Att J.1 Specification
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment0009(11RP45002).pdf | ||
| Amendment0008(11RP45002).pdf | ||
| Amendment0007(11RP45002).pdf | ||
| Amendment0006(11RP45002).pdf | ||
| DWG 225-WLB_184_1_1_-_B.zip | ZIP file | |
| Amendment0005(11RP45002).pdf | ||
| 225B-WLB_256_3_(11RP45002).zip | ZIP file | |
| Amendment0004(11RP45002).pdf | ||
| Govt Property Rpt | — | |
| Amendment0003(11RP45002).pdf | ||
| 225-WLB_635_1_1_-_J.pdf | ||
| Amendment0002(11RP45002).pdf | ||
| SPAR DD12 Q004 WI 74 Drawing Refs.zip | ZIP file | |
| WORK ITEM 74 Rev1 Hydraulic Steering Cooler Install.pdf | ||
| Amendment0001(11RP45002).pdf | ||
| AttJ.3Clarification_Form(11RP45002).doc | DOC document | |
| Solicitation(SchedA-M)(11RP45002).doc | DOC document | |
| AttJ.2ElectronicSectionB(11RP45002).xls | XLS spreadsheet |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC SPAR (WLB 206)
225 FOOT "B CLASS" SEAGOING BUOY TENDER
SPECIFICATION FOR DRYDOCK REPAIRS
Developed By: CWO Ken Miller
(Rev-0, 26Aug 2011)
USCGC SPAR (WLB-225B) DRYDOCK AVAILABILITY 2012
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ....................................................................................................................................... iv Consolidated List of References ................................................................................................................. v Consolidated List of Government-furnished Property .............................................................................. xii Consolidated List of Critical Inspection Items ......................................................................................... xv Principal Characteristics .......................................................................................................................... xvi
General Requirements WORK ITEM 1: Hull Plating, U/W Body, Inspect WORK ITEM 2: Hull Plating (U/W Body), Ultrasonic Testing
WORK ITEM 3: Appendages (U/W), Leak Test WORK ITEM 4: Propulsion Shaft Fairwaters and Rope Guards, Inspect and Repair WORK ITEM 5: Appendages (U/W) - Internal, Preserve
WORK ITEM 6: Chain Lockers, Clean WORK ITEM 7: Tanks (MP Fuel Service), Clean WORK ITEM 8: Voids (Non-Accessible), Leak Test
WORK ITEM 9: Chain Lockers, Inspect
WORK ITEM 10: Tanks (MP Fuel Service), Inspect WORK ITEM 11: Voids (Non-Accessible), Preserve Internal Surfaces WORK ITEM 12: Cargo Hatch, Overhaul and Repair
WORK ITEM 13: Propulsion Shafting Remove, Inspect, and Reinstall WORK ITEM 14: Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renewal
WORK ITEM 15: Strain Gage Alignment, Check WORK ITEM 16: Propulsion Shaft Bearings (External), Check Clearances WORK ITEM 17: Propulsion Tail Shaft Sleeve, Skim Cut
WORK ITEM 18: Propulsion Shaft Bearing, Stave Renewal WORK ITEM 19: Controllable Pitch Propeller, System Maintenance
WORK ITEM 20: Controllable Pitch Propeller, Hub General Maintenance
WORK ITEM 21: Controllable Pitch Propellers, Clean and Inspect WORK ITEM 22: Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean WORK ITEM 23: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean WORK ITEM 24: Fathometer Transducer, Renew WORK ITEM 25: Doppler Speed Log Transducer (s), Renew WORK ITEM 26: Fwd Scan Sonar Transducer, General Maintenance
WORK ITEM 27: Sea Strainers - Duplex (All Sizes), Overhaul WORK ITEM 28: Sea Bay, Inspect WORK ITEM 29: Sea Bay, Preserve - Partial WORK ITEM 30: Sea Bay, Preserve 100%
WORK ITEM 31: Fixed CO2 FF Bottles, Inspect and Hydrostatic Test WORK ITEM 32: Rudder Stock Bearings, Check Clearances WORK ITEM 33: Rudder, Inspect and Repair
WORK ITEM 34: Rudder and Rudder Stock, Removal and Inspection WORK ITEM 35: Thruster Unit‟s (General), Overhaul iii (Rev-0)
WORK ITEM 36: Hydraulic Chain Stoppers, Overhaul WORK ITEM 37: Pad Eyes, Inspect and Test WORK ITEM 38: Crossdeck Winches, Overhaul WORK ITEM 39: Hydraulic Inhaul Winch, Overhaul
WORK ITEM 40: Mechanical Chain Stoppers, Overhaul WORK ITEM 41: Anchor Windlass, Overhaul ( Level 2 ) WORK ITEM 42: Anchor Chain (s) and Ground Tackle, Inspect and Repair WORK ITEM 43: Warping Capstan, Level 2 Inspect and Repair WORK ITEM 44: Buoy Cargo Hold Deck, Preserve 100%
WORK ITEM 45: Chain Locker, Preserve 100%
WORK ITEM 46: Chain Locker, Preserve Partial
WORK ITEM 47: Decks - Exterior( Buoy ), Preserve WORK ITEM 48: Decks - Exterior, Preserve ( “ Non-Skid Broadcast Grit” System) WORK ITEM 49: U/W Body, Preserve “100%” WORK ITEM 50: Stern Tube Interior Surfaces, Preserve 100%
WORK ITEM 51: Hull Plating Freeboard, Preserve “ 100% ” WORK ITEM 52: Cathodic Protection / Zincs, Renew
WORK ITEM 53: Impressed Current Cathodic Protection System Anodes, Renew WORK ITEM 54: Impressed Current Cathodic Protection System Reference Cells, Renew WORK ITEM 55: Impressed Current Cathodic Protection System Dielectric Shield (Capastic Fairing), Renew
WORK ITEM 56: Drydocking WORK ITEM 57: Temporary Services, Provide WORK ITEM 58: Temporary Messing and Berthing, Provide
WORK ITEM 59: Sea Trial Performance, Provide Support WORK ITEM 60: Buoy Chain (In-Haul ) Winch, Modify
WORK ITEM 61: Buoy Crane Swing Drive Brake Assemblies, Modify WORK ITEM 62: Air Conditioning Condenser Seawater Cooling Overboard Discharge Piping, Modify
WORK ITEM 63: Sea Valves and Waster Pieces, Overhaul or Renew WORK ITEM 64: Firemain Valves, Overhaul Or Renew
WORK ITEM 65: Auxiliary Sea Water System Valves, Overhaul Or Renew WORK ITEM 66: Bilges (Machinery Space), Preserve WORK ITEM 67: ATON Shop Deck, Preserve WORK ITEM 68: ATON Storeroom Deck, Preserve
WORK ITEM 69: Hawse Pipe, Renew WORK ITEM 70: Boat Boom, Inspect and Repair WORK ITEM 71: Single Point Davit, Inspect and Repair WORK ITEM 72: Buoy Crane, Inspect and Repair WORK ITEM 73: Transom Bulkhead Repair
WORK ITEM 74: Hydraulic Steering Cooler, Install iv (Rev-0)
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
Consolidated List of References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free or charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 225 WLB 184-001, Rev B, CRP-V850 Transducer Adaptor Ring
Coast Guard Drawing 225 WLB 549-001, Rev D, Onboard Lubrication Requirements
Coast Guard Drawing 225 WLB 573-011, Rev -, ATON Tie Downs
Coast Guard Drawing 225 WLB 573-202, Rev -, Buoy Chain Winch, Model CW1
Coast Guard Drawing 225 WLB 581-001, Rev E, Anchor Handling System Arrangement
Coast Guard Drawing 225 WLB 601-001, Rev G; General Arrang e ment Inboard and Outboard Profiles
Coast Guard Drawing 225 WLB 601-001, Rev M; General Arrangement Inboard & Outboard Profiles
Coast Guard Drawing 225 WLBB 601-002, Rev G Booklet of General Drawings
Coast Guard Drawing 225B W LB 424 -001, Rev C , Acoustic Navigation System Block & Isometric
Coast Guard Drawing 225B WLB 111-001, Rev A, Shell Expansion
Coast Guard Drawing 225B WLB 111-001, Rev A; Shell Expansion
Coast Guard Drawing 225B WLB 114-001, Rev C; Shell Appendages
Coast Guard Drawing 225B WLB 243-001, Rev C, Propulsion Shaft Arrangement
Coast Guard Drawing 225B WLB 243-001, Rev C, Propulsion Shafting Arrangement
Coast Guard Drawing 225B WLB 243-002, Rev E, Stern Tube and Bearings A&D
Coast Guard Drawing 225B WLB 256-001, Rev M, Seawater Cooling System Diagram
Coast Guard Drawing 225B WLB 256-1, Rev M, Seawater System Cooling Diagram
Coast Guard Drawing 225B WLB 256-4, Rev F, SW Cooling System FR 66 Aft Block 940, 950 & 970
Coast Guard Drawing 225B WLB 256-5, Rev -, Mods to Seawater Cooling Ovbd - A/C Condensers
Coast Guard Drawing 225B WLB 259-001, Rev C, Combustion Intake & Exhaust Diagram
Coast Guard Drawing 225B WLB 259-005, Rev C, Combustion Intake & Exhaust A&D Hull Block 940
Coast Guard Drawing 225B WLB 259-006, Rev C, Combustion Intake & Exhaust A&D Hull Blocks 970 & http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace vi (Rev-0)
Coast Guard Drawing 225B WLB 505-1, Rev D, General Requirements for Piping Systems
Coast Guard Drawing 225B WLB 508-1, Rev A, Thermal Insulation for Mchry, Equipment and Piping
Coast Guard Drawing 225B WLB 541-001, Rev G; Fuel Oil System Diagram
Coast Guard Drawing 225B WLB 549-001, Rev A, Onboard Lubrication Requirements
Coast Guard Drawing 225B WLB 555-005, Rev D, CO2 System A/D, Fr 48 Aft, Block 930, 940, 950, 960A
Coast Guard Drawing 225B WLB 555-006, Rev A, CO2 System, A/D, Flammable Liquid Storeroom, Blk 901, Coast Guard Drawing 225B WLB 555-007, Rev B, CO2 System, A/D, Emergency Generator Rm, Block 970
Coast Guard Drawing 225B WLB 556-001, Rev F, Hydraulic System Diagram
Coast Guard Drawing 225B WLB 562-002, Rev C; Rudder Structural A & D
Coast Guard Drawing 225B WLB 573-002, Rev -, Weight Handling System Arrangement
Coast Guard Drawing 225B WLB 573-011, Rev -, ATON Tie Downs
Coast Guard Drawing 225B WLB 581-001 Rev C, Anchor Handling System Arrangement
Coast Guard Drawing 225B WLB 601-002 Rev H, Booklet of General Drawings
Coast Guard Drawing 225B WLB 601-002, Rev G, Booklet of General Drawings
Coast Guard Drawing 225B WLB 633-001, Rev B, Cathodic Protection System Arrangement, Block Diagram, Wiring Deck Plan, and Elementary Diagrams
Coast Guard Drawing 225B WLB 633-002, Rev A; Cathodic protection passive
Coast Guard Drawing 225B WLB 801-006, Rev C; Docking Drawing
Coast Guard Drawing 225B WLB 801-006, Rev D, Docking Drawing
Coast Guard Drawing 225B WLB 801-006, Rev D; Docking Drawing
Coast Guard Drawing 225B WLB 801-6, Rev C, Docking Drawing
Coast Guard Drawing 225B WLB 114-001, Rev C, Shell Appendages
Coast Guard Drawing 225B WLB 114-002, Rev -, Flow Accelerating Fin
Coast Guard Drawing 225B WLB 541-007, Rev D; Incinerator Fuel Oil Service Tank
Coast Guard Drawing 225B WLB 568-001, Rev A, Bow Thruster A & D
Coast Guard Drawing 225B WLB 573-001, Rev E, Buoy Handling System Arrangement
Coast Guard Drawing 225B WLB 801-006, Rev D, Docking Drawing
Coast Guard Drawing 225B-WLB 561-003, Rev A; STEERING GEAR ARRANGEMENT
Coast Guard Drawing 225B-WLB 562-001, Rev B; STEERING COMPONENTS A/D
Coast Guard Drawing 225B-WLB 562-002, Rev C; RUDDER - STRUCT A & D
Coast Guard Drawing 225B-WLB 601 00 2 , Rev H, Booklet Of General Drawings
Coast Guard Drawing 225B-WLB 233-1, Rev C, Propulsion Train Installation Drawing
Coast Guard Drawing 225B-WLB 243-1, Rev C, Propulsion Shafting Arrangement
Coast Guard Drawing 225B-WLB 243-2, Rev E, Stern Tube and Bearing a & D
Coast Guard Drawing 225B-WLB 243-2, Rev E; Stern Tube and Bearing a & D
Coast Guard Drawing 225B-WLB 243-2, Rev E; Stern Tube and Bearing A & D
Coast Guard Drawing 225B-WLB 556-8, Rev C, CPP Hydraulic System Diagram
Coast Guard Drawing 225B-WLB 562-2, Rev C, Rudder Structural a & D
Coast Guard Drawing 225B-WLB 562-3, Rev -; Thordon Lower Rudder Stock Bearing
Coast Guard Drawing 225B-WLB 562-4, Rev -; Pintle Bearing
Coast Guard Drawing 225B-WLB 611-1, Rev D, Lifting Pads - Main and Aux Machinery Room
Coast Guard Drawing 225-WLB 243-203, Rev E, Stern Tube Split Dovetail Carrier Casting
Coast Guard Drawing 225-WLB 611-4, Rev J; Lifting Pads Outside Machinery Spaces
Coast Guard Drawing 225-WLB 631-2, Rev -, Painting Schedule, Hulls 202-205
Coast Guard Drawing 225-WLB 901-3, Rev -, Hull Block 901 Block Assembly
Coast Guard Drawing 225-WLB 244-203, Rev -, Stern Tube Split Dovetail Carrier Casting
Coast Guard Drawing FL 1204-3, Rev A; Welded Padeyes & Links
Coast Guard Drawing FL 2605-031, Rev D, Mechanical Chain Stopper, 1-7/8" Buoy Cha
Coast Guard Drawing FL 2605-034, Rev C, Mechanical Chain Stopper Repair K it: 1-7/8", 1-5/8" & 1-1/4" vii (Rev-0)
Coast Guard Drawing FL 2804-13, Rev G, Visual I D Kit Sched
Coast Guard Drawing FL 2804-15, Rev-, Draft Figs
Coast Guard Drawing FL 4823-60, Rev G, Cast Steel Waster Pieces
Coast Guard Drawing FL-2605-013, Rev-, Buoy Chain Model CW1: Pins
Coast Guard Drawing FL-2605-035, Rev-, Buoy Chain Winch Pedestal Bearing Modification
Coast Guard Drawing FL-7101-573, Rev J, Buoy Chain Winch, Model CW1
Coast Guard Fleet Drawing FL 2804-11, Rev D, Visual I D Numeral & Letter for Ships
Coast Guard Fleet Drawing FL 2804-12, Rev-, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL-2605-29, Rev B, Retractable Roller Assembly
Coast Guard Fleet Drawing FL-2605-30, Rev B, Chain Stopper Plate
NAVSEA Drawing 803-1385866, Rev Rev E; Penetrations; Bulkhead and Deck
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
NAVSEA Drawing 804-1385781, Rev E; Pipe Hangers for Surface Ships (Superseding Navsea Drawing .
810-1385781)
NAVSEA Drawing 810-1385880, Rev Rev D; Fittings, Cu-Ni Alloy, Slip on Sleeve
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series) , Coatings and Color Manual
Coast Guard Commandant Instruction (COMDTINST) M10360.3, (Series), Coatings and Colors Manual
Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and Color
Manual
Coast Guard Commandant Instruction (COMDTINST) M10360.3, (Series), Coatings and Colors Manual
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Coast Guard Te chnical Publication (TP) 3717, Jun 2003 , Hydraulic Cargo Hatch
Coast Guard Technical Publication (TP) 3498, Section A, Feb 200 8 , Buoy Chain Winch
Coast Guard Technical Publication (TP) 3498, Section A, Feb 2008, Buoy Chain Winch
Coast Guard Technical Publication (TP) 3523, APR 2002, SWBS 241-A, Reduction Gear - Model
96DHCMG-Cp
Coast Guard Technical Publication (TP) 3523-241-A&B, 225 WLB MIB, VOL 5, SWBS 241, GEAR, REDUCTION, MMC PN 241-01-01
Coast Guard Technical Publication (TP) 3523-242-A-C, 225 WLB MIB, SWBS 242, Coupling, Torsional, MMC PN 242-01-01 & 242-01-02
Coast Guard Technical Publication (TP) 3524, 07-JAN-97, Manufacturer's Instruction Book-SWBS Group(s)
243-262
Coast Guard Technical Publication (TP) 3524, Jan 1997, Manufacturer's Instruction Book-SWBS Group(s)
243-262
Coast Guard Technical Publication (TP) 3524-244-A, 225 WLM MIB, SWBS 244-A, Bearing, Line Shaft, MMC PN 244-01-03, TP 244-A
Coast Guard Technical Publication (TP) 3524-245-A&B, 225 WLB, SWBS 245-A & 245-B, Propeller
System, CPP, MMC PN 245-01-01,, 0
Coast Guard Technical Publication (TP) 3554, MAY 1996, Manufacturer's Instruction Book, SWBS 556
Coast Guard Technical Publication (TP) 3556, Jun 2009, Manufacturer’s Instruction Book-SWBS Group(s)
568, Bow and Stern Thruster – Model 125/3 STAY/FP
Coast Guard Technical Publication (TP) 3557, Section 573-C, Jul 2005, Manufacturer's Instruction Book-
SWBS Group 568-573, Buoy Crane – Model EB-480-60-40 (225B-Class)
Coast Guard Technical Publication (TP) 3558, Apr 2008, Manufacturer’s Instruction Book-SWBS Group(s)
573, Section A, Cross Deck Winch – Model BMD-390
Coast Guard Technical Publication (TP) 3558, Apr 2008, Manufacturer’s Instruction Book-SWBS Group(s)
573, Section B, Cross Deck Winch – Model BMD-471
Coast Guard Technical Publication (TP) 3559, JAN 1997, Manufacturer's Instruction Book - SWBS Group(s) viii (Rev-0)
573-582
Coast Guard Technical Publication (TP) 3559, Section 582B, Apr 2009, Aft Capstan, 21” - Model BMD-475
Coast Guard Technical Publication (TP) 3562, Aug 1998, Section a, Manufacturer's Instruction Book SWBS
Groups 583-589, RHIB Handling Davit P/S - Model RAD30-15.5
Coast Guard Technical Publication (TP) 3574, Mar 2009, Volume 1 of 1, SWBS Group 633-638, 225 FT
Juniper Class Seagoing Buoy Tender
Coast Guard Technical Publication (TP) 3762, 15-OCT-04, Daul Point Davit - ATON Workboat - Model
TWPIV5-0A
Coast Guard Technical Publication (TP) E-424-006, Version WLB97-1, Wesmar 3060-08/M-8/AC Forward
Scan Sonar
COMDTINST M10360.3 (series) , Coatings and Colors Manual
COMDTINST M10360.3, Coatings and Colors Manual, Revision C
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, Jan 2009; General
Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0740, Jan 2009, Welding and Allied
Processes
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0850, Jun 2009, General
Requirements for Drawing Preparation
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 5000, Jan 2009, Inspect, Repair, And
Test Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000 ), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0000 (Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std 0740), Jan 2009, Welding and Allied
Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740 ), Jan 2009, Welding and
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740 ), Jan 2009, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), Jan 2009, Shipboard
Electrical, Cable Removal, Relocation, Splice, Repair and Installation
Surface Forces Logistics Center Standard Specification 5 000 (SFLC Std Spec 5000 ), Jan 2009, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), Jan 2009, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), Jan 2009, Provide
Temporary Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Jan 2009, Temporary
Hull Accesses
Surface Forces Logistics Command (SFLC) Naval Engineering Directive (NED) 5735-01, Inspection and Test
Procedure For Buoy Chain Winch Model CW-1 Onboard WLM 551-564 and WLB 201-215, May 2010
Technical Publication 7610-01-GF5-8501, Apr 1995, AN/SRD-421 Sperry Doppler Speed Log
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power ix (Rev-0)
Tool Cleaning
OTHER REFERENCES
A S TM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component
Adhesives (An)
AAA/CAA - http://www.aaan e wsroom.net/Main.asp?CategoryID=9&SubCategoryID=22&
American Society for Testing and Materials (ASTM) A105/A105M, 2005; Standard Specification for Carbon
Steel Forgings for Piping Applications
American Society for Testing and Materials (ASTM) A106/A106M, 2006a; Standard Specification for
Seamless Carbon Steel Pipe for High-Temperature Service
American Society for Testing and Materials (ASTM) A181/A181M, 2006; Standard Specification for Carbon
Steel Forgings, For General-Purpose Piping
American Society for Testing and Materials (ASTM) A27/A27M, 2005; Standard Specification for Steel
Castings, Carbon, For General Application
American Society for Testing and Materials (ASTM) A36/A36M, 2005; Standard Specification for Carbon
Structural Steel
American Society for Testing and Materials (ASTM) A519, 2006; Standard Specification for Seamless Carbon and Alloy Steel Mechanical Tubing
American Society for Testing and Materials (ASTM) B151/B151M, 2005; Standard Specification for Copper-
Nickel-Zinc Alloy (Nickel Silver) And Copper-Nickel Rod and Bar
American Society for Testing and Materials (ASTM) B171/B171M, 2004; Standard Specification for Copper-
Alloy Plate and Sheet for Pressure Vessels, Condensers, And Heat Exchangers
American Society for Testing and Materials (ASTM) F683, 2003a; Standard Practice for Selection and
Application of Thermal Insulation for Piping and Machinery
American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding
End
American Society of Mechanical Engineers (ASME) B16.5, Rev 2003, 12/1/2003; Pipe Flanges & Flanged
Fittings: Nps 1/2 Through Nps 24
ASTM International (AS T M) D5363, 2008; Standard Specification for Anaerobic Single-Component
Adhesives (An)
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel
ASTM International (ASTM) D5363, 2008, Standard Specification for Anaerobic Single Component
Adhesives (An)
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health Standards for Shipyard Employment
Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-
Petrolatum
Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting
Commercial Item Descriptions (CID) A-A-59323, Rev A; Cloths, Cleaning, Low-Lint
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Federal Specification (Fed Spec) RR-C-271, Nov 1995, Chain and Attachments, Welded and Weldless
Federal Specification HH-P-151, Rev F, Not 1; Packing, Rubber Sheet, Cloth Insert x (Rev-0)
FL 1204-3. Rev -; WLEDED PADEYES AND LINKS
FORBES (formerly MOBIL) Travel Guide - http://www.forbestravelguide.com/
Hotel and Motel Fire Safety Act of 1990 (PL101-391)
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball
Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze
Gate, Globe, Angle and Check Valves
MIL PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-A-22262, Mar 1 9 96; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-C-24633 , Apr 1998 , Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded
MIL-DTL-15024, Rev Rev F, 11/28/1997; Plates, Tags and Bands for Identification of Equipment
MIL-DTL-23549, Feb 2007 , Grease, General Purpose
MIL-G-24696, Rev B, Amd 1; Gasket, Sheet, Non-Asbestos
MIL-PRF-1149, Rev Rev D, 6/10/1998; Gasket Materials, Synthetic Rubber, 50 and 65 Durometer Hardness
MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application
MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-S-22473 , Rev E(8); Sealing, Locking, and Retaining Compounds: (Single Component), 11/18/1993
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-STD-1627, Rev Rev C, 9/30/1994; Bending of Pipe or Tube for Ship Piping Systems
MIL-T-16420, Rev Rev K, Amd 1, 9/16/1988; Tube, Copper-Nickel Alloy, Seamless and Welded (Copper
Alloy Numbers 715 and 706)
Naval Sea Systems Command (NAVSEA) S9243-AW-TRS-011, Surface Ships Main Propulsion Shafting
Refurbishment Procedures, Volume I, Part 1
Naval Sea Systems Command (NAVSEA) S9243-AW-TRS-012, Surface Ships Main Propulsion Shafting
Examination, Test and Repair Action Record, Volume 1, Part 2
Naval Sea Systems Command (NAVSEA) T9074-AS-GIB-010/271, Apr 1997, Requirements for
Nondestructive Testing Methods
NAVSEA Dwg 803-2145807, Propulsion Shafting & Components
NAVSEA Dwg 803-5001104, Rev -; Rudder Stock Bearings and Seals
ODOM Echotrac DF3200 MKII, Rev 2, Technical Manual
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and
Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 1999, Grease, Plug
Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation St a ndard
SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel Surfaces
Prepared by Dry Abrasive Blast Cleaning
The Society for Protective Coatings (SSPC), June 1996, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages xi (Rev-0)
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard
SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard
SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard
SSPC-SP 12/NACE No.5, 2004, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and
Ultrahigh Pressure Water Jetting
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard
SSPC-SP 12/NACE No.5, 2007, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and
Ultrahigh Pressure Water Jetting
The Society for Protective Coatings (SSPC)/NACE Joint Surface Preparation Standard SSPC-SP 10/NACE
No.2, 2004, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard
SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)-SP 3, Power Tool Cleaning, 11-1-1982
The Society for Protective Coatings SSPC-SP 10/NACE No.2, Rev -; Near-White Blast Cleaning xii (Rev-0)
Consolidated List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM
DESCRIPTION
NSN/PN QTY ESTIMATED
COST
($/UNIT)
13 Y **Propeller shaft NSN: 2010-01-399-5912 1 ea. 165,000
14 N 225' WLB Major
Overhaul Kit
01-520-5284 1 ea. 35,249.00
14 N **225' WLB Seat
(Split)
John Crane (Wartsila), H72579-
01-7
1 ea. 12,500.00
14 Y Seal Compression
Tool
Onboard Tool 1 ea. 200.00
19 N Stat-O-Seal Washers NSN: 5310-01-212-5987
PN: 0-4-3-5
12 ea. 55.61
19 N O-Ring, Hub Flange
Bolt Cover
NSN: 5331-00-983-9878
PN: 0-2-2-5
12 ea. 50.00
20 N **Blade Bolts NSN: 5306-01-410-6893 4 ea. 1,854.12
20 N Blade Bolt O-rings NSN: 5330-01-408-7251
(0-3-2-11)
48 ea. 2.25
20 N Blade Seal NSN: 5330-01-409-1058
(0-4-4-22)
4 ea. 55.00
20 Y *Lifting Device, Propeller Blade
NSN: 2020-01-F02-6825 1 ea. 100.00
24 N *** Fathometer
Transducer, Shallow
Water, 50-200 kHz
NSN: 5845-01-470-2500 1 ea. 148.92
24 N ***Fathometer
Transducer, Deep
Water, 24kHZ
PN: TH24-20SAW-RA 1 ea. 11,250.00
25 Y ***AN/SRD 500
Sperry Doppler Speed
Log
NSN: 5999-01-472-7499 1 ea. 12,936.00
N Rudder Seal Kit 5330-01-565-8083 1 ea. 2,000
N **Upper bearing NSN: 3110-01-466-9924 1 ea. 5,002.41
35 N Seal 5330-01-495-3435 2x 5 ea. 237.60
36 N Overhaul Kit
(for Para. 3.1, Tasks
#2 and #3)
NSN: 2040-01-496-9418 2 ea. 1,000.00
N Roller bearing Unit
(for Para. 3.2.1, Task
#4)
NSN:3130-01-504-4363 2 ea. 4,012.00 xiii (Rev-0)
N
Grease seal
(for Para. 3.2.1, Task
#5)
NSN:5330-01-462-5544 4 ea. 79.25
N
Level wind pivot bushing
(for Para. 3.2, Task
#6)
PN:7101-573-1 PC-17
(Marinette Marine)
1 ea. 392.00
N
Level wind thrust bearing
(for Para. 3.2.1, Task
#6)
PN:7101-573-1 PC-16
(Marinette Marine)
2 ea. 249.00
N
Hand Pump
(for Para. 3.2.1, Task
#7)
NSN:4320-01-015-9422
PN:P-18 (Enerpac, LTD_
1 ea. 218.76
Y Level wind hydraulic cylinder
(for Para. 3.2.1, Task
#8)
NSN: 3040-01-441-3721 1 ea. 7,423.00
N 3:1 Pilot Ratio, Vented
Counterbalance Valve
Assembly
(For Para. 3.2.1, Task
#17)
PN: CWEA-LHN (Sun
Hydraulics Corp)
1 ea 98.70
N Fully Adjustable
Needle Valve
(for Para. 3.2.1, Task
#17)
PN: NFDC-LAN (Sun
Hydraulics Corp)
1 ea 48.75
Y **Hydraulic Motor
(for Para. 3.2.1, Task
#21)
NSN: 4320-01-445-2248 1 ea 23,998
N Anode, elliptical, platinum & niobium,
37.5 A
Siemens Water Technologies
(US Filter Electrocatalytic)
74200-1
NSN 5342-01-408-5388
4 ea. 7,555.00
N Reference electrode, silver & silver chloride
Siemens Water Technologies
(US Filter Electrocatalytic)
32622-050
NSN 5977-01-346-0750
2 ea. 1,300.02
56 Y *Transducer Cover
Plate
N/A 4 ea. 50.00
N
Pivot Pin, Level Wind
Assembly Arm 5315-01-515-9868 1 ea 3,400.00
N
Pivot Pin, Hydraulic
Cylinder Foot End 5315-01-515-9847 1 ea 510.00 xiv (Rev-0)
N
Clevis Pin, Hydraulic
Cylinder Rod End 5315-01-515-9912 1 ea 380.00
61 N Wet Brake Unit Set
(Consists of 5 Brk Per
Kit)
NSN: 3040-01-F06-1016 1 Kit 4,500.00
70 N (14 mm x 40m), prefabricated with eye on one end, and tapered/welded on the other end
99-225-7786 1 ea.
70 N (14 mm x 37.75m), prefabricated with eye on one end, and tapered/welded on the other end
99-859-7924 1 ea
70 N Sheave bearing and seal
5014-1411 13 ea
70 N Sheave bearing and seal
5014-1511 2 ea
71 N Swing Brake Seal Kit NSN: 90-016-2141 2 ea
71 N Swing Brake Disc &
Bearing Kit
NSN: 90-016-2131 2 ea
71 N Counterbalance Valve PN: YMD-3763 1
71 N Swing Bearing NSN: 00-100-0624
PN: 95925
72 N Slide Pad/shim kit PN: YMD-8956 1 Kit
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xv (Rev-0)
Consolidated List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph
3.2.6.5 (Inspection report particulars)):
Work
Item Title
1 Hull Plating, U/W Body, Inspect
2 Hull Plating (U/W Body), Ultrasonic Testing
3 Appendages (U/W), Leak Test
8 Voids (Non-Accessible), Leak Test
10 Tanks (MP Fuel Service), Inspect
Cargo Hatch, Overhaul and Repair
Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renewal
Strain Gage Alignment, Check
Propulsion Shaft Bearings (External) , Check Clearances
19 Controllable Pitch Propeller , System Maintenance
20 Controllable Pitch Propeller , Hub General Maintenance
21 Controllable Pitch Propellers , Clean and Inspect
28 Sea Bay, Inspect
32 Rudder Stock Bearings, Check Clearances
33 Rudder , Inspect and Repair
36 Hydraulic Chain Stoppers, Overhaul
38 Crossdeck Winches, Overhaul
39 Hydraulic Inhaul Winch, Overhaul
40 Mechanical Chain Stopper s , Overhaul
41 Anchor Windlass , Overhaul ( Level 2 )
42 Anchor Chain (s) and Ground Tackle, Inspect and Repair
43 Warping Capstan, Level 2 Inspect and Repair
61 Buoy Crane Swing Drive Brake Assemblies , Modify
66 Bilge s (Machinery Space), Preserve
70 Boat Boom, Inspect and Repair
71 Single Point Davit, Inspect and Repair
72 Buoy Crane , Inspect and Repair xvi (Rev-0)
PC_225B_WLB_1109
Principal Characteristics
225' WLB (B-CLASS)
PHYSICAL CHARACTERISTICS
Length Overall 225' 0" Length between Perpendiculars 206' 0" Maximum Beam 46' Designed Draft 13' 0" Full Load Displacement 2000 long tons Light Ship Displacement 1523 long tons Minimum Operating Displacement 1800 long tons Mast Height (Above 12' Waterline) 67' 5"
Anchor
Two 4000 lb standard Navy stockless anchors, 8 shots each, port and starboard, 1-3/8 die lock chain
HULL CHARACTERISTICS
Bilge Keels (Port & Starboard) Frames 42-79 Frame Spacing
FR 0 to 12 21" FR 12 to 30 22"
FR 30 to 102 24"
MACHINERY CHARACTERISTICS
Main Propulsion Diesel Reduction
Diesel Engines Two Caterpillar 3608, TA, 3100 BHP each @ 900 RPM
Number of Propellers 1 Number of Blades 4 Diameter 10' Pitch Controllable
RPM 254
Ship's Service Diesel Generators Two Caterpillar 3508 TA, 450 kW
Emergency Diesel Generator One Caterpillar 3406 DITA, 280 kW Shore Tie Two 450 VAC, 400 Amp, 3-wire
Shaft Bearing, Forward Cooper Bearing 01-BCP-1400-EX-
TL
Shaft Bearing, Aft Water Lubricated Cutless Bearing
TANK CAPACITIES
Diesel Oil 76,498 gal Fresh Water Capacity 8056 gal Hydraulic Oil Capacity 2785 gal Lube Oil Storage 764 gal Grey Water Tank 2700 gal Sewage Holding Tank 1700 gal
1 (Rev-0)
00000_PWB_0211_FLT
REC_0000_FLT_ Commercial Project @ Contractor’ Facility (0211)
General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and
Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface
Profile of Blast Cleaned Steel
Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting
Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel
Surfaces Prepared by Dry Abrasive Blast Cleaning
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
2 (Rev-0)
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.4 HW disposal. The Contractor is considered as the generator of all contract-generated hazardous wastes and shall use its facility‟s EPA generator ID number for management, transportation, and disposal of said hazardous wastes. Ensure the following:
3.4.1 Contractor‟s hazardous waste handlers shall comply with applicable requirements of 40 CFR 262.
3.4.2 All contract generated hazardous wastes shall be packaged in 49 CFR-compliant containers.
3.4.3 The designated wastes shall be disposed of at a state or Federally-approved and permitted HW TSDF.
3.4.4 Name of destination TSDF shall be submitted to the KO at the Arrival Conference.
3.5 Pre-surface preparation test coupon. In order to ensure production of required surface profile, the Contractor shall accomplish the following tasks, whenever abrasive-blasting is required in a work item that is deemed a
”critical-coated‟ surface:
3.5.1 Coupon material and test set-up particulars.
3.5.1.1 Conduct a performance test on all abrasive blasting operations on a Contractor- provided test coupon, prior to starting abrasive blasting operations on the vessel. Ensure the following:
The coupon shall be a new metal plate, of the same metal type and material properties as the vessel area to be blasted - steel or aluminum plate, as applicable, and shall have no existing anchor profile - other than the surface irregularities from the manufacturing process.
The test coupon shall be flat, with nothing welded to the side used for the anchor profile test, no thinner than a 1/8-inch plate and measuring no smaller than 1-foot by 1-foot.
For steel substrates, the coupon shall have the mill scale intact, and be in a Rust Grade "A" condition, in accordance with SSPC-VIS 1.
The test coupon shall be affixed so as to not permit excessive movement during the performance test, but shall not be affixed to the vessel.
3.5.1.2 Ensure that the abrasive-blasting operation for the test coupon is conducted with the identical setup and parameters that will be used blasting the designated vessel surfaces – including, but not limited to:
The abrasive media type and media size selected to achieve the anchor profile range, as specified in the applicable work items.
Nozzle size and type (straight bore, high velocity nozzle, angle nozzle...).
Delivery rate and pressure settings.
3 (Rev-0)
3.5.1.3 Blast a one-square foot area on one side of the test coupon to the abrasive surface preparation standard specified in the work item, and perform an anchor profile test of the blasted surface in accordance with ASTM
D4417, Method B or C. Notify the COTR in advance of the abrasive blasting operation test, to permit the witnessing of the test by the COTR. Submit a CFR documenting the results of the abrasive blasting operation test. The CFR shall include at a minimum, the following:
Area of the vessel for which the verified setup will be used to abrasive blast.
The selected abrasive media type and size.
The nozzle size and type.
The delivery rate and pressure.
The test coupon starting properties (material type and surface conditions).
The resultant anchor profile readings from the test (a minimum of 3 locations, separated by a minimum of
2 inches shall be recorded).
NOTES
1. A performance test of the abrasive blasting operations on a test coupon and measuring the resultant anchor profile prior to performing the abrasive blasting operation on the cutter is required. The test coupon will be used to evaluate the anchor profile produced by the equipment setup and selected abrasive media.
2. The reverse side of the test coupon may be used for the subsequent test, provided that the conditions in paragraph 3.5.1 (Coupon material and test set-up particulars) are met.
3. Ultra high pressure water jetting does not create an anchor profile and is exempt from the anchor profile test coupon check.
3.5.1.4 Repeat the abrasive blasting operation test in the following instances:
The equipment setup, that was evaluated during the test coupon abrasive blasting performance test in paragraph 3.5.1 (Coupon material and test set-up particulars), has changed.
The resultant anchor profile readings observed on the vessel are outside the specified anchor profile range.
Media is changed from MIL-A-22262 to CID A-A-59316 or vice versa.
The supplier of the abrasive blasting media changes, regardless if the new source for the media has the same specifications.
When Directed by the COTR.
CAUTION!
Ensure that blast media from the performance test does not strike the vessel during the test.
3.6 Interim changes to SFLC Std Spec 0000. The Contractor shall be aware of the fact that the requirements of paragraph 3.3.2.1.1 (Water depth) have been revised to read as follows:
3.6.1 Contents of paragraph 3.3.2.1.1 (Water depth) have been revised to read as follows:
“3.3.2.1.1 Water depth. Ensure that water depth is sufficient at the pier to allow the vessel's lowest underwater appendage to clear the bottom by at least two feet at:
Ordinary low water mark on non-tidal rivers.
4 (Rev-0)
At all tide conditions predicted during the availability for tidal rivers and other navigable waterways (Bay, Lake, etc.).”
3.6.2 Paragraph 3.2.11.1 (Sanitary facilities for vessel-personnel – due to disruption of grey water system) has been revised as follows:
“3.2.11.1 Sanitary facilities for vessel-personnel – due to disruption of grey water and sewage systems. When the shipboard grey water and sewage systems are disrupted due to repairs required by contract work, the Contractor shall provide vessel-personnel with a sanitary facility, within a five minute walking distance from the vessel, to include the amenities listed in Table II (Sanitary Facility Amenities). Ensure the following:
Shower stalls are equipped with privacy screens.
Sinks are provided with fresh hot and cold water.
Electrical convenience GFI receptacles, in accordance with NFPA 70, National Electric Code (NEC), are located in vicinity of sinks.
Toilets have doors or privacy dividers.
Lockers are capable of being locked.
3.7 Planning Document and Commitment From Tech Reps – The Contractor shall provide a preliminary electronic copy of the planning document required by SFLC Standard Spec 0000 Para 3.5.2 for Government review no later than 1 week after contract award. In addition to requirements of paragraph 3.5.2, all planning documents shall identify work item time periods that require OEM tech rep assistance. The Contractor shall also provide the names, contact information, and written commitment from all tech reps required by the Contract indicating they are available for work during the proposed time period.
3.8 NACE Level III Inspector Notification of Duties – If an independant NACE Level III Inspector is used to meet requirements of In-Process QC measures for “critical coated surfaces” as described by SFLC Std Spec0000
Para 3.2.4.2, the Contractor shall ensure the NACE Level III inspector is aware of, able, willing, and formally directed via subcontract documentation to perform of all duties enumerated in SFLC Std Specification 0000 Para
3.2.4.2.3 for all „critical coated surfaces” defined by SFLC Std Spec Para 1.3. Documentation of this contract and assumption of duties shall be provided to the Government by the Contractor after contract award.
3.9 Contractor Choice of Paint Systems – The Contractor shall submit documentation of the Contractors choice of intended paint systems to be used for all “critical coated surfaces” at the Arrival Conference for Government review and approval. Documentation shall be broken out by work item and shall document the brand name, color, intended mil thickness, time between coats, and intended final cure time prior to immersion or full duty rating.
Contractor shall also provide all product data sheets for all paint systems as a reference.
3.10 Critical Coated Surfaces Cure Times – Hard cure times or cure time prior to immersion for any “critical coated system” shall be met as published on the Product Data Sheets available online. No early undocking or relaxation of these published requirements is permitted without prior approval from the Contracting Officer. OEM representatives may not relax these requirements. Painting and curing of all tank coating systems shall occur while the cutter is out of the water. The CAPAC system shall not be energized until full cure of all underwater paint systems has occurred.
3.11 Critical Coated Surfaces and Ambient Controls - If ambient condition control equipment and tenting is required to achieve ambient condition parameters necessary for full paint cure or to meet environmental conditions as required in SFLC Std Spec 0000, para. A.2.1.4, contractor shall provide at no additional cost to the
5 (Rev-0)
Government.
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
http://www.uscg.mil/directives/cim.asp
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile using ASTM D4417-Methods B or C against COMDTINST M10360.3. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer‟s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer‟s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame &
Deck, relation to equipment, etc.)
TEMPERATURE % REL.
HUMID-
ITY DEW PT. SURFACE AMBIENT ΔT
| DP - Surface |
8 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Pl…