Exhibits_B1_through_B7_FRFP.xlsx

XLSX spreadsheet 208 KB Posted

Attached to
Missile Defense Data Center (MDDC) Program Federal contract opportunity
Solicitation number
HQ0147-10-R-0030
Issued by
DOD Missile Defense Agency

About this file

Exhibit B

View the file

Other files for this federal contract opportunity

Other files attached to Missile Defense Data Center (MDDC) Program, newest first.
File Type Posted
HQ0147-10-R-0030_AMD08_MDDC_Atch_11_Section_L.docx DOCX document
HQ0147-10-R-0030_AMD_0008.doc DOC document
Exhibits_B1 through B8_(Revised Exhibit B8 - April 19 2012).xlsx XLSX spreadsheet
Atch_11_Section_L_MDDC_FRFP_April 19 2012.pdf PDF
HQ0147-10-R-0030 SF30 Amd 0007.doc DOC document
HQ0147-10-R-0003 SF30 Amd 0005.doc DOC document
HQ0147-10-R-0030 SF30 Amd 0004.doc DOC document
Exhibit_C_BOE_Summary_(Revised April 12 2012).xlsx XLSX spreadsheet
List of Documents in Bidders Library revised since Initial Release.pdf PDF
HQ0147-10-R-0030 SF30 Amd 0002.doc DOC document
MDDC Questions_Answers_April 13_2012.pdf PDF
HQ0147-10-R-0030 SF30 Amd 0003.doc DOC document
HQ0147-10-R-0003 SF30 Amd 0006.doc DOC document
Exhibit A CDRL_DD_Form_1423_FRFP_Amd01.doc DOC document
Exhibit C BOE Summary_FRFP_Amd01.xlsx XLSX spreadsheet
HQ0147-10-R-0030 Amendment 0001.doc DOC document
Atch_12_Section_M_MDDC_FRFP_Amd01 .pdf PDF
Atch_9_PPQTransmittalLtr_FRFP_Amd01.pdf PDF
Atch_8_PPInfoSheet_FRFP_Amd01.docx DOCX document
Atch_3_Govt_Labor_Categories_FRFP_Amd01.pdf PDF
Atch_1_MDDC_SOW_FRFP_Amd01.pdf PDF
Exhibits B1 through B8_FRFP_Amd01.xlsx XLSX spreadsheet
Atch_11_Section_L_MDDC_FRFP_Amd0001.pdf PDF
Joint Ventures and SB Teaming.pdf PDF
MDDC Amendment e-mail.docx DOCX document
MDDC Preproposal Conference Slides.pptx PPTX presentation
Gate 9 directions to East Entrance.pptx PPTX presentation
MDDC Preproposal Conference Information.docx DOCX document
Exhibit_A_CDRL_DD_Form_1423_FRFP.doc DOC document
Exhibit_C_BOE_Summary_FRFP.xlsx XLSX spreadsheet
DD 1707_MDDC.pdf PDF
Contracting_Officer_Cover_Letter_MDDC.pdf PDF
Atch_14_Preaward_Survey_FRFP.docx DOCX document
Atch_4_GFE List_FRFP.xlsx XLSX spreadsheet
Atch_3_Govt_Labor_Categories_FRFP.docx DOCX document
Atch_12_Section_M_MDDC_FRFP.docx DOCX document
Atch_1_MDDC_SOW_FRFP.docx DOCX document
HQ0147-10-R-0030_MDDC_FRFP.docx DOCX document
Atch_8_PPQInfoSheet_FRFP.docx DOCX document
Atch_10_PPSample SubContractor Consent Ltr_FRFP.docx DOCX document
Atch_7_PastPerformanceQuestionnaire_(PPQ)_FRFP.docx DOCX document
Atch_5_OCI Policy Memo_FRFP.pdf PDF
Atch_9_PPTransmittalLetter_FRFP.docx DOCX document
Atch_13_Compliance_Matrix-FRFP.xls XLS spreadsheet
Atch_6_OCI Analysis-Disclosure Form_FRFP.doc DOC document
Atch_11_Section_L_MDDC_FRFP.docx DOCX document
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FBLR Exhibit B1

Exhibit B1: Fully Burdened Labor Rate (FBLR)
PRIME/SUBCONTRACTOR
CONTRACTOR/SUBCONTRACTOR: __________________________________________
Prime & Major Contractor Labor Category to MDDC Labor Category CrosswalkFringe BenefitsOverheadG&A BaseG&AFBLR Labor Rate Through G&A* Fee/Profit for Subcontractors Only12-Month Period 1 FBLR including sub fee
%age of E%age of E(E)+(F)+(G)%age of H(H) + (I)% of J(J) + (K)
Insert Fringe Rate ** ▼Insert Govt-Site Overhead Rate ** ▼Insert G&A Rate ** ▼Insert Profit Factor ** ▼
MDDC Labor CategoryContractor Labor Category% of total MDDC Labor CategoryContractor Labor Category Direct Labor RatesPrime or Major Sub MDDC Direct Labor Rate20.0%15.0%10.0%0.0%
Example (Please Delete in Proposal)

campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee

Chief Bottle Washer1st Class Bottle Washer50%$ 24.00$ 21.36$ 4.27$ 3.20$ 28.84$ 2.88$ 31.72$ - 0$ 31.72
Container Cleaner III25%$ 18.95
Jug Washer25%$ 18.50
Program Manament III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Manament II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Manament I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Support II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Support I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Disaster Recovery Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Disaster Recovery Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Legacy Data Analyst II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Legacy Data Analyst I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Technical Writer II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Technical Writer I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
* Prime Fee is included on the CLIN Pricing Exhibit
NOTE: The Indirect rate structure on this Exhibit is notional. Offerors must tailor this Exhibit to match their unique rate structure and cost accounting system.
Fully Burdened Labor Rate (FBLR) Exhibit B1
CONTRACTOR/SUBCONTRACTOR: __________________________________________2nd 12-Month Period and Escalated FBLRs for Periods 3 through 10
Prime & Major Contractor Labor Category to MDDC Labor Category CrosswalkFringe BenefitsOverheadG&A BaseG&AFBLR Labor Rate Through G&A* Fee/Profit for Subcontractors Only12-Month Period 2 FBLR including sub fee
%age of E%age of E(E)+(F)+(G)%age of H(H) + (I)% of J(J) + (K)
Insert Fringe Rate ** ▼Insert Govt-Site Overhead Rate ** ▼Insert G&A Rate ** ▼Insert Profit Factor ** ▼
MDDC Labor CategoryContractor Labor Category% of total MDDC Labor CategoryContractor Labor Category Direct Labor RatesPrime or Major Sub MDDC Direct Labor Rate20.0%15.0%10.0%0.0%
Example (Please Delete in Proposal)

campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee

Chief Bottle Washer1st Class Bottle Washer50%$ 24.72$ 22.00$ 4.40$ 3.30$ 29.70$ 2.97$ 32.68$ - 0$ 32.68
Container Cleaner III25%$ 19.52
Jug Washer25%$ 19.06
Program Manament III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Manament II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Manament I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Support II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Support I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Disaster Recovery Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Disaster Recovery Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Legacy Data Analyst II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Legacy Data Analyst I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Technical Writer II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Technical Writer I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
* Prime Fee is included on the CLIN Pricing Exhibit
NOTE: The Indirect rate structure on this Exhibit is notional. Offerors must tailor this Exhibit to match their unique rate structure and cost accounting system.

&"Times New Roman,Italic"&11HQ0147-10-R-0030 Section J, Exhibit B1 Prime/Subcontractor Fully Burdened Labor Rates (RBLR) Page &P of &N

Minor Subs FBLR Exhibit B2

Exhibit B2: Minor Subcontractor Fully Burdened Labor Rates (FBLR)
Prime Contractor:
Minor SubcontractorMDDC Labor Category12-Month12-Month12-Month12-Month12-Month12-Month12-Month12-Month12-Month12-Month
PeriodPeriodPeriodPeriodPeriodPeriodPeriodPeriodPeriodPeriod
Examples:12345678910
Consulting Inc.Database Development Specialist III$ 86.02$ 87.74$ 89.50$ 91.29$ 93.11$ 94.97$ 96.87$ 98.81$ 100.79$ 102.80
Software Development Specialist III$ 64.52$ 65.81$ 67.13$ 68.47$ 69.84$ 71.24$ 72.66$ 74.11$ 75.60$ 77.11
Very High Tech IncorporatedEngineer / Scientist / Technical Analyst IV$ 85.00$ 86.70$ 88.43$ 90.20$ 92.01$ 93.85$ 95.72$ 97.64$ 99.59$ 101.58
Engineer / Scientist / Technical Analyst III$ 56.00$ 57.12$ 58.26$ 59.43$ 60.62$ 61.83$ 63.07$ 64.33$ 65.61$ 66.93
Chief Bottle Washer$ 45.00$ 45.90$ 46.82$ 47.75$ 48.71$ 49.68$ 50.68$ 51.69$ 52.72$ 53.78

HQ0147-10-R-0030

Section J, Exhibit B2 Minor Subcontractor FBLR

Composite Team FBLR B3

Exhibit B3: Prime's Composite (Team) Fully Burdened Labor Rate (FBLR)(Prime only)
Prime Contractor:
12-Month Period 3 Loaded Labor Rate including sub fee12-Month Period 4 Loaded Labor Rate including sub fee12-Month Period 5 Loaded Labor Rate including sub fee12-Month Period 6 Loaded Labor Rate including sub fee12-Month Period 7 Loaded Labor Rate including sub fee12-Month Period 8 Loaded Labor Rate including sub fee12-Month Period 9 Loaded Labor Rate including sub fee12-MonthPeriod 10 Loaded Labor Rate including sub fee
12-Month Period 112-Month Period 2% Period 2% Period 3% Period 4% Period 5% Period 6% Period 7% Period 8% Period 9
MDDC Labor CategoryStaffing approach for each MDDC Labor CategoryFBLR From Exhibit B1 or B2Prime Burden on Sub Labor if applicablePrime & Subs Per Hour Labor CostComposite Cost MDDC Cost Per HourFBLR From Exhibit B1 or B2Prime Burden on Sub Labor if applicablePrime's Per Hour Labor CostComposite Cost MDDC Cost Per HourInsert Escalaution Factor ** ▼Insert Escalaution Factor ** ▼Insert Escalaution Factor ** ▼Insert Escalaution Factor ** ▼Insert Escalaution Factor ** ▼Insert Escalaution Factor ** ▼Insert Escalaution Factor ** ▼Insert Escalaution Factor ** ▼
1%1%2.0%2.0%2.0%2.0%2.0%2.0%2.0%2.0%
Example (Please Delete in Proposal)

campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirect rates, and Fee

Chief Bottle WasherSB Prime Inc.50%$ 31.72$ 31.72$ 34.65$ 32.68$ 32.68$ 35.88$ 36.60$ 37.33$ 38.08$ 38.84$ 39.62$ 40.41$ 41.22$ 42.04
XYZ Corp.30%$ 32.00$ 0.32$ 32.32$ 33.29$ 0.33$ 33.62
Very High Tech Incorporated20%$ 45.00$ 0.45$ 45.45$ 46.81$ 0.47$ 47.28
Program Management III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Management II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Management I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Management / Technical Staff I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Support II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative Support I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Database Development Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Disaster Recovery Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Disaster Recovery Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Engineer / Scientist / Technical Analyst I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Legacy Data Analyst II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Legacy Data Analyst I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Library / Help Desk Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Media Migration / Data Processing Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Network Management / IT Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist IV$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Program Support Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Security Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist III$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Software Development Specialist I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Technical Writer II$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Technical Writer I$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

NOTE: The Indirect rate structure on this Exhibit is notional (a single prime burden on Subcontracts Labor dollars) . Offerors must tailor this Exhibit to match their unique rate structure and cost accounting system.

&"Times New Roman,Italic"&11HQ0147-10-R-0030 Section J, Exhibit B3 Composite Team FBLR

CLIN Pricing Exhibit B4

MDDCCLIN 0001 CPIF/LOEOption CLIN 0005 CPIF/LOEOption CLIN 0009 CPIF/LOEOption CLIN 0013 CPIF/LOEOption CLIN 0017 CPIF/LOEOption CLIN 0021 CPIF/LOE
Contract Labor Categories12-Month Period 112-Month Period 212-Month Period 312-Month Period 412-Month Period 5Totals12-Month Period 612-Month Period 712-Month Period 812-Month Period 912-Month Period 10
Chief Bottle Washer

campbellj: Notional Example: In yellow -- NOT intended to influence proposed labor mix, Direct or Indirct rates, and Fee 1,000 1,000 1,000 1,000 1,000 5,000 1,000 1,000 1,000 1,000 1,000

Program Manament III
Program Manament II
Program Manament I
Senior Management / Technical Staff IV
Senior Management / Technical Staff III
Senior Management / Technical Staff II
Senior Management / Technical Staff I
Administrative Support II
Administrative Support I
Database Development Specialist III
Database Development Specialist II
Database Development Specialist I
Disaster Recovery Specialist II
Disaster Recovery Specialist I
Engineer / Scientist / Technical Analyst IV
Engineer / Scientist / Technical Analyst III
Engineer / Scientist / Technical Analyst II
Engineer / Scientist / Technical Analyst I
Legacy Data Analyst II
Legacy Data Analyst I
Library / Help Desk Specialist III
Library / Help Desk Specialist II
Library / Help Desk Specialist I
Media Migration / Data Processing Specialist III
Media Migration / Data Processing Specialist II
Media Migration / Data Processing Specialist I
Network Management / IT Specialist IV
Network Management / IT Specialist III
Network Management / IT Specialist II
Network Management / IT Specialist I
Program Support Specialist IV
Program Support Specialist III
Program Support Specialist II
Program Support Specialist I
Security Specialist III
Security Specialist II
Security Specialist I
Software Development Specialist III
Software Development Specialist II
Software Development Specialist I
Technical Writer II
Technical Writer I
Total DPLH1,0001,0001,0001,0001,000
CONTRACT FBLRs
Chief Bottle Washer$ 34.65$ 35.90$ 37.15$ 38.40$ 39.65$ 40.84$ 42.06$ 42.06$ 43.32$ 43.32
Program Manament III
Program Manament II
Program Manament I
Senior Management / Technical Staff IV
Senior Management / Technical Staff III
Senior Management / Technical Staff II
Senior Management / Technical Staff I
Administrative Support II
Administrative Support I
Database Development Specialist III
Database Development Specialist II
Database Development Specialist I
Disaster Recovery Specialist II
Disaster Recovery Specialist I
Engineer / Scientist / Technical Analyst IV
Engineer / Scientist / Technical Analyst III
Engineer / Scientist / Technical Analyst II
Engineer / Scientist / Technical Analyst I
Legacy Data Analyst II
Legacy Data Analyst I
Library / Help Desk Specialist III
Library / Help Desk Specialist II
Library / Help Desk Specialist I
Media Migration / Data Processing Specialist III
Media Migration / Data Processing Specialist II
Media Migration / Data Processing Specialist I
Network Management / IT Specialist IV
Network Management / IT Specialist III
Network Management / IT Specialist II
Network Management / IT Specialist I
Program Support Specialist IV
Program Support Specialist III
Program Support Specialist II
Program Support Specialist I
Security Specialist III
Security Specialist II
Security Specialist I
Software Development Specialist III
Software Development Specialist II
Software Development Specialist I
Technical Writer II
Technical Writer I
Chief Bottle Washer$ 34,648$ 34,649$ 34,650$ 34,651$ 34,653173,251$ 40,837$ 42,062$ 42,062$ 43,324$ 43,324
- 0
Program Manament III- 0
Program Manament II- 0
Program Manament I- 0
Senior Management / Technical Staff IV- 0
Senior Management / Technical Staff III- 0
Senior Management / Technical Staff II- 0
Senior Management / Technical Staff I- 0
Administrative Support II- 0
Administrative Support I- 0
Database Development Specialist III- 0
Database Development Specialist II- 0
Database Development Specialist I- 0
Disaster Recovery Specialist II- 0
Disaster Recovery Specialist I- 0
Engineer / Scientist / Technical Analyst IV- 0
Engineer / Scientist / Technical Analyst III- 0
Engineer / Scientist / Technical Analyst II- 0
Engineer / Scientist / Technical Analyst I- 0
Legacy Data Analyst II- 0
Legacy Data Analyst I- 0
Library / Help Desk Specialist III- 0
Library / Help Desk Specialist II- 0
Library / Help Desk Specialist I- 0
Media Migration / Data Processing Specialist III- 0
Media Migration / Data Processing Specialist II- 0
Media Migration / Data Processing Specialist I- 0
Network Management / IT Specialist IV- 0
Network Management / IT Specialist III- 0
Network Management / IT Specialist II- 0
Network Management / IT Specialist I- 0
Program Support Specialist IV- 0
Program Support Specialist III- 0
Program Support Specialist II- 0
Program Support Specialist I- 0
Security Specialist III- 0
Security Specialist II- 0
Security Specialist I- 0
Software Development Specialist III- 0
Software Development Specialist II- 0
Software Development Specialist I- 0Grand Total all discreetly priced CLINs
Technical Writer II- 0
Technical Writer I- 0
Totals
Total proposed Labor Cost34,64834,64934,65034,65134,653173,25140,83742,06242,06243,32443,324384,860
Prime Target Fee Rate5%5%5%5%5%5%5%5%5%5%
Target Fee1,7323463473473473,1182,0422,1032,1032,1662,16613,699
Totals36,38034,99534,99734,99834,999176,36942,87944,16544,16545,49045,490398,560

NOTE: PLEASE REMEMBER TO REMOVE EXAMPLE FROM PROPOSAL

Section J, Exhibit B4 CLIN Pricing

Overhead Exhibit B5 Exhibit B5: Overhead or Other Indirct Rates

Company Name: [ ] Prime [ ] Major Subcontractor

Overhead or Service Center Pool = _______________ Base of Application = __________________________

* Specify Type of Overhead Burden: Labor, Onsite, Offsite, Engineering, Procurement, Service Center(s), etc.

OFFEROR'S FISCAL YEAR BEGINS ____________ AND ENDS ____________.

ContractorContractorContractorContractorContractorContractorContractorContractor
Cost Elements withinFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal Year
the Overhead Burden PoolPrior Yr 3Prior Yr 2Prior Yr 1_____________________________________________
Payroll Taxes
FICA (Fed Income Tax)
FUI (Federal Unemployment)
SUI (State Unemployment)
WC (Workers Comp)
Fringes:
Retirement
Health/Life Insurance
Paid Leave
Other
Other (Identify)
Facilities
Depreciation
Total Overhead Pool Expenses
Application Base ($)
Contractor FY Rate (%)
CONVERSION OF BURDEN RATE TO CONTRACT YEAR
Contract PeriodContract Period
Year 1*Year 2
Proposed Contract Year Rate

Section J, Exhibit B5 Overhead

G&A Exhibit B6

Exhibit B6: General and Administrative Expenses
Company Name:[ ] Prime[ ] Major Subcontractor
OFFEROR'S FISCAL YEAR BEGINS ____________ AND ENDS ____________.
Base of Application = __________________________
ContractorContractorContractorContractorContractorContractorContractorContractor
Cost ElementsFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal Year
Within the G&A Expense PoolPrior Yr 3Prior Yr 2Prior Yr 1_____________________________________________

Labor: (Identify)

Labor Related Cost: (Taxes & Fringes Etc.)

B&P
IR&D
Corporate Allocations:
Other (Specify):
Facilities
Depreciation
Total G&A Expenses
Distribution Base Dollars:
Existing Business Base
This Contract Base
Forecasted Business Base
Total Distribution Base $
Calculated G&A Rates (%)
CONVERSION OF BURDEN RATE TO CONTRACT YEAR
Contract PeriodContract Period
Year 1Year 2
Proposed Contract Year Rate

Section J, Exhibit B6 G and A

DPLHs Exhibit B7

DPLHs
12-Month Period 112-Month Period 212-Month Period 312-Month Period 412-Month Period 512-Month Period 612-Month Period 712-Month Period 812-Month Period 912-Month Period 10
Government provided total DPLHs317,981313,892312,603311,134305,673305,987306,512307,239308,160309,266
Total proposed DPLHs on Exhibit B4 and the BOE Summary must equal the DPLHs provided on this Exhibit

HQ0147-10-R-0030

Section J, Exhibit B7 Direct Person Labor Hours