Exhibit B Rev 1 - SOW updated 3-31-26 -Lab C.docx
DOCX document 57 KB Posted
- Attached to
- Lab A Electric Heat Install
- Solicitation number
- ISD-378581-RO
About this file
This is a Statement of Work (SOW) for the electrification of heating systems, upgrading electrical infrastructure, and installing controls at Fermi National Accelerator Laboratory's Neutrino Lab A facilities. The project encompasses two locations (NLA and NLA-B) and requires a complete, turn-key HVAC system installation managed by a single prime contractor. The work includes mobilization, hazardous energy control (LOTO) with zero-voltage verification, demolition of existing water and boiler lines, installation of electric baseboard and hanging heaters (INDEECO or approved equivalent), electrical panels, breakers, transformers, and all associated conduit and conductors. Controls integration is mandated to Intelli-Building Controls LLC per cybersecurity protocols, with the prime contractor responsible for supplying all control-related wiring, thermostats, and hardware integration. The project is located in DuPage and Kane Counties in Illinois and includes final commissioning, system verification, O&M manual submission, and site decontamination.
The estimated schedule spans from March 4, 2026 to October 30, 2026, with key milestones including Notice to Proceed at day 0, hazard analysis and cost-loaded schedule submission by day 10, product submittals and shop drawings by day 31, construction completion by day 181, punch-list completion by day 211, and final closeout documentation by day 241. Bid submissions must include a sectional breakdown with clear cost analysis, a cost-loaded Critical Path Method (CPM) schedule with costs assigned at the individual task level, and location-specific pricing and scheduling data. This is a small business set-aside under NAICS code 238220 (Plumbing, Heating and Air-Conditioning Contractors) with a small business size standard of $19.0 million, and a pre-proposal meeting is scheduled for April 2, 2026 at 9:30 AM.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work 01.06.2025 Infrastructure Services Division Fall
SOW DATE: 3/4/2026
PROJECT TITLE: R311975/R311976/ NLA/NLA-B Electrification of heating system, upgrading electrical, and controls.
PROJECT: 60 TASK: 60.03.14.16.02
FermiForward POINT OF CONTACT: Joseph M. Perona x4772 41904N COUNTY THAT WORK WILL BE COMPLETED IN: DuPage☒ Kane☐ Fermilab County Line
INTRODUCTION
PROJECT OVERVIEW
The Contractor shall provide all supervision, labor, materials, and equipment required to deliver a complete and fully operational HVAC system. This turn-key project shall comply with the attached Construction Documents, with the scope encompassing all transportation, bonding, safety management, and quality control.
BID SUBMISSION REQUIREMENTS
To ensure a comprehensive evaluation, all bids must be submitted according to the following criteria:
· Sectional Breakdown: Proposals must be broken down into clear, logical sections as defined in the bid forms to allow for detailed cost analysis.
· Cost-Loaded Schedule: The Contractor shall provide a cost-loaded CPM (Critical Path Method) schedule, with costs assigned to each activity at the individual task level.
· Location-Specific Pricing: All scheduling and cost data must be further broken down per location, ensuring that resource allocation and milestone tracking are transparent for each specific site within the project.
SCOPE OF WORK
(Two Locations)
PHASE 1: NEUTRINO LAB A (NLA) – Fims#600 (ID#311975)
1. MOBILIZATION & PRE-OPERATIONAL REQUIREMENTS
· 1.1 Site Mobilization: Mobilize to Neutrino Lab A (NLA).
· 1.2 Hazardous Energy Control (LOTO): Execute LOTO on all electrical and fluid systems.
· a. Perform and document a certified "Zero-Voltage" verification.
· b. Audit and verify all provided panel schedules; report inaccuracies to TM/CC prior to commencement.
2. DEMOLITION & SITE REMEDIATION
· 2.1 System Demolition: Demolish existing water lines and baseboard boiler lines.
· a. Reference attached drawings for structural and estimation data.
· b. Coordinate debris removal via TM/CC-provided metal dumpsters.
· 2.2 Site Remediation: Restore work area to a "ready state" for new installation.
· a. Clear 100% of debris; remove all abandoned bolts, anchors, and supports from walls/floors.
3. MECHANICAL & ELECTRICAL INSTALLATION
· 3.1 Equipment Furnishing: Supply and install electric baseboard and hanging heaters (INDEECO or approved equivalent).
· a. Supply and install all electrical panels, breakers, and transformers as specified in the project drawings.
· 3.2 Installation Standards:
· a. Install all hanging/support apparatus strictly per manufacturer specifications.
· b. Size and install conduit, conductors, and breakers according to the manufacturer’s MOCP.
4. CONTROLS & CYBERSECURITY INTEGRATION
· 4.1 Mandated Subcontracting: Controls subcontract is mandated to Intelli-Building Controls LLC per lab cybersecurity protocols.
· 4.2 Contractor Responsibilities:
· a. Supply all control-related wiring, thermostats, and hardware.
· b. Ensure full configuration/integration with existing lab infrastructure.
5. COMMISSIONING & PHASE 1 CLOSEOUT
· 5.1 Verification: Perform final inspection and individual system checks on all new units.
· 5.2 Paperwork: Submit all O&M manuals and project paperwork to TM/CC.
· 5.3 Decontamination: Execute final site cleaning and project walkthrough for NLA.
PHASE 2: NEUTRINO LAB A (NLA-B) – Fims#601 (ID#311976)
6. MOBILIZATION & PRE-OPERATIONAL REQUIREMENTS
· 6.1 Site Mobilization: Mobilize to Neutrino Lab A-B (NLA-B).
· 6.2 Hazardous Energy Control (LOTO): Execute LOTO on all electrical and fluid systems.
· a. Perform and document a certified "Zero-Voltage" verification.
· b. Audit and verify all provided panel schedules; report inaccuracies to TM/CC.
7. DEMOLITION & SITE REMEDIATION
· 7.1 System Demolition: Demolish existing water lines and baseboard boiler lines per attached drawings.
· 7.2 Site Remediation: Restore work area to a "ready state."
· a. Remove all abandoned hardware (bolts/anchors) from surfaces to ensure a clean workspace.
8. MECHANICAL & ELECTRICAL INSTALLATION
· 8.1 Equipment Furnishing: Supply and install electric baseboard heaters (INDEECO or approved equivalent).
· a. Supply and install all electrical panels, breakers, and transformers as specified in the project drawings.
· 8.2 Installation Standards:
· a. Install all support apparatus and electrical components (conduit, conductors, breakers) to manufacturer MOCP and specifications.
9. CONTROLS & CYBERSECURITY INTEGRATION
· 9.1 Mandated Subcontracting: Controls subcontract is mandated to Intelli-Building Controls LLC.
· 9.2 Contractor Responsibilities:
· a. Supply all control-related wiring, thermostats, and hardware.
· b. Ensure full configuration and integration with existing lab infrastructure.
10. COMMISSIONING & FINAL DEMOBILIZATION
· 10.1 Systems Verification: Perform final inspections and system checks on all units.
· 10.2 Final Closeout: Submit O&M manuals, perform final site decontamination/cleaning, and complete the final project walkthrough.
Schedule The following table lists each deliverable milestone and FFDG’s expectation of scheduled calendar days for each phase. Calendar days are listed from the project's start date. Values in parentheses are calendar days from completion of the previously listed entry.
| Milestone |
| Calendar Days |
| Description |
| 1 |
| 0 |
(+0) Notice to Proceed (NTP). This Milestone marks the point when construction work may begin.
| 2 |
| 10 |
(+10) Hazard Analysis, Bid Bond, and Cost-loaded schedule (Per location).
| 3 |
| 31 |
(+21) All product submittals and shop drawings have been submitted and reviewed.
| 4 |
| 181 |
(+150) Construction is complete with punch-list items remaining.
| 5 |
| 211 |
(+30) Punch-list items complete.
| 6 |
| 241 |
(+30) Closeout documentation submitted. Final invoices and retainage paid. Project complete.
GOVERNMENT FURNISHED PROPERTY
N/A
PLACE OF PERFORMANCE
Fermi National Accelerator Laboratory (Fermilab) NLA/NLA-B, Batavia, IL 60510.
ESTIMATED SCHEDULE/PERIOD OF PERFORMANCE
EST START DATE: 3/4/2026 EST END DATE: 10/30/2026