J10_Progress Chart.xlsx

XLSX spreadsheet 100 KB Posted

Attached to
Competitive 8(a) SATOC JOC (DRAFT RFP)
Solicitation number
W9124P
Issued by

About this file

The document provided is a Construction Progress Chart for a federal contract opportunity. The chart shows the planned and actual progress of various construction tasks such as demolition, architecture, mechanical, communications, plumbing, flooring, and electrical work, among others. The contract is for a Job Order Contract (JOC) to provide new construction, alterations, maintenance, repair, sustainment, restoration, and modernization services for the U.S. Army Garrison - Redstone (USAG-Redstone) and its tenant organizations. This is a 100% 8(a) small business set-aside acquisition with a Solicitation Number of W9124P. The contract supports the USAG-Redstone's mission to maintain oversight of construction activities on Redstone Arsenal, including unspecified minor military construction, lab revitalization, and other Sustainment, Restoration, and Modernization (SRM) projects. Potential projects include a variety of administrative, support, and research facilities, as well as infrastructure such as roads, utilities, and airfield structures.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Construction Progress Chart

Project Description:

Contractor: ________________________ Date:

Contract No: _______________________ Task Order No: _________________ Building No:

Item Contract Feature Wt. Estimated Cost Actual Cost January February March April May June

100
Scheduled
01Demo0.0653992883$20,400.00
Actual
100
Scheduled

AGM: AGM:

02Arch.0.2949379669$92,000.00
Actual0.0816208765
60100
Scheduled0.3379078639
03Mech.0.20$62,740.00
Actual0.4543214824
Scheduled1000.6196646684
04Comm. Floor0.0699996794$21,835.00
Actual0.9397467381
50100
Scheduled1
05Plumbing0.0224409323$7,000.00
Actual
100
Scheduled
06Flooring0.0352643221$11,000.00
Actual
100
Scheduled
07Ceramic Tile0.0093610746$2,920.00
Actual
100
Scheduled
08Sprinkler System0.0160933543$5,020.00
Actual
80100
Scheduled
09Secondary Power0.1272240567$39,685.00
Actual
60100
Scheduled
10Civil0.0259673645$8,100.00
Actual
10100
Scheduled
11Primary Power0.0392075145$12,230.00
Actual
50100
Scheduled
12Communications0.0705286442$22,000.00
Actual
Scheduled100
13Doors0.0224409323$7,000.00
Actual
8.16%33.79%45.43%61.97%93.97%100.00%
Scheduled
TOTAL1.00$311,930.00
Actual

Attachment J10 Progress Chart 02 May 2023