J10_Progress Chart.xlsx
XLSX spreadsheet 100 KB Posted
- Attached to
- Competitive 8(a) SATOC JOC (DRAFT RFP)
- Solicitation number
- W9124P
About this file
The document provided is a Construction Progress Chart for a federal contract opportunity. The chart shows the planned and actual progress of various construction tasks such as demolition, architecture, mechanical, communications, plumbing, flooring, and electrical work, among others. The contract is for a Job Order Contract (JOC) to provide new construction, alterations, maintenance, repair, sustainment, restoration, and modernization services for the U.S. Army Garrison - Redstone (USAG-Redstone) and its tenant organizations. This is a 100% 8(a) small business set-aside acquisition with a Solicitation Number of W9124P. The contract supports the USAG-Redstone's mission to maintain oversight of construction activities on Redstone Arsenal, including unspecified minor military construction, lab revitalization, and other Sustainment, Restoration, and Modernization (SRM) projects. Potential projects include a variety of administrative, support, and research facilities, as well as infrastructure such as roads, utilities, and airfield structures.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
Construction Progress Chart
Project Description:
Contractor: ________________________ Date:
Contract No: _______________________ Task Order No: _________________ Building No:
Item Contract Feature Wt. Estimated Cost Actual Cost January February March April May June
| 100 | ||||||
| Scheduled | ||||||
| 01 | Demo | 0.0653992883 | $20,400.00 | |||
| Actual | ||||||
| 100 | ||||||
| Scheduled |
AGM: AGM:
| 02 | Arch. | 0.2949379669 | $92,000.00 | |||||
| Actual | 0.0816208765 | |||||||
| 60 | 100 | |||||||
| Scheduled | 0.3379078639 | |||||||
| 03 | Mech. | 0.20 | $62,740.00 | |||||
| Actual | 0.4543214824 |
| Scheduled | 100 | 0.6196646684 | ||||||||||||
| 04 | Comm. Floor | 0.0699996794 | $21,835.00 | |||||||||||
| Actual | 0.9397467381 | |||||||||||||
| 50 | 100 | |||||||||||||
| Scheduled | 1 | |||||||||||||
| 05 | Plumbing | 0.0224409323 | $7,000.00 | |||||||||||
| Actual | ||||||||||||||
| 100 | ||||||||||||||
| Scheduled | ||||||||||||||
| 06 | Flooring | 0.0352643221 | $11,000.00 | |||||||||||
| Actual | ||||||||||||||
| 100 | ||||||||||||||
| Scheduled | ||||||||||||||
| 07 | Ceramic Tile | 0.0093610746 | $2,920.00 | |||||||||||
| Actual | ||||||||||||||
| 100 | ||||||||||||||
| Scheduled | ||||||||||||||
| 08 | Sprinkler System | 0.0160933543 | $5,020.00 | |||||||||||
| Actual | ||||||||||||||
| 80 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 09 | Secondary Power | 0.1272240567 | $39,685.00 | |||||||||||
| Actual | ||||||||||||||
| 60 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 10 | Civil | 0.0259673645 | $8,100.00 | |||||||||||
| Actual | ||||||||||||||
| 10 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 11 | Primary Power | 0.0392075145 | $12,230.00 | |||||||||||
| Actual | ||||||||||||||
| 50 | 100 | |||||||||||||
| Scheduled | ||||||||||||||
| 12 | Communications | 0.0705286442 | $22,000.00 | |||||||||||
| Actual |
| Scheduled | 100 | ||||||||||
| 13 | Doors | 0.0224409323 | $7,000.00 | ||||||||
| Actual | |||||||||||
| 8.16% | 33.79% | 45.43% | 61.97% | 93.97% | 100.00% | ||||||
| Scheduled | |||||||||||
| TOTAL | 1.00 | $311,930.00 | |||||||||
| Actual |
Attachment J10 Progress Chart 02 May 2023