ITB 12278 Attachment B Technical Specifications Collier Memorial Park Improvement.pdf
PDF 2 MB Posted
- Solicitation number
- S-63400-00012818
- Issued by
- Jackson County, Cheshire CDP, Oregon
About this file
This is a technical specifications document from the Oregon Parks and Recreation Department (OPRD) for the Collier Memorial State Park Campground Entrance Improvement Project (#36607, Contract #12278) dated November 2024. The project involves substantial improvements to the park campground entrance including site preparation, demolition, asphalt excavation, earthwork, base rock installation, asphalt paving, pavement markings, concrete work, RV dump station construction, waterline installation, electrical work, trash compactor enclosure, and building construction/improvements. The owner will provide certain items for contractor installation including a double arm maintenance gate, parking lot signs, and kiosk assembly. The campground will be closed to the public during construction.
The work must be performed during normal operating hours of 7AM-5PM Monday-Friday unless otherwise arranged, with no work permitted on holidays or weekends without prior approval. The contractor must provide all permits, labor, equipment, tools, supervision, materials and incidentals required to complete the work according to plans and specifications. The contractor must also implement and maintain an Erosion Sediment Control Plan, protect cultural resources, minimize vegetation removal, control noise levels, and follow strict environmental protection measures. The specifications detail extensive requirements for temporary facilities, utilities, barriers, tree protection, and site maintenance during construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB 12278 Attachment E-2 STRUCTURAL ENGINEERING CALCULATIONS.pdf | ||
| ITB 12278 Attachment A- FORM A-2 Pricing Form~1.xlsx | XLSX spreadsheet | |
| Intent to Award OregonBuys~1.docx | DOCX document | |
| Addendum 1 ITB 12278.pdf | ||
| Pre-Bid Conference sign-in sheet.docx | DOCX document | |
| ITB 12278 Collier Campground Entrance Improvement Project _.docx | DOCX document | |
| ITB 12278 Attachment E-1 INADVERTENT DISCOVERY PLAN.docx | DOCX document | |
| ATT B TECHNICAL SPECIFICATIONS Collier Memorial SP Addendum 2 022825.pdf | ||
| ITB 12278 Bid Tabulation and Responsive PW PI.xlsx | XLSX spreadsheet | |
| ITB 12278 Addendum 2 and Question and Answer 022825.docx | DOCX document | |
| ITB 12278 Attachment C PLANS AND DRAWINGS.pdf | ||
| Preliminary Bid Results.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Oregon Parks and Recreation
Department
TECHNICAL SPECIFICATIONS
For
Collier Memorial State Park – Campground Entrance Improvement Project
Project Number: OPRIS #36607 Contract Number: #12278
Date: November 2024
Prepared by:
Oregon Parks and Recreation Department Engineering Section
725 Summer Street NE, Suite C Salem, Oregon 97301
THIS PAGE INTENTIONALLY LEFT BLANK
i Table of Contents
TABLE OF CONTENTS
PAGE
SECTION 01010 – SUMMARY OF WORK
SECTION 01019 – CONTRACT CONSIDERATIONS
SECTION 01025 – MEASUREMENT AND PAYMENT
SECTION 01028 – MODIFICATION PROCEDURES
SECTION 01062 – PERMITS
SECTION 01090 – REFERENCE STANDARDS
SECTION 01300 – PROJECT MANAGEMENT & COORDINATION
SECTION 01330 – SUBMITTALS PROCEDURE
SECTION 01350 – PROTECTION OF CULTURAL RESOURCES
SECTION 01500 – TEMPORARY FACILITIES AND CONTROLS
SECTION 01560 – ENVIRONMENTAL CONTROLS
SECTION 01570 – TRAFFIC CONTROL
SECTION 01730 – OPERATING AND MAINTENANCE INSTRUCTIONS
SECTION 02100 – SITE CLEARING
SECTION 02200 – EARTHWORK
SECTION 02220 – EARTHWORK FOR UTILITIES & VAULTS
SECTION 02240 – CONTROL OF WATER
SECTION 02322 – EARTHWORK FOR ROADWAY REPAIRS
SECTION 02510 – WATER SYSTEMS
SECTION 02511 – HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS
SECTION 02512 – PEX DOMESTIC WATER PIPING
SECTION 02530 – SANITARY SEWER
SECTION 02700 – ASPHALTIC CONCRETE PAVING AND RESURFACING
SECTION 02765 – PAVEMENT MARKINGS
SECTION 03300 – CAST-IN-PLACE CONCRETE
SECTION 06100 – ROUGH CARPENTRY
SECTION 06200 – FINISH CARPENTRY
SECTION 07210 – BUILDING INSULATION
SECTION 07600 – FLASHING AND SHEET METAL
SECTION 07610 – SHEET METAL ROOFING
SECTION 07920 – JOINT SEALANTS
SECTION 08110 – STEEL DOORS AND FRAMES
SECTION 08330 – ROLLING COUNTER DOORS
SECTION 08560 – VINYL WINDOWS
SECTION 08710 – DOOR HARDWARE
SECTION 08810 – GLASS AND GLAZING
SECTION 09900 – PAINTING
SECTION 15010 – GENERAL MECHANICAL PROVISIONS
SECTION 15050 – BASIC MATERIALS AND METHODS
SECTION 15400 – PLUMBING
SECTION 16010 – GENERAL ELECTRICAL PROVISIONS
SECTION 16040 – IDENTIFICATION
SECTION 16050 – BASIC ELECTRICAL MATERIALS & METHODS
SECTION 16060 – GROUNDING AND BONDING
SECTION 16210 – ENTRANCE EQUIPMENT AND METERING
SECTION 16215 – UNDERGROUND SECONDARY
Campground Entrance Improvement Project Collier Memorial State Park
Section 01010 - 1
SUMMARY OF WORK
SECTION 01010 – SUMMARY OF WORK
PART 1 – GENERAL
1.01 DESCRIPTION OF WORK
A. Requirements of the STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS (“General Conditions”) dated January 1, 2012, as modified by the Oregon Department of Justice on November 13, 2024, apply to the Technical Specifications and Plans for this Project.
B. The Work shall be as shown on the Plans and as specified herein at the following location(s):
46000 Highway 97 N, Chiloquin OR 97624
C. Contractor shall furnish all permits, labor, equipment, tools, supervision, materials and incidentals required to complete the Work in accordance with the Plans, Specifications and terms of the Contract. Also refer to the Invitation to Bid (“ITB”) and the Contract for additional requirements and information. Work includes, but is not limited to, the following:
Base Bid:
A1 Permits and Mobilization A2 Site Preparation and Demolition A3 Asphalt Excavation A4 General Excavation and Earthwork A5 Base Rock A6 Asphalt Paving – Leveling and Wearing Courses Combined A7 Pavement Markings and Striping A8 Cast in Place Concrete Curb A9 4” Concrete sidewalk A10 6” Concrete slabs A11 Concrete culvert A12 RV Dump Station and Washdown Area A13. Site Waterline – 1” A14. Site Electrical A15 Trash Compactor Enclosure A16 Landscape – Restoration to Pre-construction State A17 Installation of Owner Provided Items
B1 Building Construction and Improvements B2 Building Mechanical B3 Building Electrical
Alternate #1:
C1 Roadway Improvements to Well House Building
Refer to Plans and Specifications for other items.
D. Specific items furnished by Owner and installed by Contractor:
Section 01010 - 2
SUMMARY OF WORK
Base Bid:
1. Double Arm Maintenance Gate
2. Parking Lot Signs
3. Kiosk Assembly
Alternate #1:
1. Single Arm Maintenance Gate
E. Specific items furnished and installed by others:
1. Trash compactor.
F. Project is for the Oregon Parks and Recreation Department, herein referred to as Owner.
1. Where “Architect” or “Engineer” is used in the Contract Documents it shall mean “Owner”.
2. Where “General Contractor” is used in the Contract Documents it shall mean “Contractor”.
G. The Owner’s Authorized Representative, herein referred to as Project Manager is:
Kevin Johnson Oregon Parks & Recreation Department 62976 OB Riley Road Bend, OR 97703 541-306-9811 kevin.johnson@oprd.oregon.gov
1.02 CONSTRUCTION STAKEOUT AND LAYOUT
A. The Plans show approximate locations and dimensions of existing utilities and facilities adjacent to and in the proposed Work, as shown on the Plans, for the Contractor’s information. Final stakeout of the construction Work shall be provided by Contractor and approved by Project Manager. The Contractor will be solely responsible for locating all existing utilities within the Project sites. Stakeout of project improvements will not be provided by the Owner. However, digital drawings of the site improvements will be made available upon request.
B. Contractor is responsible for properly laying out the Work and for lines and measurements for the Work. Contractor to verify the figures shown on the Plans before any construction takes place or products are ordered. Report errors or inaccuracies to the Project Manager for resolution before commencing Work. Submit as-built plans after completion of the Project to record any changes that took place in accordance with Section 01330.
Section 01010 - 3
SUMMARY OF WORK
1.03 PROJECT RECORD DRAWINGS
A. Maintain at the site one complete set of full-sized original prints for recording installed conditions (As-Builts). Keep record drawings (As-Builts) clean, undamaged and up to date as Work progresses. Accurately indicate all deviations, additions and omissions from the original drawings in red ink.
B. The purpose of these record drawings is to provide the Project Manager with an easy to read, complete record of the installation so that at the end of the Project the Project Manager can revise the original Contract Plans to represent the actual installation. Color-coded and highlighted notes shall be used if these would make the record drawings easier to read.
C. At the completion of the Work, Contractor shall furnish the Project Manager this original set of marked-up drawings. Final payment to the Contractor will not be authorized until these drawings have been submitted to and accepted by the Project Manager.
1.04 OWNER OCCUPANCY
A. The Owner will not close any areas of the Park except the area under construction and temporary closures as approved in advance by the Park Manager for approved limited durations.
B. Coordinate all Work with Park Manager to minimize conflict and to facilitate on-going use and operation of the Park.
C. It is the Contractors responsibility to coordinate with The Owner and Owner’s other contractors and consultants as they will be on-site performing other work elsewhere on-site during construction. Coordinate fully with separate contractors so that work under other contracts may be carried out smoothly, without interfering with or delaying Work of this Contract.
1.05 CONTRACTOR USE OF SITE AND PREMISES
A. Construction Operations: Limited to construction areas around the Project site(s).
B. Contractor shall at all times conduct their operations to ensure the greatest public safety and least inconvenience to the public and adjacent land owners.
C. Contractor shall receive approval from the Park Manager as to the staging and stockpiling of the equipment and materials used on the Project.
D. Storage of material onsite is at Contractor’s own risk.
E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of material.
Load restrictions shall meet state load restrictions.
1. Contractor can utilize the single entrance road to the campground area of the park. The campground will be closed to the public during construction.
Section 01010 - 4
SUMMARY OF WORK
F. Parking: Contractor and Subcontractors shall park at approved locations, and as approved by the Park Manager.
G. Restrooms: Contractor shall provide temporary rest room facilities for its workers and
Subcontractors as required.
H. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except where indicated to be removed or altered as per project construction documents. It is the contractors sole responsibility to Repair any and all damages to existing facilities not shown as demolition items in the project plans.
I. Owner may allow Contractor to utilize park for temporary work force accommodation during construction. Location and utility availability to be coordinated and approved by Project Manager and Park Manager prior to arriving on site.
1.06 CONSTRUCTION SCHEDULE
A. Refer to the Contract for construction schedule Substantial and Final Completion dates.
B. Contractor shall not begin any on-site Work of this Project before required permits have been obtained, a preconstruction conference has been held, a proposed construction schedule is submitted, along with required submittals in accordance with Section 01300 and required submittals have been submitted in accordance with Section 01330, and the Project Manager has given written approval of the submittals and construction schedule provided by the Contractor.
1.07 SPECIFICATION LANGUAGE
A. Portions of the Specifications are written in imperative and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise.
1. The words “shall be” shall be included by inference where a colon (:) is used within sentences or phrases. Example: Aggregate: ASTM C33. Singular words will be interpreted as plural and plural words shall be interpreted as singular where applicable and where full context of the Contract Documents so indicates.
2. The word provide or furnish means “purchase, furnish and install”.
1.08 PROJECT IDENTIFICATION SIGN
A. The Project identification sign, if used, will be by the Owner.
1.09 CUTTING
A. Perform or arrange and pay for required cutting of asphalt, concrete, masonry, wood, structural framing, etc. and obtain approval from the Project Manager prior to cutting.
B. Cutting or channeling of underpinning or structural members shall not be permitted without prior permission of the Project Manager.
Section 01010 - 5
SUMMARY OF WORK
C. No weakening of structural parts is permitted and the Contractor will pay for and correct any Work impaired.
1.10 PATCHING
A. Where trenching is done through existing paving, walks, curbs, etc. (with prior approval from the Project Manager), the Contractor is responsible to patch and repair these structures to original condition.
B. Patch all openings in and through concrete and masonry with dry pack.
C. In new Work, patch and refinish all damaged finished surfaces that are a result of the
Contractor’s activities to match the adjacent surface as approved by the Project Manager.
D. Where new electrical Work is installed in an existing building, patch and refinish surfaces damaged to match existing. Refinishing is to be as approved by the Project Manager.
PART 2 – PRODUCTS (Not Applicable)
PART 3 – EXECUTION (Not Applicable)
END OF SECTION
Section 01019 - 6
CONTRACT CONSIDERATIONS
SECTION 01019 – CONTRACT CONSIDERATIONS
1.01 SPECIAL PROJECT REQUIREMENTS
A. The campground portion of the Park will be closed to the public for the duration of construction. The Contractor shall erect barricades and signage to prevent public access in the construction site and provide for public safety during construction. Devices required to provide for public safety during construction shall be provided and installed by the Contractor at the expense of the Contractor. If required safety devices are not installed, Work shall not be allowed to commence until such devices are installed. The Contract Time will not be extended based on working Days lost due to the noncompliance of safety devices.
B. Construction operations shall be restricted to normal daily operating hours and the normal
Open/Close schedule of the Park but not outside the hours of 7AM – 5PM, Monday – Friday unless otherwise arranged and approved in writing by the Project Manager and Park Manager.
C. No Work shall be performed on any legal holiday or weekends without prior written approval from the Park Manager.
D. If special circumstances or emergency conditions require Work beyond the hours as specified, the Contractor shall:
1. Notify the Project Manager and Park Manager 72 hours in advance of any proposed extended work hours for preauthorization. The Contractor’s written request shall specify the Work to be performed and the circumstances that warrant the request. The request shall include any additional measures to mitigate noise generated by this construction activity, if deemed necessary by the Project Manager.
2. If an emergency situation occurs that warrants extended hours, the Contractor shall notify the Park Manager and Project Manager immediately upon determining the need for this Work.
E. Contractor shall notify the Park Manager in advance when Contractor, Subcontractor or any employees of such shall be on Park property.
F. Comply fully with manufacturer’s instructions and recommendations. Should manufacturer’s instructions conflict with Contract Documents, request clarification from Project Manager before proceeding.
G. Contractor shall furnish all planning, investigation, material, equipment, labor and permits to complete the Work in accordance with the Plans, Specifications and terms of this Contract, except as specified otherwise herein.
H. Day Use Park Fees will not be charged by the Park for contractors or deliveries.
Section 01019 - 7
CONTRACT CONSIDERATIONS
I. All changes to normal traffic patterns must be clearly explained in the Traffic Control Plan and approved by the Project Manager.
J. For paving projects, Contractor shall stay on roadway surfaces at all times. No staging of equipment or storage of materials shall be allowed off the existing roadway surface.
1.02 EXISTING UTILITIES
A. In general, the locations of existing utilities, whether above ground or underground or under the roof, are to be determined as needed by the Contractor. Work in some cases must be done in close proximity to said utilities and live electrical service lines, pipes, drains, and structures not shown, which may require a change in operations, cost and time.
B. Utilities damaged by Contractor’s activities shall be reestablished, to the satisfaction of the Park Manager and/or Project Manager. If the Contractor fails to repair the damaged utility, costs for repairing the utility shall be deducted from final payment.
C. Comply with Oregon Administrative Rules Chapter 952, Relating to Abandoned
Underground Facilities. An “Abandoned Facility” means an underground facility that is no longer in service and is physically disconnected from the operating facility that is in service. In addition to notification requirements of this rule, notify Project Manager of any Abandoned Underground Facilities which are discovered during the course of the Project.
1.03 PROGRESS CLEANING
A. Maintain areas free of waste materials, debris, and rubbish at all times. Maintain site in a clean and orderly condition. Provide legal debris disposal (or recycle waste materials if feasible) off-site for all debris generated while working on this Project.
B. Remove debris and rubbish from pipe chases and other closed or remote spaces on a daily basis.
C. Remove waste materials, debris and rubbish from the site immediately upon such materials becoming unfit for use in the Work. In the event this material is not removed, Project Manager will give one notification in writing as to the removal of such waste materials, debris and rubbish. If the Contractor does not clean up the waste materials, debris and rubbish within 24 hours as approved by the Project Manager, the Project Manager reserves the right, but does not have the duty, to have the material removed and the expense shall be deducted from payment to the Contractor. This debris shall be removed at the end of each workday.
D. Provide legal debris disposal off-site for all debris generated while working on this
Project.
1.04 TEMPORARY UTILITIES
A. Connections to existing utilities (electric, water, sewer, telephone service) may be allowed as approved by the Project Manager. Contractor to make arrangements for connections. Contractor to pay for cost of connection and use. Exercise measures to conserve energy and water.
Section 01019 - 8
CONTRACT CONSIDERATIONS
B. Provide toilet and wash-up facilities for the workforce at the site. Comply with applicable laws, ordinances and regulations pertaining to public health and sanitation.
PART 2 – PRODUCTS (Not Applicable)
PART 3 – EXECUTION (Not Applicable)
Section 01019 - 9
CONTRACT CONSIDERATIONS
Section 01025 - 10
MEASUREMENT AND PAYMENT
SECTION 01025 – MEASUREMENT AND PAYMENT
1.01 SUMMARY
A. All Payments shall be as provided in the State of Oregon General Conditions for Public Improvement Contracts. References to other documents in the Plans and in the Specifications, such as ODOT and ODOT/APWA are not intended to include references to measurement and payment that may exist in those other documents. Specific Measurements for Work Items are detailed in this Section.
B. If no Item exists for a portion of the Work, include the costs in a related Item.
C. No separate payment will be made for any item that is not specifically set forth in the Solicitation, and all costs therefore shall be included in the prices named in the Solicitation for the various appurtenant items of Work.
D. Quantities listed in the Contract Document do not govern final payment. Payments to the Contractor will be made only for actual quantities of Contract items performed in accordance with terms of the Contract and for items of Work actually performed under Change Orders.
E. Overhead costs, such as supervision, profit, and any project specific insurance and bonds required by the Contract, all shall be allocated to each item as applicable for Work defined in the item. No separate payment will be made to the Contractor for these items.
F. Disposal Fees: There shall be no separate measurement and payment item for Disposal Fees. Payment shall be incidental to other bid items.
G. Payments shall include full compensation for all labor, equipment, and materials necessary to perform the specified Work.
H. Partial payments to be made under the Contract shall be based on the percent of Work complete as approved by the Project Manager according to the State of Oregon General Conditions for Public Improvement Contracts.
I. Material requiring weighing to be weighed by scale. Allowable scales with Project Manager approval are commercial vehicle weigh scales, plant automatic weight batching and mixing control printer system, or plant weight hopper printer system.
1. Pay Items to be measured by weight shall include all Contractor costs for furnishing appropriate weight tickets and transporting materials to the scales or to check weighing.
2. The scales shall conform to ORS 618, and NIST Handbook 44, and shall be:
a. Licensed by the Oregon Department of Agriculture;
b. Technically suitable for weighing the materials;
c. Properly installed and maintained; and
d. Accurate to the required tolerances.
Section 01025 - 11
3. The Owner may periodically have a representative at the scales to observe the weighing procedures.
1.02 BID ITEMS, MEASUREMENT AND PAYMENT
(NOTE: See the ITB Pricing Submittal Form. Payment shall include full compensation for all labor, equipment, materials and incidentals needed to accomplish the Work as shown and described in the Contract Documents.
A. BID ITEMS - SITE RELATED:
A1 Permits and Mobilization:
a. Measurement and payment for this bid item shall be made on a lump sum basis. The amount to be allowed for Mobilization in the partial payment to be made under the Contract will be as follows:
i. When 5% of the total original Contract amount is earned from other items, 50% of the amount bid for Mobilization, or 2.5% of the original Contract amount, whichever is the least, will be paid.
ii. When 10% of the total original Contract amount is earned from other items, 100% of the amount bid for Mobilization, or 5% of the original Contract amount, whichever is the least, will be paid.
iii. Upon completion of all Work on the Project, payment of any amount bid for Mobilization in excess of 5% of the total original Contract amount will be paid.
b. The above schedule of progress payments for Mobilization shall not limit or preclude progress payments otherwise provided by the Contract.
A2 Site Preparation and Demolition:
b. The Contractor shall provide all erosion control measures necessary to comply with the requirements of Section 01560, all applicable permits, and all local, state and federal requirements.
c. The Work includes providing all labor, equipment, materials and incidentals needed to complete the Work in conformance with the Contract Documents and as approved by the Project Manager.
A3 Asphalt Excavation:
a. Measurement and payment for this bid item shall be based on a per square foot basis to the nearest 0.1 foot as field measured by determining
Section 01025 - 12
MEASUREMENT AND PAYMENT
the dimensions of the finished excavation prior to placement of backfill.
b. Work shall include all material, equipment and labor necessary to remove existing asphalt at locations shown on the Plans or as located in the field, including, but not limited to, excavation, and disposal of material at a Oregon Department of Environmental Quality (“DEQ”) approved dump site. Payment will only be made for asphalt excavation Work approved by the Project Manager.
c. If base materials are required to be excavated below asphalt surface, as approved by Project Manager, they shall be paid as General Excavation and Earthwork.
A4 General Excavation and Earthwork:
basis for all material moved or removed to the lines and grades shown on the
b. Payment shall include full compensation for all excavation and earthwork required to repair or construct roads, paths, equipment or building pads, building foundations and all other structures as shown in the Contract Documents. No payment will be made for over-excavation except as approved by the Project Manager. Payment includes compensation for hauling and legal disposal of excess material.
c. Geotextile fabric, where indicated by the Contract Documents, shall be incidental to this Work.
d. Rock excavation, if encountered, shall be paid under the Rock Excavation bid item.
A5 Base Rock or Shoulder Rock:
a. Measurement and payment for this bid item shall be made on a ton basis.
The quantities for payment shall be calculated from weight tickets collected at the job site.
b. Work includes providing the labor, equipment, materials and incidentals needed to furnish and install the base rock or shoulder rock in conformance with the Contract Documents and as approved by the
A6 Asphalt Paving - Leveling and Wearing Courses Combined:
a. Measurement and payment for this bid item shall be made on a ton in place basis to the nearest 0.01 ton. The quantities for payment shall be calculated from weight tickets collected at the job site.
b. Work shall include installing all pavement overlay including pre-leveling as shown on the Plans and as approved by the Project Manager.
Section 01025 - 13
c. Asphalt paving used as cap materials in road base repair shall be paid as
Asphalt Paving - Wearing and Leveling Courses Combined.
d. All pavement outside the Project limits, damaged as a result of the
Contractor’s operations will be removed and replaced to the satisfaction of the Project Manager, at the Contractor’s expense.
A7 Pavement Markings & Striping:
b. Work includes providing the labor, equipment, materials and incidentals needed to furnish and install the pavement markings in conformance with the Contract Documents and as approved by the Project Manager.
A8 Cast-in-Place Concrete Curb:
a. Measurement and payment for this bid item shall be made on a lineal foot basis. The payment shall include all excavation, forms, placement and finishing the Work.
b. Work includes providing all labor, equipment, materials and incidentals needed to furnish and install the concrete curb in conformance with the
A9 4” Concrete Sidewalks:
a. Measurement and payment for this bid item shall be made on a square yard basis. The payment shall include all Portland concrete placement, reinforcement, forms, base rock, base shaping, expansion joint material, handicap ramps, and any other required items indicated in the Contract Documents.
A10 6” Concrete Slabs:
a. Measurement and payment for this bid item shall be made on a square yard basis. The payment shall include all Portland concrete placement, reinforcement, forms, base rock, base shaping, expansion joint material, handicap ramps, and any other required items indicated in the Contract Documents.
A11 Concrete Culvert:
Section 01025 - 14
a. a. Measurement and payment for this bid item shall be made on a lump sum
b. Work includes providing the labor, equipment, materials and incidentals needed to furnish and install the pavement markings in conformance with the Contract Documents and as approved by the Project Manager.
A12 RV Dump Station and Washdown Area:
a. Measurement and payment for this bid item shall be provided on a lump sum basis.
b. This Work includes the installation of new water and sewer piping, modification of the existing sewer line, connecting the new line to the existing sewer system, fixtures and any related Work as shown on the Plans and as specified herein
c. Work shall include all materials, equipment, and labor required to Install
RV Dumpstation and Washdown Area at locations shown on Plans and as approved by the Project Manager and in conformance with the Contract Documents.
A13 Site Waterline - 1 inch:
a. Measurement and payment for this bid item shall be made on a linear foot basis. Payment length will be measured horizontally along the centerline of the waterline through the fittings from beginning to ending points of the pipe.
b. Payment will be provided per linear foot for this Work as shown or described in the Contract Documents. Payment shall provide full compensation for all materials, equipment and labor required including but not limited to, fittings, pipe, glue, pipe welding materials, tracer wires and markers, temporary and permanent plugs, blow-offs and caps, testing, miscellaneous materials, boring, excavation, trenching and backfill, temporary shoring and all other Work required for a complete system.
A14 Site Electrical:
basis for the construction, testing, and startup of electrical power, and controls for the proposed Work as indicated in the Plans and Specification, and as otherwise required by the equipment manufacturer(s).
b. Measurement and payment for this bid item to up to within five feet of buildings and other structures and all electrical Work required for the operation of utilities such as pump stations, site lighting, telecommunication systems, etc., including boring, excavation, trenching and backfill and any other Work required for a complete system.
Section 01025 - 15
c. Payment shall include full compensation for all labor, equipment, fees and materials necessary to complete the Work as shown and described in the Contract Documents.
A15 Trash Compactor Enclosure:
b. Payment shall include full compensation for all labor, equipment, materials and incidentals required to accomplish the Work as shown and
A16 Landscape – Restoration to Pre-construction State:
a. Measurement and payment for this bid item shall be made on lump sum
a. Work includes providing the labor, equipment, materials and incidentals needed to restore the site to pre-construction condition in conformance with the Contract Documents and as approved by the Project Manager.
A17 Installation of owner provided items:
basis required to install the owner-provided Double Arm Maintenance Gate, Parking Lot Signage and Kiosk Assembly.
b. Payment shall include full compensation for all labor, equipment, fees and materials necessary to complete the Work as shown and described in the Contract Documents.
B. BID ITEMS – BUILDING RELATED:
B1 Building Construction and Improvements:
b. Payment shall include full compensation for all labor, equipment, B2 Building Mechanical:
Section 01025 - 16
B3 Building Electrical:
C. BID ITEMS – ALTERNATE #1:
C1 Roadway Improvements to Well House Building
PART 2 – PRODUCTS (not applicable)
PART 3 – EXECUTION (not applicable)
Section 01028 - 17
MODIFICATION PROCEDURES
SECTION 01028 – MODIFICATION PROCEDURES
A. Section includes the administrative requirements for Requests for Information (“RFI”) and
Proposal Requests (“PR”).
B. Prior to execution of a Change Order (“CO”), the following documents shall be submitted as indicated.
1.02 REQUEST FOR INFORMATION
A. General:
1. RFI's are requests for information originated, prepared and submitted by the Contractor to the Project Manager only when the Contractor is unable to determine from the Contract Documents, the material, process, system or Work to be installed. Endeavor to keep the number of RFI’s to a minimum. For critical or emergency items, contact Project Manager at once.
2. If Project Manager clarification results in additional cost or time, do not proceed with the Work indicated by the RFI until the Project Manager provides an approved copy of the RFI or until a PR is fully-executed. A CO will be processed to include this type of change.
3. Submit RFI’s on form provided by Project Manager.
4. Number RFI's sequentially; include date submitted.
5. Identify Project, pertinent Plan sheet, detail number, and Specification Section.
6. Specifically identify time response information as required to avoid impact on construction schedule or cost. Project Manager will endeavor to respond to proper RFI’s within 7-Days, if possible.
B. RFI’s shall include written and graphic solutions proposed by Contractor. Project Manager will determine if Contractor’s proposal is in accordance with Contract Documents and design intent of Project.
1. Contractor's failure to make a reasonable effort to propose realistic solution may result in RFI's being returned with no action.
2. RFI's that request information that is clearly shown in the Contract Documents will be considered frivolous/improper and will be returned with no action.
C. Maintain current and accurate RFI Log.
Section 01028 - 18
MODIFICATION PROCEDURES
1.03 PROPOSAL REQUEST
1. Provide quotations for extra Work or changes in Work when requested by the
Project Manager, on a PR form to be provided by the Project Manager.
2. Provide a detailed itemization of the costs to the degree necessary for evaluation by the Project Manager. Indicate if a change to the Contract Period is warranted.
B. Maintain current and accurate Proposal Request log.
C. Issuance of a PR is not an authorization to proceed with extra or changed Work until fully executed by Owner and Contractor. Do not proceed with the Work indicated in the PR until the Project Manager provides a fully-executed copy. A CO will be processed to include approved Proposal Requests.
PART 2 – PRODUCTS (Not Used )
PART 3 – EXECUTION (Not Used)
Section 01062 - 19
PERMITS
SECTION 01062 – PERMITS
A. The Contractor shall be responsible to abide by permitting requirements as stated in the State of Oregon General Conditions for Public Improvement Contracts
1.02 PERMITS
A. See Supplemental General Conditions for Public Improvement Contract “Exhibit 7” in for supplemental or additional permit requirements.
B. Owner shall obtain and pay for:
1. Plan review fees from Klamath County
D. Contractor shall obtain and pay for all construction and trade permits from Klamath
County and/or local utility providers that are necessary complete the work.
PART 2 – PRODUCTS (Not Used)
Section 01062 - 20
PERMITS
Section 01090 - 21
REFERENCE STANDARDS
SECTION 01090 – REFERENCE STANDARDS
PART 1 – GENERAL
1.01 REFERENCED STANDARDS:
All Work shall conform to the issue of following referenced standards which is current at date of Contract Execution. Whenever the following abbreviations are used in these Contract Documents, they are to be construed the same as follows:
AA Aluminum Association AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute ACM American Construction Manual AISC American Institute of Steel Construction ANSI American National Standards Institute APA American Plywood Association APWA American Public Works Association ASHRAE American Society of Heating, Refrigerating and Air-Conditioning
Engineers ASCE American Society of Civil Engineers ASME American Society of Mechanical Engineers ASTM American Society for Testing and Materials AWPA American Wood Preservers' Association AWS American Welding Society AWWA American Water Works Association CRSI Concrete Reinforcing Steel Institute EPA Environmental Protection Agency FM Factory Mutual FS Federal Specifications (“FS”) ICEA. Insulated Cable Engineers Association IEEE Institute of Electrical and Electronic Engineers JIC Joint Industrial Council MIL Military Standards NEC National Electric Code (Oregon Amended) NECA National Electrical Contractors Association NEMA National Electrical Manufacturers Association NESC National Electrical Safety Code NFPA National Fire Protection Association NSF National Sanitation Foundation ODOT Oregon Standard Specifications for Highway Construction by the Oregon
Department of Transportation ODOT/APWA Oregon Standard Specifications for Construction by the Oregon
Department of Transportation and Oregon Chapter of APWA OSSC Oregon Structural Specialty Code OSHA Occupational Safety and Health Administration QPL Qualified Products Listing by the Oregon Department of Transportation, Materials and Research Section PCI MNL Pre-stressed Concrete Institute SAMA. Scientific Apparatus Manufactures Association SMACNA Sheet Metal and Air Conditioning Contractors' National Association UBC Uniform Building Code State of Oregon, Structural Specialty Code
Amended UFC Uniform Fire Code with State and Local Amendments
Section 01090 - 22
REFERENCE STANDARDS
UL Underwriters Laboratories UPC Uniform Plumbing Code State of Oregon, Plumbing Specialty Code WCLIB West Coast Lumber Inspection Bureau
Section 01300 - 23
PROJECT MANAGEMENT AND COORDINATION
SECTION 01300 – PROJECT MANAGEMENT & COORDINATION
1.01 SUMMARY
A. This section includes administrative provisions for coordinating construction operations on the Project.
1.02 PROJECT COORDINATION
A. Coordinate with the Project Manager to locate area for mobilization, field offices and sheds, vehicle access, traffic, and parking facilities.
B. Coordinate construction operations included in Contract Documents to avoid conflicts and assure efficient and orderly installation of each part of the Work.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of Work depends on installation of other components.
2. Coordinate installation of different components to assure maximum accessibility for required maintenance, service, and repair.
3. Coordinate storage or staging areas for all trades.
4. Locate and verify all utility service connection points. Coordinate actual location and depth of all utilities with utility connections. Modify designed location of points of connection to accommodate actual site locations.
5. Coordinate space requirements and installation of irrigation and/or electrical work depicted diagrammatically on Drawings. Follow routing shown for pipes and conduit as closely as practicable. Utilize spaces as efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
C. Coordinate testing and inspections by building officials and Owner’s testing and inspection services.
D. During construction, coordinate use of site and facilities through the Project Manager.
E. Comply with Project Manager procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.
F. Coordinate with Project Manager for use of temporary utilities.
G. The Contractor shall maintain Daily Reports documenting which subcontractors are on site, jobsite activities, materials deliveries, high/low temperatures and general weather conditions, meetings and significant decisions, visitors, accidents and unusual events, and other significant items. These Daily Reports shall be made available to the Project Manager upon request.
1.03 CONTRACTOR’S CONSTRUCTION SCHEDULE
Section 01300 - 24
PROJECT MANAGEMENT AND COORDINATION
A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart type, Contractor’s construction schedule within (15) days of date of Notice to Proceed.
Base schedule on the construction schedule in the Contract and additional information received since the start of the project.
B. The proposed construction schedule shall be in a critical path method format and shall be updated throughout the duration of the Project to reflect the progress of the Work.
1. Revise the schedule at monthly intervals to reflect actual construction progress and activities. Issue revised schedule with progress payment requests.
2. Revise the schedule immediately after each progress meeting or other activity where revisions have been recognized or discussed. Issue the revised schedule with the associated meeting notes.
1.04 PROJECT MEETINGS
A. General: Contractor is responsible for conducting meetings unless otherwise noted.
Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Project Manager of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Contractor shall record significant discussions and agreements achieved. Distribute the meeting minutes to attendees and concerned parties, including Project Manager, within three (3) days of the meeting.
B. Preconstruction Conference: Owner Project Manager will coordinate with Contractor to schedule and conduct a preconstruction conference before starting construction, at a time convenient to both parties, but no later than fifteen (15) days after Notice to Proceed.
1. Attendees: Authorized representatives of Owner, Project Manager, and their consultants; Contractor and its superintendent; major subcontractors; suppliers;
and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Designation of key personnel, their responsibilities and duties.
b. Lines of communication.
c. Procedures for processing Submittals, RFIs, Proposal Requests and
Change Orders.
d. Initial construction schedule.
e. Schedule and format for Progress Meetings.
f. Critical work phasing, sequencing, and long-lead items.
g. Procedures for testing and inspecting.
h. Working hours.
Section 01300 - 25
PROJECT MANAGEMENT AND COORDINATION
i. Parking availability, construction access and delivery routes.
j. Traffic control and public safety.
k. Security.
l. Permits and regulations of authorities having jurisdiction.
m. Procedures for processing Applications for Payment.
n. Owner's occupancy requirements.
o. Preparation of record documents.
C. Preinstallation Conferences: Contractor shall conduct a preinstallation conference for each construction activity that requires coordination between construction disciplines, and as specified in Contract Documents.
1. Attendees: Installer and representatives of subcontractors, manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting.
2. Schedule preinstallation conference a minimum of one week prior to commencing related work. Advise Project Manager of scheduled meeting dates.
3. Review conditions of installation, preparation, and installation procedures, coordination with related work, and protection of adjacent work.
4. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Contractor shall conduct progress meetings weekly or as discussed at preconstruction meeting.
1. Attendees: Project Manager and Contractor Superintendent, with representative subcontractors, suppliers, and other entities concerned with current progress or involved in planning, coordination, or performance of future activities. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda:
a. Review minutes of previous progress meeting.
b. Review field observations, problems, decisions, and corrective actions.
c. Review Contractor's Construction Schedule:
1) Review work progress since last meeting and planned progress during succeeding work period.
2) Review fabrication and delivery schedules.
3) Discuss whether schedule revisions are required to ensure that the Work will be completed within the Contract Time.
d. Review present and future needs of each entity present, including the following:
1) Sequence of operations.
2) Status of correction of deficient items.
3) Status of submittals.
4) Status of RFIs.
5) Status of Proposal Requests and Change Orders.
Section 01300 - 26
PROJECT MANAGEMENT AND COORDINATION
Section 01330 - 27
SUBMITTALS PROCEDURE
SECTION 01330 – SUBMITTALS PROCEDURE
A. This section specifies procedures for the technical submittals required in the Plans and Specifications.
NOTE:
1. The Contractor is responsible for making technical submittals as called for in the Plans and individual Specification Sections. The Contractor shall develop a submittal list within 14 Days after being issued the Notice To Proceed for Owner to review and approve. Contractor shall modify the submittal list as requested by Owner until approved.
2. During construction, if the Contractor installs products or materials which are not in conformance with the Plans and Specifications, that are not approved by the Owner through the submittal process, the Contractor will be required to remove such products or materials and replace with the specified product or material at no additional cost to the Owner.
B. Submittals shall contain information that will enable the Project Manager to assess whether the Contractor’s proposed materials, equipment or methods of work are in general conformance to the design intent and in compliance with the Plans and Specifications. The information may consist of product data, drawings, specifications, descriptive data, certificates, samples, mock-ups, test results and/or other information, as required in the individual Specification Sections and Plans.
1.02 CONTRACTOR RESPONSIBILITIES
A. Prior to submittal transmittal to the Project Manager,
1. Ensure the accuracy and completeness of the information contained in each submittal and that the material, equipment or method of work is as described in the submittal.
2. Ensure information is legible by the Owner. Faxed submittals are NOT acceptable.
3. Ensure that the information is transmitted and approved by Owner and as follows:
a. Prior to purchasing/leasing/ordering/installing
b. Early enough to allow a 7-day review period by the Owner, and to meet the construction schedule.
4. Verify the material and equipment described in each submittal conforms to the requirements of the Specifications and Plans.
Section 01330 - 28
5. Ensure there is no conflict with other submittals.
6. Notify the Project Manager in each case where such submittal may affect the Work of another contractor or Owner.
B. Substitutions:
1. “Or Approved Equal” Substitutions: Shall be considered during bidding for products requiring an approved equal, provided they are submitted within the time period allowed stated in the ITB and the substitution complies with the Technical Specifications herein. Obtain written approval from the Project Manager, prior to bidding, by submitting the Substitution Request Form to the Single Point of Contact (located in the ITB document).
2. “Or Equal” or “Basis of Design” Substitutions: May be considered by the Project
Manager during construction through the Submittal process.
a. Manufacturers and products listed in the Contract Documents establish minimum requirements for appearance, quality, utility, durability, function, and purpose, and are all considered to have the designation “or equal” associated with the manufacturer or product.
b. Substitutions Submittals should include complete data substantiating compliance of proposed substitution with Contract Documents.
C. Refer to the Contract Documents and State of Oregon General Conditions for additional information regarding submittals and substitutions.
PART 2 – PRODUCTS (not applicable)
PART 3 – EXECUTION
3.01 TRANSMITTAL PROCEDURE
1. For each required submittal, submit two (2) copies of all required information not less than fourteen (14) Days prior to purchase or installation (if previously purchased). One copy will be returned to the Contractor. Individual sheets shall not exceed 22 inches x 34 inches. NOTE: SUBMITTALS MAY BE MADE
ELECTRONICALLY VIA EMAIL WITH PDF ATTACHMENT(S) AS
APPROVED BY PROJECT MANAGER.
2. Use a Submittal/Transmittal Form for material and equipment submittals. Use a separate form for items specified in separate, discrete sections for which the submittal is required. Use a single form for submittals for various items when the items taken together constitute a manufacturer’s package, or are related such that expediency indicates review of the package as a whole.
3. Note the unique sequentially assigned number that will accompany each item submitted, on the transmittal form. Original submittal numbers shall have the format: “XXX”; where “XXX” is the sequential number assigned by the Contractor. Resubmittals shall have the format: “XXX-Y”; where “XXX” is the originally assigned submittal number and “Y” is a sequential letter assigned for resubmittals, i.e., A, B or C being the 1st, 2nd and 3rd resubmittals, respectively.
Section 01330 - 29
B. Deviation from Contract: Submit a request for substitution for deviations from the
Specifications or Plans. Include the reason for the deviation and cost differential for the deviation. Deviations from the Contract shall be authorized by Change Order only.
C. Submittal Completeness: submittals that do not have all the information required to be submitted are not acceptable and will be returned without review.
D. Project Manager reserves the right to ask for submittals not referenced in this document.
3.02 REVIEW PROCEDURE
A. The Project Manager will review the submittal and return it to the Contractor. The returned material will consist of one (1) marked-up copy of the submittal. The returned submittal will indicate one of the following actions:
1. If the review indicates the material, equipment or work method is in general conformance with the Plans/Specifications, the submittal copies shall be marked “Approved.” In this event, the Contractor may begin to incorporate the material/equipment/work method covered in the submittal.
2. If the review indicates the submittal is insufficient or that limited corrections are required, the submittal copies may be marked “Approved as Noted.” The Contractor may begin to implement the work method or incorporate materials/comments covered in the submittal in accordance with the corrections/comments noted.
3. If the review reveals the submittal is insufficient or contains incorrect data and the comments require revision and resubmittal, the submittal copies shall be marked “Not Approved, Resubmit.” In this case, the Contractor shall not undertake Work covered by this submittal until the submittal has been revised, resubmitted and returned to the Contractor with a marking of “Approved” or “Approved as Noted.”
4. If the review reveals the material, equipment, or Work does not require submittal, then the submitted copies shall be marked “Review Not Required Per Contract Documents.” In this event, the Contractor may begin to incorporate the material/equipment/Work covered by the submittal and no further action is required.
3.03 EFFECT OF REVIEW OF CONTRACTOR’S SUBMITTALS
A. Submittal review of what the Contractor proposes to provide shall not relieve the Contractor of his responsibility for errors therein, nor shall it be regarded as an assumption of risks or liability by the Owner, or by any officer or employee of the Owner. Contractor shall have no claim under the Contract on account of the failure, or partial failure, of the method of work, material or equipment so reviewed. A mark of “Approved” or “Approved as Noted” shall mean the Project Manager has no objection to the Contractor, upon the Contractor’s own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.
Section 01330 - 30
SUBSTITUTION REQUEST FORM
TO _________________________________________________________________________________
PROJECT ___________________________________________________________________________
We hereby submit for your consideration the following product instead of the specified item for the above Project
Section _________________ Paragraph ____________________ Specified Item ___________________
Proposed Substitution:
Attach complete technical data, including laboratory tests, if…
This is the start of the file's text. The full file is on GovTribe.