HSCG85‐15‐R‐P45450

Question and Answer Matrix 3

KTR requests a one week extension of the bid due date be granted. Bid is currently due Feb. 17, 2015, the day after Presidents Day and additionally KTR and its subcontractors need the additional time in order to provide USCG with our best price and proposal.

No extension will be granted.

KTR requests bidders questions submittal period be extended in order to fully develop understanding of the work scope.

No extension will be granted.

Attachment 2, Provisions

Availability

RFP states “Offerers shall provide a 90 day timeline….commencing no sooner than 15 April and no later than 30 April 2015. Is the start (commencing) date of the availability at KTR scheduling discretion or is it USCG option for an open two week window to arrive at the shipyard?

The start date (within the two week window) is at the prospective offeror's discretion and shall be provided with the proposal.

Specification Work Item D‐12

Temporary Fuel Offload

In order to formulate price & schedule KTR requests information regarding fuel off‐loading & on‐loading capabilities of vessel. 1) What rate of transfer, in gallons per hour, can KTR reasonably expect the vessel to be capable of during fuel transfers? 2) How many hours per day & what days of the week can the KTR expect vessel to perform fuel pumping operations?

PSTAR is configured with 2 fuel xfer pumps, Delaval IMO models B323FBX362 and CT‐3LB‐400P, on a single fuel xfer system. CG's best practice is to conduct fuel oil offloads starting an hour after sunrise and concluding one hour prior to sunset, with no restriction on days. While actual fuel flow rates vary with respect to the receiving facilities configuration (pipe specifics, boost pumps, storage height), POLAR STAR has attained fuel transfer flow rates as high as 700 gpm, as low as 250 gpm, with projected transitional delays as vessel approaches light ship fuel loading condition.

Attachment 2, Provisions

Deadlines14

HSCG85‐15‐R‐P45450

Question and Answer Matrix 3

Specification Work Item D‐14 3.2.2

U/W Body Preserve (Partial)

Para. 3.2.2 refers SFLC Spec 6310 Appendix A SFLC Std Spec 6310 Appendix A. Para.3.1.8.7 Flash rusting/surface oxidation limitations. For surfaces prepared by water jetting, the rust must be tight and adherent.International Paint Inertsheild 163 Inerta 160, Manufacturer’s Recommendations do not allow for any oxidation at all. “If oxidation has occurred between blasting and application of Inerta 160, the surface should be reblasted to specified visual standard. Will the USCG wave the Manufacturer’s recommendation of no oxidation between blasting and application and allow the Contractor to apply Inerta 160 over a WJ‐ 2M Moderate Flash Rusting?

The USCG will not waive Manufacturer’s Recommendations for paint application.