This document is a U.S. Department of Housing and Urban Development (HUD) form HUD-5369, providing standard Instructions to Bidders for Public and Indian Housing Programs contracts. The instructions cover comprehensive bidding procedures for a specific project involving tub and shower surround installations at 30 apartments located at 355, 2742, and 2757 Phyllis Circle in Billings, Montana. The document outlines detailed requirements for bid preparation, submission, modifications, bid guarantees, and contract award processes, with specific guidelines for contractors interested in performing renovation work on these residential units.

The instructions mandate that bidders must submit a negotiable bid guarantee of at least 5% of the total bid amount, which can be in the form of a certified check, bank draft, U.S. Government Bonds, or a bid bond from a surety company. The contract award will be made to the responsible bidder whose bid is most advantageous to the Housing Authority of Billings, considering price and price-related factors. Successful bidders will be required to provide an assurance of completion, which may include a performance and payment bond, cash escrow, or an irrevocable letter of credit. The document also specifies that a preconstruction conference will be held after contract award to discuss contract requirements and operational details.

View the file

Other files

File Type Posted
(HUD-5372) Construction Progress Schedule.pdf PDF
(HUD-92010) EEOC.pdf PDF
Advertisement.pdf PDF
Article 50 SupplementaryConditions.pdf PDF
Bidder statements 5369-a.pdf PDF
G704-2017 - Certificate of Substantial Completion.pdf PDF
Request for Approval of Substitutions.pdf PDF
Section 3 60002A.pdf PDF
Signature sheet.pdf PDF
(HUD-51002) Schedule of C.O.s.pdf PDF
(HUD-51003) Schedule of Materials Stored.pdf PDF
2328 - HomeFront Tub Surrounds Addendum No 1.pdf PDF
Attachment D (Section 3 Clause).pdf PDF
Disclosure of Lobbying Activites (SF-LLL).pdf PDF
G706-1994 - Contractor_s Affidavit of Payment of Debts and Claims.pdf PDF
Low-income Resident Hiring Plan - Contract.pdf PDF
NoticeToProceed.pdf PDF
SpecialCond.pdf PDF
(HUD-50071) Cert. of Payments.pdf PDF
(HUD-51000) Sched. of Payments.pdf PDF
(HUD-51001) Periodic Payments.pdf PDF
(HUD-5370) General Conditions.pdf PDF
(HUD-92554M) Supplementary Conditions.pdf PDF
(Supplemental Conditions to HUD-5370).pdf PDF
G706A-1994 - Contractor_s Affidavit of Release of Liens.pdf PDF
G707-1994 - Consent Of Surety to Final Payment.pdf PDF
Release and waiver.pdf PDF
TUB SURROUNDS Bid Set.pdf PDF
(HUD-11) Record of Employee Interview.pdf PDF
(HUD-2554) Supplementary Conditions.pdf PDF
(HUD-51004) Schedule of materials.pdf PDF
Agreement for storage.pdf PDF
Bid Form.pdf PDF
DB 01-2023.pdf PDF
Davis Bacon Standards HUD-4010.pdf PDF
IFB 8.1.1 - Attachment G-1.1 (Supplemental Conditions to HUD-5370).pdf PDF
Spec Cover.pdf PDF
TABLE OF CONTENTS.pdf PDF
bid - hab non collusive affidavit.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Previous edition is obsolete form HUD-5369 (10/2002)

Instructions to Bidders for Contracts Public and Indian Housing Programs

U.S. Department of Housing and Urban Development Office of Public and Indian Housing

Instructions to Bidders for Contracts Public and Indian Housing Programs

Table of Contents Clause Page

1. Bid Preparation and Submission 1

2. Explanations and Interpretations to Prospective Bidders 1

3. Amendments to Invitations for Bids 1

4. Responsibility of Prospective Contractor 1

5. Late Submissions, Modifications, and Withdrawal of Bids 1

6. Bid Opening

7. Service of Protest

8. Contract Award

9. Bid Guarantee

10. Assurance of Completion

11. Preconstruction Conference

1. Bid Preparation and Submission

(a) Bidders are expected to examine the specifications, drawings, all instructions, and, if applicable, the construction site (see also the contract clause entitled Site Investigation and Conditions Affect-ing the Work of the General Conditions of the Contract for Construc-tion). Failure to do so will be at the bidders’ risk.

(b) All bids must be submitted on the forms provided by the Public Housing Agency/Indian Housing Authority (PHA/IHA). Bidders shall furnish all the information required by the solicitation. Bids must be signed and the bidder’s name typed or printed on the bid sheet and each continuation sheet which requires the entry of information by the bidder. Erasures or other changes must be initialed by the person signing the bid. Bids signed by an agent shall be accompanied by evidence of that agent’s authority. (Bidders should retain a copy of their bid for their records.)

(c) Bidders must submit as part of their bid a completed form HUD- 5369-A, “Representations, Certifications, and Other Statements of Bidders.”

(d) All bid documents shall be sealed in an envelope which shall be clearly marked with the words “Bid Documents,” the Invitation for Bids (IFB) number, any project or other identifying number, the bidder’s name, and the date and time for receipt of bids.

(e) If this solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words “No Bid” in the space provided for any item on which no price is submitted.

(f) Unless expressly authorized elsewhere in this solicitation, alter-nate bids will not be considered.

(g) Unless expressly authorized elsewhere in this solicitation, bids submitted by telegraph or facsimile (fax) machines will not be considered.

(h) If the proposed contract is for a Mutual Help project (as de-scribed in 24 CFR Part 905, Subpart E) that involves Mutual Help contributions of work, material, or equipment, supplemental informa-tion regarding the bid advertisement is provided as an attachment to this solicitation.

2. Explanations and Interpretations to Prospective Bidders

(a) Any prospective bidder desiring an explanation or interpretation of the solicitation, specifications, drawings, etc., must request it at least 7 days before the scheduled time for bid opening. Requests may be oral or written. Oral requests must be confirmed in writing.

The only oral clarifications that will be provided will be those clearly related to solicitation procedures, i.e., not substantive technical information. No other oral explanation or interpretation will be provided. Any information given a prospective bidder concerning this solicitation will be furnished promptly to all other prospective bidders as a written amendment to the solicitation, if that information is necessary in submitting bids, or if the lack of it would be prejudicial to other prospective bidders.

(b) Any information obtained by, or provided to, a bidder other than by formal amendment to the solicitation shall not constitute a change to the solicitation.

3. Amendments to Invitations for Bids

(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.

(b) Bidders shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the amendment, (2) by identifying the amendment number and date on the bid form, or (3) by letter, telegram, or facsimile, if those methods are authorized in the solicitation. The PHA/IHA must receive acknowledgement by the time and at the place specified for receipt of bids. Bids which fail to acknowledge the bidder’s receipt of any amendment will result in the rejection of the bid if the amendment(s) contained information which substantively changed the PHA’s/IHA’s requirements.

(c) Amendments will be on file in the offices of the PHA/IHA and the Architect at least 7 days before bid opening.

4. Responsibility of Prospective Contractor

(a) The PHA/IHA will award contracts only to responsible prospec-tive contractors who have the ability to perform successfully under the terms and conditions of the proposed contract. In determining the responsibility of a bidder, the PHA/IHA will consider such matters as the bidder’s:

(1) Integrity;

(2) Compliance with public policy;

(3) Record of past performance; and

(4) Financial and technical resources (including construction and technical equipment).

(b) Before a bid is considered for award, the bidder may be re-quested by the PHA/IHA to submit a statement or other documenta-tion regarding any of the items in paragraph (a) above. Failure by the bidder to provide such additional information shall render the bidder nonresponsible and ineligible for award.

5. Late Submissions, Modifications, and Withdrawal of Bids

(a) Any bid received at the place designated in the solicitation after the exact time specified for receipt will not be considered unless it is received before award is made and it:

(1) Was sent by registered or certified mail not later than the fifth calendar day before the date specified for receipt of offers (e.g., an offer submitted in response to a solicitation requiring receipt of offers by the 20th of the month must have been mailed by the 15th);

(2) Was sent by mail, or if authorized by the solicitation, was sent by telegram or via facsimile, and it is determined by the PHA/IHA that the late receipt was due solely to mishandling by the PHA/IHA after receipt at the PHA/IHA; or

(3) Was sent by U.S. Postal Service Express Mail Next Day Service - Post Office to Addressee, not later than 5:00 p.m. at the place of mailing two working days prior to the date specified for receipt of proposals. The term “working days” excludes weekends and observed holidays.

(b) Any modification or withdrawal of a bid is subject to the same conditions as in paragraph (a) of this provision.

(c) The only acceptable evidence to establish the date of mailing of a late bid, modification, or withdrawal sent either by registered or certified mail is the U.S. or Canadian Postal Service postmark both on the envelope or wrapper and on the original receipt from the U.S.

or Canadian Postal Service. Both postmarks must show a legible date or the bid, modification, or withdrawal shall be processed as if mailed late. “Postmark” means a printed, stamped, or otherwise placed impression (exclusive of a postage meter machine impres-sion) that is readily identifiable without further action as having been supplied and affixed by employees of the U.S. or Canadian Postal Service on the date of mailing. Therefore, bidders should request the postal clerk to place a hand cancellation bull’s-eye postmark on both the receipt and the envelope or wrapper.

(d) The only acceptable evidence to establish the time of receipt at the PHA/IHA is the time/date stamp of PHA/IHA on the proposal wrapper or other documentary evidence of receipt maintained by the PHA/IHA.

(e) The only acceptable evidence to establish the date of mailing of a late bid, modification, or withdrawal sent by Express Mail Next Day Service-Post Office to Addressee is the date entered by the post office receiving clerk on the “Express Mail Next Day Service-Post Office to Addressee” label and the postmark on both the envelope or wrapper and on the original receipt from the U.S. Postal Service.

“Postmark” has the same meaning as defined in paragraph (c) of this provision, excluding postmarks of the Canadian Postal Service.

Therefore, bidders should request the postal clerk to place a legible hand cancellation bull’s eye postmark on both the receipt and Failure by a bidder to acknowledge receipt of the envelope or wrapper.

(f) Notwithstanding paragraph (a) of this provision, a late modifica-tion of an otherwise successful bid that makes its terms more favorable to the PHA/IHA will be considered at any time it is received and may be accepted.

(g) Bids may be withdrawn by written notice, or if authorized by this solicitation, by telegram (including mailgram) or facsimile machine transmission received at any time before the exact time set for opening of bids; provided that written confirmation of telegraphic or facsimile withdrawals over the signature of the bidder is mailed and postmarked prior to the specified bid opening time. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for opening of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.

6. Bid Opening All bids received by the date and time of receipt specified in the solicitation will be publicly opened and read. The time and place of opening will be as specified in the solicitation. Bidders and other interested persons may be present.

7. Service of Protest

(a) Definitions. As used in this provision:

“Interested party” means an actual or prospective bidder whose direct economic interest would be affected by the award of the contract.

“Protest” means a written objection by an interested party to this solicitation or to a proposed or actual award of a contract pursuant to this solicitation.

(b) Protests shall be served on the Contracting Officer by obtaining written and dated acknowledgement from — Patti Webster housing Authority of Billings

[Contracting Officer designate the official or location where a protest may be served on the Contracting Officer]

(c) All protests shall be resolved in accordance with the PHA’s/ IHA’s protest policy and procedures, copies of which are maintained at the PHA/IHA.

8. Contract Award

(a) The PHA/IHA will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advan-tageous to the PHA/IHA considering only price and any price-related factors specified in the solicitation.

(b) If the apparent low bid received in response to this solicitation exceeds the PHA’s/IHA’s available funding for the proposed contract work, the PHA/IHA may either accept separately priced items (see 8(e) below) or use the following procedure to determine contract award. The PHA/IHA shall apply in turn to each bid (proceeding in order from the apparent low bid to the high bid) each of the separately priced bid deductible items, if any, in their priority order set forth in this solicitation. If upon the application of the first deductible item to all initial bids, a new low bid is within the PHA’s/IHA’s available funding, then award shall be made to that bidder. If no bid is within the available funding amount, then the PHA/IHA shall apply the second deductible item. The PHA/IHA shall continue this process until an evaluated low bid, if any, is within the PHA’s/IHA’s available funding. If upon the application of all deductibles, no bid is within the PHA’s/IHA’s available funding, or if the solicitation does not request separately priced deductibles, the PHA/IHA shall follow its written policy and procedures in making any award under this solicitation.

(c) In the case of tie low bids, award shall be made in accordance with the PHA’s/IHA’s written policy and procedures.

(d) The PHA/IHA may reject any and all bids, accept other than the lowest bid (e.g., the apparent low bid is unreasonably low), and waive informalities or minor irregularities in bids received, in accordance with the PHA’s/IHA’s written policy and procedures.

(e) Unless precluded elsewhere in the solicitation, the PHA/IHA may accept any item or combination of items bid.

(f) The PHA/IHA may reject any bid as nonresponsive if it is materially unbalanced as to the prices for the various items of work to be performed. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

(g) A written award shall be furnished to the successful bidder within the period for acceptance specified in the bid and shall result in a binding contract without further action by either party.

9. Bid Guarantee (applicable to construction and equip-ment contracts exceeding $25,000)

All bids must be accompanied by a negotiable bid guarantee which shall not be less than five percent (5%) of the amount of the bid.

The bid guarantee may be a certified check, bank draft, U.S.

Government Bonds at par value, or a bid bond secured by a surety company acceptable to the U.S. Government and authorized to do business in the state where the work is to be performed. In the case where the work under the contract will be performed on an Indian reservation area, the bid guarantee may also be an irrevocable Letter of Credit (see provision 10, Assurance of Completion, below). Certified checks and bank drafts must be made payable to the order of the PHA/IHA. The bid guarantee shall insure the execution of the contract and the furnishing of a method of assurance of completion by the successful bidder as required by the solicitation. Failure to submit a bid guarantee with the bid shall result in the rejection of the bid. Bid guarantees submitted by unsuccessful bidders will be returned as soon as practicable after bid opening.

10. Assurance of Completion

(a) Unless otherwise provided in State law, the successful bidder shall furnish an assurance of completion prior to the execution of any contract under this solicitation. This assurance may be [Contracting Officer check applicable items] —

[ ] (1) a performance and payment bond in a penal sum of 100 percent of the contract price; or, as may be required or permitted by State law;

[ ] (2) separate performance and payment bonds, each for 50 percent or more of the contract price;

[ ] (3) a 20 percent cash escrow;

[ ] (4) a 25 percent irrevocable letter of credit; or, [ ] (5) an irrevocable letter of credit for 10 percent of the total contract price with a monitoring and disbursements agreement with the IHA (applicable only to contracts awarded by an IHA under the Indian Housing Program).

(b) Bonds must be obtained from guarantee or surety companies acceptable to the U.S. Government and authorized to do business in the state where the work is to be performed. Individual sureties will not be considered. U.S. Treasury Circular Number 570, published annually in the Federal Register, lists companies approved to act as sureties on bonds securing Government contracts, the maximum underwriting limits on each contract bonded, and the States in which the company is licensed to do business. Use of companies listed in this circular is mandatory. Copies of the circular may be downloaded on the U.S. Department of Treasury website http:// www.fms.treas.gov/c570/index.html, or ordered for a minimum fee by contacting the Government Printing Office at (202) 512-2168.

(c) Each bond shall clearly state the rate of premium and the total amount of premium charged. The current power of attorney for the person who signs for the surety company must be attached to the bond. The effective date of the power of attorney shall not precede the date of the bond. The effective date of the bond shall be on or after the execution date of the contract.

(d) Failure by the successful bidder to obtain the required assur-ance of completion within the time specified, or within such extended period as the PHA/IHA may grant based upon reasons determined adequate by the PHA/IHA, shall render the bidder ineligible for award. The PHA/IHA may then either award the contract to the next lowest responsible bidder or solicit new bids. The PHA/IHA may retain the ineligible bidder’s bid guarantee.

11. Preconstruction Conference (applicable to construction contracts)

After award of a contract under this solicitation and prior to the start of work, the successful bidder will be required to attend a preconstruction conference with representatives of the PHA/IHA and its architect/engineer, and other interested parties convened by the PHA/IHA. The conference will serve to acquaint the participants with the general plan of the construction operation and all other require-ments of the contract (e.g., Equal Employment Opportunity, Labor Standards). The PHA/IHA will provide the successful bidder with the date, time, and place of the conference.