About this file
The document is an AIA Document G704 - 2017 Certificate of Substantial Completion, a standard form used in construction contract administration. This specific certificate appears to be related to a tub surround installation project at multiple apartment locations on Phyllis Circle in Billings, Montana. The project involves removing existing tubs and tile shower walls and installing walk-in shower inserts on the first floor and tub surrounds on the second floor across 30 apartments at addresses including 355, 2742, and 2757 Phyllis Circle.
The certificate serves to document the substantial completion of the construction work, marking the point at which the project is sufficiently complete for the owner to occupy or utilize the space for its intended purpose. While specific financial details are not fully populated in this template document, the certificate is designed to outline the remaining work to be completed, warranty commencement dates, and assign responsibilities between the owner, contractor, and architect for final project closeout. The document provides a framework for formally acknowledging the near-completion status of the renovation project and establishing the next steps for final acceptance and warranty periods.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Document G704® – 2017 Certificate of Substantial Completion
AIA Document G704® – 2017. Copyright © 1963, 1978, 1992, 2000 and 2017 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, "G704," and “AIA Contract Documents” are registered trademarks and may not be used without permission. This document was produced by AIA software at 11:18:17 ET on 01/04/2022 under Order No.3441151926 which expires on 09/25/2022, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (3B9ADA41)
PROJECT: (name and address) CONTRACT INFORMATION: CERTIFICATE INFORMATION:
. Contract For: General Construction Certificate Number: 003 Date: Date:
OWNER: (name and address) ARCHITECT: (name and address) CONTRACTOR: (name and address)
The Work identified below has been reviewed and found, to the Architect’s best knowledge, information, and belief, to be substantially complete. Substantial Completion is the stage in the progress of the Work when the Work or designated portion is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use. The date of Substantial Completion of the Project or portion designated below is the date established by this Certificate.
(Identify the Work, or portion thereof, that is substantially complete.)
ARCHITECT (Firm Name) SIGNATURE PRINTED NAME AND TITLE DATE OF SUBSTANTIAL COMPLETION
WARRANTIES
The date of Substantial Completion of the Project or portion designated above is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below:
(Identify warranties that do not commence on the date of Substantial Completion, if any, and indicate their date of commencement.)
WORK TO BE COMPLETED OR CORRECTED
A list of items to be completed or corrected is attached hereto, or transmitted as agreed upon by the parties, and identified as follows:
(Identify the list of Work to be completed or corrected.)
The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. Unless otherwise agreed to in writing, the date of commencement of warranties for items on the attached list will be the date of issuance of the final Certificate of Payment or the date of final payment, whichever occurs first. The Contractor will complete or correct the Work on the list of items attached hereto within ( ) days from the above date of Substantial Completion.
Cost estimate of Work to be completed or corrected: $
The responsibilities of the Owner and Contractor for security, maintenance, heat, utilities, damage to the Work, insurance, and other items identified below shall be as follows:
(Note: Owner’s and Contractor’s legal and insurance counsel should review insurance requirements and coverage.)
The Owner and Contractor hereby accept the responsibilities assigned to them in this Certificate of Substantial Completion:
CONTRACTOR (Firm Name)
SIGNATURE PRINTED NAME AND TITLE DATE
OWNER (Firm Name) SIGNATURE PRINTED NAME AND TITLE DATE