Transmission & Substation Structures for Van Meter Substation
Solicitation number
IFB 25-072-JG
Issued by
Florida

About this file

This is a Bid Tabulation document for Kissimmee Utility Authority (KUA), a Florida-based utility agency, relating to Invitation for Bid (IFB) 25-072-JG for Transmission & Substation Structures for the Van Meter Substation. The procurement encompasses 15 total steel structures: 8 tubular steel transmission structures and 7 substation steel structures, with specifications detailed in Sections 33 71 16.23 and 33 72 14. The bid opening occurred on October 14, 2025, at 2:00 PM, with proposals due on October 7, 2025. The contract is structured as a fixed-price agreement with potential for additions or deletions during the contract term, and the targeted delivery date is July 1, 2026. Bidders were required to provide comprehensive pricing including labor, materials, equipment, transportation, overhead, and taxes, along with detailed vendor information such as manufacturer plant location, shipping method, and delivery capability, with structures to be shipped FOB destination.

Two vendors submitted timely bids for evaluation. Energy Reps Inc. (Klute) submitted a total bid of $952,506.95, comprising $816,584.71 for Item #1-8 (tubular steel transmission structures) and $135,922.24 for Item #9-15 (substation steel structures), with a 65-week lead time. Superior Power Products LLC (Dis-Tran Steel, LLC) submitted the apparent low bid of $910,474.00, comprising $721,241.00 for Item #1-8 and $189,233.00 for Item #9-15, with a 56-week lead time. All bids are subject to KUA's terms and conditions, and any additional terms submitted by bidders are rejected unless formally approved through addenda. The tabulation indicates that Superior Power Products LLC is the apparent low bidder, subject to final evaluation and review before an intent to award is made.

View the file

Other files

File Type Posted
IFB_25-072-JG_Notice_of_Intent.pdf PDF
IFB_25-072-JG_Notice_of_Intent.pdf PDF
IFB_25-072-JG_Bid_Tabulation.pdf PDF
IFB_25-072-JG_Bid_Opening_Names.pdf PDF
IFB_25-072-JG_Bid_Opening_Names.pdf PDF
IFB_25-072-JG_Addendum_4.pdf PDF
IFB_25-072-JG_MarkUp_File_Drawings_with_Questions.pdf PDF
IFB_25-072-JG_S7400_REV_C_Revised_Drawings.pdf PDF
IFB_25-072-JG_Addendum_4.pdf PDF
IFB_25-072-JG_Van_Meter_Transmission_Loads-Addendum_4.xlsx XLSX spreadsheet
IFB_25-072-JG_MarkUp_File_Drawings_with_Questions.pdf PDF
IFB_25-072-JG_S7400_REV_C_Revised_Drawings.pdf PDF
IFB_25-072-JG_Van_Meter_Transmission_Loads-Addendum_4.xlsx XLSX spreadsheet
IFB_25-072-JG_Addendum_3.pdf PDF
IFB_25-072-JG_Addendum_3.pdf PDF
IFB_25-072-JG_Addendum_3.pdf PDF
IFB_25-072-JG_Addendum_2.pdf PDF
IFB_25-072-JG_Addendum_2.pdf PDF
IFB_25-072-JG_Addendum_2.pdf PDF
IFB_25-072-JG_REVISED_SECTION_3-Addendum_1.pdf PDF
IFB_25-072-JG_Addendum_1.pdf PDF
IFB_25-072-JG_Addendum_1.pdf PDF
IFB_25-072-JG_REVISED_SECTION_3-Addendum_1.pdf PDF
IFB_25-072-JG_Addendum_1.pdf PDF
IFB_25-072-JG_REVISED_SECTION_3-Addendum_1.pdf PDF
Exhibit_A_Price_Sheet.xlsx XLSX spreadsheet
IFB_25-072-JG_Transmission_&_Substation_Structures_for_Van_Meter_Substation.pdf PDF
Exhibit_A_Price_Sheet.xlsx XLSX spreadsheet
IFB_25-072-JG_Transmission_&_Substation_Structures_for_Van_Meter_Substation.pdf PDF
Exhibit_A_Price_Sheet.xlsx XLSX spreadsheet
IFB_25-072-JG_Transmission_&_Substation_Structures_for_Van_Meter_Substation.pdf PDF
Exhibit_A_Price_Sheet.xlsx XLSX spreadsheet
IFB_25-072-JG_Transmission_&_Substation_Structures_for_Van_Meter_Substation.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kissimmee Utility Authority Finance & Administration 1701 W. Carroll Street Kissimmee, Florida 34741 Phone: (407) 933-9809

VENDOR NAME→ ENERGY REPS INC (KLUTE)

SUPERIOR POWER

PRODUCTS LLC (DIS-

TRAN STEEL, LLC)

N/A N/A N/A N/A N/A

ITEM # 1 - 8 - TUBULAR STEEL

TRANSMISSION STRUCTURES $816,584.71 $721,241.00

ITEM # 9 - 15 - SUBSTATION

STEEL STRUCTURES $135,922.24 $189,233.00

LEAD TIME (IN WEEKS) 65 56

TOTAL $952,506.95 $910,474.00

OPENED BY:JENNIFER GRIEVES VERIFIED BY:

Solicitation Tabulation

Remarks: Offers from the vendors listed herein are the only offers received timely as of the above opening date and time. All other offers submitted in response to this solicitation, if any, are hereby rejected as late. Shaded or circled prices indicates apparent low bidder subject to evaluation and review before an intent to award is made.

Rules: All bids accepted by Kissimmee Utility Authority are subject to the Agencies terms and conditions and any and all additional terms and conditions submitted by the bidders are rejected and shall have no force and effect unless receiving prior consideration and approval of the Authority in the form of Addenda to this bid.

2:00 PM

10/14/25 Transmission & Substation Structures for Van Meter Substation IFB 25-072-JGSolicitation Number:

Solicitation Title Solicitation Opening Date:

Solicitation Opening Time

IFB 25-072-JG Bid Tabulation page 1 of 1

Ramandeep Mann

Tabulation

File details come from the government source that posted it. Updated .