About this file

This is a Proposed Project Schedule template attachment for the Kentucky Transportation Cabinet (KYTC) Electric Vehicle Charging Program RFP 4, requiring proposers to submit a detailed project schedule demonstrating comprehensive understanding of project requirements. The schedule must address all tasks outlined in the Scope of Work, including Preliminary Engineering and NEPA Clearance, Final Design and Permitting, Construction and Commissioning, Operations and Maintenance for one typical year, and Project Close-Out. Proposers are required to provide detailed subtasks, critical activities, key milestones, deliverable submissions, and Notices to Proceed for each primary task, with estimated number of days required to complete all activities and meet reporting deadlines. The completed schedule must clearly demonstrate understanding of project requirements and illustrate all steps necessary for project completion.

The template requires proposers to complete the spreadsheet by filling in light blue boxes for each task with corresponding activities and days required, with provisions to add as many rows as necessary under each task to provide comprehensive scheduling detail. The schedule must address the Operations and Maintenance period with typical year tasks and activities, and the completed file must be submitted in XLSX format rather than PDF. All tasks must show total days required, and proposers must include their business name, Federal UEI, zone, and site location address in the schedule submission.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Proposed Project Schedule
Instructions
Proposer must provide a detailed Proposed Project Schedule based on the requirements outlined in the Request for Proposals (RFP). Detail must be provided at a level that illustrates a comprehensive understanding of the Project Requirements. The schedule must address the Tasks outlined in Attachment 2, Scope of Work (SOW), including but not limited to, critical activities, subtasks, key milestones, submission and review of deliverables, and Notices to Proceed (NTP) required to accomplish the primary Tasks as outlined in the SOW. The schedule shall include the estimated number of days required to meet all Tasks, activities, and requirements of the project, including reporting deadlines. The completed Project Schedule should clearly indicate, in detail, all the steps required to complete the project and should illustrate a clear understanding of the project requirements.
How to Complete the Template
On the "Project Schedule" tab of this spreadsheet, fill in each light blue boxes next to each Task.

Add as many rows under each task as needed to provide a detailed and comprehensive schedule.

For the Operations and Maintenance (O&M) Period, please provide tasks and activities required in a typical year. Only one year is required for O&M in the schedule.

Submit this file as an XLSX file and not a PDF.

Proposed Project Schedule

PROPOSED PROJECT SCHEDULE

Proposer Business Name
Federal UEI
Zone
Site Location Address
TaskActivity# of Days
0
Task 1Preliminary Engineering and NEPA ClearanceTotal:0

Task 2 Final Design and Permitting Total: 0

Task 3 Construction and Commissioning Total: 0

Task 4 Operations & Maintenance (One Typical Year) Total: 0

Task 5 Project Close-Out Total: 0