Amendment 02 RFP ISD-378581-RO.pdf

PDF 121 KB Posted

Attached to
Lab A Electric Heat Install
Solicitation number
ISD-378581-RO
Issued by

About this file

This is Amendment No. 2 to RFP ISD-378581-RO issued by Fermi Forward Discovery Group, LLC for the "Lab A electric heat install" project. The amendment was issued on April 13, 2026, with an original RFP issuance date of March 26, 2026, and maintains the proposal due date of 4:00 PM CT on April 16, 2026.

The amendment provides clarifications to two questions submitted by offerors regarding the project specifications. First, regarding control installation methods, the contracting officer confirmed that control lines may be installed "free-air" through rings at the ceiling with EMT stubs, rather than requiring EMT throughout the system, provided that the wire is duct-rated. Second, the amendment clarifies that the contractor is responsible for supplying the breaker for transformer TR-NL-5. All other terms and conditions of the original solicitation remain unchanged. Offerors must acknowledge receipt of this amendment by signature and return one copy with their qualifications submission. The contracting officer is Ryan O'Sullivan, Procurement Specialist II, reachable at (630) 840-2402 or ryanosul@fnal.gov, with the contracting office located at Fermi Forward Discovery Group, LLC in Batavia, Illinois.

View the file

Other files

File Type Posted
Exhibit B Rev 1 - SOW updated 3-31-26 -Lab C.docx DOCX document
Exhibit A Rev 1 - Drawings Lab C redacted JP 3-31-26.pdf PDF
Exhibit C Rev 1 - 010010 3-31-26 Updated JP.pdf PDF
Amendment 01 RFP ISD-378581-RO.pdf PDF
Exhibit T - Proposal Form ISD-371462-RO Cross Gallery Southwest Annex Refresh Project.pdf PDF
Exhibit D - 010010 - General Requirements.pdf PDF
Exhibit J - Bond Bid FL-41.pdf PDF
Exhibit K - Bond Payment FL-42.pdf PDF
Exhibit R - Davis Bacon Wage Rates General Decision IL20260008 Mod 1.txt TXT text file
Exhibit F - 013300_Submittals_FermiForward.pdf PDF
Exhibit M - SF1413.pdf PDF
Exhibit O - Construction Environmental Safety Health Certification.pdf PDF
Exhibit A - SOW.pdf PDF
Exhibit B - Drawings.pdf PDF
Exhibit C - SECTION_230529_-_HANGERS_AND_SUPPORTS_FOR_HVAC_PIPING_AND_EQUIPMENT.pdf PDF
Exhibit E - 013100_ESH_Requirements.pdf PDF
Exhibit I - 2025 Construction Insurance Requirements.pdf PDF
Exhibit L - Bond Performance FL-40.pdf PDF
Exhibit N - Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit P - SARC_Subcontractor Annual RepsCerts.pdf PDF
1.0 RFP ISD-378581-RO.pdf PDF
Exhibit G - 014100_Quality_Requirements.pdf PDF
Exhibit H - FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit Q - PUR-466_Proposal Certifications.pdf PDF
Exhibit S - Sample Subcontract.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT TO SOLICITATION

AMENDMENT NO.

DATE OF AMENDMENT:

April 013, 2026

SOLICITATION NO.

ISD-378581-RO

DATE RFP ISSUED:

March 26, 2026

PROJECT NO.

PROPOSAL DUE DATE:

4:00 PM CT on April 16, 2026

TITLE OF PROJECT:

Lab A electric heat install

Offerors must acknowledge this Amendment prior to the hour and date set forth in the solicitation by the following method:

1. Return the Amendment with a signature on the acknowledgment signature line.

If by virtue of this Amendment you desire to change an offer already submitted, such change may be made by email making reference to the Solicitation and this Amendment and it is received prior to the due date and time set for proposals.

The above referenced Solicitation is amended as follows:

- This Amendment to the RFP ISD-378581-RO is being issued to provide responses (in red) to the questions submitted:

1. Can the controls be installed free-air at the ceiling? With EMT stubs to ceiling? Or is the system required to be EMT throughout? Yes the lines can be “free-air” ran through rings. I would like the wire to be duct rated though.

2. Who is to supply breaker for transformer TR-NL-5? The contractor would need to supply.

All other terms and conditions as referenced remain unchanged.

Kindly acknowledge receipt by signing and returning one (1) copy of this Amendment with your qualification’s submission.

Company Name

Signature & Date

Name & Title of Individual

Fermi Forward Discovery Group, LLC Kirk Road & Wilson St.

P.O. Box 500, MS 312

Batavia, Illinois 60510-0500 USA

Ryan O’Sullivan Procurement Specialist II

(630) 840-2402 ryanosul@fnal.gov mailto:ryanosul@fnal.gov

File details come from the government source that posted it. Updated .