HOOD, OR DRYWALL CEILINGS TO REMAIN
REMOVE EXISTING CEILING GRID AND TILE AND PREP FOR NEW CEILING1
REMOVE EXISTING DRYWALL LIGHTING COVE BULKHEAD AND PREP FOR NEW CEILING2
REMOVE EXISTING SUSPENDED CLOUD CEILING GRID AND TILE AND PREP FOR NEW CEILING3
REMOVE EXISTING DRYWALL PARTITION AND PREP FOR NEW CEILING4
CUT OPENING ABOVE CEILING IN BULKHEAD IN THIS AREA FOR DUCTWORK AND PATCH5
EXISTING ACOUSTIC CEILING TO REMAIN6
KITCHEN HOOD7
EXISTING COOLER/FREEZER CEILING8
EXISTING KITCHEN HOOD TO BE REMOVED, SEE MEP9
EXISTING STAIRWELL10
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
A011
DEMO RCP
18 JUNE, 2025
JAH
TFP
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
1/8" = 1'-0"
LEVEL 2 DEMO - RCP
N O
D
E S
C R
IP
T
IO
N
D A
T E
REFLECTED CEILING DEMOLITION PLAN KEY
UP
UP
UP
UP
UPUP
UP
S
DD
A
B
C
D
E
F
G
1 2 3 4 5 6 7
A101
4,000 PSI, 6"
CONCRETE PAD
A101
A101
DEMO WALL BETWEEN COLUMNS ABOVE
BACKSPLASH HEIGHT CAP & RE-FINISH
WALL. PAINT TO MATCH EXISTING.
A101
NEW COUNTER OVER
EXISTING WALL
RETAINING WALL
MIN
4' - 0"
4" PERF FOOTING DRAIN, CONT.
TO DAYLIGHT OR STORM DRAIN
#57 STONE, WRAPPED
IN FILTER FABRIC
4,000 PSI, 6" CONCRETE PAD
6" MAX
TO NOT EXCEED 4' TALL
GRAVEL FILL
CORE AND DOWEL
ADHERED CAP STONES
REMOVE GLASS AND MULLION FROM
CURTAIN WALL AND INFILL. TURN
WINDOW HARDWARE & FRAME OVER
TO OWNER. SEE MECHANICAL.
LEVEL 2
21' - 0"
DRYWALL BULKHEAD
WIDTH OF WINDOW
DRYWALL INFILL
LEVEL 2
21' - 0"
LEVEL 2
21' - 0"
2' - 1"
DEMO WALL BETWEEN COLUMNS
ABOVE BACKSPLASH HEIGHT CAP &
RE-FINISH WALL. PAINT TO MATCH
EXISTING.
REMAINING WALL TO BE
FASTENED TO THE BASE
CABINETS FROM WITHIN
THE CABINETS.4
10" COUNTER
SUPPORTS @ 12" O.C.
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
A101
SECOND FLOOR
PLAN
18 JUNE, 2025
JAH
TFP
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
1/8" = 1'-0"
02 - LEVEL 2 NEW PLAN
N O
D
E S
C R
IP
T
IO
N
D A
T E
1/8" = 1'-0"
KEY STONE WALL SECTION
1/4" = 1'-0"
CURTIAN WALL
1/4" = 1'-0"
RETURN GRILLE BULKHEAD
1/4" = 1'-0"
WALL TERMINATION SECTION
E
F
G
1 2 3 4 5 6
A.F.F.
NEW 2' x 2' ACT
8' - 0"
A.F.F.
NEW 2' x 2' ACT
8' - 0"
A.F.F.
NEW 2' x 2' ACT
8' - 6"A.F.F.
NEW 2' x 2' ACT
8' - 0"
A.F.F.
EXISTING 2' x 2' ACT
7' - 6"
A.F.F.
EXISTING 2' x 2' ACT
8' - 0"
A.F.F.
EXISTING 2' x 2' ACT
8' - 0"
A.F.F.
EXISTING 2' x 2' ACT
8' - 0"
A.F.F.
EXISTING 2' x 2' ACT
7' - 6" A.F.F.
NEW 2' x 2' ACT
8' - 0"
A.F.F.
NEW 2' x 2' ACT
8' - 6"
A.F.F.
EXISTING 2' x 2' ACT
7' - 6"
A.F.F.
MOISTURE RESISTANT 2' x 2' ACT
8' - 0"
A.F.F.
NEW 2' x 2' ACT
8' - 0"
A.F.F.
NEW 2' x 2' ACT
8' - 6"
A.F.F.
MOISTURE RESISTANT 2' x 2' ACT
8' - 0"
SUPPLY DIFFUSER
RETURN GRILLE
EXHAUST GRILLE
2X2 RECESSED LIGHT FIXTURE
EXIT SIGN
SURFACE MOUNTED ROUND LIGHT FIXTURE
FIRE PROTECTION HEAD
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
A111
NEW RCP
18 JUNE, 2025
JAH
TFP
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
1/8" = 1'-0"
LEVEL 2 - RCP
N O
D
E S
C R
IP
T
IO
N
D A
T E
REFLECTED CEILING LEGEND
GENERAL NOTES:
• 2' X 2' ACT CEILING INSTALL NEW TRACK AND
CEILING TILE, CEILING TILE SUPPLIED BY OWNER.
• MOLD RESISTANT 2' X 2' ACT CEILING INSTALL
NEW TRACK AND CEILING TILE.
E
F
G
1 2 3 4 5 6
MAKE SAFE EXISTING FIRE PROTECTION HEADS FOR INSTALLTION IN NEW CEILING. ADJUST HEIGHTS OF HEADS IN DINING AREA FOR NEW CEILING HEIGHT. MAKE ADJUSTMENTS TO FIRE PROTECTION PIPING TO AVOID
CONFLICTS W/ NEW DUCTWORK.
1. PROVIDE FIRE PROTECTION SYSTEM DESIGN AND INSTALLATION
AS NECESSARY TO MEET CODES, STANDARDS, AND
REQUIREMENTS OF ALL AUTHORITIES HAVING JURISDICTION
(AHJ) AND INSURANCE UNDERWRITERS.
2. COORDINATE ALL WORK w/ OTHER TRADES PRIOR TO THE
FABRICATION OR INSTALLATION OF ANY PIPING.
3. PROVIDE SYSTEM DEVICES, PIPING, AND COMPONENTS AS
NECESSARY TO INSTALL A COMPLETE FIRE PROTECTION
SYSTEM. THE EXISTING SYSTEM COMPONENTS AND PIPING MAY
BE REUSED w/ THE APPROVAL OF THE AHJ.
4. RETAIN THE SERVICES OF A NICET LEVEL 4 SYSTEM DESIGNER
TO DESIGN AND LAYOUT THE FULL SYSTEM AS NECESSARY TO
MEET THE CURRENT NFPA, STATE, AND LOCAL REQUIREMENTS.
ZONE THE FIRE PROTECTION SYSTEM AS NECESSARY. PROVIDE
ALL DEVICES AS REQUIRED FOR THE INSTALLATION OF A
COMPLETE, TEST INSPECTED, CODE COMPLIANT SYSTEM.
OBTAIN ALL NECESSARY APPROVALS PRIOR TO INSTALLATION
OF SYSTEM. OBTAIN FINAL INSPECTION AS REQUIRED BY AHJ.
5. SUBMIT DETAILED FIRE PROTECTION DRAWINGS, HYDRAULIC
CALCULATIONS, & ALL ITEMS STATED ON THE ICC CHECKLIST TO
THE CODE REVIEW OFFICIAL. AFTER THE APPROVAL OF THE
CODE REVIEW OFFICIAL, SEND THE FIRE PROTECTION
DRAWINGS & HYDRAULIC CALCULATIONS TO THE ARCHITECT &
ENGINEER FOR APPROVAL.
6. DRAWINGS ARE DIAGRAMMATIC IN NATURE. THE CONTRACTOR
MUST FIELD VERIFY ACTUAL CONDITIONS AT THE SITE PRIOR TO
PRECEDING w/ THE WORK.
7. LOCAL UTILITY BOARD PRIOR TO THE START OF DESIGN. COPY
DESIGN BASIS FLOW TEST DATA TO THE OWNER.
8. PROVIDE DEVICES AND INTERCONNECTION TO THE FIRE ALARM
SYSTEM FOR ALL ZONING, NOTIFICATION, AND ALARM AS
REQUIRED. COORDINATE w/ FIRE ALARM CONTRACTOR PRIOR TO
BIDDING.
9. SEE ARCHITECTURAL DRAWINGS FOR EXACT LOCATION OF FIRE
EXTINGUISHER CABINETS, FIRE HOSE CABINETS, AND SIAMESE
CONNECTIONS.
10. CENTER HEADS IN CEILING TILES. VERIFY BEFORE INSTALLATION
THE EXACT CEILING TYPE & PATTERN.
11. COORDINATE FINAL LOCATIONS OF SPRINKLER HEADS, PIPING, &
ALL NEW WORK w/ LIGHT FIXTURES, DIFFUSERS, GRILLES, SMOKE DETECTORS, SPEAKERS, & OTHER CEILING MOUNTED
DEVICES. MAKE MINOR MODIFICATIONS TO SUIT.
12. PROVIDE SLEEVES & FIRESTOP SEALANTS WHERE PIPES
PENETRATE FIRE RATED FLOORS & WALLS. COMPLY w/ ASTM
E-814 & UL 1479.
13. CONFORM TO ICC, FM, NFPA REQUIREMENTS AND/OR OWNER'S
INSURANCE UNDERWRITER. OBTAIN PERMITS & REVIEW STAMPS
FROM THE A.H.J.
14. SPRINKLER MAIN SIZES SHOWN ARE SIZED FOR FUTURE
CONNECTIONS
15. PIPING SHOWN IS ABOVE CEILING UNLESS OTHERWISE NOTED.
16. ALL CONTROL VALVES SHALL BE MONITORED.
17. THE SPRINKLER SYSTEM SHALL BE DESIGNED & SIZED BY THE
SPRINKLER CONTRACTOR. THESE DOCUMENTS SHALL BE USED
AS A GUIDE FOR INTENT ONLY. THE SPRINKLER HEAD TYPES
SHOWN ON THE DOCUMENTS SHALL BE CONFORMED TO.
SPRINKLER CONTRACTOR SHALL INFORM & COORDINATE ALL
ELECTRICAL & FIRE ALARM DEVICES w/ THE ELECTRICAL
CONTRACTOR.
18. INSPECTOR'S TEST VALVES SHALL NOT DRAIN ONTO CONCRETE
SIDEWALKS, PADS, OR CONCRETE PLAZA'S DUE TO STAINING. IF
DRAINING TO GRASS AREA PROVIDE MEANS TO ELIMINATE MUD
OF THEIR DEBRIS FROM SPLASHING ONTO BUILDING.
FIRE PROTECTION NOTES
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
F101
FIRE PROTECTION
PLAN
18 JUNE, 2025
TRT
TWT
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
1/8" = 1'-0"
FIRE PROTECTION PLAN
N O
D
E S
C R
IP
T
IO
N
D A
T
1. PROVIDE ALL MATERIALS AND EQUIPMENT AND PERFORM ALL
LABOR REQUIRED TO INSTALL COMPLETE AND OPERABLE
PLUMBING SYSTEMS AS INDICATED ON THE DRAWING, AS
SPECIFIED, AND REQUIRED BY CODE.
2. RUN ALL SOIL WASTE AND VENT PIPING WITH 2% MIN. GRADE
UNLESS OTHERWISE NOTED. HORIZONTAL VENT PIPING SHALL
BE GRADED TO DRIP BACK TO THE SOIL OR WASTE PIPE BY
GRAVITY.
3. PROVIDE SHUTOFF VALVES IN ALL DOMESTIC WATER PIPING
SYSTEMS AT ALL SERVICE POINTS AND AT BRANCHES IN WHICH
PIPING SERVES TWO OR MORE FIXTURES.
4. UNLESS OTHERWISE NOTED, ALL DOMESTIC COLD AND HOT
WATER PIPING SHALL BE A MIN. OF 1/2" SIZE.
5. UNLESS OTHERWISE NOTED, ALL PIPING IS OVERHEAD, TIGHT TO
UNDERSIDE OF SLAB w/ SPACE FOR INSULATION IF REQUIRED.
PIPING IS TO BE "TOP DOWN".
6. INSTALL PIPING SO THAT ALL VALVES, STRAINERS, UNIONS,
TRAPS, FLANGES, AND OTHER APPURTENANCES REQUIRING
ACCESS ARE ACCESSIBLE.
7. ALL PIPING SHALL CLEAR DOORS AND WINDOWS.
8. ALL PIPING SHALL GRADE TO LOW POINTS. PROVIDE HOSE END
DRAINS VALVES AT THE BOTTOM OF ALL RISERS AND LOW
POINTS.
9. UNIONS AND/OR FLANGES SHALL BE INSTALLED AT EACH PIECE
OF EQUIPMENT, IN BYPASSES, AND IN LONG PIPING RUNS
(GREATER THAN 100 FEET) TO PERMIT DISASSEMBLY FOR
ALTERATIONS AND REPAIRS.
10. ALL VALVES SHALL BE ADJUSTED FOR SMOOTH AND EASY
OPERATION.
11. PROVIDE ALL PLUMBING FIXTURES AND EQUIPMENT w/
ACCESSIBLE STOPS.
12. PROVIDE CLEANOUTS IN SANITARY AND STORM DRAINAGE
SYSTEMS AT ENDS OF RUNS, AT CHANGES IN DIRECTIONS, NEAR
THE BASE OF STACKS, EVERY 50'-0" IN HORIZONTAL RUN AND
ELSEWHERE AS INDICATED.
13. ALL CLEANOUTS SHALL BE FULL SIZE OF PIPE FOR PIPE SIZES 4
INCHES AND SMALLER AND SHALL BE 4 INCHES FOR PIPE SIZES
LARGER THAN 4 INCHES.
14. ALL BALANCING VALVES AND BUTTERFLY VALVES SHALL BE
PROVIDED w/ POSITION INDICATORS AND MAXIMUM ADJUSTABLE
STOP (MEMORY STOPS).
15. ALL VALVES SHALL BE INSTALLED SO THAT THE VALVE REMAINS
IN SERVICE WHEN EQUIPMENT OR PIPING ON EQUIPMENT SIDE
OF VALVE IS REMOVED.
16. ALL PIPING WORK SHALL BE COORDINATED w/ ALL TRADES
INVOLVED. OFFSETS IN PIPING AROUND OBSTRUCTIONS SHALL
BE PROVIDED AT NO ADDITIONAL COST TO THE OWNER.
17. PROVIDE FLEXIBLE CONNECTIONS IN ALL PIPING SYSTEMS
CONNECTED TO PUMPS AND OTHER EQUIPMENT WHICH
REQUIRE VIBRATION ISOLATION. FLEXIBLE CONNECTIONS SHALL
BE PROVIDED AS CLOSE TO THE EQUIPMENT AS POSSIBLE OR AS
INDICATED ON THE DRAWINGS.
18. DOMESTIC WATER PIPING TO BE TYPE "L" COPPER w/ SOLDERED
OR MECHANICALLY PRESSED FITTINGS.
19. WASTE PIPING TO BE CAST IRON NO-HUB (EXPOSED).
20. COORDINATE ALL STUB-UPS, EXACT FIXTURE TYPE AND SIZES,
ETC. w/ GENERAL CONTRACTOR AND FOR FIT w GENERAL
CONTRACTOR INSTALLED CABINETRY, ETC. AND FOR FINAL WALL
LOCATIONS. FIELD ADJUST LOCATIONS FOR COORDINATION AS
NECESSARY. AVOID EXCESSIVE ADDITIONAL PIPE FITTINGS.
PRESSURE TEST ALL SUBGRADE PIPING AND MAINTAIN
PRESSURE TESTING DURING CONCRETE POURS.
21. FINAL COORDINATION OF SCOPE OF WORK, DIMENSIONS,
FIXTURE PLACEMENT, ROUTING, ETC. IS THE RESPONSIBILITY OF
THE GENERAL CONTRACTOR AND ALL SUB-CONTRACTORS
PRIOR TO BIDDING. VERIFY ALL FIELD CONDITIONS AND
MEASUREMENTS PRIOR TO BIDDING. COORDINATE ALL WORK w/ OTHER TRADES. COORDINATE ALL MOUNTED DEVICES w/ ALL
OTHER TRADES PRIOR TO INSTALLATION. FIRESTOP ALL
PENETRATIONS OF FIRE WALL (SEE ARCH. PLANS) AND FLOORS.
22. ALL WORK TO MEET REQUIREMENTS OF CURRENT
INTERVENTIONAL PLUMBING CODE, INTERNATIONAL
MECHANICAL CODE, STATE AND LOCAL CODES AND
REQUIREMENTS AND INTERNATIONAL FUEL GAS CODE.
PLUMBING NOTES
L
--------------------A------------------------------------------------------------------------------------
AAV AUTOMATIC AIR VENT
ABV ABOVE
AD ACCESS DOOR
ADA AMERICANS WITH DISABLITIES ACT
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AHU AIR HANDLING UNIT
ALT ALTERNATE
ALUM ALUMINUM
AP ACCESS PANEL
APPROX APPROXIMATELY
ASSOC ASSOCIATED
ASSY ASSEMBLY
ATC AUTOMATIC TEMPERATURE CONTROL
AUTO AUTOMATIC
AUX AUXILIARY
AV AIR VENT
AVG AVERAGE
AWT AVERAGE WATER TEMPERATURE
---------------B----------------------------------------------------------------------------------------
BB BASEBOARD
BC BALANCING COCK
BD BLOW DOWN
BFF BELOW FINISHED FLOOR
BFG BELOW FINISHED GRADE
BFP BACKFLOW PREVENTER
BFV BUTTERFLY VALVE
BHP BRAKE HORESPOWER
BLDG BUILDING
BLR BOILER
BLW BELOW
BO BLOW OFF
BTM BOTTOM
BOP BOTTOM OF PIPE
BTUH BRITISH THERMAL UNIT PER HOUR
BV BALL VALVE
---------------C---------------------------------------------------------------------------------------
CA COMPRESSED AIR
CAP CAPACITY
CCW COUNTER CLOCKWISE
CDL CONDENSATE DRAIN LINE
CFH CUBIC FEET PER HOUR
CFM CUBIC FEET PER MINUTE
CFS CUBIC FEET PER SECOND
CHKV CHECK VALVE
CHWR CHILLED & HOT WATER RETURN
CHWS CHILLED & HOT WATER SUPPLY
CHWS&R CHILLED & HOT WATER SUPPLY AND RETURN
CIRC CIRCULATING
CI CAST IRON
CIRC CIRCULATING
CKT CIRCUIT
CLG CEILING
CL CENTER LINE
CMU CONCRETE MASONRY UNIT
C/O CLEAN OUT
COL COLUMN
COMB COMBINATION
COMP COMPRESSOR
CONC CONCRETE
COND CONDENSATE
CONN CONNECTION
CONT CONTINUATION
CONST CONSTRUCTION
COP COEFFICIENT OF PERFORMANCE
CORR CORRIDOR
CT COOLING TOWER
CU CONDENSING UNIT
CUH CABINET UNIT HEATER
Cv COEFFICIENT, VALVE FLOW
CW COLD WATER/CLOCKWISE
CWFT CONDENSER WATER FROM TOWER
CWR CHILLED WATER RETURN
CWS CHILLED WATER SUPPLY
CWS&R CHILLED WATER SUPPLY AND RETURN
CWTT CONDENSER WATER TO TOWER
---------------D----------------------------------------------------------------------
D DEEP
Db DRY BULB TEMPERATURE(ºF)
DCO DOUBLE CLEAN OUT
DEMO DEMOLISH
DEPT DEPARTMENT
DIA DIAMETER
DIAG DIAGRAM
DISCH DISCHARGE
DCW DOMESTIC COLD WATER
DHW DOMESTIC HOT WATER
DHWR DOMESTIC HOT WATER RETURN
DN DOWN
DP DIFFERENTIAL PRESSURE
DPT DEW POINT TEMPERATURE(ºF)
DR DRAIN
DWG DRAWING
DWH DOMESTIC WATER HEATER
DX DIRECT EXPANSION
----------------E----------------------------------------------------------------------
EA EACH
EC ELECTRICAL CONTRACTOR
EFF EFFICIENCY
ELEC ELECTRIC
ELEV ELEVATION
ENCL ENCLOSURE
ENT ENTERING
EP END PANEL/EXPLOSION PROOF
EQUIP EQUIPMENT
ER ECCENTRIC REDUCER(BOTTOMS FLAT)
ESP EXTERNAL STATIC PRESSURE
EXH EXHAUST
EXIST EXISTING
EXP EXPANSION
EWC ELECTRIC WATER COOLER
EWT ENTERING WATER TEMPERATUR(ºF)
----------------F----------------------------------------------------------------------
ºF FAHRENHEIT
FA FREE AREA
FB FREE BLOW
F&T FLOAT AND THERMOSTATIC TRAP
FC FLEXIBLE CONNECTION
FCD FLOW CONTROL DEVICE
FCO FLOOR CLEAN OUT
FCU FAN COIL UNIT
FD FIRE DAMPER/FLOOR DRAIN
FDN FOUNDATION
FF FOULING FACTOR
FIN FINISHED
FLA FULL LOAD AMPS
FLG FLANGE
FLR FLOOR
FNL FUNNEL
FOR FUEL OIL RETURN
FOS FUEL OIL SUPPLY
FOS&R FUEL OIL SUPPLY AND RETURN
FOV FUEL OIL VENT
FPB FAN POWERED BOX
FPM FEET PER MINUTE
FPS FEET PER SECOND
FT FIN-TUBE/FEET
FTG FITTING
FURN FURNISH
FV FACE VELOCITY
FW FEED WATER
----------------G----------------------------------------------------------------------
G GAS
GALV GALVANIZED
GA GAUGE, GAGE
GC GENERAL CONTRACTOR
GCWR GLYCOL CHILLED WATER RETURN
GCWS GLYCOL CHILLED WATER SUPPLY
GHWR GLYCOL HOT WATER RETURN
GHWS GLYCOL HOT WATER SUPPLY
GLV GLOBE VALVE
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GRAV GRAVITY
GRV GRAVITY ROOF VENTILATOR
GV GATE VALVE
----------------H----------------------------------------------------------------------
H HEIGHT
HB HOSE BIBB
HC HEATING CONTRACTOR;
HANICAPPED
HD HEAD/HUB DRAIN
HG MERCURY
HGR HANGER
HP HORSEPOWER/HEAT PUMP
HORIZ HORIZONTAL
HPD HIGH PRESSURE DRIP
HPR HIGH PRESSURE RETURN
HPS HIGH PRESSURE STEAM
HR HOUR
HTG HEATING
HTR HEATER
HUH HORIZONTAL UNIT HEATER
HV HIGH VELOCITY
HVAC HEATING, VENTILATING, AND AIR
CONDITIONING
HW HOT WATER
HWBG HOT WATER BELOW GRADE
HWOH HOT WATER OVER HEAD
HWR HOT WATER RETURN
HWS HOT WATER SUPPLY
HWS&R HOT WATER SUPPLY AND
RETURN
----------------I----------------------------------------------------------------------
ID INSIDE DIAMETER
IE INVERT ELEVATION
IN INCHES
INV INVERT
IN-WG INCHES-WATER GAGE
INSUL INSULATION
IPS IRON PIPE SIZE
IVS ISOLATION VALVE STATION
IW INDIRECT WASTE
----------------J----------------------------------------------------------------------
JT JOINT
----------------K ---------------------------------------------------------------------
KS KITCHEN SINK
----------------L----------------------------------------------------------------------
L LENGTH
LAV LAVATORY
LBS POUNDS
LBS/HR POUNDS PER HOUR
LF LINEAR FEET
LP LOW PRESSURE
LPD LOW PRESSURE DRIP
LPR LOW PRESSURE RETURN
LPG LOW PETROLEUM GAS
LPS LOW PRESSURE STEAM
LV LOW VELOCITY
LVG LEAVING
LWCO LOW WATER CUTOFF
LWT LEAVING WATER
TEMPERATURE(ºF)
----------------M----------------------------------------------------------------------
MAU MAKE-UP AIR UNIT
MAV MANUAL AIR VENT
MAX MAXIMUM
MBH THOUSAND BTUH
MC MECHANICAL CONTRACTOR
MCC MOTOR CONTROL CENTER
MECH MECHANICAL
MFG MANUFACTURER
MH MANHOLE
MIN MINIMUM
MISC MISCELLANEOUS
MPD MEDIUM PRESSURE DRIP
MPR MEDIUM PRESSURE RETURN
MPS MEDIUM PRESSURE STEAM
MS MINI-SPLIT SYSTEM
MTD MOUNTED
MTG MOUNTING
MTL METAL
MTR MOTOR
MWT MEAN WATER TEMPERATURE(ºF)
----------------N----------------------------------------------------------------------
N NORTH
N/A NOT APPLICABLE
NC NORMALLY CLOSED; NOISE CRITERIA
NEG NEGATIVE
NIC NOT IN CONTRACT
NM NONMETALLIC
NMAG NONMAGNETIC
NO NORMALLY OPEN
No NUMBER
NOM NOMINAL
NORM NORMAL
NPW NON POTABLE WATER
NTS NOT TO SCALE
NWL NORMAL WATER LEVEL
----------------O----------------------------------------------------------------------
OA OVERALL; OUTSIDE AIR
OC ON CENTER
OCC OCCUPANCY
OCPD OVERCURRENT PROTECTION DEVICE
OD OUTSIDE DIAMETER; OUTSIDE DIMENSION
ODS OXYGEN DEPRIVATION SENSOR
OF/CI OWNER FURNISHED / CONTRACTOR INSTALLED
OF/OI OWNER FURNISHED / OWNER INSTALLED
OFD OVER FLOW DRAIN
OH OVERHEAD
OPER OPERATED
OPP OPPOSITE
OPT OPTIONAL; OPTIMUM
OSHA OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION
OSV OIL SAFETY VALVE
OUT OUTLET
OVC OVERCURRENT
OVF OVERFLOW
OZ OUNCE
----------------P----------------------------------------------------------------------
P PUMP
PC PLUMBING CONTRACTOR
PD PRESSURE DROP/PUMP
PE PNEUMATIC - ELECTRIC
PG PRESSURE DROP/PUMP DISCHARGE
PH PHASE
PLBG PLUMBING
PNL PANEL
PR PANEL RADIATOR
PRESS PRESSURE
PRV POWER ROOF VENTILATOR/PRESSURE REDUCING
VALVE
PS PIPE SUPPORT
PSI POUND PER SQUARE INCH
PSIA POUNDS PER SQUARE INCH ABSOLUTE
PSIG POUNDS PER SQUARE INCH GAGE
PT PRESSURE/TEMPERATURE TAP
PTAC PACKAGED TERMINAL AIR CONDITIONER
PVC POLYVINYL CHLORIDE
----------------Q----------------------------------------------------------------------
QTY QUANTITY
----------------R----------------------------------------------------------------------
RA RELIEF/RETURN AIR
RAD RADIATOR
RAF RETURN AIR FIXTURES
RCP RADIANT CEILING PANEL
RD ROOF DRAIN
REC RECESSED/RECEIVED
REFRIG REFRIGERANT
REG REGISTER
REINF REINFORCED
REQD REQUIRED
RET RETURN
REV REVISION
RF RETURN/RELIEF FAN
RH REHEAT COIL
RHG REFRIGERANT HOT
RL REFRIGERANT LIQUID
RM ROOM
RPM REVOLUTIONS PER MINUTE
RS REFRIGERANT SUCTION
RV RELIEF VALVE
RWC RAIN WATER CONDUCTOR
----------------S----------------------------------------------------------------------
SA SUPPLY AIR
SCH SCHEDULE
SDPR SMOKE DAMPER
SENS SENSIBLE
SEP SEPARATOR
SF SUPPLY FAN
SHT SHEET
SK SINK
SP STATIC PRESSURE (INCHES OF WATER)
SPEC SPECIFICATION
SPGR SPECIFIC GRAVITY
SQ SQUARE
SQFT SQUARE FOOT
SS STAINLESS STEEL UNIT
STAT STATIC
STD STANDARD
STL STEEL
STR STRAINER
SUP SUPPLY
SV SAFETY VALVE
SW SWITCH
----------------T----------------------------------------------------------------------
TA THROW AWAY
TCV TEMPERATURE CONTROL VALVE
TD TEMPERATURE DIFFERENCE
TDV TRIPLE DUTY VALVE
TEMP TEMPERATURE
TH THERMOMETER
THK THICK
TK TANK
TMV THRTMOSTATIC MIXING VALVE
TOT TOTAL
TP TRAP PRIMER/TRAP PRIMER SUPPLY
TRANS TRANSITION
TSP TOTAL STATIC PRESSURE
TSTAT THERMOSTAT
TYP TYPICAL
----------------U----------------------------------------------------------------------
UC UNDERCUT
UF UNDER FLOOR
UG UNDERGROUND
UH UNIT HEATER
UR URINAL
----------------V----------------------------------------------------------------------
V VOLTAGE/VALVE/VENT
VAC VACUUM
VEL VELOCITY
VERT VERTICAL
VFD VARIABLE FREQUENCY DRIVE
VFS VENTURI FLOW STATION
VOL VOLUME
VRF VARIABLE REFRIGERANT FLOW
VTR VENT THROUGH ROOF
----------------W----------------------------------------------------------------------
W WIDTH
W/ WITH
W/O WITHOUT
WA WATER HAMMER ARRESTER
Wb WET BULB TEMPERATURE(ºF)
WC WATER COLUMN/WATER CLOSET
WCO WALL CLEANOUT
WG WATER GAUGE
WH WALL HEATER
WL WATER LEVEL
WP WEATHERPROOF
WT WEIGHT
----------------Y----------------------------------------------------------------------
YCO YARD CLEANOUT
----------------Z----------------------------------------------------------------------
Z ZONE
ZCV ZONE CONTROL VALVE
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
P000
PLUMBING
ABBREVIATIONS
18 JUNE, 2025
TRT
TWT
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
PLUMBING ABBREVIATIONS
PLUMBING SYSTEM LEGEND
ABBREVIATION SYSTEM TYPE
CON CONDENSATE
DCW DOMESTIC COLD WATER
DHW DOMESTIC HOT WATER
SAN SANITARY
N O
D
E S
C R
IP
T
IO
N
D A
E
F
G
1 2 3 4 5 6
ADJUST ELEVATION OF VRF CONDENSATE PIPING
TO AVOID CONFLICT W/ NEW DUCTWORK.
ADJUST PIPING IN THIS AREA AS NECESSARY TO
AVOID ANY CONFLICTS WITH NEW DUCTWORK.
S A
N
DHW
DCW
C O
N
1. PROVIDE ALL MATERIALS AND EQUIPMENT AND PERFORM ALL
LABOR REQUIRED TO INSTALL COMPLETE AND OPERABLE
PLUMBING SYSTEMS AS INDICATED ON THE DRAWING, AS
SPECIFIED, AND REQUIRED BY CODE.
2. RUN ALL SOIL WASTE AND VENT PIPING WITH 2% MIN. GRADE
UNLESS OTHERWISE NOTED. HORIZONTAL VENT PIPING SHALL
BE GRADED TO DRIP BACK TO THE SOIL OR WASTE PIPE BY
GRAVITY.
3. PROVIDE SHUTOFF VALVES IN ALL DOMESTIC WATER PIPING
SYSTEMS AT ALL SERVICE POINTS AND AT BRANCHES IN WHICH
PIPING SERVES TWO OR MORE FIXTURES.
4. UNLESS OTHERWISE NOTED, ALL DOMESTIC COLD AND HOT
WATER PIPING SHALL BE A MIN. OF 1/2" SIZE.
5. UNLESS OTHERWISE NOTED, ALL PIPING IS OVERHEAD, TIGHT TO
UNDERSIDE OF SLAB w/ SPACE FOR INSULATION IF REQUIRED.
PIPING IS TO BE "TOP DOWN".
6. INSTALL PIPING SO THAT ALL VALVES, STRAINERS, UNIONS,
TRAPS, FLANGES, AND OTHER APPURTENANCES REQUIRING
ACCESS ARE ACCESSIBLE.
7. ALL PIPING SHALL CLEAR DOORS AND WINDOWS.
8. ALL PIPING SHALL GRADE TO LOW POINTS. PROVIDE HOSE END
DRAINS VALVES AT THE BOTTOM OF ALL RISERS AND LOW
POINTS.
9. UNIONS AND/OR FLANGES SHALL BE INSTALLED AT EACH PIECE
OF EQUIPMENT, IN BYPASSES, AND IN LONG PIPING RUNS
(GREATER THAN 100 FEET) TO PERMIT DISASSEMBLY FOR
ALTERATIONS AND REPAIRS.
10. ALL VALVES SHALL BE ADJUSTED FOR SMOOTH AND EASY
OPERATION.
11. PROVIDE ALL PLUMBING FIXTURES AND EQUIPMENT w/
ACCESSIBLE STOPS.
12. PROVIDE CLEANOUTS IN SANITARY AND STORM DRAINAGE
SYSTEMS AT ENDS OF RUNS, AT CHANGES IN DIRECTIONS, NEAR
THE BASE OF STACKS, EVERY 50'-0" IN HORIZONTAL RUN AND
ELSEWHERE AS INDICATED.
13. ALL CLEANOUTS SHALL BE FULL SIZE OF PIPE FOR PIPE SIZES 4
INCHES AND SMALLER AND SHALL BE 4 INCHES FOR PIPE SIZES
LARGER THAN 4 INCHES.
14. ALL BALANCING VALVES AND BUTTERFLY VALVES SHALL BE
PROVIDED w/ POSITION INDICATORS AND MAXIMUM ADJUSTABLE
STOP (MEMORY STOPS).
15. ALL VALVES SHALL BE INSTALLED SO THAT THE VALVE REMAINS
IN SERVICE WHEN EQUIPMENT OR PIPING ON EQUIPMENT SIDE
OF VALVE IS REMOVED.
16. ALL PIPING WORK SHALL BE COORDINATED w/ ALL TRADES
INVOLVED. OFFSETS IN PIPING AROUND OBSTRUCTIONS SHALL
BE PROVIDED AT NO ADDITIONAL COST TO THE OWNER.
17. PROVIDE FLEXIBLE CONNECTIONS IN ALL PIPING SYSTEMS
CONNECTED TO PUMPS AND OTHER EQUIPMENT WHICH
REQUIRE VIBRATION ISOLATION. FLEXIBLE CONNECTIONS SHALL
BE PROVIDED AS CLOSE TO THE EQUIPMENT AS POSSIBLE OR AS
INDICATED ON THE DRAWINGS.
18. DOMESTIC WATER PIPING TO BE TYPE "L" COPPER w/ SOLDERED
OR MECHANICALLY PRESSED FITTINGS.
19. WASTE PIPING TO BE CAST IRON NO-HUB (EXPOSED).
20. COORDINATE ALL STUB-UPS, EXACT FIXTURE TYPE AND SIZES,
ETC. w/ GENERAL CONTRACTOR AND FOR FIT w GENERAL
CONTRACTOR INSTALLED CABINETRY, ETC. AND FOR FINAL WALL
LOCATIONS. FIELD ADJUST LOCATIONS FOR COORDINATION AS
NECESSARY. AVOID EXCESSIVE ADDITIONAL PIPE FITTINGS.
PRESSURE TEST ALL SUBGRADE PIPING AND MAINTAIN
PRESSURE TESTING DURING CONCRETE POURS.
21. FINAL COORDINATION OF SCOPE OF WORK, DIMENSIONS,
FIXTURE PLACEMENT, ROUTING, ETC. IS THE RESPONSIBILITY OF
THE GENERAL CONTRACTOR AND ALL SUB-CONTRACTORS
PRIOR TO BIDDING. VERIFY ALL FIELD CONDITIONS AND
MEASUREMENTS PRIOR TO BIDDING. COORDINATE ALL WORK w/ OTHER TRADES. COORDINATE ALL MOUNTED DEVICES w/ ALL
OTHER TRADES PRIOR TO INSTALLATION. FIRESTOP ALL
PENETRATIONS OF FIRE WALL (SEE ARCH. PLANS) AND FLOORS.
22. ALL WORK TO MEET REQUIREMENTS OF CURRENT
INTERVENTIONAL PLUMBING CODE, INTERNATIONAL
MECHANICAL CODE, STATE AND LOCAL CODES AND
REQUIREMENTS AND INTERNATIONAL FUEL GAS CODE.
PLUMBING NOTES
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
P101
PLUMBING PLAN
18 JUNE, 2025
TRT
TWT
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
1/8" = 1'-0"
SECOND FLOOR PLUMBING PLAN
PLUMBING SYSTEM LEGEND
ABBREVIATION SYSTEM TYPE
CON CONDENSATE
DCW DOMESTIC COLD WATER
DHW DOMESTIC HOT WATER
SAN SANITARY
N O
D
E S
C R
IP
T
IO
N
D A
LABOR REQUIRED TO INSTALL, COMPLETE, AND OPERATE AS
INDICATED ON THE DRAWINGS, SPECIFICATIONS, AND
REQUIRED BY CODE.
2. SEPARATE BALANCE DAMPERS WILL BE INSTALLED AT ALL
TAKE-OFFS FROM MAIN DUCTS. FIRE DAMPERS WILL BE
INSTALLED AT LOCATIONS SHOWN OR WHERE ANY DUCT
PENETRATES A FIRE RATED WALL. REFER TO ARCHITECTURAL
SHEETS FOR RATED WALLS. FIRE DAMPERS ARE TO MATCH THE
RATING OF THE WALL OR CEILING BEING PENETRATED.
3. ALL DUCT TAKE-OFFS AND TRANSITIONS WILL BE TAPERED.
ELBOWS AND TURNS SHALL BE CONSTRUCTED w/ A SMOOTH
RADIUSED FITTING MIN 1.5 TIMES THE WIDTH OF THE DUCT.
TURNING VANES ARE NOT PERMITTED, UNLESS APPROVED BY
ENGINEER OR INDICATED ON DRAWINGS.
4. CERTAIN ITEMS SUCH AS RISERS AND DROPS IN DUCTWORK,
ACCESS DOORS, VOLUME DAMPERS, ETC. ARE INDICATED ON
THE CONTRACT DOCUMENT DRAWINGS FOR CLARITY FOR A
SPECIFIC LOCATION REQUIREMENT AND SHALL NOT BE
INTERPRETED AS THE EXTENT OF THE REQUIREMENTS FOR
THOSE ITEMS.
5. ALL DUCTWORK IS TO BE EXTERNALLY INSULATED. INTERIOR
MOUNTED DUCTWORK SHALL HAVE FOIL FACED 1-1/2 TO 2"
FIBERGLASS INSULATION AND SEALED w/ FIBERGLASS
REINFORCED FOIL TAPE.
6. CONSTRUCT ALL DUCTWORK PER SMACNA STANDARDS FOR
LOW PRESSURE DUCTWORK (2.0" STATIC). ALL JOINTS ARE TO
BE SEALED w/ MASTIC.
7. PROVIDE AIR LOUVERS w/ GRAVITY BACKDRAFT DAMPERS. ALL
EXTERIOR LOUVERS WILL HAVE 60% MIN. OPEN AREA AND BUG
SCREENS. INSTALL ALL w/ BIRD SCREEN. COLORS BY OWNER/ARCHITECT. COORDINATE LOCATIONS w/ GENERAL
CONTRACTOR.
8. PROVIDE FULLY ADHERED VELOCITY DUCT LINER FROM UNIT
DISCHARGE AND RETURN TO 10'-0" BEYOND UNIT. PROVIDE
NOSING AT THE BEGINNING AND END OF THE DUCT LINER.
9. UNLESS OTHERWISE SHOWN, LOCATE ALL ROOM
THERMOSTATS AND HUMIDISTATS AT 5'-0" ABOVE FINISHED
FLOOR. FINAL THERMOSTAT LOCATION BY OWNER/ARCHITECT.
10. ALL DUCTWORK SHALL CLEAR DOORS AND WINDOWS.
11. ALL DUCTWORK DIMENSIONS, AS SHOWN ON THE DRAWINGS,
ARE INTERNAL CLEAR DIMENSIONS AND DUCT SIZE SHALL BE
INCREASED TO COMPENSATE FOR DUCT LINING WHERE
APPLICABLE.
12. COORDINATE DIFFUSERS, REGISTER, AND GRILLE LOCATIONS
w/ ARCHITECTURAL REFLECTED CEILING PLANS, LIGHTING, AND
OTHER CEILING ITEMS. MAKE MINOR DUCT MODIFICATIONS TO
SUIT.
13. LOCATE ALL MECHANICAL EQUIPMENT FOR UN-OBSTRUCTED
ACCESS TO UNIT ACCESS PANELS, CONTROL, AND VALVING.
14. PROVIDE FLEXIBLE CONNECTIONS IN ALL DUCTWORK SYSTEMS
CONNECTED TO AIR HANDLING UNITS, FANS, AND OTHER
EQUIPMENT WHICH REQUIRE VIBRATION ISOLATION.
OTHERWISE NOTED, ALL DUCTWORK IS OVERHEAD, TIGHT TO
THE UNDERSIDE OF THE STRUCTURAL, WITH SPACE FOR
INSULATION.
15. RUNS OF FLEXIBLE DUCT SHALL NOT EXCEED 3'-0". FLEXIBLE
DUCT IS TO BE USED FOR FINAL CONNECTIONS TO GRILLES
AND DIFFUSER ONLY.
16. ALL DUCTWORK SHALL BE COORDINATED w/ ALL TRADES
INVOLVED. OFFSETS IN DUCTS, INCLUDING DIVIDED DUCTS AND
TRANSITIONS AROUND OBSTRUCTIONS, SHALL BE PROVIDED AT
NO ADDITIONAL COST TO THE OWNER.
17. PROVIDE ACCESS DOORS IN DUCTWORK TO PROVIDE ACCESS
FOR ALL SMOKE DETECTORS, FIRE DAMPERS, SMOKE
DAMPERS, HUMIDIFIERS, COILS AND OTHER ITEMS LOCATED IN
DUCTWORK WHICH REQUIRE SERVICE OR INSPECTION.
18. SEE SPEC FOR DUCTWORK GAUGES, BRACING, HANGERS, AND
OTHER REQUIREMENTS.
19. EXTERIOR LOUVERS ARE INDICATED FOR INFORMATION ONLY.
DETAILED DESCRIPTIONS ARE PROVIDED IN THE
ARCHITECTURAL SPECIFICATIONS. LOUVER SIZES, LOCATIONS,
MOUNTING, AND DETAILS SHALL BE COORDINATED w/ OTHER
TRADES INVOLVED.
20. PERFORM WORK IN ACCORDANCE w/ CURRENT INTERNATIONAL
MECHANICAL CODE, FUEL GAS CODE, ASHRAE, SMACNA, STATE,
AND LOCAL CODES AND REQUIREMENTS.
21. VERIFY ALL FIELD CONDITIONS AND MEASUREMENTS PRIOR TO
BIDDING. COORDINATE ALL WORK w/ OTHER TRADES.
COORDINATE ALL CEILING MOUNTED DEVICES w/ ALL OTHER
TRADES PRIOR TO INSTALLATION. FINAL COORDINATION OF
SCOPE OF WORK, DIMENSIONS, FIXTURE PLACEMENT, ROUTING
ETC. IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR
AND ALL SUB-CONTRACTORS PRIOR TO BIDDING.
MECHANICAL NOTES
1. PROVIDE ALL MATERIALS AND EQUIPMENT AND PERFORM ALL
LABOR REQUIRED TO INSTALL COMPLETE AND OPERABLE
PIPING SYSTEMS AS INDICATED ON THE DRAWINGS,
SPECIFICATIONS, AND REQUIRED BY CODE.
2. MAINTAIN A MIN. OF 3'-0" OF GROUND COVER OVER ALL
UNDERGROUND HAVC PIPING, UNLESS OTHERWISE NOTED.
3. NATURAL GAS PIPING IS TO BE P40 STEEL w/ BLACK IRON
FITTINGS. PROVIDED WELD GAS PIPING BY SIZE AS REQUIRED
BY FUEL GAS CODE.
4. PROVIDE BALL VALVE STOPS AT ALL FIXTURES. PROVIDE
UNIONS, DIRT LEGS, AND REGULATORS ON ALL EQUIPMENT.
5. COORDINATE ALL STUB-UPS AND FIELD ADJUST LOCATIONS FOR
COORDINATION AS NECESSARY. AVOID EXCESSIVE ADDITIONAL
PIPE FITTINGS.
6. PROVIDE AN AIR VENT AT THE HIGH POINT OF EACH DROP IN
THE HEATING WATER, CHILLED WATER, AND OTHER CLOSED
WATER PIPING SYSTEMS. ALL PIPING SHALL GRADE TO LOW
POINTS. PROVIDE HOSE END DRAIN VALVES AT BOTTOM OF
RISERS AND LOW POINTS.
7. UNLESS OTHERWISE NOTED, ALL PIPING IS TO OVERHEAD,
TIGHT TO UNDERSIDE OF STRUCTURE OR DECK w/ SPACE FOR
INSULATION.
8. INSTALL PIPING SO THAT ALL VALVES, STRAINERS, UNIONS,
TRAPS, FLANGES, ETC. ARE ACCESSIBLE.
9. ALL BALANCING VALVES AND BUTTERFLY VALVES SHALL BE
PROVIDED w/ POSITION INDICATORS AND MANUAL ADJUSTABLE
STOPS.
10. ALL VALVES (EXCEPT CONTROL VALVES) AND STRAINERS SHALL
BE FULL SIZE OF PIPE BEFORE REDUCING SIZE TO MAKE
CONNECTIONS TO EQUIPMENT AND CONTROLS.
11. UNIONS AND/OR FLANGES SHALL BE INSTALLED AT EACH PIECE
OF EQUIPMENT, IN BYPASSES, AND IN LONG PIPING RUNS O
PERMIT DISASSEMBLY FOR ALTERATIONS AND REPAIRS.
12. ALL PIPING SHALL CLEAR DOORS AND WINDOWS. ALL VALVES
SHALL BE ADJUSTED FOR SMOOTH AND EASY OPERATION.
13. ALL PIPING WORK SHALL BE COORDINATED w/ ALL TRADES
INVOLVED. OFFSETS IN PIPING AROUND OBSTRUCTIONS SHALL
BE PROVIDED AT NO ADDITIONAL COST TO THE OWNER.
14. PROVIDED FLEXIBLE CONNECTIONS IN ALL PIPING SYSTEMS
CONNECTED TO PUMPS, CHILLERS, COOLING TOWERS, AND
OTHER EQUIPMENT WHICH REQUIRE VIBRATION ISOLATION
EXCEPT WATER COILS.
15. ALL WORK TO MEET REQUIREMENTS OF CURRENT
INTERNATIONAL PLUMBING CODE, INTERNATIONAL MECHANICAL
CODE, APPLICABLE LOCAL CODES, LOCAL UTILITY
REQUIREMENTS, AND THE INTERNATIONAL FUEL GAS CODE.
16. FINAL COORDINATION OF SCOPE OF WORK, DIMENSIONS,
FIXTURE PLACEMENT, ROUTING, ECT. IS THE RESPONSIBILITY OF
THE PRIME CONTRACTOR AND ALL SUB-CONTRACTORS PRIOR
TO BIDDING.
PIPING NOTES
--------------------SYMBOLS------------------------------------------------------------------------
# NUMBER
& AND
º DEGREES
ºF DEGREES FAHRENHEIT
--------------------A------------------------------------------------------------------------------------
AAV AUTOMATIC AIR VENT
ABV ABOVE
AFF ABOVE FINISHED FLOOR
AHU AIR HANDLING UNIT
ALT ALTERNATE
ALUM ALUMINUM
APPROX APPROXIMATELY
AUX AUXILIARY
AVG AVERAGE
---------------B----------------------------------------------------------------------------------------
BFV BUTTERFLY VALVE
BH BASEBOARD HEATER
BHP BRAKE HORESPOWER
BLR BOILER
BTUH BRITISH THERMAL UNIT PER HOUR
BV BALL VALVE
---------------C---------------------------------------------------------------------------------------
CA COMPRESSED AIR
CAP CAPACITY
CFM CUBIC FEET PER MINUTE
CHKV CHECK VALVE
CIRC CIRCULATING
CI CAST IRON
CKT CIRCUIT
CMU CONCRETE MASONARY UNIT
C/O CLEAN OUT
CON CONDENSATE
CONT CONTINUATION
CT COOLING TOWER
CU CONDENSING UNIT
---------------D----------------------------------------------------------------------
DIA DIAMETER
DWG DRAWING
DWH DOMESTIC WATER HEATER
----------------E----------------------------------------------------------------------
EA EXHAUST AIR
EAT ENTERING AIR TEMPERATURE(ºF)
EC ELECTRICAL CONTRACTOR
EF EXHAUST FAN
EFF EFFICIENCY
ELEC ELECTRIC
ELEV ELEVATION
EQUIP EQUIPMENT
ESP EXTERNAL STATIC PRESSURE
EXH EXHAUST
EXIST EXISTING
EWT ENTERING WATER TEMPERATUR(ºF)
----------------F----------------------------------------------------------------------
ºF FAHRENHEIT
FCU FAN COIL UNIT
FD FIRE DAMPER/FLOOR DRAIN
FLA FULL LOAD AMPS
FLR FLOOR
FO FLAT OVAL
FPM FEET PER MINUTE
FPS FEET PER SECOND
FT FEET
----------------G----------------------------------------------------------------------
GAS NATURAL GAS
GALV GALVANIZED
GA GAUGE
GC GENERAL CONTRACTOR
GLV GLOBE VALVE
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
GV GATE VALVE
----------------H----------------------------------------------------------------------
HCWL HYDRONIC CHILLED WATER LOOP
HCWR HYDRONIC CHILLED WATER RETURN
HCWS HYDRONIC CHILLED WATER SUPPLY
HHWL HYDRONIC HOT WATER LOOP
HHWR HYDRONIC HOT WATER RETURN
HHWS HYDRONIC HOT WATER SUPPLY
HORIZ HORIZONTAL
HP HORSEPOWER/HEAT PUMP
HR HOUR
HTG HEATING
HVAC HEATING, VENTILATING, AND AIR CONDITIONING
HZ HERTZ
----------------I----------------------------------------------------------------------
ID INSIDE DIAMETER
IN INCHES
INV INVERT
----------------J----------------------------------------------------------------------
JB JUNCTION BOX
----------------K----------------------------------------------------------------------
KW KILOWATT
KWH KILOWATT HOUR
----------------L----------------------------------------------------------------------
LAT LEAVING AIR TEMPERATURE(ºF)
LBS POUNDS
LBS/HR POUNDS PER HOUR
LF LINEAR FEET
LP LIQUID PROPANE
LV LOUVER
LVG LEAVING
LWT LEAVING WATER TEMPERATURE(ºF)
----------------M----------------------------------------------------------------------
MAU MAKE-UP AIR UNIT
MAV MANUAL AIR VENT
MAX MAXIUM
MBH THOUSAND BTUH
MC MECHANICAL CONTRACTOR
MCC MOTOR CONTROL CENTER
MECH MECHANICAL
MFG MANUFACTURER
MIN MINIMUM
MISC MISCELLANEOUS
MS MINI-SPLIT SYSTEM
----------------N----------------------------------------------------------------------
N/A NOT APPLICABLE
NC NORMALLY CLOSED; NOISE CRITERIA
NEC NATIONAL ELECTRICAL CODE
NEG NEGATIVE
NFC NATIONAL FIRE CODE
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
NO NORMALLY OPEN
NTS NOT TO SCALE
----------------O----------------------------------------------------------------------
OA OUTSIDE AIR
OC ON CENTER
OCC OCCUPANCY
OD OUTSIDE DIAMETER
OSHA OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION
OSV OIL SAFETY VALVE
OZ OUNCE
----------------P----------------------------------------------------------------------
P PUMP
PC PLUMBING CONTRACTOR
PNL PANEL
PRV PRESSURE REDUCING VALVE
PSI POUNDS PER SQUARE INCH
PSIA POUNDS PER SQUARE INCH ABSOLUTE
PSIG POUNDS PER SQUARE INCH GAGE
PTAC PACKAGED TERMINAL AIR CONDITIONER
----------------Q----------------------------------------------------------------------
QTY QUANTITY
----------------R----------------------------------------------------------------------
RA RETURN AIR
RAD RADIATOR
RCP RADIANT CEILING PANEL
REFRIG REFRIGERANT
REQD REQUIRED
REV REVISION
RH RELATIVE HUMIDITY
RPM REVOLUTIONS PER MINUTE
RV RELIEF VALVE
----------------S----------------------------------------------------------------------
SA SUPPLY AIR
SCH SCHEDULE
SD SMOKE DAMPER
SENS SENSIBLE
SP STATIC PRESSURE (INCHES OF WATER)
SPEC SPECIFICATION
SQ SQUARE
SQFT SQUARE FOOT
SS STAINLESS STEEL
STD STANDARD
STRUCT STRUCTURAL
----------------T----------------------------------------------------------------------
T THERMOSTATE
TA TRANSFER AIR
TCV TEMPERATURE CONTROL VALVE
TDV TRIPLE DUTY VALVE
TEMP TEMPERATURE
TOT TOTAL
TRANS TRANSITION
TSTAT THERMOSTAT
TV TURNING VANES
TYP TYPICAL
----------------U----------------------------------------------------------------------
UH UNIT HEATER
UV UNIT VENTILATOR
----------------V----------------------------------------------------------------------
VOLTS VOLTAGE
VA VOLT AMPERES
VAC VACUUM
VAV VARIABLE AIR VOLUME
VEL VELOCITY
VERT VERTICAL
VFD VARIABLE FREQUENCY DRIVE
VOL VOLUME
VOLTS VOLTAGE
VRF VARIABLE REFRIGERANT FLOW
VVT VARIABLE VOLUME AND TEMPERATURE
----------------W----------------------------------------------------------------------
W/ WITH
W/O WITHOUT
WP WEATHERPROOF
WT WEIGHT
----------------Z----------------------------------------------------------------------
Z ZONE
ZCV ZONE CONTROL VALVE
Montum Architecture, LLC
55 ER Path
Keyser, WV 26726
304-276-7151 www.montumarch.com
PA OFFICE:
429 LAUREL RUN ROAD
CARMICHAELS, PA 15320
PH: (724) 966-5655
WV OFFICE:
54 WEST RUN RD.
MORGANTOWN, WV 26508
PH: (304) 291-2234
SHEET NAME:
MILLER ENGINEERING INC.
COPY RIGHT:
CHECKED BY:
DRAWN BY:
DESIGNED BY:
BCM
SEAL:
CONSULTANT:
PROJECT NAME:
PROJECT OWNER:
PROJECT STATUS:
PROJECT NUMBER:
ORIGINAL PAGE SIZE: 22x34
M000
MECHANICAL
ABBREVIATIONS
18 JUNE, 2025
TRT
TWT
24014
CONSTRUCTION
DOCUMENTS
WV ARMY NATIONAL
GUARD
CHALLENGE
ACADEMY SOUTH
KITCHEN HVAC
UPGRADES
MECHANICAL ABBREVIATIONS
ANNOTATION STYLE DUCTWORK SHAPE
24" x 12" RECTANGULAR
24" ø ROUND
24" / 12" FLAT OVAL
DUCTWORK SHAPE LEGEND
DUCT SYSTEM LEGEND
ABBREVIATION SYSTEM NAME
EA EXHAUST AIR
OA OUTDOOR AIR
RA RETURN AIR
SA SUPPLY AIR
MECH. PIPING SYSTEM LEGEND
ABBREVIATION SYSTEM TYPE
GAS NATURAL GAS
HCWL HYDRONIC CHILLED WATER LOOP
HCWR HYDRONIC CHILLED WATER RETURN
HCWS HYDRONIC CHILLED WATER SUPPLY
HHWR HYDRONIC HOT WATER RETURN
HHWS HYDRONIC HOT WATER SUPPLY
N O
D
E S
C R
IP
T
IO
N
D A
INDICATED ON THE DRAWINGS, SPECIFICATIONS, AND
REQUIRED BY CODE.
2. SEPARATE BALANCE DAMPERS WILL BE INSTALLED AT ALL
TAKE-OFFS FROM MAIN DUCTS. FIRE DAMPERS WILL BE
INSTALLED AT LOCATIONS SHOWN OR WHERE ANY DUCT
PENETRATES A FIRE RATED WALL. REFER TO ARCHITECTURAL
SHEETS FOR RATED WALLS. FIRE DAMPERS ARE TO MATCH THE
RATING OF THE WALL OR CEILING BEING PENETRATED.
3. ALL DUCT TAKE-OFFS AND TRANSITIONS WILL BE TAPERED.
ELBOWS AND TURNS SHALL BE CONSTRUCTED w/ A SMOOTH
RADIUSED FITTING MIN 1.5 TIMES THE WIDTH OF THE DUCT.
TURNING VANES ARE NOT PERMITTED, UNLESS APPROVED BY
ENGINEER OR INDICATED ON DRAWINGS.
4. CERTAIN ITEMS SUCH AS RISERS AND DROPS IN DUCTWORK,
ACCESS DOORS, VOLUME DAMPERS, ETC. ARE INDICATED ON
THE CONTRACT DOCUMENT DRAWINGS FOR CLARITY FOR A
SPECIFIC LOCATION REQUIREMENT AND SHALL NOT BE
INTERPRETED AS THE EXTENT OF THE REQUIREMENTS FOR
THOSE ITEMS.
5. ALL DUCTWORK IS TO BE EXTERNALLY INSULATED. INTERIOR
MOUNTED DUCTWORK SHALL HAVE FOIL FACED 1-1/2 TO 2"
FIBERGLASS INSULATION AND SEALED w/ FIBERGLASS
REINFORCED FOIL TAPE.
6. CONSTRUCT ALL DUCTWORK PER SMACNA STANDARDS FOR
LOW PRESSURE DUCTWORK (2.0" STATIC). ALL JOINTS ARE TO
BE SEALED w/ MASTIC.
7. PROVIDE AIR LOUVERS w/ GRAVITY BACKDRAFT DAMPERS. ALL
EXTERIOR LOUVERS WILL HAVE 60% MIN. OPEN AREA AND BUG
SCREENS. INSTALL ALL w/ BIRD SCREEN. COLORS BY OWNER/ARCHITECT. COORDINATE LOCATIONS w/ GENERAL
CONTRACTOR.
8. PROVIDE FULLY ADHERED VELOCITY DUCT LINER FROM UNIT
DISCHARGE AND RETURN TO 10'-0" BEYOND UNIT. PROVIDE
NOSING AT THE BEGINNING AND END OF THE DUCT LINER.
9. UNLESS OTHERWISE SHOWN, LOCATE ALL ROOM
THERMOSTATS AND HUMIDISTATS AT 5'-0" ABOVE FINISHED
FLOOR. FINAL THERMOSTAT LOCATION BY OWNER/ARCHITECT.
10. ALL DUCTWORK SHALL CLEAR DOORS AND WINDOWS.
11. ALL DUCTWORK DIMENSIONS, AS SHOWN ON THE DRAWINGS,
ARE INTERNAL CLEAR DIMENSIONS AND DUCT SIZE SHALL BE
INCREASED TO COMPENSATE FOR DUCT LINING WHERE
APPLICABLE.
12. COORDINATE DIFFUSERS, REGISTER, AND GRILLE LOCATIONS
w/ ARCHITECTURAL REFLECTED CEILING PLANS, LIGHTING, AND
OTHER CEILING ITEMS. MAKE MINOR DUCT MODIFICATIONS TO
SUIT.
13. LOCATE ALL MECHANICAL EQUIPMENT FOR UN-OBSTRUCTED
ACCESS TO UNIT ACCESS PANELS, CONTROL, AND VALVING.
14. PROVIDE FLEXIBLE CONNECTIONS IN ALL DUCTWORK SYSTEMS
CONNECTED TO AIR HANDLING UNITS, FANS, AND OTHER
EQUIPMENT WHICH REQUIRE VIBRATION ISOLATION.
OTHERWISE NOTED, ALL DUCTWORK IS OVERHEAD, TIGHT TO
THE UNDERSIDE OF THE STRUCTURAL, WITH SPACE FOR
INSULATION.
15. RUNS OF FLEXIBLE DUCT SHALL NOT EXCEED 3'-0". FLEXIBLE
DUCT IS TO BE USED FOR FINAL CONNECTIONS TO GRILLES
AND DIFFUSER ONLY.
16. ALL DUCTWORK SHALL BE COORDINATED w/ ALL TRADES
INVOLVED. OFFSETS IN DUCTS, INCLUDING DIVIDED DUCTS AND
TRANSITIONS AROUND OBSTRUCTIONS, SHALL BE PROVIDED AT
NO ADDITIONAL COST TO THE OWNER.
17. PROVIDE ACCESS DOORS IN DUCTWORK TO PROVIDE ACCESS
FOR ALL SMOKE DETECTORS, FIRE DAMPERS, SMOKE
DAMPERS, HUMIDIFIERS, COILS AND OTHER ITEMS LOCATED IN
DUCTWORK WHICH REQUIRE SERVICE OR INSPECTION.
18. SEE SPEC FOR DUCTWORK GAUGES, BRACING, HANGERS, AND
OTHER REQUIREMENTS.
19. EXTERIOR LOUVERS ARE INDICATED FOR INFORMATION ONLY.
DETAILED DESCRIPTIONS ARE PROVIDED IN THE
ARCHITECTURAL SPECIFICATIONS. LOUVER SIZES, LOCATIONS,
MOUNTING, AND DETAILS SHALL BE COORDINATED w/ OTHER
TRADES INVOLVED.
20. PERFORM WORK IN ACCORDANCE w/ CURRENT INTERNATIONAL
MECHANICAL CODE, FUEL GAS CODE, ASHRAE, SMACNA, STATE,
AND LOCAL CODES AND REQUIREMENTS.
21. VERIFY ALL FIELD CONDITIONS AND MEASUREMENTS PRIOR TO
BIDDING. COORDINATE ALL WORK w/ OTHER TRADES.
COORDINATE ALL CEILING MOUNTED DEVICES w/ ALL OTHER
TRADES PRIOR TO INSTALLATION. FINAL COORDINATION OF
SCOPE OF WORK, DIMENSIONS, FIXTURE PLACEMENT, ROUTING
ETC. IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR
AND ALL SUB-CONTRACTORS PRIOR TO BIDDING.
MECHANICAL NOTES
FCU-4
FCU-7
FCU-2
FCU-6
FCU-5
FCU-1
FCU-8
A
B
C
D
E
F
G
1 2 3 4 5 6 7
DEMO FCU (TYP) DEMO DUCTWORK, DIFFUSERS, & GRILLES (TYP)
REMOVE MARKED SPRINKLER HEADS AND
REPLACE IN FIELD TO ACCOMODATE NEW
DUCTWO…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .