This is an Invitation for Bid (IFB) Cost Estimate Worksheet for a construction project at Alton National Cemetery. The worksheet is a lump sum cost estimation template designed for Solicitation Number 36C78626B0014, Project Number 800-NSP26-001, titled the National Shrine Project at Alton National Cemetery located at 600 Pearl Street, Alton, Illinois 62002. The project is being administered by the Department of Veterans Affairs National Cemetery Administration.

The cost estimate worksheet requires contractors to provide lump sum bids for each applicable construction division. The divisions included are: Special Sections; General Requirements (Division 01); Existing Conditions (Division 02); Concrete (Division 03); Masonry (Division 04); Metals (Division 05); Wood, Plastic, and Composites (Division 06); Thermal and Moisture Protection (Division 07); Openings (Division 08); Finishes (Division 09); Specialties (Division 10); Equipment (Division 11); Furnishings (Division 12); Special Construction (Division 13); Fire Suppression (Division 14); Plumbing (Division 22); HVAC (Division 23); Integrated Automation (Division 25); Electrical (Division 26); Communications (Division 27); Electronic Safety and Security (Division 28); Earthwork (Division 31); Exterior Improvements (Division 32); and Utilities (Division 33). Contractors must mark divisions not being used as "N/A" and may add additional line items as deemed appropriate. The worksheet includes separate rows for bonds, overhead, profit, and grand totals to arrive at the final contract price.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

IFB Contractor Cost Estimate Worksheet
Lump Sums are required for each Division that will be utilized in this project to total the final lump sum number.

If a Division is not being used put N/A in that field.

You can Add additional items you feel are appropriate.

Solicitation Number36C78626B0014
Project Nunber800-NSP26-001
Project NameNational Shrine Project at Alton National Cemetery
DivisionUnitCLIN 001Total
Division 0
Special Sections
Division 01
General Requirements
Division 02
Existing Conditions
Division 03
Concrete
Division 04
Masonry
Division 05
Metals
Division 06
Wood, Plastic, and Composites
Division 07
Thermal and Moisture Protection
Division 08
Openings (Doors, Windows, etc...)
Division 09
Finishes
Division 10
Specialties
Division 11
Equipment
Division 12
Furnishings
Division 13
Special Construction
Division 14
Fire Suppression
Division 22
Plumbing
Division 23
Heat, Ventilating, and Air Conditioning
Division 25
Integrated Automation
Division 26
Electrical
Division 27
Communications
Division 28
Electronic Safety and Security
Division 31
Earthwork
Division 32
Exterior Improvements
Division 33
Utilities
Bonds

Overhead

Profit

GRAND TOTALS $ $