IFB Attachment 2 - ORIGINAL DWG_534-24-706.pdf

PDF 18 MB Posted

Attached to
Y1DA--534-24-706 EHRM Data Center Upgrades Construction - Charleston
Solicitation number
36C77626B0027
Issued by

About this file

This document is an Invitation for Bid (IFB) attachment containing architectural construction drawings and project specifications for the EHRM Data Center Upgrades at the Ralph H Johnson VA Medical Center in Charleston, South Carolina (Project 534-24-706). The renovation scope encompasses a phased upgrade of data center room B200 located on the second floor of Building 1, requiring extensive demolition, mechanical/electrical/plumbing modifications, telecommunications infrastructure installation, fire protection system upgrades, and structural work.

The project is organized into six construction phases designed to maintain facility operations throughout the upgrade. Key deliverables include installation of new CRAC (Computer Room Air Conditioning) units, UPS systems with battery cabinets, server racks with static dissipative flooring, fire suppression and clean agent systems, cable tray and power distribution infrastructure, and associated mechanical ductwork and electrical panels. The work requires compliance with strict infection control risk assessment (ICRA) protocols, including dust barriers, negative air pressure maintenance, and specialized cleaning procedures appropriate for a healthcare facility. Critical design elements include one-hour rated fire barriers, firestopping at all penetrations, temporary cooling systems rated at 51.8 KW for general cooling and 10.5 KW for UPS support, and comprehensive coordination across mechanical, electrical, telecommunications, and fire protection disciplines. The Architect/Engineer of Record is AE Works, LTD, with structural engineering by Pennoni Associates and fire protection engineering by Koffel Engineers. All work must conform to the 2021 International Building Code, NFPA standards, VA Fire Protection Design Manual, and applicable federal, state, and local regulations.

View the file

Other files

File Type Posted
Special Notice Issuance of Bid Abstract 36C77626B0027.pdf PDF
36C77626B0027 Bid Abstract 9-14-2026.pdf PDF
36C77626B0027 Amendment 0005.pdf PDF
36C77626B0027 Amendment 0004.pdf PDF
Specification 07 51 00 - Built-Up Bituminous Roofing.pdf PDF
Tech Questions Tracker - EHRM Charleston Final.pdf PDF
ACM Survey_Data Center_AEWLA23075 VAMC Charleston SC EHRM Upgrades Pre-Construction ACM Survey-12-25.pdf PDF
Fire Calculations and Fire Water Flow Testing Documentations.pdf PDF
Specification 02 08 13.19 - Asbestos Floor Tile and Mastic Abatement.pdf PDF
Spec 28 05 28.33 - Conduits and Backboxes for Electronic Safety and Security.pdf PDF
36C77626B0027 Amendment 0003.pdf PDF
36C77626B0027 Amendment 0002.pdf PDF
Site Visit Sign In Sheet Charleston EHRM.pdf PDF
Updated IFB 36C77626B0027.pdf PDF
36C77626B0027 Amendment 0001.pdf PDF
IFB Attachment 3 - ICRA_534-24-706_Upgrade Data Center for EHRM.pdf PDF
IFB Attachment 6 - VAMC Charleston SC EHRM Upgrades ACM Survey-12-25.pdf PDF
IFB Attachment 8 - Limitations on Subcontracting.docx DOCX document
IFB Attachment 10 - Brand Name Justification - Charleston EHRM Data Center.pdf PDF
IFB 36C77626B0027.pdf PDF
IFB Attachment 7 - Site Visit - Charleston.pdf PDF
IFB Attachment 1 - FINAL SPECS_534-24-706.pdf PDF
IFB Attachment 4 - PCRA_534-24-706_Upgrade Data Center for EHRM_100625.pdf PDF
IFB Attachment 5 - NEPA_PCRA_534-24-706_Signed.pdf PDF
IFB Attachment 9 - DBA Rates - Charleston - 5-18-26.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseArchitect/Engineer of Record StampConsultant

321 4 5 6 7 8 9 10

Sprinkler Status

AE Works, LTD.

418 Beaver Street

Sewickley, PA 15143

Phone: 412-287-7333 www.aeworks.comAE WORKS®1900 Market Street, Suite 300 Philadelphia, PA 19103

215.222.3000

8815 Centre Park Drive, Suite 200 Philadelphia, MD 21045

410.750.2246

A u to d e s k D o c s /V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r/ V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r.

rv t

/4 /2

:4

:2

P M

G001

COVER SHEET EHRM DATA CENTER UPGRADES

FOR JSA-FDS - CHARLESTON, SC

109 BEE ST. CHARLESTON SC 29401

534-24-706

02.06.26 LP TW

BID DOCUMENTS

EHRM Data Center Upgrades for JSA-FDS Charleston, SC

PROJECT NO. 534-24-706

RALPH H JOHNSON VA MEDICAL CENTER

109 BEE STREET

CHARLESTON, SC 29401

PROJECT DIRECTORY

OWNER:

U.S. DEPARTMENT OF

VETERANS AFFAIRS

RALPH H JOHNSON VA

MEDICAL CENTER

109 BEE STREET

CHARLESTON, SC 29401

(843) 304-8910

ARCHITECT/ENGINEER:

AE WORKS, LTD

418 BEAVER STREET

SEWICKLEY, PA 15143

(412) 287-7333

FIRE PROTECTION ENGINEER:

KOFFEL ENGINEERS

8815 CENTRE PARK DRIVE

SUITE 200

COLUMBIA, MD 21045

VICINITY MAP

SITE

LOCATION MAP

GENERAL

G001 COVER SHEET

G101 PHASING PLANS

G102 PHASING PLANS

G121 ICRA AND ABATEMENT

LS101 LIFE SAFETY PLAN - DATA CENTER

S000 GENERAL NOTES

S001 DESIGN CRITERIA

S400 SECTIONS AND DETAILS

ARCHITECTURAL

A001 ABBREVIATIONS, NOTES AND SYMBOLS

A100 OVERALL PLAN

AD101 FLOOR AND REFLECTED CEILING DEMOLITION PLANS

A101 FLOOR AND CEILING PLANS

A121 ROOF PLAN

AI101 FINISH PLAN

A601 DOOR AND PARTITION SCHEDULE AND DETAILS

FIRE PROTECTION

FA001 FIRE ALARM COVER SHEET

FA101 PARTIAL SECOND FLOOR FIRE ALARM DEMO PLAN - DATA CENTER

FA201 PARTIAL SECOND FLOOR FIRE ALARM PLAN - DATA CENTER

FA501 FIRE ALARM DETAIL SHEET

FS001 FIRE SUPPRESSION COVER SHEET

FS100 PARTIAL SECOND FLOOR FIRE SUPPRESSION EXISTING PLAN - B SECTION

FS101 PARTIAL SECOND FLOOR FIRE SUPPRESSION DEMO PLAN - DATA CENTER

FS201 PARTIAL SECOND FLOOR FIRE SUPPRESSION PLAN - DATA CENTER

FS501 FIRE SUPPRESSION DETAIL SHEET

SITE

CONTACT: JOHN HOFFMAN, PECONTACT: JONATHAN STECKO CONTACT: MICHAEL CARROLL, PE

MECHANICAL

M001 MECHANICAL SYMBOLS, ABBREVIATIONS, AND GENERAL NOTES

MD101 DATA CENTER HVAC - DEMOLITION PLAN

M100 OVERALL MECHANICAL PLAN

M101 DATA CENTER HVAC PLAN

M102 DATA CENTER SECTIONS

M501 HVAC DETAILS

M701 HVAC SCHEDULES

M801 CONTROL DIAGRAMS

ELECTRICAL

E001 ELECTRICAL SYMBOLS AND ABBREVIATIONS

E101 OVERALL ELECTRICAL PLAN

ED401 DATA CENTER LIGHTING DEMOLITION PLAN

ED402 DATA CENTER ELECTRICAL DEMOLITION PLANS

E401 DATA CENTER LIGHTING PLAN

E402 DATA CENTER POWER PLAN

E403 ENLARGED ELECTRICAL ROOM PLANS

E404 ENLARGED GROUNDING PLANS

E501 ELECTRICAL DETAILS

E502 ELECTRICAL DETAILS

E601 ELECTRICAL SCHEDULES

E602 PANEL SCHEDULES

E701 DATA CENTER PARTIAL ONE-LINE DIAGRAM

TELECOM

TN001 COMMUNICATIONS SYMBOLS AND GENERAL INFORMATION

TN100 COMMUNICATIONS FLOOR PLAN - SECOND FLOOR

TN201 COMMUNICATIONS CABINET ELEVATIONS

TN401 DATA CENTER ENLARGED PLAN

TN501 COMMUNICATIONS OUTLET DETAILS AND SCHEDULES

TN502 COMMUNICATIONS PATHWAY DETAILS

TN503 COMMUNICATIONS BONDING DETAILS

TN504 ELECTRONIC SAFETY AND SECURITY DETAILS AND SCHEDULES

STRUCTURAL AND ENVIRONMENTAL ENGINEERS:

PENNONI

1900 MARKET STREET

SUITE 300

PHILADELPHIA, PA 19103

CONTACT: RICHARD ROBERTS, PE

STRUCTURAL

# Revisions Date

SHEET INDEX

WS AA LM LO O

H F

T

02-06-26

DNDN

G

COR2BD1

DIAG IMG CORR

ELVLOB2

COMMON ELEV

LOBBY

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

(E) CRAC-3

(E) CRAC-1

(E) CRAC-2

(E) UPS-1

(E) UPS-2

(E) BATTERY CABINETS

CABINET

TO REMAIN

(E) CABINETS TO REMAIN (E) CABINETS TO REMAIN

ICRA BARRIER

CONSTRUCTION

BARRIER, TYP.

B200

DATA CENTER

(X) DISCONNECT SWITCH

2L13

2L12

2L11

CSI

G

COR2BD1

DIAG IMG CORR

ELVLOB2

COMMON ELEV

LOBBY

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

(E) BATTERY CABINETS

(X) CRAC-2

CONSTRUCTION

BARRIER, TYP.

CONSTRUCTION

BARRIER, TYP.

(E) UPS-1

(E) UPS-2

CONSTRUCTION

BARRIER, TYP.

(X) CRAC-1

B200

DATA CENTER

(E) CRAC-3

TEMPORARY COOLING AREATEMPORARY COOLING AREA

ICRA BARRIER

2L13

2L12

2L11

CSI

G

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

COR2BD1

DIAG IMG CORR

ELVLOB2

COMMON ELEV

LOBBY

DEMO CRAC-3

COORDINATE

REMOVAL OF THIS

DOOR WITH VA TO

LIMIT ACCESS TO

B206F.

(X) UPS-1

(X) UPS-2

(X) BATTERY CABINETS

CONSTRUCTION

BARRIER, TYP.

CONSTRUCTION

BARRIER, TYP.

DEMO RACKS

CONSTRUCTION

BARRIER, TYP.

B200

DATA CENTER

TEMPORARY COOLING AREA

TEMPORARY COOLING AREA

PDU-2

UPS-2

MBC-2

BATT

CAB 2

MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

ICRA BARRIER

G

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

COR2BD1

DIAG IMG CORR

ELVLOB2

COMMON ELEV

LOBBY

(E) CRAC-3

(E) CRAC-2

(E) UPS-1

(E) UPS-2

(E) BATTERY CABINETS

LEGACY CABINETS

(E) CRAC-1

CONSTRUCTION

BARRIER, TYP.

B200

DATA CENTER

ICRA BARRIER

2L13

2L12

2L11

CSI

G

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

COR2BD1

DIAG IMG CORR

ELVLOB2

COMMON ELEV

LOBBY

(E) CRAC-3

NEW CABINETS

(E) UPS-1

(E) UPS-2

(E) BATTERY CABINETS

CONSTRUCTION

BARRIER, TYP.

B200

DATA CENTER

CONSTRUCTION

BARRIER, TYP.

TEMPORARY COOLING AREA

TEMPORARY COOLING AREA

PDU-2

UPS-2

MBC-2

BATT

CAB 2

ICRA BARRIER

MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

G

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

COR2BD1

DIAG IMG CORR

ELVLOB2

COMMON ELEV

LOBBY

NEW CABINETS

CRAC-2

CONSTRUCTION

BARRIER, TYP.

B200

DATA CENTER

TEMPORARY COOLING AREA

TEMPORARY COOLING AREA

TEMPORARY COOLING AREA

PDU-2

UPS-2

MBC-2

BATT

CAB 2

ICRA BARRIER

MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

PHASE ONE - DEMO NOTES

ARCHITECTURE

- REMOVE ACCESS FLOORING AS INDICATED

- REMOVE CEILING CORRESPONDING TO THE

AMOUNT OF FLOORING REMOVED

- REMOVE WALL SHELVING

- INSTALL CONSTRUCTION AND ICRA BARRIERS AS

INDICATED.

ELECTRICAL

- REMOVE UNSUED DISCONNECT SWITCH

MECHANICAL

- REMOVE UNNECESSARY SYSTEMS

TELECOMMUNICATIONS

- REMOVE UNUSED LEGACY CABLING, EQUIPMENT

CABINETS, AND INFRASTRUCTURE.

- VA TO RELOCATE/CONSOLIDATE EQUIPMENT IN

REMAINING LEGACY CABINETS TO

ACCOMMODATE NEW CABINETS AND

ENTRANCE DOOR.

- CONTRACTOR TO TEMPORARILY SUPPORT

EXISTING TO REMAIN EQUIPMENT CABINET TO

ALLOW FOR RAISED FLOOR REMOVAL. RESET

CABINET ONCE FINISHED FLOORING IS

COMPLETE.

FIRE PROTECTION

- REMOVE ALL HEADS WHEN CEILING IS REMOVED

PHASE ONE - NEW WORK NOTES

ARCHITECTURE

- NO NEW WORK

ELECTRICAL

- NO NEW WORK

MECHANICAL

- NO NEW WORK

TELECOMMUNICATIONS

- NO NEW WORK

FIRE PROTECTION

- NO NEW WORK

PHASE TWO - DEMO NOTES

ARCHITECTURE

- REMOVE ACCESS FLOORING AS INDICATED.

- INSTALL CONSTRUCTION BARRIERS AS

INDICATED.

- REMOVE CEILING CORRESPONDING TO THE

AMOUNT OF FLOORING REMOVED

ELECTRICAL

- NO WORK

MECHANICAL

- REMOVE E-CRAC-01 - EVAP

- REMOVE E-CRAC-01 - COND

- REMOVE E-CRAC-02 - EVAP

- REMOVE E-CRAC-02 - COND

- UTILIZE TEMP COOL UNITS

TELECOMMUNICATIONS

- VA TO RELOCATE/CONSOLIDATE EQUIPMENT

FROM REMAINING LEGACY CABINETS TO NEW

PHASE TWO CABINETS TO ACCOMMODATE NEW

CABINETS.

FIRE PROTECTION

- NO WORK

PHASE TWO - NEW WORK NOTES

ARCHITECTURE

- INSTALL CONSTRUCTION BARRIERS AS

INDICATED.

MECHANICAL

- PREPARE FOR CRAC-2 INSTALL.

- UTILIZE TEMP COOL UNITS.

TELECOMMUNICATIONS

- INSTALL NEW EQUIPMENT CABINETS, CABLE

TRAY, POWER DISTRIBUTION, AND BACKBONE

CABLING IN NOTED LOCATIONS.

- INSTALL TEMPORARY FIBER OPTIC CABLE

CHANNEL BETWEEN EXISTING AND NEW CORE

NETWORK EQUIPMENT. COORDINATE LOCATIONS

WITH LOCAL CLIENT REPRESENTATIVES.

- VA TO POPULATE NEW EQUIPMENT CABINETS.

FIRE PROTECTION

- NO WORK

PHASE THREE - DEMO NOTES

ARCHITECTURE

- DEMO DOOR INTO ROOM B206F.

- REMOVE ACCESS FLOORING AS INDICATED.

- INSTALL CONSTRUCTION BARRIERS AS

INDICATED.

- REMOVE CEILING CORRESPONDING TO THE

AMOUNT OF FLOORING REMOVED.

ELECTRICAL

- REMOVE EXISTING UPS-1 AND UPS-2

- REMOVE MTS-UPS-B200

- REMOVE EXISTING BATTERY CABINETS

MECHANICAL

- REMOVE E-CRAC-03 - EVAP.

- REMOVE E-CRAC-03 - COND.

- UTILIZE TEMP COOL UNITS.

TELECOMMUNICATIONS

- VA TO RELOCATE/CONSOLIDATE EQUIPMENT

FROM NOTED LEGACY CABINETS TO NEW

CABINETS.

FIRE PROTECTION

- NO WORK

PHASE THREE - NEW WORK NOTES

ARCHITECTURE

- INFILL WALL OPENING BETWEEN DATA CENTER

AND ROOM B206F

ELECTRICAL

- PROVIDE POWER TO NEW CRAC-2 (EVAP AND

COND).

- INSTALL TEMPORARY FEEDS FROM PDU-2 TO

PANELS CSI AND 2L13.

MECHANICAL

- INSTALL NEW CRAC-2 - EVAP.

- INSTALL NEW CRAC-2 - COND.

- UTILIZE TEMP COOL UNITS.

TELECOMMUNICATIONS

- INSTALL NEW EQUIPMENT CABINETS, CABLE

TRAY, POWER DISTRIBUTION, AND BACKBONE

CABLING IN NOTED LOCATIONS.

- VA TO POPULATE NEW EQUIPMENT CABINETS.

FIRE PROTECTION

- NO WORK

ELECTRICAL

- INSTALL TRANSFORMER T-LP-DC IN ROOM H200.

- INSTALL MTS-UPS-2

- INSTALL UPS-2, PDU-2, MBC-2

- INSTALL PANEL LP-DC

- INSTALL BATT CAB 2

- INSTALL ROW 1 BUS B

- INSTALL ROW 2 BUS B

- INSTALL 24" GROUND BAR (GB-DC)

TEMPORARY COOLING:

- TEMP COOL: 51.8 KW (MIDDLE) 16 TON SENSIBLE

- TEMP COOL FOR UPS 10.5 KW (LEFT) 5 TON SENSIBLE.

- EXHAUST HEAT DISSIPATION AND DUST CONTROL NEED NEW

TEMPORARY PENETRATIONS IN DATA CENTER AND ROOF.

TEMPORARY COOLING:

- TEMP COOL: 51.8 KW (MIDDLE) 16 TON SENSIBLE

- TEMP COOL FOR UPS 10.5 KW (LEFT) 5 TON SENSIBLE.

- EXHAUST HEAT DISSIPATION AND DUST CONTROL NEED NEW

TEMPORARY PENETRATIONS IN DATA CENTER AND ROOF.

TEMPORARY COOLING:

- TEMP COOL: 51.8 KW (MIDDLE) 16 TON SENSIBLE

- TEMP COOL FOR UPS 10.5 KW (LEFT) 5 TON SENSIBLE.

- EXHAUST HEAT DISSIPATION AND DUST CONTROL NEED NEW

TEMPORARY PENETRATIONS IN DATA CENTER AND ROOF.

TEMPORARY COOLING:

- TEMP COOL: 51.8 KW (MIDDLE) 16 TON SENSIBLE

- TEMP COOL FOR UPS 10.5 KW (LEFT) 5 TON SENSIBLE.

- EXHAUST HEAT DISSIPATION AND DUST CONTROL NEED NEW

TEMPORARY PENETRATIONS IN DATA CENTER AND ROOF.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

N

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseArchitect/Engineer of Record StampConsultant

321 4 5 6 7 8 9 10

Sprinkler Status

AE Works, LTD.

418 Beaver Street

Sewickley, PA 15143

Phone: 412-287-7333 www.aeworks.comAE WORKS®1900 Market Street, Suite 300 Philadelphia, PA 19103

215.222.3000

8815 Centre Park Drive, Suite 200 Philadelphia, MD 21045

410.750.2246

A u to d e s k D o c s /V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r/ V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r.

rv t

/4 /2

:4

:3

P M

G101

PHASING PLANS EHRM DATA CENTER UPGRADES

FOR JSA-FDS - CHARLESTON, SC

109 BEE ST. CHARLESTON SC 29401

534-24-706

02.06.26 LP TW

BID DOCUMENTS

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - DEMO PHASE ONE

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - DEMO PHASE TWO

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - DEMO PHASE THREE

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE ONE

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE TWO

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE THREE

# Revisions Date

WS AA LM LO O

H F

G

CRAC- 2

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

CONSTRUCTION

BARRIER, TYP.

ICRA BARRIER

ICRA BARRIER

CONSTRUCTION

BARRIER, TYP.

B200

DATA CENTER

TEMPORARY COOLING AREA

TEMPORARY COOLING AREA

PDU-2

UPS-2

MBC-2

BATT

CAB 2

BATT

CAB 1 UPS-1 PDU-1

MBC-1

MTS-UPS-1 MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

G

CRAC- 2

CRAC- 1

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

B200

DATA CENTER

TEMPORARY COOLING AREA

PDU-2

UPS-2

MBC-2

BATT

CAB 2

BATT

CAB 1 UPS-1 PDU-1

MBC-1

MTS-UPS-1 MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

ICRA BARRIER

G

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

COR2BD1

DIAG IMG CORR

ELVLOB2

COMMON ELEV

LOBBY

CRAC-1

CRAC- 2

B200

DATA CENTER

PDU-2

UPS-2

MBC-2

BATT

CAB 2

BATT

CAB 1 UPS-1 PDU-1

MBC-1

MTS-UPS-1 MTS-UPS-2

LP-DC

D-LP-DC

GB-DC

ICRA BARRIER

G

11 1/4" 5' - 4"

CRAC- 2

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

CONSTRUCTION

BARRIER, TYP.

ICRA BARRIER

ICRA BARRIER

B200

DATA CENTER

TEMPORARY COOLING AREA

TEMPORARY COOLING AREA

PDU-2

UPS-2

MBC-2

BATT

CAB 2

MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

G

CRAC- 2

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

B200

DATA CENTER

ICRA BARRIER

TEMPORARY COOLING AREA

TEMPORARY COOLING AREA

PDU-2

UPS-2

MBC-2

BATT

CAB 2

BATT

CAB 1 UPS-1 PDU-1

MBC-1

MTS-UPS-1 MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

G

CRAC- 2

CRAC- 1

B206F

DIAG IMG RM #1

B206E

DIAG IMG BONE

DENSITOMETER

B200

DATA CENTER

MTS-UPS-1

PDU-2

UPS-2

MBC-2

BATT

CAB 2

BATT

CAB 1 UPS-1 PDU-1

MBC-1

MTS-UPS-2

LP-DC

D-LP-DC

2L13

2L12

2L11

CSI

GB-DC

ICRA BARRIER

PHASE FOUR - NEW WORK NOTES

ARCHITECTURE

- INSTALL NEW DOOR, FRAME AND HARDWARE

- INFILL CORRIDOR WALL WITH RATED

CONSTRUCTION.

- REPLACE CORRIDOR WALL PANELING AND

FLOORING.

ELECTRICAL

- INSTALL MTS-UPS-1

- INSTALL UPS-1, PDU-1, MBC-1

- INSTALL BATT CAB 1

- INSTALL ROW 1 BUS A

- INSTALL ROW 2 BUS A

MECHANICAL

- PREPARE FOR CRAC-1 INSTALL.

- INSTALL CAV-B200.

TELECOMMUNICATIONS

- INSTALL NEW EQUIPMENT CABINETS, CABLE

TRAY, POWER DISTRIBUTION, AND BACKBONE

CABLING IN NOTED LOCATIONS.

- VA TO POPULATE NEW EQUIPMENT CABINETS.

FIRE PROTECTION

- NO WORK

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

PHASE FOUR - DEMO NOTES

ARCHITECTURE

- REMOVE DOUBLE DOOR, FRAME AND HARDWARE.

- REMOVE RAMP AND RAILING.

- REMOVE OPENING IN CORRIDOR WALL AS

INDICATED.

- INSTALL CONSTRUCTION BARRIERS AS

INDICATED.

ELECTRICAL

- NO WORK

MECHANICAL

- UTILIZE TEMP COOL UNITS.

TELECOMMUNICATIONS

- VA TO RELOCATE/CONSOLIDATE EQUIPMENT

FROM REMAINING LEGACY CABINETS TO NEW

CABINETS.

FIRE PROTECTION

- NO WORK

TEMPORARY COOLING:

- TEMP COOL: 51.8 KW (MIDDLE) 16 TON SENSIBLE

- TEMP COOL FOR UPS 10.5 KW (LEFT) 5 TON SENSIBLE.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

PHASE FIVE - DEMO NOTES

ARCHITECTURE

- INSTALL CONSTRUCTION BARRIERS AS

INDICATED.

- REMOVE REMAINING ACCESS FLOORING AND

CEIILING.

- PREP EXISTING SLAB FLOOR FOR NEW FINISHES.

- COMPLETE CORRIDOR WORK

ELECTRICAL

- NO WORK

MECHANICAL

- UTILIZE TEMP COOL UNITS.

TELECOMMUNICATIONS

- VA TO RELOCATE/CONSOLIDATE EQUIPMENT

FROM REMAINING LEGACY CABINETS TO NEW

CABINETS.

FIRE PROTECTION

- NO WORK

TEMPORARY COOLING:

- TEMP COOL: 51.8 KW (MIDDLE) 16 TON SENSIBLE

- TEMP COOL FOR UPS 10.5 KW (LEFT) 5 TON SENSIBLE.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

PHASE FIVE - NEW WORK NOTES

ARCHITECTURE

- INSTALL FLOOR AND WALL FINISHES AS

INSTALLATION OF EQUIPMENT ALLOWS.

- INSTALL CHASE WITH SHAFT WALLS.

ELECTRICAL

- PROVIDE POWER TO NEW CRAC-1 (EVAP AND COND)

MECHANICAL

- INSTALL CRAC-1 EVAP.

- INSTALL CRAC-1 COND.

- INSTALL NEW RETURN AIR DUCTS.

- UTILIZE TEMP COOL UNITS.

TELECOMMUNICATIONS

- INSTALL NEW EQUIPMENT CABINETS, CABLE TRAY,

POWER DISTRIBUTION, AND BACKBONE CABLING IN

NOTED LOCATIONS.

- VA TO POPULATE NEW EQUIPMENT CABINETS.

FIRE PROTECTION

- NO WORK

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

PHASE SIX - NEW WORK NOTES

ARCHITECTURE

- PAINT WALLS

- INSTALL SIGNAGE

ELECTRICAL

- ESTABLISH EPO SYSTEM

MECHANICAL

- COMPLETE RETURN AIR DUCTWORK TO CRACS.

- INSTALL RACK SENSOR SYSTEM.

- BRING CRAC UNITS ONLINE.

TELECOMMUNICATIONS

- INSTALL NEW EQUIPMENT CABINETS, CABLE

TRAY, POWER DISTRIBUTION, AND BACKBONE

CABLING IN NOTED LOCATIONS.

- VA TO POPULATE NEW EQUIPMENT CABINETS.

FIRE PROTECTION

- INSTALL NEW SPRINKLER HEADS (GRIDS 15-16)

- INSTALL NEW SPRINKLER HEADS (GRIDS 16-17)

- INSTALL NEW SPRINKLER HEADS (GRIDS 17-18.25)

- INSTALL NEW GASEOUS TANKS AND PIPING

- INSTALL NEW FIRE ALARM DEVICES

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

PHASE SIX - DEMO NOTES

ARCHITECTURE

- REMOVE WALLS AND FURRING AROUND COLUMN

ELECTRICAL

- REMOVE PANELS CSI / 2L11 / 2L12 / 2L13

MECHANICAL

- REMOVE TEMP COOL UNITS.

TELECOMMUNICATIONS

- NO WORK

FIRE PROTECTION

- NO WORK

TEMPORARY COOLING:

- REMOVE TEMPORARY COOLING AND PATCH TEMPORARY

PENETRATIONS WHEN CRAC-1 AND 2 ARE OPERATIONAL

AND COMMISSIONED WITH COMPLETION OF RETURN AIR

DUCTWORK INSTALLTION.

ICRA BARRIER

SEE SHEET G121

CONSTRUCTION BARRIER. INSTALL SLAB TO

DECK DUST BARRIER. SIMILAR TO SWIFTWALL

PRO OR STARC LITEBARRIER.

N

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseArchitect/Engineer of Record StampConsultant

321 4 5 6 7 8 9 10

Sprinkler Status

AE Works, LTD.

418 Beaver Street

Sewickley, PA 15143

Phone: 412-287-7333 www.aeworks.comAE WORKS®1900 Market Street, Suite 300 Philadelphia, PA 19103

215.222.3000

8815 Centre Park Drive, Suite 200 Philadelphia, MD 21045

410.750.2246

A u to d e s k D o c s /V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r/ V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r.

rv t

/4 /2

:4

:4

P M

G102

PHASING PLANS EHRM DATA CENTER UPGRADES

FOR JSA-FDS - CHARLESTON, SC

109 BEE ST. CHARLESTON SC 29401

534-24-706

02.06.26 LP TW

BID DOCUMENTS

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE FOUR

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE FIVE

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE SIX

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - DEMO PHASE FOUR

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE FIVE DEMO

1/4" = 1'-0"

PARTIAL SECOND FLOOR PLAN - PHASE SIX DEMO

# Revisions Date

WS AA LM LO O

H F

INFECTION CONTROL RISK ASSESSMENT FOR CONSTRUCTION

TABLE 1: CONSTRUCTION, RENOVATION, AND/OR MAINTENANCE ACTIVITY

CATEGORIES:

CATEGORY A

INSPECTION AND/OR FACILITY UPKEEP

• WORK CAN BE COMPLETED IN A SINGLE SHIFT, NOT EXCEEDING 10 DAYS.

• WORK THAT DOES NOT CREATE DUST OR DEBRIS.

• REMOVAL OF CEILING TILES OR ACCESS TO MECHANICAL OR ELECTRICAL

CHASE FOR VISUAL INSPECTION LIMITED TO 1 TILE PER 50 SQUARE FEET

WITH LIMITED EXPOSURE TIME (NOT TO EXCEED AN HOUR FOR EACH

TILE) WITHIN THE SHIFT.

• MINOR INTERIOR UPDATES (E.G., REPLACING FLOOR OR CEILING TILES,

CARPENTRY WORK TO INCLUDE HANGING SIGNAGE, AND PAINTING

WITHOUT SANDING) THAT DO NOT CREATE DUST OR DEBRIS.

• LIMITED BUILDING SYSTEM MAINTENANCE SUCH AS PLUMBING ON

POTABLE SYSTEMS LIMITED TO FAUCET REPLACEMENT ETC. AND

ELECTRICAL WORK SUCH AS REPLACEMENT OF BULBS, RECEPTACLES,

OR SWITCHES.

CATEGORY B

GENERAL MAINTENANCE AND REPAIR WORK GENERALLY DEFINED AS

FOLLOWS:

• PROLONGED INSPECTION AND WORK THAT MAY TAKE LONGER THAN A

SINGLE SHIFT BUT NOT EXCEEDING A WEEK.

• PATIENTS AND EMPLOYEES ARE NOT TO BE IN THE AREA UNTIL ACTIVITY

IS COMPLETED.

• WORK THAT CREATES MINIMAL DUST AND DEBRIS.

• INTERIOR FINISH OR SURFACE REPAIRS, UPDATES, OR MODIFICATIONS

SUCH AS REPAIR OF FIREWALLS AND BARRIERS, AND NEW FLOORING

THAT PRODUCES MINIMAL DUST AND DEBRIS. CONTROLLED SANDING

ACTIVITIES (E.G. WET OR DRY SANDING) THAT PRODUCE MINIMAL DUST

AND DEBRIS.

• PLUMBING WORK SUCH AS INSTALLATION OR REPLACEMENT OF SINGLE

FIXTURE OR PIPING FOR A SINGLE FIXTURE. ANY WORK ON SANITARY

PLUMBING INCLUDING SNAKING OF DRAINS.

• ELECTRICAL WORK SUCH AS INSTALLATION OF CABLING/WIRING/CONDUIT

FOR A SINGLE DEVICE, INSTALLATION OF NEW DEVICE SUCH AS A LIGHT

FIXTURE THAT PRODUCES MINIMAL DUST AND DEBRIS.

TYPE C

SMALL-SCALE CONSTRUCTION, RENOVATION, OR MAINTENANCE

GENERALLY DEFINED AS FOLLOWS:

• AIR HANDLER AND/OR FAN SHUTDOWN/STARTUP AND HVAC WORK SUCH

AS REPLACEMENT OF A SINGLE DIFFUSER, SINGLE TERMINAL UNIT OR A

SINGLE DEVICE THAT PRODUCES MINIMAL DUST AND DEBRIS.

• PATIENTS AND EMPLOYEES ARE NOT TO BE IN THE AREA UNTIL ACTIVITY

IS COMPLETED.

• DEMOLITION/REMOVAL OF PREEXISTING FLOOR COVERING, CASEWORK,

LAY-IN CEILING, OR OTHER ARCHITECTURAL ELEMENTS

• DEMOLITION/REMOVAL OF MORE THAN 32 FT2 OF DRYWALL/FRAMING,

HARD CEILINGS, AND DOORS/FRAMING AND MINIMAL INFRASTRUCTURE

SUCH AS ELECTRICAL CIRCUITS AND BRANCH PIPING.

• INSTALLATION OF NEW WALLS, CEILINGS AND DOORS INCLUDING

FRAMING, DRYWALL/PLASTER AND ASSOCIATED WORK.

• PLUMBING WORK SUCH AS THE INSTALLATION OF NEW SINKS, SHOWERS

AND TOILETS AND ASSOCIATED PLUMBING.

• SHUT DOWN OF SECTIONS OF POTABLE WATER SYSTEMS.

• ELECTRICAL WORK SUCH AS INSTALLATION OF CONDUIT AND WIRE FOR

LIGHTING, RECEPTACLES AND SWITCHES FOR AN AREA, THE

INSTALLATION OF CONDUIT AND WIRE FOR NEW DEVICES SUCH AS

TERMINAL UNITS, FANS ETC.

• MODIFICATION OF EXISTING FIRE ALARM AND SUPPRESSION SYSTEMS.

• MECHANICAL WORK SUCH AS THE INSTALLATION OF DUCTWORK,

DIFFUSERS, AND TERMINAL UNITS FOR AN AREA.

STEP #2: SELECT RISK GROUP BELOW AND MARK BOTTOM OF COLUMN

A) INFECTION CONTROL RISK GROUPS

GROUP 1 - LOW: OFFICE AREAS:

GROUP 2 - MEDIUM: CARDIOLOGY, ECHOCARDIOGRAPHY, ENDOSCOPY,

NUCLEAR MEDICINE, PHYSICAL THERAPY, RADIOLOGY/MRI, RESPIRATORY

THERAPY

GROUP 3 - HIGH RISK: CCU, EMERGENCY ROOM, LABORATORIES,

OUTPATIENT SURGERY, PHARMACY, POST ANESTHESIA CARE UNIT,

SURGICAL UNITS

GROUP 4 - HIGHEST RISK: ANY AREA CARING FOR IMMUNOCOMPROMISED

PATIENTS, CARDIAC CATH LAB, CENTRAL SUPPLY, INTENSIVE CARE UNITS,

MEDICAL UNITS, NEGATIVE AIRFLOW ROOMS, ONCOLOGY, OPERATING

ROOMS

TABLE 4: LEVEL OF INFECTION PREVENTION AND CONTROL PRECAUTIONS

MATCH THE OVERALL PATIENT RISK CATEGORY (LOW, MEDIUM, HIGH,

HIGHEST) DETERMINED FROM TABLE 3 WITH THE PLANNED

CONSTRUCTION/RENOVATION/MAINTENANCE ACTIVITY CATEGORY (A, B, C,

D) FROM TABLE 1 TO DETERMINE THE MINIMUM LEVEL OF INFECTION

PREVENTION AND CONTROL PRECAUTIONS (I, II, III, OR IV) USING

TABLE 4 BELOW

PATIENT RISK

CATEGORY A B C D

LOW RISK I II II III

MEDIUM RISK I II III IV

HIGH RISK I II IV IV

HIGHEST RISK II III IV IV

ELECTRICAL

YES

POTABLE

WATER

YES

HVAC

YES

MEDICAL

VACUUM

YES

SEWER

YES

PROJECTED UTILITY OUTAGES IMPACTING INFECTION CONTROL

STEP #4: COMPLETE THE INFECTION CONTROL CONSTRUCTION PERMIT:

1. EXECUTE WORK BY METHOD TO MINIMIZE RAISING DUST FROM

CONSTRUCTION OPERATIONS

2. IMMEDIATELY REPLACE A CEILING TILE DISPLACED FOR VISUAL INSPECTION

1. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST FROM DISPERSING

INTO ATMOSPHERE.

2. WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING

3. SEAL UNUSED DOORS WITH DUCT TAPE

4. BLOCK OFF AND SEAL AIR VENTS.

5. PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK AREA.

6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE WORK IS BEING

PERFORMED.

1. REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE

TO PREVENT CONTAMINATION OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS, I.E. SHEETROCK, PLYWOOD, PLASTIC,

TO SEAL AREA FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE

METHOD (CART WITH PLASTIC COVERING & SEALED CONNECTION TO WORK

SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE

CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORKSITE UTILIZING HEPA-

EQUIPPED AIR FILTRATION UNITS.

4. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORTATION IN TIGHTLY

COVERED CONTAINERS.

5. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS

SOLID LID IS USED.

1. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO

PREVENT CONTAMINATION OF DUCT SYSTEM.

2. COMPLETE ALL CRITICAL BARRIERS, I.E., SHEETROCK, PLYWOOD, PLASTIC,

TO SEAL AREA FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE

METHOD (CART WITH PLASTIC COVERING & SEALED CONNECTION TO WORK

SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE

CONSTRUCTION BEGINS.

3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORKSITE UTILIZING HEPA-

EQUIPPED AIR FILTRATION UNITS.

4. SEAL HOLES, PIPES, CONDUITS AND PUNCTURES APPROPRIATELY.

5. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS

THROUGH THIS ROOM SO THEY CAN BE VACUUMED USING A HEPA VACUUM

CLEANER BEFORE LEAVING WORK SITE; OR THE CAN WEAR CLOTH OR PAPER

COVERALLS THAT ARE REMOVED EACH TIME THEY LEAVE THE WORK SITE.

6. ALL PERSONNEL ENTERING THE WORK SITE ARE REQUIRED TO WEAR

SHOE COVERS. SHOE COVERS MUST BE CHANGED EACH TIME THE WORKER

EXITS THE WORK AREA.

7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED

PROJECT IS INSPECTED BY SAFETY MANAGEMENT & INFECTION CONTROL &

THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT.

1. CLEAN WORK UPON COMPLETION OF TASK

1. WIPE WORK SURFACES WITH DISINFECTANT.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY

COVERED CONTAINERS.

3. WET MOP &/OR VACUUM BEFORE LEAVING WORK AREA.

4. REMOVE ISOLATION OF HVAC SYSTEM IN AREA WHERE WORK IS BEING

PERFORMED.

1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED

PROJECT IS INSPECTED BY SAFETY MANAGEMENT & INFECTION

CONTROL & THOROUGHLY CLEANED BY ENVIRONMENTAL MANAGEMENT.

2. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING

OF DIRT & DEBRIS ASSOCIATED WITH CONSTRUCTION.

3. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.

4. WET MOP WITH DISINFECTANT.

5. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS

BEING PERFORMED.

1. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING

OF DIRT & DEBRIS ASSOCIATED WITH CONSTRUCTION.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY

COVERED CONTAINERS.

3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING

UNLESS SOLID LID.

4. VACUUM WORK AREA WITH HEPA-FILTERED VACUUMS.

5. WET MOP WITH DISINFECTANT.

6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS

BEING PERFORMED.

CLASS I - DURING CONSTRUCTION PROJECT

CLASS I - UPON COMPLETION OF PROJECTS

CLASS II - DURING CONSTRUCTION PROJECT

CLASS II - UPON COMPLETION OF PROJECTS

CLASS III - DURING CONSTRUCTION PROJECT

CLASS III - UPON COMPLETION OF PROJECTS

CLASS IV - DURING CONSTRUCTION PROJECT

CLASS IV - UPON COMPLETION OF PROJECTS

(TO BE COMPLETED BY CONTRACTOR AND SIGNED BY INFECTION CONTROL NURSE)

CONTRACTOR'S SIGNATURE AND DATE

INFECTION CONTROL NURSE'S SIGNATURE AND DATE

ACTIVITY CATEGORY

TYPE D

LARGE-SCALE CONSTRUCTION, RENOVATION, OR MAINTENANCE

GENERALLY DEFINED AS FOLLOWS:

• WORK EXCEEDING 6 MONTHS IN DURATION.

• PATIENTS AND EMPLOYEES ARE NOT TO BE IN THE AREA UNTIL ACTIVITY

IS COMPLETED.

• LARGE-SCALE DEMOLITION OF BUILDING COMPONENTS AND

INFRASTRUCTURE INCLUDING REMOVAL OF MULTIPLE DOORS, WALLS,

FRAMING, CEILINGS, FLOORING, PIPING, ELECTRICAL AND HVAC.

• THE INSTALLATION BUILDING COMPONENTS SUCH AS NEW WALLS,

CEILINGS AND DOORS INCLUDING FRAMING, DRYWALL AND ASSOCIATED

PLASTER WORK.

• PLUMBING WORK SUCH AS THE INSTALLATION OF:

- NEW MEDICAL GAS SYSTEMS,

- STEAM/HEATING HOT WATER, CONDENSATE SYSTEMS,

- MULTIPLE SINKS, SHOWERS AND TOILETS INCLUDING ASSOCIATED

PLUMBING.

• SHUTDOWN OF POTABLE WATER, STEAM/HEATING HOT WATER,

CONDENSATE, AND MEDICAL GAS SYSTEMS.

• ELECTRICAL WORK SUCH AS INSTALLATION OF ELECTRICAL FEEDERS,

DISTRIBUTION PANELS, CONDUIT AND WIRE FOR LIGHTING, RECEPTACLES

AND SWITCHES FOR AN AREA, THE INSTALLATION OF CONDUIT AND WIRE

FOR NEW DEVICES SUCH AS TERMINAL UNITS, FANS ETC.

• INSTALLATION OF FIRE ALARM AND SUPPRESSION SYSTEMS.

• ELECTRICAL SHUTDOWN OF MULTIPLE PANELS.

• MECHANICAL WORK SUCH AS THE INSTALLATION OF AIR HANDLING

EQUIPMENT, ASSOCIATED DUCTWORK, DIFFUSERS, HEAT EXCHANGERS,

TERMINAL UNITS AND CONTROLS.

DUST CONTROL PLAN NOTES / DUST CONTROL PLAN HAZARD ASSESSMENT

PRIOR TO INITIATING WORK, CONTRACTOR WILL ASSESS THE SCOPE OF THE CONSTRUCTION ACTIVITIES AND

DETERMINE THE POTENTIAL RISK GROUPS INVOLVED BASED ON THE LOCATION OF ACTIVITIES AND EXTENT AND

DURATION OF THE WORK. LOW RISK GROUPS ARE CONSIDERED "OFFICE WORKERS", MEDIUM RISK GROUPS ARE

CONSIDERED ALL INPATIENT AND OUTPATIENT AREAS NOT IN THE HIGH RISK GROUP. HIGH RISK GROUP

DESIGNATION INCLUDES INPATIENT AREAS SUCH AS PEDIATRIC AND ADULT OPERATING/DELIVERY ROOMS, CATH

LABS, MYELO SUPPRESSION UNITS, ICUS, DIALYSIS, NURSERIES AS WELL AS CLINIC AREAS (CLINICS ASSOCIATED

WITH HEMATOLOGY, ONCOLOGY, PEDIATRIC INFECTION DISEASE, OR TRANSPLANT SERVICES) AND SERVICE

AREAS (CENTRAL PROCESSING, STERILE PROCESSING, FOOD PREP & SERVICE AREA AND PHARMACIES. THE

VAMC INFECTION CONTROL GROUP WILL CONFIRM AND APPROVE THE DESIGNATION PROVIDED IN THIS

SUBMITTED DUST CONTROL PLAN. VAMC IS ALSO RESPONSIBLE FOR ANY AND ALL INFECTION CONTROL

MEASURES DETERMINED AND ESTABLISHED BY VAMC POLICY, SUCH AS THE RELOCATION OF HIGH RISK

PATIENTS, APPROVING ALTERNATE TRAFFIC PATHS FOR CONSTRUCTION WORKERS OR ESTABLISH ALTERNATE

TRAFFIC PATTERNS FOR STAFF, PATIENTS AND VISITORS. THE PLAN SHOULD BE REVISED ACCORDING TO

SPECIFIC VAMC POLICIES OR CHANGING CONDITIONS AT THE SITE AS THEY MAY OCCUR.

CHARLESTON VAMC RENOVATION

FOR THE PURPOSE OF THIS RENOVATION, THE CONSTRUCTION WORK IS CONSIDERED ADJACENT TO MEDIUM

RISK AND COMPRISES WORK WHICH COULD GENERATE MODERATE TO HIGH LEVELS OF DUST NOT WITHIN THE

CONFINES OF A SUITE OR OFFICE AND INCLUDES EXTENSIVE CONSTRUCTION WORK (DEMOLITION) IN BUILDING

100 THROUGHOUT THE CORE AND SERVICE BAYS ON THE FIRST FLOOR. THE DUST CONTROL PLAN SHALL BE

DISTRIBUTED AND REVIEWED BY ALL CONTRACTORS PERFORMING WORK ON THIS CONSTRUCTION PROJECT.

A. EXTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES

• DETERMINE IF THE IMPACTED AREAS OF THE FACILITY CAN OPERATE TEMPORARILY ON RECIRCULATED AIR; IF

FEASIBLE SEAL OFF ADJACENT AIR INTAKES.

• IF THIS IS NOT POSSIBLE OR PRACTICAL, CHECK THE LOW-EFFICIENCY FILTER BANKS FREQUENTLY AND

REPLACE AS NEEDED TO AVOID BUILDUP OF PARTICULATE.

• SEAL WINDOWS AND REDUCE WHEREVER POSSIBLE OTHER SOURCES OF OUTSIDE AIR INTRUSION (OPEN

DOORS IN STAIRWELLS AND CORRIDORS) ESPECIALLY IN PROTECTIVE ENVIRONMENT (PE) AREAS.

B. INTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES DUST AND DEBRIS CONTROL

• BARRIER SYSTEMS: THE AREA SHOULD BE ISOLATED, AS THE PROJECT REQUIRES. SMALL, SHORT DURATION

PROJECTS GENERATING MINIMAL DUST MAY USE FIRE-RATED PLASTIC SHEETING, BUT SHOULD BE SEALED AT

FULL CEILING HEIGHT WITH AT LEAST 2-FOOT OVERLAPPING FLAPS FOR ACCESS TO ENTRY. PROJECTS THAT

PRODUCE MODERATE TO HIGH LEVELS OF DUST REQUIRE RIGID, DUST-PROOF, AND FIRE-RATED BARRIER

WALLS (E.G., DRYWALL) WITH CAULKED SEAMS FOR A TIGHT SEAL EXTENDING FLOOR TO CEILING. SEAL OFF

AND BLOCK RETURN AIR VENTS IF RIGID BARRIERS ARE USED FOR CONTAINMENT. LARGE DUST PROJECTS

NEED AN ENTRY VESTIBULE FOR CLOTHING CHANGES AND TOOL STORAGE AND TIGHT SEALS SHOULD BE

MAINTAINED AT THE FULL PERIMETER OF WALLS AND WALL PENETRATIONS. AN INTERIM PLASTIC DUST

BARRIER (MINIMUM 4-MIL) MAY BE REQUIRED TO PROTECT THE AREA WHILE THE RIGID IMPERVIOUS BARRIER

IS BEING CONSTRUCTED. ANY DUST SHALL BE IMMEDIATELY CLEANED IF TRACKED OUTSIDE OF THE

CONSTRUCTION BARRIER. UPON COMPLETION OF THE CONSTRUCTION PROJECT DUST BARRIERS SHALL BE

REMOVED CAREFULLY TO MINIMIZE SPREADING OF DUST AND THE CONTRACTOR SHALL HAVE TEMPORARY

DUST PROTECTION IN PLACE BEFORE REMOVAL OF A PERMANENT BARRIER. CONTRACTOR PERSONNEL

SHALL MONITOR AND PERFORM BARRIER MAINTENANCE AND BE EDUCATED TO NOTICE SIMPLE CLUES SUCH

AS ACCUMULATIONS OF VISIBLE DUST EVIDENCED BY FOOTPRINTS, OPENED DOORS/WINDOWS EVIDENCED BY

PRESENCE OF INSECTS AND FLIES, WET CEILING TILE, ETC.

• TRAFFIC CONTROL; DESIGNATED ENTRY AND EXIT PROCEDURES SHALL BE DEFINED. EGRESS PATHS SHOULD

BE FREE OF DEBRIS; DESIGNATED ELEVATORS SHOULD BE USED DURING SCHEDULED TIMES; AND ONLY

AUTHORIZED PERSONNEL SHOULD BE ALLOWED TO ENTER THE CONSTRUCTION ZONE. SIGNAGE SHOULD

DIRECT PEDESTRIAN TRAFFIC AWAY FROM THE CONSTRUCTION AREA AND MATERIALS.

• DEMOLITION DEBRIS: DEBRIS SHOULD BE REMOVED IN CARTS WITH TIGHTLY FITTED COVERS, USING

DESIGNATED TRAFFIC ROUTES. EFFORTS SHOULD BE MADE TO MINIMIZE USE OF ELEVATORS WITH AN

EMPHASIS ON TRANSPORT DURING THE LOWEST PERIOD OF ACTIVITY. DEBRIS SHOULD BE REMOVED DAILY

AND AT TIMES SPECIFIED BY THE VAMC. IF CHUTES ARE USED TO DIRECT DEBRIS OUTSIDE, HIGH EFFICIENCY

PARTICULATE AIR (HEPA) FILTERED NEGATIVE AIR MACHINES SHOULD BE USED, AND THE CHUTE OPENING

SHOULD BE SEALED WHEN NOT IN USE. FILTERS SHOULD BE BAGGED AND SEALED BEFORE BEING

TRANSPORTED OUT OF THE CONSTRUCTION AREA. THE CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH

PATIENT-CARE AREAS WITH PRIOR APPROVAL OF THE VAMC.

• EXTERIOR WINDOWS: WINDOWS SHOULD BE SEALED TO MINIMIZE INFILTRATION FROM ANY ADJACENT

EXCAVATION DEBRIS.

• CEILINGS THAT ARE REMOVED/MODIFIED TO ALLOW CONSTRUCTION OF ICRA BARRIERS SHOULD BE

REINSTALLED TO PRE-CONSTRUCTION CONDITIONS.

VENTILATION AND ENVIRONMENTAL CONTROLS

• AIR SYSTEM FLOW: DETERMINE WHETHER THE CONSTRUCTION AREA USES FRESH/OUTSIDE OR

RECIRCULATED AIR; FILTERS SHOULD BE ADDED OR RETURN VENTS COVERED AS NEEDED WITH FILTER

MATERIAL OR PLASTIC. AIR MUST FLOW FROM CLEAN TO DIRTY AREAS.

• NEGATIVE AIR PRESSURE: THE AIR WITHIN THE CONSTRUCTION AREA MUST BE NEGATIVE WITH RESPECT TO

SURROUNDING AREAS AND WITH NO DISRUPTION OF AIR SYSTEMS OF ADJACENT AREAS. USE OF THE

NEGATIVE AIR PRESSURE SYSTEM WITHIN THE ENCLOSURE TO REMOVE DUST SHOULD PASS AIR THROUGH AN

INDUSTRIAL GRADE, PORTABLE HEPA FILTER CAPABLE OF FILTRATION RATES OF 300-800 CUBIC FEET PER

MINUTE (FT3//MIN), OR EXHAUST AIR DIRECTLY TO THE OUTSIDE IF APPROVED BY VAMC. IF EXHAUST MUST BE

TIED INTO A RE-CIRCULATED AIR SYSTEM, A PRE-FILTER AND HEPA FILTER SHOULD BE USED BEFORE

EXHAUST TO PREVENT CONTAMINATION OF THE DUCTS.

• ADJACENT AREAS: THE STATUS OF SEALED PENETRATIONS AND INTACT CEILING SHOULD BE VERIFIED DAILY.

• AIR EXCHANGE RATES AND PRESSURE RELATIONSHIPS: VAMC AND/OR CONTRACTOR WILL VERIFY AND

MAINTAIN PROPER RATES IN CRITICAL AREAS NEAR CONSTRUCTION ACTIVITY AND ENSURE AIR IS NOT BEING

RE-CIRCULATED WITHOUT FILTRATION FROM THE CONSTRUCTION AREA ELSEWHERE. VAMC WILL MAKE

DETERMINATION ON PROVIDING FOR THE ACCOUNTABILITY AND FREQUENCY OF TESTING AIR PRESSURE

THROUGHOUT THE PROJECT.

• MANOMETERS SHOULD BE LOCATED ON ICRA PARTITION DOOR AND ON THE NON-CONSTRUCTION SIDE OF THE

PARTITION.

CONTAMINATION OF PATIENT ROOMS

• WORKSITE CLOTHING: CONTRACTOR PERSONNEL CLOTHING SHOULD BE FREE OF LOOSE SOIL AND DEBRIS

BEFORE LEAVING THE CONSTRUCTION AREA. IF PROTECTIVE APPAREL IS NOT WORK (E.G. COVERALLS, FOOTGEAR AND HEADGEAR) A HEPA-FILTERED VACUUM SHOULD BE USED TO REMOVE DUST FROM CLOTHING

BEFORE LEAVING THE BARRICADE. IF PROTECTIVE APPAREL IS UTILIZED THE CONTRACTOR SHALL

CONSTRUCT A SPACE OR ANTEROOM FOR CHANGING CLOTHING AND STORING EQUIPMENT (DESIGNATED

AREA). ALL EQUIPMENT, TOOLS, TOOL CARTS, MATERIALS, ETC. TRANSPORTED THROUGH OCCUPIED AREAS

SHALL BE MADE FREE FROM DUST AND MOISTURE BY VACUUMING AND WET WIPING BEFORE THEIR REMOVAL

FROM THE CONSTRUCTION ZONE OR WORK AREA.

• CONTRACTOR CLEANING: THE CONSTRUCTION ZONE SHOULD BE MAINTAINED IN A CLEAN MANNER BY

CONTRACTORS AND SWEPT OR HEPA-VACUUMED DAILY FOR MORE FREQUENTLY AS NEEDED TO MINIMIZE

DUST. ADJACENT AREAS THAT MAY BE IMPACTED BY THE CONSTRUCTION SHOULD BE DAMP MOPPED DAILY

OR MORE FREQUENTLY AS NEEDED. WALK-OFF MATS WITH TACKY OR ADHESIVE SURFACES SHOULD BE

UTILIZED TO MINIMIZE TRACKING OF HEAVY DIRT AND DUST FROM CONSTRUCTION AREAS.

ACCESSIBLE ACM LOCATIONS

AE WORKS' SUBCONSULTANT PENNONI ENGINEERING PERFORMORMED A LIMITED ASBESTOS SURVEY ON DECEMBER 10, 2025 TO IDENTIFY IF ACCESSIBLE ACM (ASBESTOS CONTAINING MATERIAL) MAY BE DISTURBED BY THE PLANNED RENOVATION

PROJECT. THE SURVEY WAS CONDUCTED BY MR. THOMAS ADAMS, ONE OF PENNONI'S UNITED STATES ENVIRONMENTAL PROTECTION AGENCY (USEPA) TRAINED IN THE STATE OF SOUTH CAROLINA, LICENSED ASBESTOS BUILDING INSPECTORS.

DURING THIS INSPECTION, 100 SAMPLES OF THE FOLLOWING IDENTIFIED SUSPECT ACM SYSTEMS WERE COLLECTED (SEE APPENDIX B – ASBESTOS FIELD INSPECTION FORMS, APPENDIX C – SITE PHOTOGRAPHS AND APPENDIX D – SAMPLE LOCATION

DRAWING). THE FOLLOWING SUSPECT ACM, LISTED HERE BY HOMOGENEOUS IDENTIFICATION NUMBER (HID), WERE IDENTIFIED AND SAMPLED DURING THIS INVESTIGATION:

101. DRYWALL (NAD)

102. JOINT COMPOUND (NAD)

103. 2’X4’ LAY-IN CEILING TILE, DOT (NAD)

104. 2’X2’ LAY-IN CEILING TILE, DOT (NAD)

105. 2’X2’ LAY-IN CEILING TILE, ROUGH FINISH (NAD)

106. 2’X2’ LAY-IN CEILING TILE, SMOOTH FINISH (NAD)

107. COVEBASE MOLDING MASTIC (NAD)

108. 12”X12” OFF-WHITE WITH TAN FLOOR TILE (NAD), TAN MASTIC (NAD) AND BLACK MASTIC (POS)

109. RAISED FLOOR PEDESTAL MASTIC (NAD)

110. GRAY FLOOR LEVELING COMPOUND (NAD)

111. CERAMIC FLOOR MORTAR/WETBED (NAD)

112. FIRE STOP (NAD)

113. PLASTER WALL (NAD)

114. PLASTER PATCH (NAD)

115. END CAP MASTIC (NAD)

(NAD) - NO ASBESTOS DETECTED; (POS) - POSITIVE FOR ASBESTOS CONTENT.

116. FIBERGLASS PIPE INSULATION (NON-SUSPECT)

117. TAR (POS) ASSOCIATED WITH FOIL WRAP PIPE INSULATION (NAD) AND HID 118.

118. FITTING (NAD) ASSOCIATED WITH FIBERGLASS PIPE INSULATION

119. ROOFING FIELD – BUILT-UP ROOFING (NAD), FLASHING (NAD), FELT (NAD), INSULATION (NAD) AND FOAM (NAD)

120. ROOF FLASHING, EQUIPMENT – FLASHING1 (NAD), FLASHING2 (NAD) AND INSULATION (NAD)

121. EQUIPMENT FLASHING, CAP CAULK (NAD)

122. EQUIPMENT FLASHING, SILVER COATING (NAD)

123. ENDCAP MASTIC (NAD) ASSOCIATED WITH PIPE INSULATION

124. PITCH POCKET (NAD)

125. EQUIPMENT PENETRATION PATCH TAR (NAD)

THE GOAL OF THE PRE-CONSTRUCTION SURVEY WAS TO IDENTIFY READILY ACCESSIBLE ACM THAT MAY BE IMPACTED BY THE RENOVATION PROJECT ASSOCIATED WITHIN ROOM B200 AND ROOFING SYSTEM IN SUPPORT OF THE EHRM

INFRASTRUCTURE UPGRADES. PENNONI’S SURVEY DID NOT INCLUDE AREAS OUTSIDE THE SCOPE OF RENOVATION AS WELL AS OPERATIONAL UTILITY SYSTEMS, BELOW-GRADE OR SUBFLOOR SAMPLING, CONCEALED PIPE CHASE SPACES, INACCESSIBLE CRAWLSPACES ASSOCIATED WITH FOUNDATIONS, OR THE EXTERIOR. HAZARDOUS MATERIALS MAY BE PRESENT IN THESE AREAS. THE VA SHOULD BE CONTACTED IMMEDIATELY IF RENOVATION OR DEMOLITION ACTIVITIES

UNCOVER MATERIALS THAT ARE NOT IDENTIFIED IN THIS REPORT.

1 LAYER TYPE "X" GWB EACH SIDE. REFER

TO UL DOCUMENT FOR PANEL THICKNESS -

COORDINATE WITH METAL STUD SIZE

PROVIDE BATT INSULATION IF REQUIRED

BY UL DOCUMENT BASED ON STUD SIZE

AND GWB THICKNESS

5/8" G.W.B.

METAL STUDS FRAMING - REFER TO UL

DOCUMENT FOR SIZE, SPACING AND WIDTH -

COORDINATE WITH GWB THICKNESS

BASE - SEE FINISH

SCHEDULE FOR TYPE

STEEL TRACK, FASTEN 2'-0" OC MAX.

FLOOR SLAB

S E

E S

C H

E D

U

LE

P A

R T

IT

IO

N W

ID

T

H

FIRE RATED SEALANT, BOTH SIDES -

REFER TO UL DOCUMENT

UNDERSIDE OF

STRUCTURE

ICRA GENERAL NOTES:

1. FOR EXISTING PARTITIONS USED AS ICRA BARRIERS, THE CONTRACTOR

SHALL COMPLETE THE FOLLOWING:

· MODIFY EXISTING PARTITION TO A ONE-HOUR RATED ICRA BARRIER

· EXTEND PARTITION TO FLOOR DECK WITH 5/8” G.W.B. ON EACH SIDE

· FINISH WALL PARTITION AS DIRECTED BY UL RATING

REQUIREMENTS

· INFILL EXISTING OPENINGS WITH 5/8” G.W.B ON EACH SIDE

· PROVIDE FIRESTOPPING AT ALL EXISTING PENETRATIONS

2. PROVIDE 45 MINUTE RATED DOOR TO ACCESS CONSTRUCTION AREA AT

ALL NEW AND EXISTING ICRA BARRIERS. DOORS SHALL BE 3X7. SELF

CLOSING WITH POSITIVE LATCHING. PROVIDE STOREROOM FUNCTION

LOCKSETS.

3. THE CONTRACTOR SHALL NOT BLOCK SPRINKLER PROTECTION ON THE

VA-OCCUPIED SIDE OF THE ICRA BARRIER.

BASE

HEAD

PLAN

EXISTING CEILING OUTSIDE CONSTRUCTION

AREA - MODIFY AS REQUIRED FOR

TEMPORARY PARTITION.

UL NO. U419 - 1 HOUR RATED

N

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseArchitect/Engineer of Record StampConsultant

321 4 5 6 7 8 9 10

Sprinkler Status

AE Works, LTD.

418 Beaver Street

Sewickley, PA 15143

Phone: 412-287-7333 www.aeworks.comAE WORKS®1900 Market Street, Suite 300 Philadelphia, PA 19103

215.222.3000

8815 Centre Park Drive, Suite 200 Philadelphia, MD 21045

410.750.2246

A u to d e s k D o c s /V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r/ V

C H

A -0

C h a rl e s to n E

H R

M D a ta

C e n te r.

rv t

/4 /2

:4

:5

P M

G121

ICRA AND ABATEMENT EHRM DATA CENTER UPGRADES

FOR JSA-FDS - CHARLESTON, SC

109 BEE ST. CHARLESTON SC 29401

534-24-706

02.06.26 LP TW

BID DOCUMENTS

# Revisions Date

ICRA BARRIER

WS AA LM LO O

H F

174 SF / 16.1 m²

VOL SVC

NO NAME

B201 240 SF / 22.3 m²

DIAG IMG

NUCLEAR MEDICINE PHYSICIANS

OFFICES

B202

179 SF / 16.7 m²

DIAG IMG

NUC MED WAIT RM

B203

200 SF / 18.6 m²

DIAG IMG

BONE DENSITOMETER

B206E

576 SF / 53.5 m²

DIAG IMG

WAIT AREA

D200

283 SF / 26.3 m²

DIAG IMG

X-RAY RM - 1

D243 52 SF / 4.8 m²

DIAG IMG

CLEAN LINEN

D244

79 SF / 7.3 m²

DIAG IMG

PAT HOLDING

D245

166 SF / 15.4 m²

DIAG IMG

NO SIGN

D246

COMMON

CORR

COR2CD1

205 SF / 19 m²

VERTICAL SPACE

STAIR

44 SF / 4.1 m²

COMMON

ELEC CLO

A290

VERTICAL SPACE

387 SF / 36 m²

COMMON

ELEV LOBBY

ELVLOB2

VERTICAL SPACE

89 SF / 8.3 m²

VERTICAL SPACE

ELEV

P-4

40 SF / 3.7 m²

CONTROL RM

17 SF / 1.6 m²

COMMON

ELEC CLO

D200A

69 SF / 6.4 m²

COMMON

TELECOM CLO

B280

98 SF / 9.1 m²

VERTICAL SPACE

ELEV

S-1

93 SF / 8.6 m²

VERTICAL SPACE

ELEV

S-2

84 SF / 7.8 m²

DIAG IMG

NRS PRACTITIONER

B202A

97 SF / 9 m²

DIAG IMG

STAFF RAD

B202F

982 SF / 91.2 m²

DIAG IMG

CORR

COR2BD1

33 SF / 3 m²

VERTICAL SPACE

CHASE

RCC209C

56 SF / 5.2 m²

VERTICAL SPACE

CHASE

RCC223C

46 SF / 4.3 m²

VERTICAL SPACE

CHASE

RCC224C

188 SF / 17.4 m²

7 SF / 0.7 m²

COMMON

FAC

RCC201R

21 SF / 1.9 m²

SURGICAL

CHASE

RCC235C

349 SF / 32.4 m²

DIAG IMG

IMAGING RM #1

B206F

FEC

FEC

115'-6" MTD

56'-10" CPT

PROJECT AREA

SECOND FLOOR

N

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

OFFICE OF

CONSTRUCTION

AND FACILITIES

MANAGEMENT

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseArchitect/Engineer of Record StampConsultant

321 4 5 6 7 8 9 10

Sprinkler Status

AE Works, LTD.

418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.aeworks.comAE WORKS®1900 Market Street, Suite 300

Philadelphia, PA 19103 215.222.3000

8815 Centre Park Drive, Suite 200 Philadelphia, MD 21045

410.750.2246

EHRM DATA CENTER UPGRADES

FOR JSA-FDS - CHARLESTON, SC

109 BEE ST. CHARLESTON SC 29401

534-24-706

02.06.26 JAH BWE

100% CONSTRUCTION

DOCUMENTS

# Revisions Date

LS101

LIFE SAFETY PLAN -

DATA CENTER

1/4" = 1'-0"1 LIFE SAFETY PLAN - DATA CENTER

XX m MTD

GROSS DOOR WIDTH

(NET CLEAR WIDTH)

(MM)

EXIT

SMOKE RESISTIVE

1-HOUR SMOKE BARRIER

1-HOUR FIRE BARRIER

2-HOUR FIRE BARRIER

3-HOUR FIRE WALL

EXISTING FIRE EXTINGUISHER

(2-A:C CO2)

AREA NOT IN SCOPE

XXX XXX

XXXXXX

CAPACITY

# OF PEOPLE

STAIR WIDTH

(MM)

ACTUAL LOAD

# OF PEOPLE

LEGEND

XX m CPT

TRAVEL DISTANCE TO EXIT

COMMON PATH OF TRAVEL

DEAD END DISTANCE

EXIT CAPACITY

FEC

XX m MDE

IBC: TYPE 1B

NFPA 220: TYPE II (222)

FIRE-RESISTANCE RATING OF FLOOR/CEILING ASSEMBLY:

2 HOUR

CONSTRUCTION TYPE

· NFPA 101®, LIFE SAFETY CODE®, 2021 EDITION

· INTERNATIONAL BUILDING CODE, 2021 EDITION

· VA FIRE PROTECTION DESIGN MANUAL(VAFPDM) - NINTH EDITION, NOVEMBER 2023

· NFPA 13, STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS - 2022 EDITION

· NFPA 25, STANDARD FOR THE INSPECTION, TESTING, AND MAINTENANCE OF WATER-BASED FIRE

PROTECTION SYSTEMS - 2023 EDITION

· NFPA 70, NATIONAL ELECTRICAL CODE - 2023 EDITION

· NFPA 72, NATIONAL FIRE ALARM AND SIGNALING CODE - 2022 EDITION

· NFPA 75, STANDARD OF THE FIRE PROTECTION OF INFORMATION TECHNOLOGY EQUIPMENT - 2020 EDITION

· NFPA 2001, STANDARD ON CLEAN AGENT FIRE EXTINGUISHING SYSTEMS - 2022 EDITION

APPLICABLE CODES & STANDARDS

COMPLETELY SPRINKLER-PROTECTED

IBC: GROUP I-2 (SECTION 308.3.1.2)

NFPA 101: EXISTING HEALTH CARE (CHAPTER 19)

USE AND OCCUPANCY TYPE

GENERAL NOTES

1. THIS RENOVATION DOES NOT IMPACT THE OCCUPANT LOAD WITHIN THE AREA

OF WORK. THE MEANS OF EGRESS FOR THE BUILDING IS AN EXISTING

APPROVED CONDITION.

2. INTERIM LIFE SAFETY MEASURES (ILSM'S) MUST BE PLANNED, REVIEWED AND

IMPLEMENTED PRIOR TO ANY CHANGES/CONSTRUCTION IN EGRESS

CORRIDORS DUE TO DOOR AND WALL WORK.

3. EXISTING DATA ROOM ENCLOSURE PROVIDED WITH 1-HOUR FIRE BARRIERS

AND 60-MINUTE FIRE-RATED DOORS. EXISTING DATA ROOM DOES NOT HAVE

ANY SMOKE BARRIER WALLS SHOWN.

4. PENETRATIONS OF FIRE-RATED ASSEMBLIES SHALL BE SEALED WITH A U.L.

CERTIFIED THROUGH-PENETRATION SYSTEM APPROPRIATE FOR THE

MATERIALS INVOLVED AND THE RATING OF THE WALL PENETRATED.

5. THE NEW DATA ROOM SHALL BE CLASSIFIED AS A MISSION CRITICAL

TELECOMMUNICATION SPACE.

6. THERE ARE NUMEROUS PENETRATIONS IN THE EXISTING RATED WALLS. ALL

PENETRATIONS IN ALL ROOM RATED WALLS SHALL BE FIRESTOPPED WITH

APPROPRIATE UL CERTIFIED SYSTEMS.

7. PATCH AND REPAIR EXISTING WALLS BOTH ABOVE AND BELOW EXISTING

CEILING TO ENSURE SPACE IS AIR-TIGHT PRIOR TO NEW WORK.

THE PROJECT INVOLVES THE RENOVATION OF DATA CENTER ROOM (B200) LOCATED ON FLOOR 2 OF THE CHARLESTON, SOUTH CAROLINA VA MEDICAL CENTER, BUILDING 1. THE NEW DATA CENTER WILL CONTAIN

ITS OWN WET-PIPE SPRINKLER, CLEAN AGENT, AND FIRE ALARM SYSTEMS.

SCOPE OF WORK

EXISTING HEALTHCARE

ZONE PACU/SURGERY

20,890 SQ FT

EXISTING HEALTHCARE

ZONE RADIOLOGY

17,310 SQ FT

EXISTING HEALTHCARE

ZONE SLEEP LAB / SPEC. CLINIC

11,235 SQ FT

1. ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH THE "2021 INTERNATIONAL BUILDING CODE" (IBC 2021) AS ADOPTED BY THE STATE OF SOUTH

CAROLINA AS WELL AS ALL APPLICABLE FEDERAL, STATE AND LOCAL CODES.

2. ALL CODES AND STANDARDS REFERENCED IN THESE NOTES APPLY TO THE DESIGN, CONSTRUCTION, DEMOLITION, QUALITY CONTROL AND SAFETY OF ALL WORK PERFORMED ON THE PROJECT. UNLESS SPECIFICALLY STATED, USE THE LATEST ADOPTED EDITIONS OF THE CODES AND STANDARDS.

3. THE STRUCTURAL DRAWINGS ARE INTENDED TO BE USED IN CONJUNCTION WITH THE ARCHITECTURAL AND ALL OTHER APPLICABLE DISCIPLINE DRAWINGS. IN CASE OF CONFLICT BETWEEN THE NOTES, DETAILS, AND SPECIFICATIONS, THE MOST RIGID REQUIREMENTS SHALL GOVERN. IF THERE IS A DISCREPANCY BETWEEN DRAWINGS, IT IS THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY THE DESIGNER'S OF RECORD PRIOR TO PERFORMING THE WORK.

4. ALL SECTIONS AND DETAILS, WHETHER EXPLICITLY CUT ON PLAN OR NOT, SHALL BE CONSIDERED TYPICAL AND APPLY AT SIMILAR CONDITIONS. MINOR DETAILS OR INCIDENTAL ITEMS NOT SHOWN OR SPECIFIED, BUT NECESSARY FOR A PROPER AND COMPLETE INSTALLATION SHALL BE INCLUDED IN THE WORK AT NO ADDITIONAL COST. SIGNIFICANT ADJUSTMENTS ACCOUNTING FOR VARYING CONDITIONS IN THE FIELD SHOULD BE SUBMITTED TO THE DESIGNER'S OF

RECORD FOR APPROVAL AND BE RESOLVED PRIOR TO BEGINNING WORK.

5. GENERAL CONTRACTOR'S RESPONSIBILITIES:

A. THE CONTRACTOR SHALL NOT MAKE DEVIATIONS FROM THE DESIGN DOCUMENTS WITHOUT WRITTEN APPROVAL FROM THE DESIGNER'S OF RECORD.

CHANGES BY THE CONTRACTOR, DUE TO CONTRACTOR PROPOSED ALTERNATIVES OR TO CORRECT CONTRACTOR ERRORS/OMISSIONS, MUST BE SUBMITTED TO THE DESIGNER'S OF RECORD FOR APPROVAL. THE CONTRACTOR IS RESPONSIBLE FOR ALL COSTS, INCLUDING ENGINEERING FEES FOR REVIEW, SITE OBSERVATIONS, STRUCTURAL CALCULATIONS AND DRAWING REVISIONS. THE CONTRACTOR SHALL ALSO PROCESS THE REVISED PLANS REFLECTING ALL SUBSTITUTIONS THROUGH THE APPROPRIATE OFFICE OF ALL GOVERNING AGENCIES.

B. THE CONTRACTOR SHALL ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION OF THIS PROJECT, INCLUDING THE SAFETY OF ALL PERSONS AND PROPERTY. THIS REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS. THE CONTRACTOR SHALL DEFEND, INDEMNIFY, AND HOLD THE ENGINEER FREE AND HARMLESS OF LIABILITY, REAL OR ALLEGED, IN CONNECTION WITH THE PERFORMANCE OF WORK ON THE PROJECT, EXCEPT FOR LIABILITY ARISING FROM THE SOLE NEGLIGENCE OF THE ENGINEER.

C. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL WORK AND COORDINATION INVOLVED TO PROVIDE OPENINGS, CHASES, CONCRETE HOUSEKEEPING PADS, INSERTS, SLEEVES AND DEPRESSIONS INDICATED ON THE ARCHITECTURAL, STRUCTURAL, MECHANICAL, ELECTRICAL, AND PLUMBING DRAWINGS.

OPENINGS SHOWN ON THE STRUCTURAL DRAWINGS SHALL NOT BE REVISED WITHOUT APPROVAL FROM THE ENGINEER.

D. IT IS THE CONTRACTOR'S RESPONSIBILITY TO VERIFY THAT THE WEIGHT OF SUPERIMPOSED DEAD LOADS RESULTING FROM MEP EQUIPMENT INSTALLED IN THE FIELD DOES NOT EXCEED THE ALLOWABLE MEP LOADS DESIGNATED ON THE LOAD MAPS AND PLANS. THE CONTRACTOR SHALL NOTIFY THE STRUCTURAL ENGINEER IF THE WEIGHT OF PROVIDED MEP EQUIPMENT EXCEEDS THAT SHOWN ON THE LOAD MAPS AND PLANS AND PROVIDE

REINFORCING AS NECESSARY AT HIS/HER OWN EXPENSE.

E. THE CONTRACTOR SHALL VISIT THE SITE AND VERIFY AND ESTABLISH ALL EXISTING SITE CONDITIONS, DIMENSIONS, ELEVATIONS AND LOCATE ALL UTILITIES PRIOR TO STARTING ANY CONSTRUCTION. IF THE EXISTING FIELD CONDITIONS DO NOT PERMIT THE INSTALLATION OF THE WORK IN ACCORDANCE WITH THE DETAILS SHOWN, THE CONTRACTOR SHALL NOTIFY THE DESIGNER'S OF RECORD IMMEDIATELY AND PROVIDE A SKETCH OF THE CONDITION WITH HIS/HER PROPOSED MODIFICATION OF THE DETAILS FOR APPROVAL PRIOR TO COMMENCING WORK. FAILURE TO NOTIFY THE DESIGNER'S OF RECORD OF UNSATISFACTORY CONDITIONS CONSTITUTES ACCEPTANCE OF THE UNSATISFACTORY CONDITIONS.

F. THE CONTRACTOR SHALL VERIFY ALL EXISTING STRUCTURES RELATED TO THE PROJECT. STRUCTURAL MEMBERS IDENTIFIED ON THESE DRAWINGS AS EXISTING (EXST) WERE OBTAINED DURING LIMITED FIELD OBSERVATIONS AND/OR FROM LIMITED EXISTING DRAWINGS (IF AVAILABLE.) ACTUAL CONDITIONS MAY DIFFER FROM THAT WHICH IS INDICATED ON THE PLANS AND DETAILS. IF FIELD CONDITIONS VARY FROM THOSE SHOWN ON THESE DRAWINGS, THE CONTRACTOR SHALL CONTACT THE DESIGNER'S OF RECORD IMMEDIATELY. ALL FIELD DIMENSIONS ARE TO BE VERIFIED AND NOTED AS

SUCH ON SHOP DRAWINGS PRIOR TO FABRICATION OF ANY NEW STRUCTURAL MEMBERS.

G. WHERE PROPOSED WORK INVOLVES ALTERATIONS OF THE EXISTING SUPPORTING STRUCTURE, THE CONTRACTOR SHALL PROVIDE TEMPORARY SHORING AND PROTECTION REQUIRED TO ENSURE THE STRUCTURAL INTEGRITY OF THE EXISTING STRUCTURE.

H. THE CONTRACTOR SHALL ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR SAFEGUARDS DURING CONSTRUCTION, AS REQUIRED PER THE APPLICABLE EDITION OF THE INTERNATIONAL BUILDING CODE AS WELL AS ALL APPLICABLE FEDERAL, STATE, AND LOCAL CODES. WHERE ADDITIONAL ENGINEERING SERVICES OUTSIDE THE SCOPE OF THESE CONSTRUCTION DOCUMENTS ARE REQUIRED AS PART OF SAFEGUARDS DURING CONSTRUCTION, THE

CONTRACTOR SHALL NOTIFY THE OWNER AND ENGINEER PRIOR TO CONSTRUCTION COMMENCING.

6. THE STRUCTURAL DRAWINGS SHALL GOVERN THE WORK FOR ALL STRUCTURAL FEATURES, UNLESS NOTED OTHERWISE. THE ARCHITECTURAL DRAWINGS SHALL GOVERN THE WORK FOR ALL DIMENSIONS AND INFORMATION NOT SHOWN. WORKING DIMENSIONS SHALL NOT BE SCALED FROM STRUCTURAL PLANS, SECTIONS, OR DETAILS. ANY REFERENCE TO WATERPROOFING AND FIREPROOFING ON THE STRUCTURAL DRAWINGS ARE FOR REFERENCE ONLY, REFER TO

THE ARCHITECTURAL DRAWINGS FOR SPECIFIC REQUIREMENTS.

7. THE STRUCTURAL DRAWINGS ARE ONLY INTENDED TO CONVEY THE REQUIREMENTS OF THE STRUCTURE DOCUMENTED IN THESE PLANS. THE STRUCTURAL DRAWINGS SHOULD NOT BE USED AS MEANS OF COORDINATING BETWEEN TRADES OR DISCIPLINES.

8. THE CONTRACTOR IS TO PROVIDE SUBMITTALS FOR ALL STRUCTURAL MATERIALS, TO THE DESIGNER'S OF RECORD FOR REVIEW PRIOR TO THE START OF

FABRICATION OR THE COMMENCEMENT OF WORK.

A. REPRODUCTION OF ANY PORTION OF THE STRUCTURAL CONTRACT DRAWINGS FOR RE-SUBMITTAL AS SHOP DRAWINGS IS PROHIBITED AND SUBMITTAL

OF SUCH DRAWINGS WILL BE REJECTED AND RETURNED.

B. SUBMITTALS SHALL BEAR THE CONTRACTOR'S STAMP OF APPROVAL WHICH CONSTITUTES CERTIFICATION THAT THE CONTRACTOR HAS VERIFIED ALL CONSTRUCTION CRITERIA, MATERIALS, AND SIMILAR DATA AND HAS CHECKED EACH DRAWING FOR COMPLETENESS, COORDINATION, AND…

This is the start of the file's text. The full file is on GovTribe.