About this file
This Excel spreadsheet is a Monthly Accident Report tracking safety metrics for a contractor, documenting job site man-hours, near misses, OSHA recordables, lost time accidents, and DART (Days Away/Restricted/Transfer) rates. The data covers a full year, with monthly breakdowns showing total man-hours worked ranging from 1,600 to 2,520, and year-to-date totaling 24,040 man-hours. Key safety incidents include a near-miss in June 2013 involving a loose pipe on a flatbed truck, which was addressed in a subsequent safety meeting. The DART rate calculation methodology is provided, with the year-to-date rate calculated at 33.28, indicating the number of work-related injuries and their impact on total hours worked.
The related federal contract opportunity is a DOD Washington Headquarters Service solicitation for Roof Fall Protection Systems Services, with critical deadlines including a mandatory site visit on December 4, 2025, a question submission deadline of December 10, 2025, and a proposal submission deadline of January 7, 2026. Vendors must attend the site visit to be eligible to submit a bid, and all proposals must be submitted by the specified time. The solicitation emphasizes strict adherence to the scheduled deadlines and site visit requirements.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Monthly Accident Report
| Project: | |
| Contractor Name: | |
| Reporting Month: | |
| Prepared By: | |
| Date: | |
| EXAMPLE |
| Monthly | Annual | Job Inception (Total) | |
| Man Hours Worked | 2,547 | 54,545 | 3,232,656 |
| Near Misses | 1 | 2 | 6 |
| # of OSHA Recordables (Rec) | 2 | 2 | 5 |
| # of Lost Time Accidents (LTA) | - 0 | 1 | 3 |
| Total # of Lost Work Days (LWD) | - 0 | 8 | 32 |
| DART Rate Days Away/Restricted/Transfer Rate | 157.05 | 11.00 | 0.49 |
| DART Rate = 200,000 x (Total number of cases recordable - Days Away/Restricted/Transfer) | |
| Total Number of Man Hours | |
| Accident/Incident Summary for the month: | |
| Near Miss - On June 06, 2013 pipe came loose off of flat bed truck and almost struck employee. Safety meeting reviewed properly securing materials. |
Asbestos Locataion O and M Program 22
Sheet2
| Project: | ||||||
| Contractor Name: | ||||||
| Reporting Month: | ||||||
| Prepared By: | ||||||
| Date: | ||||||
| Example | ||||||
| # Man Hours Worked | Near Misses | # of OSHA Recordables (Rec) | # of Lost Time Accidents (LTA) | Total# of Lost Work Days (LWD) | DART Rate | |
| January | 1600 | 1 | 2 | 0 | 250.0 | |
| February | 1600 | 0 | 0 | 0 | 0.0 | |
| March | 2016 | 0 | 0 | 0 | 0.0 | |
| April | 2016 | 0 | 0 | 0 | 0.0 | |
| May | 2016 | 0 | 1 | 0 | 99.2 | |
| June | 2520 | 2 | 0 | 0 | 0.0 | |
| July | 2520 | 1 | 0 | 0 | 0.0 | |
| August | 2520 | 3 | 0 | 0 | 0.0 | |
| September | 2016 | 0 | 1 | 10 | 99.2 | |
| October | 2016 | 0 | 0 | 0 | 0.0 | |
| November | 1600 | 0 | 0 | 0 | 0.0 | |
| December | 1600 | 0 | 0 | 0 | 0.0 |
| YTD | 24040 | 7 | 4 | 10 | 33.28 |
| DART Rate = Days Away/Restricted/Transferred | 200,000 x # of OSHA Recordables Cases | ||||
| # Man Hours Worked |