This document contains a justification for a sole source award and the related federal contract opportunity. The justification document requests a sole source award to Delta Controls for HVAC controls as part of construction project 595-15-201 to renovate Building 22 at the Lebanon VA Medical Center. Delta Controls are already implemented across the facility and compatibility is required. The contracting officer determined the anticipated costs would be fair and reasonable. The federal contract opportunity is a solicitation for the construction project, with an estimated value between $2-5 million. The NAICS code is 236220 and it is set aside 100% for SDVOSBs. The response due date is approximately July 6, 2020. The scope of work includes demolition, construction, and installation of floors, ceilings, electrical, plumbing and HVAC systems.

View the file

Other files

File Type Posted
AE-105 NEW SECOND FLOOR REFLECTED CEILING PLAN.pdf PDF
102123.pdf PDF
VA LEBANON RENOVATE BUILDING 22 - AE601 DOOR SCHEDULE - FRAME_ DOOR TYPES.pdf PDF
36C24421R0001 0001.pdf PDF
Geotech Memo Report (JULY 2019).pdf PDF
VA LEBANON RENOVATE BUILDING 22 - AE301 BUILDING SECTIONS.pdf PDF
VA LEBANON RENOVATE BUILDING 22 - I102 FINISH SCHEDULES.pdf PDF
317400 Micropiles.pdf PDF
AB-SDS-Wink-2019-GLOSS.pdf PDF
122492.pdf PDF
Wink-ProductSpecs-2019.pdf PDF
VA LEBANON RENOVATE BUILDING 22 - AE402 ENLARGED RESTROOM PLANS AND ELEVATIONS.pdf PDF
117300 REV.pdf PDF
VA LEBANON RENOVATE BUILDING 22 - AE401 ENLARGED RESTROOM PLANS AND ELEVATIONS.pdf PDF
EXHIBIT C - Calculation of Self-Performed Work.docx DOCX document
J and A (Ceiling Lifts).pdf PDF
EXHIBIT E - Past Performance Questionnaire.docx DOCX document
WD PA20200093.pdf PDF
Bid Dwgs Part 1 - Building 22.pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation Questionnaire.docx DOCX document
J and A (Secuirty System).pdf PDF
S02 Apendix C to 6500.6.pdf PDF
Bid Dwgs Part 2 - Building 22.pdf PDF
J and A (Fire Alarms).pdf PDF
EXHIBIT B - Subcontractor Information and Consent Form.docx DOCX document
36C24421R0001.docx DOCX document
EXHIBIT A - Past Performance Relevancy Questionnaire.docx DOCX document
Combined Bid Specs Building 22.pdf PDF
J and A (Locksets).pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OFOC SOP Revision 08 Original Date: 03/22/11 Revision 08 Date: 04/18/2018

Page 1 of

VHAPM Part 806.3 Other Than Full and Open Competition (OFOC) SOP Attachment 2: Request for Sole Source Justification Format >SAT

DEPARTMENT OF VETERANS AFFAIRS

Justification and Approval For

Other Than Full and Open Competition

1. Contracting Activity: The activity for this requirement is the Department of Veteran Affairs Medical Center (VAMC), Lebanon VA Medical Center, Located at 1700, South Lincoln Ave, Lebanon, PA 17042This is a Justification and Approval for Other Than Full and Open Competition Brand Name Only for HVAC Controls — Delta Controls which is a small portion of the construction materials requested on Project No.

2. Nature and/or Description of the Action Being Processed: Request for other than full and open competition — use of brand name specification for Project No.

construction project. Contractor shall furnish management, supervision, labor, transportation, equipment, and materials, and perform work to include general construction, alterations, mechanical and electrical work, and certain other items as required by project drawings and specifications for Project No. . This acquisition is fixed-firm price.

3. Description of Supplies/Services Required to Meet the Agency's Needs: HVAC Controls — Delta Controls — see Specification Section 23 09 23: Engineering, programming, controls and installation materials, installation labor, commissioning and start-up, training.

4. Statutory Authority Permitting Other than Full and Open Competition: 41 USC §253(c)(1), as implemented by FAR 6.302-1. FAR13.5 Simplified Procedures for Certain Commercial Items: The authority for applying the Simplified Procedures for Commercial Items of FAR 13.5 is 41 U.S.C. 1901 and is implemented by for restricting competition on this procurement via FAR 13.106-1(b)(2).

( ) (1) Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements per FAR 6.302-1;

( ) (2) Unusual and Compelling Urgency per FAR 6.302-2;

( ) (3) Industrial Mobilization, Engineering, Developmental or Research Capability or Expert Services per FAR 6.302-3;

( ) (4) International Agreement per FAR 6.302-4 ( ) (5) Authorized or Required by Statute FAR 6.302-5;

( ) (6) National Security per FAR 6.302-6;

( ) (7) Public Interest per FAR 6.302-7;

5. Demonstration that the Contractor's Unique Qualifications or Nature of the Acquisition Requires the Use of the Authority Cited Above (applicability of authority): HVAC Controls

— Delta Controls — see Specification Section 23 09 23: Restriction of sources for this acquisition is justified in accordance with FAR8.405-6(b)(3). Although there are other manufacturers of HVAC controls that can meet the Government's minimum requirements, it is not in the Government's best interest to award an acquisition to any brand other than Delta. Delta controls have been

Page 2 of implemented at the facility as of October 2009. The use of Delta Controls will meet the operational need of the Lebanon VAMC, by giving the engineering department redundant HVAC operational control. Use of other manufacturers would lead to storing additional inventory, functioning issues due to non-compatibility with existing equipment, multiplicity of service contracts, and increased training and operator requirements.

6. Description of Efforts Made to ensure that offers are solicited from as many potential sources as deemed practicable: A Notice of Intent to Sole Source HVAC controls — Delta Controls will be posted on beta.sam.gov with the solicitation. Offerors will be able to obtain Delta Controls from various distributors and sources available in the open market.

7. Determination by the Contracting Officer that the Anticipated Cost to the Government will be Fair and Reasonable: Based on the information above, it is hereby determined that this written justification for a particular brand names, is essential to the Government's requirements, and market research indicates other companies' similar products, or products lacking the particular feature, do not meet, or cannot be modified to meet the agency's needs. Therefore, these products will be specified as a brand name for this construction project as only these products meet the Government's needs. This procurement is an RFP, resulting in a firm-fixed price contract award. The contracting officer, IAW FAR 13.106-3(a)(1), anticipates the offered price to be fair and reasonable based on adequate price competition. Certified Cost or pricing data and audits are not required.

8. Description of the Market Research Conducted and the Results, or a Statement of the Reasons Market Research Was Not Conducted: The existing HVAC controls throughout the entire Lebanon VAMC facility are Delta Controls. Proper operation of the HVAC system requires the same controls manufacturer in all facilities throughout the campus. Per the market research conducted, the sensors can be any brand of 10k type III sensing element on temperature and must give a 0 – 10v input signal. Beyond the sensing elements, the controllers and all other equipment must be Delta to work with the Delta system.

9. Any Other Facts Supporting the Use of Other than Full and Open Competition:

All the specifications and drawings and engineering descriptions associated with Project No.

have been developed identifying Delta Controls as the standard system throughout the LVAMC.

10. Listing of Sources that Expressed, in Writing, an Interest in the Acquisition: See Section 6 above.

11. A Statement of the Actions, if any, the Agency May Take to Remove or Overcome any Barriers to Competition before Making subsequent acquisitions for the supplies or services required:

In the future if there is a requirement to re-accomplish the entire facility with a new HVAC control system, that requirement would be competed.

12. Requirements Certification: I certify that the requirement outlined in this justification is a Bona Fide Need of the Department of Veterans Affairs and that the supporting data under my

Page 3 of cognizance, which are included in the justification, are accurate and complete to the best of my knowledge and belief.

Date David Scharf Assistant Chief/Program Manager Lebanon VA Medical Center

13. Approvals in accordance with FAR 6.304 Contracting Officer's Certification (required):

a. Contracting Officer or Designee’s Certification (required): I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.

Date Melvin Moore Contracting Officer, Construction-West Network Contracting Office (NCO)4

b. One Level Above Contracting Officer (Required over SAT but not exceeding $700K):

I certify the justification meets requirements for other than full and open competition.

Date Michelle Lappen Branch Chief, Construction-West Network Contracting Office 4

Text38: 595-15-201 Renovate Bldg. 22
Check Box41: Yes
Check Box42: Off
Check Box43: Off
Check Box44: Off
Check Box45: Off
Check Box46: Off
Check Box47: Off
2020-06-17T08:09:56-0400
David C. Scharf 1024637
Text49:
2020-06-17T09:43:07-0400
Melvin E Moore 458946
Text52:
Date54_af_date: 6/17/20
Date55_af_date: 6/17/2020
2020-06-18T14:35:19-0400
MICHELLE Y. LAPPEN 1635695
Text57:
Date58_af_date: 6/18/20

File details come from the government source that posted it. Updated .