About this file

This document is a Quality Assurance (QA) Compliance Checklist for Computer-Aided Design (CAD) files, specifically focused on ensuring adherence to Electronic and Information Infrastructure (eFIC) standards. The checklist covers multiple phases of review, including submittal delivery, file structure requirements, and detailed CAD file compliance, with specific focus areas such as folder structure, file naming conventions, drawing units, reference file management, and layer/level assignments.

The checklist provides a comprehensive review process with specific compliance criteria across three primary phases: Submittal Delivery, Spot Check File Structure Requirements, and Detailed CAD File Compliance. Key technical specifications include requirements for six-digit project ID prefixes, PDF submissions, specific CAD software versions (AutoCAD v20## and MicroStation V8i/CONNECT), drawing units set to Architectural, and strict guidelines on reference files, layers, and block/cell insertions. The document is marked as related to a project with a prefix of 23-001 and includes sections for marking documents as Controlled Unclassified Information (CUI) in accordance with Department of Defense guidelines.

View the file

Other files for this federal contract opportunity

Other files attached to Roof Fall Protection Systems Services, newest first.
File Type Posted
Solicitation Amendment HQ003426RE0040001 SF 30.pdf PDF
GOVT RESPONSE TO OFFEROR QUESTIONS.pdf PDF
HQ003426RE004 Sign-In Sheet.pdf PDF
J-17 Asbestos Location OM Program.pdf PDF
J-16 F6-014500_CONTRACTOR_RESUMES_rev.pdf PDF
J-5 Past Performance Data Sheet.docx DOCX document
J-2 WD Constr. VA20250013 02-28-2025.pdf PDF
J-1 PWS.pdf PDF
J26 Contract NDA Form.pdf PDF
J-14 Pentagon Labeling Std Rev 9.pdf PDF
J-15 2021 Excavation Permit Application Form fillable.pdf PDF
J-19 Project Man Hours Work DART Rate Example.pdf PDF
J-9 PFGS Spec Sections_(01-32).pdf PDF
J-11 Pentagon_Reservation_Exterior_Standards_Manual.pdf PDF
J-10 Pentagon Historic Concrete Specifications.pdf PDF
J-4 ADAP Form 219-704 Subcontracting Plan Format.docx DOCX document
J-24 Reservation Area Designation Plan.pdf PDF
J-21 EDS Project Kickoff Presentation.pdf PDF
J-22 FSD Electronic Data Standards_6.1.pdf PDF
J-18 Project Man Hours Work DART Rate.xlsx XLSX spreadsheet
J-13 Sample_DID.pdf PDF
J-3 WD Services 2015-4281 Rev 34 07.08.2025.pdf PDF
J-20 AEC_CAD Standards 6.1.pdf PDF
J25 Contractor-Conflict-of-Interest-Disclosure-Form.pdf PDF
J-8 WHS Fire Regulations 2022 Edition.pdf PDF
J-12 Reservation_Finish_Standards.pdf PDF
J-7 WHS_Building_Code_2022.pdf PDF
J-6 Contractor Past Performance Questionnaire PPQ.docx DOCX document
Solicitation - HQ003426RE004.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

eFIC QA Checklist

eFIC QUALITY ASSURANCE CAD COMPLIANCE CHECKLIST REVIEW
Project InformationEDS v4.2 REF.AEC Reference
MPL #[MPL #]3.8.1AEC R6.1 [2.4.1] Project Code (pgs. 19-20)
Project Name (Provided by Government Contact)Project Title <found on Transmittal>
Submission Status30% / 90% / 100% / IFC / As-Built Submission
Submission Date<found in eMail or Transmittal>
QA Review Date<date of Review>
Contractor/Sub ContractorsPrime Company Name/ Sub Contractors
CAD Software and VersionCAD Software and version used to create or manipulate drawings:AutoCAD v20## | MicroStation V8i/CONNECT3.5.2.1
Reviewer Contact InformationName
Email
Phone
Phase 1: Submittal Delivery Compliance Review
Sheet File Checklist:DescriptionEDS COMPLIANT
Folder StructureEDS Directory Structure Folder and all subsequent files, both graphic and non-graphic, required for the project (e.g., seed/template files, cell libraries, dgnlib files, etc.) provided at project kick-off is followed:NA | No | Yes2.3.1The project's folder structure is incorrect.
Project File Index of Drawings Spreadsheet IncludedA drawing index spreadsheet for all files is provided:NA | No | Yes1.2.4
PDF Submission IncludedAll sheet file deliverables should be in PDF format:NA | No | Yes
Six-digit Alphanumeric Project ID Prefix used in File Names: 23-001…A six-digit project identifier prefix on all CAD files is used:NA | No | Yes2.5.1.1AEC R6.1 [2.4.1] Project Code (pgs. 19-20)
EDS File Naming: 2 4 _ 0 0 1 – A – F P – 0 1 0 0The WHS EDS file naming convention is followed:NA | No | Yes2.5.1AEC R6.1 [2.4.3] Sheet file naming convention (pg. 27)
Phase 2: Spot Check File Structure Requirements
Title & Revision BlocksThe titleblock and revision block are correctly filled out:NA | No | Yes2.10.3
All CAD files marked:
CUI (Controlled Unclassified Information)All eFIC documents are appropriately identified, marked, stored,
and accounted for as outlined in DoDM 5200.01:NA | No | Yes
AutoCAD Drawing Units = Length Type: ArchitecturalThe Drawing File Settings for Drawing Units is followed:NA | No | Yes
MicroStation Working Units = Resolution: 304800 per Distance FootThe Design File Settings for Working Units is followed:NA | No | Yes2.6.4
Raster files displayed = OnAll raster files being used are displayed:NA | No | Yes
Raster files unused = RemovedExtraneous raster files are removed (red highlighted files):NA | No | Yes
Reference/xref files prefixed with "r": r24-001-… (non self-referenced files)An "r" was placed in front of all individual reference files:NA | No | Yes2.5.1.11AEC R6.1 [2.4.1] Project Code (pg. 20)
Reference/xref files displayed = OnAll reference files being used are displayed:NA | No | Yes2.3.5
Reference/xref files unused = RemovedExtraneous reference files are removed (red highlighted files):NA | No | Yes2.5.1.11
Phase 3: Detailed CAD File Compliance Checklist
EDS Drawing Structure / AssemblyNo designs shall be inserted into sheet files. Design drawings shall only be referenced into sheet files.NA | No | Yes2.8.3AEC R6.1 [4] Level/Layer Assignments
EDS Level/Layer NamesThe level naming convention should be as the example given in

Appendix A of the AEC CAD Standards v6.1.

Levels not named accordingly are to be removed.NA | No | Yes
EDS Cells/BlocksNo models shall be inserted into another model as a block, models shall be referenced in.NA | No | Yes2.5.1.15
2.5.1.16AEC Symbols Guide v1.4 Cells/Blocks (pgs. 7-107)
eFIC Quality Assurance CAD Compliancy Review Summary =NONCOMPLIANT | COMPLIANT
Government Sponsor Approval Signature and Date:

&F