This is a Statement of Work for the installation of a ductless split heating and cooling system at the Newark Air Traffic Control Tower (EWR ATCT) facility operated by the Federal Aviation Administration's Eastern Service Area in Burlington, Massachusetts. The project is located at Room 141A of the FAA ATCT base building in Newark, New Jersey.
The scope of work encompasses a complete ductless mini-split system installation consisting of one 6-ton exterior heat pump unit anchored to the exterior concrete wall and three interior wall-mounted units. The contractor must provide all labor, materials, equipment, and supervision required for mechanical installation, including refrigerant and drain piping, wall waterproofing, and system testing and charging. Electrical work includes installation of a new dedicated 208V, 3-phase power circuit, a NEMA 4X, 60A non-fused stainless steel disconnect at the outdoor unit, and all associated conduit and wiring through concrete wall and roof deck penetrations with proper roof flashing. The contractor must integrate the mini-split system into the existing FAA Schneider Electric EcoStruxure DDC control system via BACnet, install an IP-IO module at VAV-17, submit control documentation for approval, program unit setpoints, and support full system commissioning. Structural and interior work includes concrete core penetrations, support framing and steel plates for all units, pipe and conduit supports, wall restoration, and painting. The contractor bears responsibility for coordinating all trades, maintaining roof warranty compliance through the Carlisle Roof installer, and validating system operation upon completion.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US. Department Of Transportation Eastern Service Area 1200 District Ave Burlington, Massachusetts 01803
Federal Aviation Administration
STATEMENT OF WORK
Newark ATCT (EWR) Newark, NJ TSS Ductless System Installation
Scope of Work:
The contractor must furnish all labor, materials, equipment, supervision, and services required to install a new ductless split system at the FAA ATCT base building (Room 141A, TSS). In brief, the split system consists of (1) exterior wall-mounted unit, (3) wall-mounted indoor units, integration with existing building automation controls, and all related structural, interior wall-renovations, mechanical, electrical work. Work shall include, but is not limited to, the items listed below:
Mechanical
· Install (3) indoor wall-mounted units, along with all refrigerant and drain piping.
· Install (1) 6-ton heat pump. Unit to be anchored to exterior concrete wall via on L-bracket steel frame.
· Coordinate core penetrations through concrete wall for piping, electrical, and drain lines. Installation to include all wall waterproofing.
· Provide and insulate all refrigerants and condensate piping above ceiling
· Test and charge system to verify operation.
Electrical
· Install new dedicated 208V, 3-phase power circuit
· Provide NEMA 4X, 60A non-fused stainless steel disconnect at outdoor unit
· Provide power and control conduit and wiring to/from all units
· Penetrate concrete wall.
· Provide penetration and conduit through roof deck. Patch and flash roof as required to maintain new roof warranty through Carlisle Roof installer.
Controls
· Integrate mini-split system into the existing FAA Schneider Electric EcoStruxure DDC system via BACnet
· Provide and install one IP-IO module at VAV-17 for coordinated backup cooling enable/disable
· Submit point list, graphics, and control narrative to COR for approval.
· Program unit set points, and update AHU-3 supply air setpoints
· Support commissioning of system to validate operation.
Structural & Interior
· Concrete core penetration for pipes and conduits
· Provide support framing for all units and steel plates as shown in drawing.
· Provide support for pipes and conduits.
· Work to include wall restoration and painting.