I.B.08 Attachment 7 - FRP Small Business Decision Matrix.pdf

PDF 214 KB Posted

Attached to
Facilities Reduction Program (FRP) West Region IV Federal contract opportunity
Solicitation number
W912DY-20-R-0097
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

This document contains a small business decision matrix and related federal contract opportunity solicitation. The small business decision matrix evaluates project complexity, size, and risk factors to determine whether opportunities will be set aside for small businesses or competed unrestricted. Complexity is weighted at 40%, size at 20%, and risk at 40%. Opportunities receiving a combined rating of 5 or below from the factor rankings will be considered for small business competition.

The related federal contract opportunity solicitation is from the Department of the Army Corps of Engineers Engineering Support Center Huntsville. Solicitation number W912DY-20-R-0097 is for facilities reduction program services in West Region IV, including removal, demolition, abatement and disposal of contaminants from small to very large facilities. Services also include site assessments, removal of underground storage tanks, recycling, site restoration, data collection and reporting. Abatement services include environmental assessments, removal of contaminants such as asbestos and chemicals, waste stream redirection, transportation of hazardous and non-hazardous debris, environmental sampling, and proper disposal of regulated materials.

View the file

Other files for this federal contract opportunity

Other files attached to Facilities Reduction Program (FRP) West Region IV, newest first.
File Type Posted
Attachment 16 - Sample Task Order Rev 01.pdf PDF
I.B.08 FRP West Region IV_20R0097_Amendment 0012_11SEP2020.pdf PDF
Attachment 17 - Sample Task Order Attachment B Rev 02.xlsx XLSX spreadsheet
Attachment 16 - Sample Task Order Rev 01.docx DOCX document
Attachment 19_ Responses to Questions_FRP West_20R0097.pdf PDF
I.B.08 FRP West Region IV_20R0097_Amendment 0012_Conformed Copy_11SEP2020.pdf PDF
I.B.08 MFR_PD2 Counter Error_W912DY-20-R-0097_Signed.pdf PDF
I.B.01 FRP West Region IV Comb Synopsis_20R0097_27AUG2020--.pdf PDF
I.B.08 FRP West_Region IV_20R0097_Amendment 0001-.pdf PDF
I.B.08 Attachment 1 - Performance Requirements Summary.pdf PDF
I.B.01 FRP West Region IV Comb Synopsis_20R0097.pdf PDF
I.B.08 Attachment 6- Letter of Commitment (Key Subcontractor).pdf PDF
I.B.08 Attachment 5 - Small Business Participation Commitment.pdf PDF
I.B.08 Attachment 9 - Work Plans, Sub-Plans, and Appendices.pdf PDF
I.B.08 Attachment 3 - Experience Reporting Form.pdf PDF
I.B.08 Attachment 17 - Sample Task Order Attachment B rev01.xlsx XLSX spreadsheet
I.B.08 Attachment 10 - Accident Prevention Plan Checklist.pdf PDF
I.B.08 Attachment 16 - Sample Task Orderr.pdf PDF
I.B.08 Attachment 15 - Descriptive Data for ECPs and REAs.pdf PDF
I.B.08 Attachment 8 - Monthly Progress Report Format.pdf PDF
I.B.08 Attachment 2 - Quality Assurance Surveillance Plan.pdf PDF
I.B.08 RFP FRP West_Region IV_20R0097.pdf PDF
I.B.08 Attachment 11 - Safety and Health Program Requirements.pdf PDF
I.B.08 Attachment 4- Past Performance Questionnaire.pdf PDF
I.B.08 Attachment 14 Specification Guide 02221 - Ex-Back-Site.pdf PDF
I.B.08 Attachment 18 - Estimated Quantities.xlsx XLSX spreadsheet
I.B.08 Attachment 13 Specification Guide 02220 - Demolition.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 7 – Small Business Decision Matrix Project: Example Project

Risk Factors:

Size/Dollar Value:

Multiple Mobilizations, varying site restorations, long duration

$1,581,842

Complexity - 40% Risk - 40%

Examples (or similar complexities) Rank Examples (or similar risk) Rank

337 Development Services 1 Short duration, adequate infrastructure 1

ACM/ORM Assessment

Location, close to large city, airports, easy access to material and personnel

ACM/ORM Assessment + Medical Level 1 Assessment

Short duration without adequate infrastructure

ACM/ORM Assessment + Medical Level 2 Assessment

Long duration with adequate infrastructure

Demolition of simple structures with complete ACM/ORM Assessment already completed

0-6 months fieldwork duration without adequate infrastructure

ACM/ORM Assessment and Demolition of Simple Structures

6-12 months fieldwork Long duration with adequate infrastructure

Demolition of complex structures with complete ACM/ORM Assessment and or Medical Assessment already completed

Over 12 months fieldwork Long duration with adequate infrastructure, multiple mobilizations

ACM/ORM Assessment, Medical Assessment, and Demolition of Complex Structures

Negative publicity, High political visibility, reporting

Demolition of "Hardened" Structures 9 Remote locations with complex logistics 9

Demolition of extremely complex, damaged, and or hazardous, structures

Remote locations with complex logistics

Rank Evaluation

Composite Rank

6.2 Resulting decision is - Unrestricted

Process:

* Requirements will be reviewed to determine if they will be competed as Small Business or Unrestricted

* Complexity (40%), Size (20%), and Risk (40%) will be considered

* Each factor will receive a rating from 1 – 10

* Any requirement that receives a combined factor rating of 5 or below will be considered for competition by Small Business

* After the current year, the PDT may adjust the decision point either up or down

Size - 20%

Examples Rank

< 50k 1

< 100k

< 250k

< 600k

< 750k

< 1M

< 1.5M

< 2M

< 3M 9

>4M

File details come from the government source that posted it. Updated .