Statement of Work Summary
This is a Statement of Work (SOW) for an HVAC system electrification and controls upgrade project at Fermi National Accelerator Laboratory in Batavia, Illinois. The project encompasses three locations: Neutrino Lab A (NLA, ID#311975), Neutrino Lab A-B (NLA-B, ID#311976), and Neutrino Lab C (NLC, ID#311977). The contractor must provide all supervision, labor, materials, equipment, transportation, bonding, safety management, and quality control to deliver a complete, fully operational HVAC system as a turnkey project. The estimated period of performance runs from March 4, 2026, to October 30, 2026.
The scope of work for all three locations includes: mobilization and pre-operational requirements with Lockout/Tagout (LOTO) procedures and 0-Volt verification; demolition of existing water lines and baseboard boiler lines with site remediation to a "ready state"; furnishing and installing new heating units (electric baseboard and hanging heaters for NLA and NLA-B, and electric destratification fans for NLC) with INDEECO or approved equivalent manufacturers; structural and electrical installation per manufacturer specifications; controls and cybersecurity integration with a mandated subcontract to Intelli-Building Controls LLC; and commissioning, closeout, and demobilization including final inspections, O&M manual submission, site decontamination, and project walk-through. Bidders must submit proposals with sectional breakdown, cost-loaded Critical Path Method schedules with individual task-level costs, and location-specific pricing for each of the three sites. The project schedule establishes six key milestones from Notice to Proceed through final closeout documentation, spanning 241 calendar days total.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW TEMPLATE 04.24.2023
SOW DATE: 3/4/2026
PROJECT TITLE: R311975/R311976/R311977 NLA/NLA-B/NLC Electrification of heating system, upgrading electrical, and controls.
PROJECT: 60 TASK: 60.03.14.16.02
FermiForward POINT OF CONTACT: Joseph M. Perona x4772 41904N COUNTY THAT WORK WILL BE COMPLETED IN: DuPage☒ Kane☐ Fermilab County Line
INTRODUCTION
PROJECT OVERVIEW
The Contractor shall provide all supervision, labor, materials, and equipment required to deliver a complete and fully operational HVAC system. This turn-key project shall comply with the attached Construction Documents, with the scope encompassing all transportation, bonding, safety management, and quality control.
BID SUBMISSION REQUIREMENTS
To ensure a comprehensive evaluation, all bids must be submitted according to the following criteria:
• Sectional Breakdown: Proposals must be broken down into clear, logical sections as defined in the bid forms to allow for detailed cost analysis.
• Cost-Loaded Schedule: The Contractor shall provide a cost-loaded CPM (Critical Path Method) schedule, with costs assigned to each activity at the individual task level.
• Location-Specific Pricing: All scheduling and cost data must be further broken down per location, ensuring that resource allocation and milestone tracking are transparent for each specific site within the project.
SCOPE OF WORK
(Three Locations)
1) MOBILIZATION AND PRE-OPERATIONAL REQUIREMENTS
1.1. Mobilize to Neutrino Lab A (NLA), Fims#600 (ID#311975).
1.2. Execute Hazardous Energy Control (LOTO) on all electrical and fluid systems.
a. Perform and document a certified 0-Volt verification.
b. Audit and verify all provided panel schedules; report inaccuracies to TM/CC (Task Manager/Construction Coordinator) prior to commencement.
2) DEMOLITION AND SITE REMEDIATION
2.1. Demolish existing water lines and baseboard boiler lines.
a. Reference attached drawings for structural and estimation data.
b. Coordinate debris removal with TM/CC-provided metal dumpsters.
2.2. Remediate work area to a "ready state" for new installation.
a. Ensure the workspace is 100% clear of debris.
b. Remove all abandoned bolts, anchors, and supports from walls and floors.
3) MECHANICAL AND ELECTRICAL INSTALLATION
3.1. Furnish and install new heating units.
a. Install electric baseboard and hanging heaters per attached drawings.
b. Acceptable manufacturer: INDEECO or approved equivalent.
Statement of Work 01.06.2025 Infrastructure Services Division https://fermipoint.fnal.gov/org/os/FESS/web_docs/Shared%20Documents/Fermilab%20-%20with%20County%20Lines-compressed.pdf
3.2. Structural and Electrical standards.
a. Install all hanging/support apparatus strictly per manufacturer specifications.
b. Install conduit, conductors, and breakers sized to the manufacturer’s MOCP (Minimum Overcurrent Protection).
4) CONTROLS AND CYBERSECURITY INTEGRATION
4.1. Specialized Subcontracting.
a. Due to laboratory cybersecurity protocols, the controls subcontract is mandated to Intelli-Building Controls LLC.
4.2. Contractor Supply Requirements.
a. Supply all control-related wiring, thermostats, and hardware.
b. Ensure full configuration and integration with existing lab infrastructure.
5) COMMISSIONING, CLOSEOUT, AND DEMOBILIZATION
5.1. Systems Verification.
a. Perform final inspection and individual system checks on all new units.
b. Submit all O&M (Operating and Maintenance) manuals and project paperwork to TM/CC.
5.2. Final Demobilization.
a. Execute final site decontamination and cleaning.
b. Final project walk-through and site exit.
6) MOBILIZATION AND PRE-OPERATIONAL REQUIREMENTS
1.1. Mobilize to Neutrino Lab A (NLA-B), Fims#601 (ID#311976).
1.2. Execute Hazardous Energy Control (LOTO) on all electrical and fluid systems.
a. Perform and document a certified 0-Volt verification.
b. Audit and verify all provided panel schedules; report inaccuracies to TM/CC prior to commencement.
7) DEMOLITION AND SITE REMEDIATION
2.1. Demolish existing water lines and baseboard boiler lines.
a. Reference attached drawings for structural and estimation data.
b. Coordinate debris removal with TM/CC-provided metal dumpsters.
2.2. Remediate work area to a "ready state" for new installation.
a. Ensure the workspace is 100% clear of debris.
b. Remove all abandoned bolts, anchors, and supports from walls and floors.
8) MECHANICAL AND ELECTRICAL INSTALLATION
3.1. Furnish and install new heating units.
a. Install electric baseboards per attached drawings.
b. Acceptable manufacturer: INDEECO or approved equivalent.
3.2. Structural and Electrical standards.
a. Install all hanging/support apparatus strictly per manufacturer specifications.
b. Install conduit, conductors, and breakers sized to the manufacturer’s MOCP.
9) CONTROLS AND CYBERSECURITY INTEGRATION
4.1. Specialized Subcontracting.
a. Due to laboratory cybersecurity protocols, the controls subcontract is mandated to Intelli-Building Controls LLC.
4.2. Contractor Supply Requirements.
a. Supply all control-related wiring, thermostats, and hardware.
b. Ensure full configuration and integration with existing lab infrastructure.
10) COMMISSIONING, CLOSEOUT, AND DEMOBILIZATION
5.1. Systems Verification.
a. Perform final inspection and individual system checks on all new units.
b. Submit all O&M manuals and project paperwork to TM/CC.
5.2. Final Demobilization.
a. Execute final site decontamination and cleaning.
b. Final project walk-through and site exit.
11) MOBILIZATION AND PRE-OPERATIONAL REQUIREMENTS
1.1. Mobilize to Neutrino Lab C (NLC), Fims#604 (ID#311977).
1.2. Execute Hazardous Energy Control (LOTO) on all electrical and fluid systems.
a. Perform and document a certified 0-Volt verification.
b. Audit and verify all provided panel schedules; report inaccuracies to TM/CC prior to commencement.
12) MECHANICAL AND ELECTRICAL INSTALLATION
3.1. Furnish and install new fan units.
a. Install electric destratification fan per attached drawings.
b. Acceptable manufacturer: INDEECO or approved equivalent.
3.2. Structural and Electrical standards.
a. Install all hanging/support apparatus strictly per manufacturer specifications.
b. Install conduit, conductors, and breakers sized to the manufacturer’s MOCP.
13) CONTROLS AND CYBERSECURITY INTEGRATION
4.1. Specialized Subcontracting.
a. Due to laboratory cybersecurity protocols, the controls subcontract is mandated to Intelli-Building Controls LLC.
4.2. Contractor Supply Requirements.
a. Supply all control-related wiring, thermostats, and hardware.
b. Ensure full configuration and integration with existing lab infrastructure.
14) COMMISSIONING, CLOSEOUT, AND DEMOBILIZATION
5.1. Systems Verification.
a. Perform final inspection and individual system checks on all new units.
b. Submit all O&M manuals and project paperwork to TM/CC.
5.2. Final Demobilization.
a. Execute final site decontamination and cleaning.
b. Final project walk-through and site exit.
Schedule
The following table lists each deliverable milestone and FFDG’s expectation of scheduled calendar days for each phase. Calendar days are listed from the project's start date. Values in parentheses are calendar days from completion of the previously listed entry.
Milestone Calendar Days
Description
1 0 (+0)
Notice to Proceed (NTP). This Milestone marks the point when construction work may begin.
2 10 (+10)
Hazard Analysis, Bid Bond, and Cost-loaded schedule (Per location).
3 31 (+21)
All product submittals and shop drawings have been submitted and reviewed.
4 181 (+150)
Construction is complete with punch-list items remaining.
5 211 (+30)
Punch-list items complete.
6 241 (+30)
Closeout documentation submitted. Final invoices and retainage paid.
Project complete.
GOVERNMENT FURNISHED PROPERTY
N/A
PLACE OF PERFORMANCE
Fermi National Accelerator Laboratory (Fermilab) NLA/NLA-B/NLC, Batavia, IL 60510.
ESTIMATED SCHEDULE/PERIOD OF PERFORMANCE
EST START DATE: 3/4/2026 EST END DATE: 10/30/2026
Additional justification for hard stop / start dates
N/A