J-18 Project Man Hours Work DART Rate.xlsx

XLSX spreadsheet 133 KB Posted

Attached to
Roof Fall Protection Systems Services Federal contract opportunity
Solicitation number
HQ003426RE004
Issued by
DOD Washington Headquarters Service

About this file

This Excel spreadsheet is a Monthly Accident Report tracking safety metrics for a contractor, documenting job site man-hours, near misses, OSHA recordables, lost time accidents, and DART (Days Away/Restricted/Transfer) rates. The data covers a full year, with monthly breakdowns showing total man-hours worked ranging from 1,600 to 2,520, and year-to-date totaling 24,040 man-hours. Key safety incidents include a near-miss in June 2013 involving a loose pipe on a flatbed truck, which was addressed in a subsequent safety meeting. The DART rate calculation methodology is provided, with the year-to-date rate calculated at 33.28, indicating the number of work-related injuries and their impact on total hours worked.

The related federal contract opportunity is a DOD Washington Headquarters Service solicitation for Roof Fall Protection Systems Services, with critical deadlines including a mandatory site visit on December 4, 2025, a question submission deadline of December 10, 2025, and a proposal submission deadline of January 7, 2026. Vendors must attend the site visit to be eligible to submit a bid, and all proposals must be submitted by the specified time. The solicitation emphasizes strict adherence to the scheduled deadlines and site visit requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Roof Fall Protection Systems Services, newest first.
File Type Posted
Solicitation Amendment HQ003426RE0040001 SF 30.pdf PDF
HQ003426RE004 Sign-In Sheet.pdf PDF
GOVT RESPONSE TO OFFEROR QUESTIONS.pdf PDF
J-17 Asbestos Location OM Program.pdf PDF
J-16 F6-014500_CONTRACTOR_RESUMES_rev.pdf PDF
J-5 Past Performance Data Sheet.docx DOCX document
J-2 WD Constr. VA20250013 02-28-2025.pdf PDF
J-1 PWS.pdf PDF
J-24 Reservation Area Designation Plan.pdf PDF
J-21 EDS Project Kickoff Presentation.pdf PDF
J-22 FSD Electronic Data Standards_6.1.pdf PDF
J-23 ComplianceChecklist_24_XXX_Name_Submission_Date.xlsx XLSX spreadsheet
J-13 Sample_DID.pdf PDF
J-3 WD Services 2015-4281 Rev 34 07.08.2025.pdf PDF
J26 Contract NDA Form.pdf PDF
J-14 Pentagon Labeling Std Rev 9.pdf PDF
J-15 2021 Excavation Permit Application Form fillable.pdf PDF
J-19 Project Man Hours Work DART Rate Example.pdf PDF
J-9 PFGS Spec Sections_(01-32).pdf PDF
J-11 Pentagon_Reservation_Exterior_Standards_Manual.pdf PDF
J-10 Pentagon Historic Concrete Specifications.pdf PDF
J-4 ADAP Form 219-704 Subcontracting Plan Format.docx DOCX document
J-20 AEC_CAD Standards 6.1.pdf PDF
J25 Contractor-Conflict-of-Interest-Disclosure-Form.pdf PDF
J-8 WHS Fire Regulations 2022 Edition.pdf PDF
J-12 Reservation_Finish_Standards.pdf PDF
J-7 WHS_Building_Code_2022.pdf PDF
J-6 Contractor Past Performance Questionnaire PPQ.docx DOCX document
Solicitation - HQ003426RE004.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Monthly Accident Report

Project:
Contractor Name:
Reporting Month:
Prepared By:
Date:
EXAMPLE
MonthlyAnnualJob Inception (Total)
Man Hours Worked2,54754,5453,232,656
Near Misses126
# of OSHA Recordables (Rec)225
# of Lost Time Accidents (LTA)- 013
Total # of Lost Work Days (LWD)- 0832
DART Rate Days Away/Restricted/Transfer Rate157.0511.000.49
DART Rate = 200,000 x (Total number of cases recordable - Days Away/Restricted/Transfer)
Total Number of Man Hours
Accident/Incident Summary for the month:
Near Miss - On June 06, 2013 pipe came loose off of flat bed truck and almost struck employee. Safety meeting reviewed properly securing materials.

Asbestos Locataion O and M Program 22

Sheet2

Project:
Contractor Name:
Reporting Month:
Prepared By:
Date:
Example
# Man Hours WorkedNear Misses# of OSHA Recordables (Rec)# of Lost Time Accidents (LTA)Total# of Lost Work Days (LWD)DART Rate
January1600120250.0
February16000000.0
March20160000.0
April20160000.0
May201601099.2
June25202000.0
July25201000.0
August25203000.0
September2016011099.2
October20160000.0
November16000000.0
December16000000.0
YTD24040741033.28
DART Rate = Days Away/Restricted/Transferred200,000 x # of OSHA Recordables Cases
# Man Hours Worked