Marion VA_Renovate 3B_Bid Documents_Specifications_09-20-2024 1723 pages rev1.pdf
PDF 9 MB Posted
- Attached to
- Z2DA--657A5-23-110, Renovate 3B for Patient Privacy and Intensive Care Unit, (VA-25-00018450)
- Solicitation number
- 36C25525R0015
About this file
This is a specifications document for a construction project to renovate Patient Ward 3B at the Marion VA Medical Center in Marion, Illinois, under VA Contract #36C25523R0096. The project involves renovating the ward to improve patient privacy and create an intensive care unit, with a base bid construction duration of 550 calendar days.
The specifications detail requirements across multiple divisions including demolition, structural, architectural, mechanical, electrical, plumbing and other building systems. The scope includes asbestos abatement, new headwalls, patient lifts, mechanical ductwork, solid surface wall finishes, and premanufactured metal casework. There are eight deductive bid alternates that progressively reduce scope and duration, ranging from omitting mechanical ductwork (530 days) to eliminating renovation of the visitor lounge (410 days). Key requirements include maintaining hospital operations during construction, coordination of utility interruptions, infection control measures, and protection of existing facilities. The contractor must provide construction schedules, safety plans, warranties, and training for VA staff on new equipment and systems.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications Volume 1 Renovate Patient Ward 3B for Patient Privacy and Intensive Care Marion VA Medical Center VA Contract # 36C25523R0096 Marion, Ill.
H VA MARI 23100
100% Construction Documents – Submission April 19, 2024
H VA MARI 23100
Final Bid Documents – Submission
September 20, 2024
Renovate 3B for Patient Privacy and
Intensive Care Unit Marion VA Medical Center
Marion, Illinois
Final Bid Documents
VA Project No.: 36C25523R0096
Stone Group/HFG No.: H VA MARI 23100 Issue Date: September 20, 2024
Volume1
Divisions 00 Through 14
Renovate 3B for Patient Privacy and Intensive Care Unit Final Bid Documents
Marion VA Medical Center Marion IL 09/20/2024
VA Contract #36C25523R0096 Version 11-01-23
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects � Design/Bid/Build 11-21
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements 11-23
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 � EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 � CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 � MASONRY - Not Used
DIVISION 05 � METALS
05 12 00 Structural Steel Framing 11-18
05 40 00 Cold-Formed Metal Framing 01-21
05 50 00 Metal Fabrications 08-18
DIVISION 06 � WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 20 00 Finished Carpentry 01-21
06 65 00 Solid Polymer Fabrications M+HFG
VA Contract #36C25523R0096 Version 11-01-23
00 01 10-2
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21
07 21 13 Thermal Insulation 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 17 10 Integrated Door Assemblies 01-21
08 31 13 Access Doors and Frames 04-22
08 32 13 ICU Sliding Glass Doors 01-21
08 71 00 Door Hardware 05-22
08 71 13 Automatic Door Operators 01-21
08 80 00 Glazing 01-21
DIVISION 09 � FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 30 13 Ceramic/Porcelain Tiling 01-21
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 06-22
09 65 19 Resilient Tile Flooring 05-18
09 67 23.20 Resinous Epoxy Base With Vinyl Chip Broadcast (RES 2) 12-21
09 91 00 Painting 01-21
DIVISION 10 � SPECIALTIES
10 11 33 Glassboards (Magnetic & Non-Magnetic) 01-21
10 14 00 Signage 01-21
10 21 23 Cubicle Curtain Tracks 01-21
10 25 13 Patient Bed Service Walls 05-23
10 26 00 Wall and Door Protection 01-21
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 � EQUIPMENT
11 40 11 Custom Fabricated Food Service Equipment 01-21
11 73 00 Ceiling Mounted Patient Lift System 08-20
DIVISION 12 � FURNISHINGS
12 24 00 Window Shades 08-17
VA Contract #36C25523R0096 Version 11-01-23
00 01 10-3
SECTION NO DIVISION AND SECTION TITLES DATE
12 35 70 Healthcare Casework M+HFG
12 36 00 Countertops 12-23
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-21
DIVISION 14� CONVEYING EQUIPEMENT � Not Used
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 � PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 05 12 General Motor Requirements for Plumbing Equipment 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 13 00 Facility Sanitary and Vent Piping 09-20
22 40 00 Plumbing Fixtures 12-22
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 05-23
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 05-23
DIVISION 23 � HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-23
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 08 00 Commissioning of HVAC Systems 03-23
23 09 23 Direct-Digital Control System for HVAC 03-23
23 21 13 Hydronic Piping 03-23
23 22 13 Steam and Condensate Heating Piping 08-23
23 31 00 HVAC Ducts and Casings 03-23
23 34 00 HVAC Fans 03-23
23 36 00 Air Terminal Units 03-23
23 37 00 Air Outlets and Inlets 03-23
23 73 00 Indoor Central-Station Air-Handling Units 03-23
VA Contract #36C25523R0096 Version 11-01-23
00 01 10-4
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 25 � INTEGRATED AUTOMATION - Not Used
DIVISION 26 � ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 73 Overcurrent Protective Device Coordination Study 11-22
26 08 00 Commissioning of Electrical Systems 11-22
26 09 23 Lighting Controls 11-22
26 22 00 Low-Voltage Transformers 11-22
26 24 16 Panelboards 11-22
26 27 26 Wiring Devices 11-22
26 29 11 Motor Controllers 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 41 00 Facility Lightning Protection 11-22
26 43 13 Surge Protective Devices 11-22
26 51 00 Interior Lighting 11-22
DIVISION 27 � COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 08 00 Commissioning of Communications Systems 11-16
27 52 23 Nurse Call and Code Blue Systems 10-18
DIVISION 28 � ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 13 00 Physical Access Control System 10-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 � EARTHWORK � Not Used
DIVISION 32 � EXTERIOR IMPROVEMENTS � Not Used
VA Contract #36C25523R0096 Version 11-01-23
00 01 10-5
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 33 � UTILITIES � Not Used
DIVISION 34 � TRANSPORTATION � Not Used
DIVISION 48 � Electrical Power Generation � Not Used
VA Contract #36C25523R0096 Version 05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
DRAWING NO. TITLE
01 - GENERAL
GI000 COVER SHEET
GI001 ARCH/INT NOTES
GI002 ARCH/INT NOTES
GI003 CODE REVIEW
GI011 ACCESSIBILITY & EQUIPMENT MOUNTING DETAILS
GI012 ACCESSIBILITY & EQUIPMENT MOUNTING DETAILS
GI013 ACCESSIBILITY & EQUIPMENT MOUNTING DETAILS
GI100 LIFE SAFETY PLAN - 3RD LEVEL - OVERALL
GI101 LIFE SAFETY PLAN - 3RD LEVEL - PROJECT AREA
GI102 LIFE SAFETY PLAN - 2ND LEVEL
GI110 TEMP EXITING & ICRA PLAN - 3RD LEVEL - OVERALL
GI111 TEMP EXITING & ICRA PLAN - 3RD LEVEL - PROJECT AREA
GI120 PROJECT STAGING PLAN - FACILITY MAP
GI121 PROJECT STAGING PLAN - GROUND LEVEL - PROJECT AREA
02 - STRUCTURAL
S-000 GENERAL NOTES
S-100 PARTIAL ROOF FRAMING PLAN
S-200 PENTHOUSE FLOOR DEMO AND NEW FRAMING PLAN
S-300 PENTHOUSE ROOF FRAMING PLAN & FRAMING DETAILS
03 - ARCHITECTURAL DEMOLITION
AD100 DEMOLITION PLAN - 3RD LEVEL - OVERALL
AD101 DEMOLITION PLAN - 3RD LEVEL - AREA A
AD102 DEMOLITION PLAN - 3RD LEVEL - AREA B
AD110 DEMOLITION RCP - 3RD LEVEL - OVERALL
AD111 DEMOLITION RCP - 3RD LEVEL - AREA A
AD112 DEMOLITION RCP - 3RD LEVEL - AREA B
AD113 DEMOLITION RCP - 2ND LEVEL - OVERALL
AD114 DEMOLITION RCP - 2ND LEVEL - AREA A
AD115 DEMOLITION RCP - 2ND LEVEL - AREA B
AD121 DEMOLITION PENTHOUSE PLAN - 4TH LEVEL - AREA A
04 - ARCHITECTURAL
AE100 ARCHITECTURAL FLOOR PLAN - 3RD LEVEL - OVERALL
AE101 ARCHITECTURAL FLOOR PLAN - 3RD LEVEL - AREA A
AE102 ARCHITECTURAL FLOOR PLAN - 3RD LEVEL - AREA B
VA Contract #36C25523R0096 Version 05-01-20
00 01 15 - 2
AE110 REFLECTED CEILING PLAN - 3RD LEVEL - OVERALL
AE111 REFLECTED CEILING PLAN - 3RD LEVEL - AREA A
AE112 REFLECTED CEILING PLAN - 3RD LEVEL - AREA B
AE130 ARCHITECTURAL ROOF PLAN - OVERALL
AE131 ARCHITECTURAL PENTHOUSE PLAN - 4TH LEVEL - AREA A
AE301 BUILDING SECTIONS
AE311 WALL SECTIONS
AE312 WALL SECTIONS
AE401 ENLARGED PATIENT ROOM PLANS
AE402 ENLARGED PATIENT ROOM PLANS
AE403 ENLARGED PATIENT ROOM PLANS
AE404 ENLARGED PATIENT ROOM PLANS
AE405 ENLARGED PATIENT ROOM PLANS
AE406 ENLARGED PATIENT ROOM PLANS
AE411 ENLARGED PLANS
AE421 FLOOR SLOPES & DRAINS
AE422 FLOOR SLOPES & DRAINS
AE431 ENLARGED RCP
AE501 ARCHITECTURAL DETAILS
AE502 ARCHITECTURAL DETAILS
AE503 ARCHITECTURAL DETAILS
AE601 ARCHITECTURAL SCHEDULES & ASSEMBLIES
AE900 ARCHITECTURAL PERSPECTIVES
05 - ARCHITECTURAL INTERIORS
AI100 FINISH & INTERIORS - SCHEDULES & TYPES
AI101 FINISH PLAN - 3RD LEVEL - AREA A
AI102 FINISH PLAN - 3RD LEVEL - AREA B
AI200 FURNITURE & EQUIPMENT - SCHEDULES & TYPES
AI201 FURNITURE & EQUIPMENT - SCHEDULES & TYPES
AI202 FURNITURE & EQUIPMENT PLAN - 3RD LEVEL - AREA A
AI203 FURNITURE & EQUIPMENT PLAN - 3RD LEVEL - AREA B
AI301 WALL PROTECTION PLAN - 3RD LEVEL - AREA A
AI302 WALL PROTECTION PLAN - 3RD LEVEL - AREA B
AI401 INTERIOR ELEVATIONS
AI402 INTERIOR ELEVATIONS
AI411 HEADWALL � BASIS OF DESIGN
AI412 HEADWALL � BASIS OF DESIGN � BID DEDUCT
AI501 MILLWORK SECTIONS & DETAILS
AI502 MILLWORK SECTIONS & DETAILS - BID DEDUCT
AI503 FINISH DETAILS
AI600 SIGNAGE & WAYFINDING - SCHEDULES & TYPES
VA Contract #36C25523R0096 Version 05-01-20
00 01 15 - 3
AI601 SIGNAGE & WAYFINDING PLAN - 3RD LEVEL - AREA A
AI602 SIGNAGE & WAYFINDING PLAN - 3RD LEVEL - AREA B
AI701 PATIENT LIFTS � BASIS OF DESIGN - DETAILS
AI702 PATIENT LIFTS � BASIS OF DESIGN - DETAILS
AI703 PATIENT LIFTS � BASIS OF DESIGN - DETAILS
AI704 PATIENT LIFTS � BASIS OF DESIGN - DETAILS
AI710 PATIENT LIFTS � BASIS OF DESIGN � OVERALL PLAN
AI711 PATIENT LIFTS � BASIS OF DESIGN � ENLARGED PLAN
AI712 PATIENT LIFTS � BASIS OF DESIGN � ENLARGED PLAN
AI713 PATIENT LIFTS � BASIS OF DESIGN � ENLARGED PLAN
AI714 PATIENT LIFTS � BASIS OF DESIGN � ENLARGED PLAN
AI715 PATIENT LIFTS � BASIS OF DESIGN � ENLARGED PLAN
AI716 PATIENT LIFTS � BASIS OF DESIGN � ENLARGED PLAN
06 - MECHANICAL
M-000 MECHANICAL SYMBOLS AND ABBREVIATIONS
M-103 MECHANICAL DEMOLITION FLOOR PLAN - 3RD LEVEL
M-104 MECHANICAL DEMOLITION FLOOR PLAN - ROOF
MH203 DUCTWORK FLOOR PLAN - 3RD LEVEL
MH204 MECHANICAL FLOOR PLAN - PENTHOUSE
MH205 MECHANICAL TEMPORARY FLOOR PLAN - 3RD LEVEL
MP203 HYDRONIC PIPING FLOOR PLAN - 3RD LEVEL
MC203 CONTROLS FLOOR PLAN - 3RD LEVEL
M-300 ENLARGED PLANS
M-301 SECTIONS
M-500 MECHANICAL DETAILS
M-501 MECHANICAL DETAILS
M-502 MECHANICAL CONTROLS
M-503 MECHANICAL CONTROLS
M-600 MECHANICAL SCHEDULES
M-601 MECHANICAL SCHEDULES
07 - PLUMBING
P-000 PLUMBING SYMBOLS AND ABBREVIATIONS
PF103 FIRE PROTECTION DEMOLITION FLOOR PLAN - 3RD LEVEL
PF203 FIRE PROTECTION FLOOR PLAN - 3RD LEVEL
P-102 PLUMBING DEMOLITION FLOOR PLAN - 2ND LEVEL
P-103 PLUMBING DEMOLITION FLOOR PLAN - 3RD LEVEL
PP202 PLUMBING FLOOR PLAN - 2ND LEVEL
PP203 PLUMBING FLOOR PLAN - 3RD LEVEL
PG203 MEDICAL GAS FLOOR PLAN - 3RD LEVEL
P-600 PLUMBING DETAILS AND SCHEDULES
08 - ELECTRICAL
VA Contract #36C25523R0096 Version 05-01-20
00 01 15 - 4
E-000 ELECTRICAL SYMBOLS AND ABBREVIATIONS
E-001 ELECTRICAL SYMBOLS
E-103 ELECTRICAL DEMOLITION FLOOR PLAN - 3RD LEVEL
E-104 ELECTRICAL DEMOLITION FLOOR PLAN - PENTHOUSE
EL203 LIGHTING FLOOR PLAN - 3RD LEVEL
EC203 LIGHTING CONTROL FLOOR PLAN - 3RD LEVEL
EP203 POWER FLOOR PLAN - 3RD LEVEL
EP204 POWER FLOOR PLAN - PENTHOUSE
EV203 LOW VOLTAGE FLOOR PLAN - 3RD LEVEL
E-401 LIGHTING CONTROL ZONE PLANS
E-500 ONE-LINE DIAGRAM
E-600 ELECTRICAL DETAILS
E-601 ELECTRICAL DETAILS
E-700 ELECTRICAL SCHEDULES
E-701 ELECTRICAL SCHEDULES
E-800 ENERGY CODE COMPLIANCE
TOTAL SHEET COUNT: 112
- - - E N D - - -
VA Contract #36C25523R0096 Version 11-01-21
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Renovate 3B for Patient Privacy and Intensive Care Unit, Marion
VA Medical Center, Marion, Illinois, VA Contract #36C25523R0096. as required by drawings and specifications.
B. Only one site visit will be scheduled prior to the bid date.
Attendance is highly recommended.
C. Offices of Stone HFG Architecture, as
Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. BID ITEM I, GENERAL CONSTRUCTION: BASE BID: Includes all scope communicated in the drawings, specifications and other construction documents.
Construction Duration: 550 calendar days.
VA Contract #36C25523R0096 Version 11-01-21
01 00 00 -2
Amount: $____________________________
B. Deductive Bid Alternates: The following scopes of work are specified as Deductive Bid Alternates (“DBA”).
BID ITEM II(DBA NO.1): All the work in Bid Item I except delete mechanical ductwork.
Construction Duration: 540 calendar days.
Amount: $__________________________
BID ITEM III(DBA NO.2): All the work in Bid Item II except delete all headwalls to reduce in price including headwall size and finishes.
Construction Duration: 530 calendar days.
Amount: $_________________________
BID ITEM IV(DBA NO.3): All the work in Bid Item III except omit S.O.W. related to solid surface wall finished and replace with wall tile. See specifications and AI drawings.
Construction Duration: 520 calendar days.
Amount: $_________________________
BID ITEM V(DBA NO.4):All the work in Bid Item IV except omit all premanufactured metal casework and replace with millwork. See specifications and AI drawings.
Construction Duration: 520 calendar days.
Amount: $_________________________
BID ITEM VI(DBA NO.5): All the work in Bid Item V except omit S.O.W. related to patient lifts. See specifications and AI drawings.
Construction Duration: 500 calendar days.
Amount: $_________________________
BID ITEM VII(DBA NO.6): All the work in Bid Item VI except omit S.O.W related to renovation of med/surg room
01 00 00 -3
(Room 303). Revised drawings to be provided by A/E team should this bid item be selected.
Construction Duration: 470 calendar days.
Amount: $_________________________
BID ITEM VIII(DBA NO.7): All the work in Bid Item VII except omit S.O.W. related to renovation and resizing of visitor toilet (Room 330). Revised drawings to be provided by A/E team should this bid item be selected.
Construction Duration: 440 calendar days.
Amount: $_________________________
BID ITEM IX(DBA NO.8): All the work in Bid Item VIII except omit S.O.W. related to renovation and resizing of visitor lounge (Room 331). Revised drawings to be provided by A/E team should this bid item be selected.
Construction Duration: 410 calendar days.
Amount: $__________________________
C. PERIOD OF PERFORMANCE: The contractor shall complete the work required under this Scope of Work (SOW)within five hundred and fifty (550) calendar days from Notice to
Proceed (NTP),unless otherwise directed by the Contracting
Officer.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
01 00 00 -4
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees.
This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The
General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.
See Section 08 71 00, DOOR HARDWARE and coordinate.
01 00 00 -5
D. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of
“sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
01 00 00 -6
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.
Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General
Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical
Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The
Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices), construction waste containers and utilities may be erected by the Contractor in locations indicated on the drawings and only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written
01 00 00 -7 consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workers are subject to rules of Medical Centerapplicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Centeras a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's
01 00 00 -8 personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Centerareas required to remain in operation.
3. Where access by Medical Centerpersonnel to vacated portions of buildings is not required, storage of
Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved.
1. The responsibility for coordinating and providing technical expertise for alarm panel manipulation will be provided by the general contractor and responsible subcontractor – the VA will not be responsible for managing device outages in the facility fire alarm panel.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure
01 00 00 -9 that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the
COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing dates to ensure accomplishment of this work in successive phases as indicated on the drawings.
J. Part of Bldg. 3B will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to Proceed and turned over to
Contractor.
K. Building No. 3 will be occupied during performance of work but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
01 00 00 -10
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
L. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or
Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
M. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or
01 00 00 -11 conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center
Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK
RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical
Center may occur at other than Contractor's normal working hours.
01 00 00 -12
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;
so that they are completely behind the finished surfaces.
O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
01 00 00 -13
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of
VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the
Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by
Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING
01 00 00 -14
SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-
4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.
They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
2. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
01 00 00 -15
1. Reserved items which are to remain property of the
Government are identified by attached tags or noted on drawings or in specifications as items to be stored.
Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the
Contractor and be removed by Contractor from Medical
Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of
Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the
Government in advance of work to avoid interfering with
Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during
01 00 00 -16 contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting
Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
01 00 00 -17
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by
Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
01 00 00 -18
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR [Chief Engineer][Chief of Facilities Management] within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21
Warranty of Construction at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting
Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the
Contactor and the Contracting Officer. Include in the
01 00 00 -19 warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the
Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of
Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
01 00 00 -20
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and
Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment
Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the
01 00 00 -21
Government at the contractor’s expenses, the Contracting
Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the
Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the
Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the
01 00 00 -22
Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service
Requirements:
E. Following oral or written notification by the Contracting
Officer, the Contractor shall respond to construction warranty service requirements in accordance with the
“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within
4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within
8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
01 00 00 -23
Fire suppression systems.
Fire alarm system(s).
b) Code 1-Air Conditioning Systems
Air conditioning leak in part of the building, if causing damage.
Air conditioning system not cooling properly.
c) Code 1 Doors
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
d) Code 3-Doors
Interior/exterior personnel doors or hardware not functioning properly.
e) Code 1-Electrical
Power failure (entire area or any building operational after 1600 hours).
Security lights.
Smoke detectors.
f) Code 2-Electrical
Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).
g) Code 1-Heat
Power failure affecting heat.
h) Code 1-Plumbing
Hot water heater failure.
2) Leaking water supply pipes
i) Code 2-Plumbing
Flush valves not operating properly
01 00 00 -24
Fixture drain, supply line or any water pipe leaking.
Toilet leaking at base.
j) Code 3- Plumbing
Leaky faucets.
k) Code 3-Interior
Floors damaged.
Paint chipping or peeling.
Casework damaged.
l) Code 1-Roof Leaks
Damage to property is occurring.
m) Code 3
All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.
Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
01 00 00 -25
Warranty Tags
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.14 RESIDENT ENGINEER'S FIELD OFFICE
A. The Contractor shall, within fifteen (15) days after receipt of Notice to Proceed, provide a plan desk and file storage within the work area where approved by the COR. The area shall be considered the field office.
B. The field office shall include a complete set of drawings and a project manual, shop drawings, and samples.
1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
01 00 00 -26
1. Permission to use each unit or system must be given by
COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
01 00 00 -27
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion…
This is the start of the file's text. The full file is on GovTribe.