Responses to all RFI's submitted up to 11/14/2016.
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# Question Response
Drawings LP 0 01 has 5 tables, the total of these tables is approx. 12,694 trees and shrubs and the total of LP‐1‐11 to 15 is 1,155 trees and shrubs for a combined total of 13,849 trees and shrubs. Bid Item 15‐01 and 15.02 is the Upland Tree Mitigation with units of 8,000 trees and 3,000 shrubs – which of the trees and shrubs get paid in these two items and which trees, shrubs and plugs get paid in Item 16 (Wetland Riparian Plantings) at 19.081 acres?
11/8/16 addendum provided clarification on planting.
The landscape buffer drawings (LP‐1‐11‐15) shows 1,155 trees and shrubs, but the bid quantity is 8,000 trees and 3,000 shrubs for the Upland Tree Mitigation?
11/8/16 addendum provided clarification on planting.
Drawing LP-1-16 includes a table which appears to be a summary of the individual tables on drawings LP-1-11 to 15. On the summary table, the Summersweet and Pin Oak are 97 and 70 each. When you add up the individual tables the sum of the Summersweet and Pin Oak are 105 and 71 each?
11/8/16 addendum provided clarification on planting.
Technical specifications 32 90 00. This section includes:
a. Table 1A – Planting Schedule for the Restoration of Temp. Impacted Wetlands
b. Table 1B – Planting Schedule for the Created Wetlands in Former RR
ROW
c. Table 1D – Planting Schedule for the Wetland Transition Areas
d. Table 1E – Riparian Woody Riprarian Plant Schedule These tables in the specifications include the same items as the tables on Drawing LP-0-01, but are less by 2 to 3 times. Do we disregard the tables in the specifications and use the tables on drawing LP-0-01?
Revised specification in 11/8/16 addendum removed tables.
Contractor shall use tables in Drawings.
Technical specifications 32 90 00‐14, Table 1C – Planting Schedule for the Created Wetlands Adjacent to the Consolidation Area shows a total of 1,070 plugs, trees and shrubs. Are these quantities included in any of the other tables on Drawing LP‐0‐01 or do we add these trees and shrubs and plugs?
Revised specification in 11/8/16 addendum removed tables.
Contractor shall use tables in Drawings.
Bid Item 16 (Wetland Riparian Plantings) is 19.081 acres. On drawing LP‐0‐ 01, Note 5 refers to 2.612 acres of additional wetlands to be restored adjacent to existing wetlands; Note 1 at the proposed DRCC shows a total disturbance of 9.08 acres; Note 1 at the proposed woody riparian shows
4.997 acres, for a total of 16.689 acres. Are the other 2.392 acres the transition areas and streambed and bank restoration?
G001 in the Permit Drawings for the Freshwater Wetland General Permit summarizes the impact areas as follows: permanent wetland impact: 0.917 acres, temporary wetland impact 5.010 acres, temporary transition area impact: 7.809, temporary open water impact: 0.339 acres, and termporary riparian zone impact: 4.997 acres. These sum to just over 19 acres.
Drawing LP-1-11 to15 shows a swale, approx. 25’ wide:
a. What Bid Item is the construction of this swale included in?
b. Is this swale seeded with the Native Prairie Basin Mix shown on LP-1- 16? Is this mix used anywhere else?
c. Does this swale receive erosion control matting? Is the erosion mat the NAG S75 matting?
a. Site Grading: Bid Item #10.
b. Yes, see specifications for Turfs and Grasses. Addendum published 1/8/16 clarifies that this area will receive a seed mix conistent with the DRCC stream corridor restoration areas.
c. Revised drawing CG-501 shows detail of erosion control matting required.
Q1. SPEC SECTION 01 11 00-10 1.06 WORK AND SEQUENCE
Can chipping operations continue outside of the timeframe provided for tree clearing operations?
Chipping can continue outside of the timeframw for tree clearing.
Q2. SPEC SECTION 01 11 00 1.06 WORK AND SEQUENCE
Will weather days be added to the 6 month duration allowed for the installation and removal of the Royce Brook Culvert?
The temporary culvert at Royce Brook cannot exceed the 6-month duration.
THERE APPEARS TO BE A CONFLICT IN THE SIZE OF STONE AND
DIMENSIONS USED FOR THE CONSTRUCTION ENTRANCES.
Drawing G 0 02, General Note 9 states: TRAFFIC CONTROL STANDARDS
REQUIRE THE INSTALLATION OF A 50’X30’X6” PAD OF 1 ½ “OR 2”
STONE, AT ALL CONSTRUCTION DRIVEWAYS, IMMEDIATELY AFTER
INITIAL SITE DISTURBANCE.
The construction entrances shall have a 1-inch minimum stone size.
The open-graded stone (or reclaimed rail ballast) used to construct the haul roads may also be used for the construction entrances.
DRAWING GC 5 02, CONSTRUCTION ENTRANCE NOTES 1-4 State the following.
1. STONE SIZE-USE 1-INCH STONE
2. LENGTH-NOT LESS THAN 50 FEET.
3. THICKNESS NO LESS THAN SIX (6) INCHES
4. WIDTH – TWELVE (12) FOOT MINIMUM, BUT NOT LESS THAN
THE FULL WIDTH AT POINTS WHERE INGRESS OR EGRESS OCCURS.
USE TWENTY-FOUR (24) FOOT WIDTH IF MAIN ENTRANCE TO SITE.
In addition, both stone sizes listed are smaller than the stone called out for use on the Temporary Construction Access Road and Site Construction Access Road (Drawing GC 5 04) and specification section 31 22 00 Par. 2.07 OPEN-GRADE Stone.
PLEASE CLARIFY THE DIMENSIONS OF THE CONSTRUCTION
ENTRANCE, AND THE SIZE OF STONE TO BE USED
The construction entrances shall have a 1-inch minimum stone size.
The open-graded stone (or reclaimed rail ballast) used to construct the haul roads may also be used for the construction entrances.
Spec Section 01 3 00-05 Submittal Procedures: 7.c: describes content of required TEP- says “methods to tarp and secure loads during transportion”
Does this include movement of material on site, not going over the road?
i.e. transport across site of material to AOC 15 Containment area?
02 81 00 Transporation and disposal do not specifically require the use of tarp during onsite hauling. However, it is recommended that contractor provide methods to tarp and secure loads during transportation offsite, and onsite - when needed. As an example, one instance where tarp may be needed for onsite transport could occur if loose, dry soil combined with windy conditions creates unacceptable dust from the truck.
Spec Section 02 81 00-5 N.
Loaded trucks shall not leave the Project Site unless they shall arrive at the designated waste management facility before it closes. Loaded trucks shall discharge their loads at the designated waste management facility the same day they are loaded.
This significantly limits radius of T&D from the project site. Please provide a list of approved disposal sites that are within a reasonable distance of the project site.
If selected disposal facility cannot be reached on the day the truck is loaded, please provide description of management procedures to be used to ensure effective management of waste materials.
Q6. Spec 01 11 00 1.04.B.3 Please provide a copy of these and any other permits already obtained by the GSA:
a. A Road Opening Permit from Hillsborough Township for temporary access to Township roads.
b. A Road Opening Permit from Somerset County for temporary access to Amwell Rd
c. A Soil Certification from Hillsborough Township to transport soil from the Site.
a&b. Road opening permit will be secured by contractor. AECOM is discussing with Township and County the details and expectations for the permit application.
c. Soil Certification description in specifications incorrectly describes this requirement and will be modified. The Township of Hillsborough will require dodcumentation that fill being brought onsite is not contaminated and meets NJDEP clean fill standards. This documentation must be submitted to the Tonwship Engineering Department at least 10-days prior to soil transporation.
Q7. Specifications Section 02 41 00, SITE DEMOLITION, 1.02 D states “Wood, metal, railroad ties, and other miscellaneous debris will be transported off site for disposal or recycling as described in the Drawings and Specifications.
There is no quantity for rail road ties or concrete debris.
Can the EPA please quantify the amount in tons of railroad ties to be removed for disposal as typically this is hazardous waste?
Addendum published 11/8/16 revises Schedule A to provide a quantity of rail ties to be disposed (in tons).
Q8. Specification Section 02 11 60, Site Demolition, 3.03 C, states that …provisions for placement of demolition debris in AOC-15 consolidation area provided in specifications section 31 22 00 Backfill & Grading.
A) What is the quantity of concrete demolition debris on the site in tons?
B) What percentage of this demolished concrete can be utilized in the AOC-15 consolidation area versus that which must be shipped off site as no-hazardous waste in tons?
C) Specification Section 31 22 00 Backfill & Grading, does not discuss how to place 6-in minus demolished concrete into the consolidation area as it does for various other types of materials (i.e., topsoil, 1” stone, etc.). What is the requirement for placing this unknown quantity (tons) of demolished concrete into the AOC-15 consolidation area?
a. estimates of conrete quantity shall be made by the contractor.
b. Contractor shall determine if concrete may be reused onsite (in the consolidation area or for other purposes) of if it must be disposed offsite. Contractor shall assume testing results indicate that all concrete can be reused onsite.
c. processed concrete for reuse in the consolidation area may be placed at the direction of the Construction Manager. In general, concrete debris will likely be placed at thicknesses no greater than 6-12 inches within the consolidation area mound.
Q9. Section 32 90 00 Planting There are several references to the “Landscape Establishment Period”. Is this the three year warranty period, or is this a different time requirement for the project?
The landscape establishment period shall be the period between planting and substantial completion.
Section 32 90 00‐10, Landscape maintenance and watering, including 4.01.E (watering twice per month): is this required during the entire 3‐year warranty period after the completion of the construction contract?
Watering is required for the 12-month period following planting and the reciept of notice of substantial completion.
The attachment, Tree Mitigation Plan – North Parcel, dated 10/17/2016, page 5, Table 2: The sum of zones A-F for the proposed additional shrubs is 3,000 plus the 1,250 shrubs for the Wetland Riparian Restoration is a total of 4,250 not 3,000?
November 8, 2016 addendum published to FedBizOpps provided revised planting counts.
Section 01 57 19 Temporary Environmental Control Subsection 1.05.D states that “(on-site potable water service is available on-site at no charge)”.
Please provide information regarding the location and size of the water service that is provided.
01 57 19 has been updated and reposted on 1/8/16 correcting this statement.
The “Total Project Plant Schedule” on Sheet LP116 differs from the sum of plant schedules on sheet LP111 thru LP115.
Offeror respectfully requests these documents be aligned. If they cannot be aligned, please indicate which document offeror should base pricing upon.
Total project plant schedule on LP116 has been updated in the 11/8/16 addendum to reflect a total for the landscaped buffer area. Additionally a summary of total plantings was provided. Contractor shall base pricing on the 11/8/16 summary of plantings.
The plant schedules on sheets LP111 thru LP116 have an “install Size” and “Height at Installation / Maturity” column. The “install Size” and “Height at Installation” sizes differ for the Juniperus virginiana. Which size should we defer to?
There are two sizes specified. Contractor shall use both in the amounts specified.
Sheet Nos. LP111 thru LP116 call out a Swale Seed Mix. Is this area included in Bid Item No. 11 or 14?
Seeding in the landscaped buffer area will be paid under Bid Item 11.
11/8/16 addendum updated the seed mix specification for this area.
Section I on Sheet LP106 refers to detail 1 on sheet LP305.
There is no section I on this sheet, only a section H. Please adjust the reference or add Section I.
LP-305 incorrectly shows two sections labelled H-H'. The second (on the right) will be relabelled section I-I'.
Section A on Sheet LP107 and LP108 refers the offeror to detail A on LP301. The same area, however, has a call out that refers the offeror to detail 18 on CG502. These two treatments are not the same. Please align these areas or indicate which should be used.
LP-301 shows a specific cross section. CG-502 shows a typical detail.
These drawings are consistent.
Section B on Sheet LP107 and LP108 refers the offeror to detail B on LP301. The same area, however, has a call out that refers the offeror to detail 19 on CG502. These two treatments are not the same. Please align these areas or indicate which should be used.
LP-301 shows a specific cross section. CG-502 shows a typical detail.
These drawings are consistent.
Section C on Sheet LP107 and LP108 refers the offeror to detail C on LP301. The same area, however, has a call out that refers the offeror to detail 20 on CG502. These two treatments are not the same. Please align these areas or indicate which should be used.
LP-301 shows a specific cross section. CG-502 shows a typical detail.
These drawings are consistent.
Sheet LP105 refers the offeror to both detail 22 and 23 on CG502. Please specify which treatment should be used.
There is an area of low bank restoration and an area of high bank restoration. Contractor shall use both.
What is the square footage of the Type A Swale, Type B Swale and Landscape Buffer Swale? What type of erosion control blanket gets installed in Type A & B Swales and the Landscape Buffer Swale? (Sheet CG501).
The erosion control blanket shall meet requirements provided in Drawing CG-501. Contractor shall determine square footage based on tables presented on CG-501 for Swale types A&B. Contractor shall estimate square footage for landscaped buffer swale based on Drawings LP-111 through LP-115.
Note 3 on Sheet CG502 mentions vegetated coir logs.
However, the details on this sheet say coir log / fascine bundle.
Are these supposed to be vegetated coir logs or fascine bundles?
The fascine bundle is the mechanism for vegetating the coir log.
Detail 32 and 33 on Sheet CG505 call out a live fascine bundle. However, the general notes of detail 32 mention a vegetated coir log. Are these supposed to be vegetated coir logs or fascine bundles?
Detail 32 shows Coir Log/Fascine Bundle. The fascine bundle is the mechanism for vegetating the coir log.
Please confirm that Bid Item 14 does not include any seed mixture specified in Specification Section 32 90 00, 2.04 – Wetland Creation and Restoration Seed Mixture. If wetland and restoration seed mixture is required in Bid Item 14, please adjust Unit Price section to accommodate payment for this mixture.
Bid Item 14 excludes the wetland, wetland transition, open water, and riparian zones. It does include DRCC buffer and the landscaped swale on the eastern boundary.
Please provide any requirements necessary for the ratio of seed mixture to be included in Bid Item 11 – Topsoil and Seed, as Wetland and Restoration Seed Mixture varies from Temporary and Permanent Upland Seed Mixture. If no ratio is provided, please confirm that the ratio of seed mixture bid is based on Offeror’s means and methods.
Bid Item 11 does not include wetalnd and riparian seed mixes. Please refer to 11/8/16 revision to specificaton (Turfs and Grasses).
Consolidation area final road grades on pages CT 212 and CT 213 do not match page CS 101. Please clarify which grade is correct.
Drawing CT 213 shows the final grade for the consolidation area access roads. Drawings CS 101 shows the proposed subgrade for the consolidation area. Final grade for the consolidation area access road is shown CS 102 and this matches CT 213.
Please provide estimated quantities of Asphalt Roadway to be demolished and removed. Drawings GC 112 and GC 113 do not provide clear limits of demolition
A CAD file documenting existing conditions was published on 11/8/16 that can be utilized to estimate quantities asphalt.
Please provide quantity of estimated excavated material broken out by zones (Zone 1, 2, ..., 25).
Schedule A provides quantities of excavated material across larger areas of the site. GSA is not breaking these down into various materials and/or zones. A CAD file documenting existing conditions was published on 11/8/16 that can be utilized to estimate quantities of other materials.
We would like to request an extension on the proposal due date for the Belle Meade Environmental Remediation proposal. Based on the extensive amount of information released today in Amendment 0002, we feel that additional time to modify our price would greatly benefit the Government to ensure that we have noted all changes and provided the best possible price for evaluation.
No extension is granted at this time. Bids are due Monday November 21, 2016 at 4PM EST.
Will the Government be issuing a new Bid Schedule following Amendment 0002? The Government noted that bid quantities have changed, but there was no revised bid schedule to support these changes?
11/8/16 addendum provided updated Schedule A
As plan holders for the above named project we are requesting clarification of documents to be submitted with the Price Proposal.
As per the Solicitation (C201) section IIB, the price proposal shall include ‘Completed Bid Schedule A’. However, the form for Bid Schedule A was provide in two formats‐ 1) an excel file which contained two pages labelled ‘Fixed Price Bid Schedule’ and ‘Unit Rate Allowance’ and 2) as part of a pdf file labelled ‘Bid Schedules’ which contains the same two pages and also Bid Schedules B thru G (lists of addenda, materials, subcontractors, equip, etc).
Please clarify if the Bid Schedule A two page excel file (updated in addendum 4) or the ‘Bid Schedule’ nine page pdf is to be submitted
Contractor shall complete all Bid Schedules. Schedule A was updated and provided as an excel sheet to facilitate pricing.
1) Please clarify the requirement of the HSPD‐12 security clearance and the requirements to handling SBU data as we do not believe this applies to this specific contract.
HSPD-12 clearance is required to access ePM system as required by specification 01 30 00.
Page 19 of the RFP states a requirement to subcontract to 17.3% and 6.9% to MBE/WBE, when this is already Small Business Set Aside contract.
Please clarify.
RFP clearly states contracting goals. These goals do not refer to sub-contractors, but rather the agreggate work force.
Section 2 – Management Plan – we are asked to discuss Earned Value Management System in regards to budget management, however this is a Fixed Price with Progress Payments contracts – please clarify as EVMS is not used for a FP contract.
As stated, "Describe how you will manage the initial budget upon award, utilizing Earned Value Management, or other Cost Management Techniques"
Can 11x17 paper size be utilized if needed? 11x17 may be utilized where needed. If subject to page count limitations, 11x17 paper will count as two pages.
Would the GSA consider excluded the Project Schedule from the overall page count in the Management Approach section?
Schedule may be excluded from the overall page count.
Please confirm that a font size smaller than 12pt be used in tables and graphics?
Font size for tables and graphics may be smaller than 12 pt for secondary information but not smaller than 8pt.
Consolidation area final road grades on pages CT 212 and CT 213 do not match page CS 101. Please clarify which grade is correct.
Drawing CT 213 shows the final grade for the consolidation area access roads. Drawings CS 101 shows the proposed subgrade for the consolidation area. Final grade for the consolidation area access road is shown CS 102 and this matches CT 213.
Please provide estimated quantities of Asphalt Roadway to be demolished and removed. Drawings GC 112 and GC 113 do not provide clear limits of demolition
Contractor shall estimate quantities of asphalt roadway to be demolished. The 11/8/16 addendum provided a CAD file of existing site conditions to facilitate estimation.
Please provide quantity of estimated excavated material broken out by zones (Zone 1, 2, ..., 25).
Schedule A provides quantities of excavated material across larger areas of the site. GSA is not breaking these down into various materials and/or zones. A CAD file documenting existing conditions was published on 11/8/16 that can be utilized to estimate quantities of other materials.
I am emailing in hopes of finding out the magnitude of the up coming bid project Environmental Remediation Services at the former Belle Mead Army Depot in Belle Mead, NJ Can you please provide me with the amount of this small business opportunity?
Contract is valued between $40MM and $60MM.
Can the winning contractor supply 50%, rather than 100%, payment and performance bonds on the total awarded value?
Let's check with Notigan. Same for LD requirement.
Request to extend the due date for the bid proposal to at least December 2, 2016. Due date is extended to 11/23
In the Solicitation, page 7 refers to GSA Form 527. Can this form be provided?
Form 527 can be downloaded at <http://www.gsa.gov/portal/getFormFormatPortalData.action;jsessionid =48336EBE55DEC64746FD8932152BD6BD?mediaId=30786>
Section 31 23 16‐3 requires 30‐foot grids and the contractor to install and maintain grade stakes at the grid centers. If the contractor uses GPS modelling to perform the excavation, are the center grid stakes necessary?
Contractor may propose alternate methodology for maintaining excavation grades in their proposal.
Are the site workers required to have OSHA 40‐hour Hazwoper training?
Contractor is responsible for determining OSHA compliance requirements. Site is a State hazardous waste site and would be required to comply with OSHA 1910.120 and 1926
The air monitoring plan in the RAWP: Figure 3‐1 Eastern Boundary, Figure 3‐2 NW Corridor, Figure 3‐3 Main Site: these 3 figures have in common 4 fixed air monitoring stations. 3‐1 has 4 portable air monitoring stations, 3‐ 2 has 5 and 3‐3 has 5, 2 of which are the same as in 3‐2. Do we install 4 fixed and 6 portable stations or 4 fixed and 12 portable stations?
The four fixed air monitoring locations are specifically for the consolidation area, which will be operated during the entire remediation. Depending on areas being remediated, contractor shall conduct air monitoring as described in the Air Monitoring Plan. If multiple 10-acre areas are being remediated simultaneously, additional air monitors may be required.
Please confirm the contractor is to assume the clearing debris and stumps which is grinded and chipped is disposed of off‐site and is considered clean / non‐contaminated?
Refer to Section 1.04.B10 in Summary of Work in Specification 01 11 00-09
The tree mitigation plan – north parcel (dated 10/17/16) was provided.
Table 2 shows 8,000 trees and 3000 shrubs and Wetland/Riparian Restoration shows 2800 trees and 1250 shrubs. I assume the 8,000 trees is Item 15‐01 and the 3000 shrubs is Item 15‐02. I also assume the 2800 trees and 1250 shrubs are in item 16?
Clarification provided in 11/8/16 addendum
a. The 8,000 trees and 3000 shrubs – what tables in the specifications and/or drawings are these trees and shrubs – what are these trees and shrubs?
Clarification provided in 11/8/16 addendum
b. The 2800 trees and 1250 shrubs – what tables in the specifications and/or drawings are these trees and shrubs – what are these trees and shrubs?
Clarification provided in 11/8/16 addendum
RAWP Section 6.2.1 Table 5 - List of permits page 24 of RAWP does not address any access agreements for property outside BMAP boundary that require removal action. Are access agreements required? If so, who is responsible?
Access agreements are required and will not be the responsibility of the contractor.
RAWP Section 5 fourth paragraph.- Previous actions at BMAP AOC 15 included installation of a stone cap. Can this stone be repurposed? Is it intended that the stone cap be disposed of offsite with the contaminated soil? If so, is the quantity of this stone included in the haz or non-haz disposal quantity provided?
The stone cap at the burn pit may be reused/repurposed. It is not expected that the stone would be disposed with the tar material present in soil below the cap.
RAWP section 6.3.5; and section 6.6 - Section 6.3.5 states the excavation to be backfilled with 5" of topsoil. Section 6.6 states excavations will be restored to original grade. Please clarify which is intended.
Per Drawings and Specfications, a minimum of 5-inches of topsoil will be used to backfill excavations after post-excavation grading.
Drawing GC 504 Detail 7 - Temporary construction access road Detail 7 shows 6" to 24" of compacted road base between 12' to 25' wide. Note 7 indicates the stone and geotextile to be removed during site restoration. Is there any intended repurpose of the stone at the site?
Stone can be repurposed/reused at the consolidation area, within th emound, or potentially in swales and downchutes.
Drawing CG 503 Detail 27 & 28 - In the various areas where chain link fence removal and replacement are required, can existing chain link fence removed be reused instead of new?
If contractor can preserve fence, the existing fence may be reused.
RWAP section 6.4 - Who is responsible for preparation and submission of the deed notice for AOC 15 Cap Area? The deed notice will be prepared by AECOM.
Specification 31 23 00 Par. 3.02 K - Specification requires that no more than 10 acres be grubbed at one time until excavation and restoration is completed. Can more than one 10 acre area be grubbed at one time that are not adjacent? E.g. 10 acres at the far end of the NW corridor and another 10 acre area at the main site.
Revised specification in 11/8/16 addendum allows three ten acre areas to be open at one time.
RAWP section 5.1 first bullet and comments from site walk meeting on 10/27/16. - Section 5.1 indicates removal of concrete building foundations. Comments during site walk 10/27/16 indicated the quantity of concrete foundations are inclusive of the soil quantities.
Please provide separated quantity of concrete foundations requiring removal. The removal of concrete foundations are an entirely separate level of effort required for removal and sizing to incorporate into the consolidation area and cannot be priced accurately as soil excavation.
Existing conditions maps show areas of concrete foundattions; 11/8/16 addendum provided CAD file with foundations. Contractor shall estimate concrete removal assuming the foundations are one-foot thick.
Document “20161017 Tree Mitigation North Parcel” pdf. Letter dated 10/17/16 - Referenced document indicates payment of $250,000 to the Hillsborough Tree Mitigation Fund. Who is responsible for this payment?
The proposed mitigation payment will not be the contractor's responsibility.
Document “20161017 Tree Mitigation North Parcel” pdf. - Information provided in the referenced document does not match up with specifications and drawings. Please provide an itemized tree/shrub planting schedule identifying quantities, types and locations of plantings required.
Clarification provided in 11/8/16 addendum
2016-10-19_Belle_Mead_Rev._2 - Please provide the project drawings in a *.dwg or other CAD file type. 11/8/16 addendum provided CAD file with existing conditions.
The proposed bid date is Nov. 21, 2016, which is Monday. Can the bid date be extended to Tuesday Nov. 22, 2016?
Due date is extended to 11/23
Does the imported fill (consolidated cap cover soil) and imported topsoil meet NJDEP Residential or Non-Residential Direct Contact Soil Remediation Standards?
Cap must comply with the Fill Material Guidance for SRP Sites. Data must meet RDCSRS, NRDCSRS, and the DIGWSRS.
The specifications indicate completion date of December 31, 2018. Unit price item 1, general conditions is 460 days. The payment is based upon the number of days worked. 460 work days is approximately 21 months. When does the GSA anticipate construction starting – March?
Work is anticipated to begin in mid-February 2017.
The contractor can clear between October 1 and March 15 (we can clear in Oct, Nov, Dec, Jan, Feb, Mar), if construction starts March 2017 we won’t be able to clear until Oct. How are the contractors to perform the work and meet the Dec. 31, 2018 schedule?
Contractor to provide its proposal to conduct remediation within the provided constraints.
Is a security guard required on‐site? If so, at what times? A security guard is not required.
Are the fill delivery trucks and other trucks exiting the site required to be pressure washed?
Trucks with potentially contaminated soil entrained on their tires or other components shall be decontaminated prior to exiting the site.
Is a flagman required at East Mountain Road, Mountain View Road, Amwell Road or at any other locations?
Drawings CT 4 01 - CT 4 03 indicate the use of a flagman.
If traffic control is required, can a Police Officer Allowance bid item be added?
The traffic control plan is being discussed with Township and County officials. At this time, police detail is not required.
an all the clearing and grubbing debris be chipped and left on‐site or placed in the onsite consolidation area?
Refer to Section 1.04.B10 in Summary of Work in Specification 01 11 00-09
Perforated Storm Drains are shown on the GC drawings:
‐There these existing drains to be removed?
‐What are the approximate depths?
‐What size and type of drains are these lines?
‐Are these drains disposed of off‐site or can they be placed in the onsite consolidation area?
Porous concrete drainage pipe present in the rail bed are to be removed. These pipes are present within the former rail bed material and are 6-12 inches deep and are approximately 12-inches in diameter.
Concrete may be placed in consolidation area. Contractor shall comply with existing applicable NJDEP regulation and guidance.
What item is the geotextile layer in the on-site consolidation area included in?
As described in 01 22 00 Unit Prices, Bid Item #13 includes geotextile fabric beneath consolidation area structures shown on the Drawings.
What item are the swales and pipe culverts shown on the CG drawings included in?
Restoration grading would be paid under Bid Item #10. Pipe culverts are exisitng and will remain or will be removed/daylighted.
LP-1 shows wetland construction backfill, detail 16 & 17 on CG-5-01 shows 12” & 30” thick wetland soil:
-What item is this backfill included in?
-What is the quantity of the wetlands backfill?
Wetland backfill shall be paid under Bid Item #16.
The site access road cross‐sections shows fill from the Excavation Grade to the Restoration Grade:
‐What item is this backfill included in?
‐What is the quantity of this backfill?
Bid Item #10 Site Grading. Site grading cut and fill balances; no offsite fill is anticipated.
Is temporary seeding required over the entire excavated subgrade?
Contractor shall comply with the Soil Erosion and Sediment Control Plan and Sepcifications for Temporary Environmental Controls (01 57 19), Erosion and Sediment Control (31 25 00), and Turfs and Grasses (32 92 00).
During excavation, how is the construction/contact water handled? Water in excavations may be allowed to percolate into the subsurface.
Item 17 – Site Construction Access Roads. Does this item include all the temporary and permanent access roads?
-Is there a single, temporary 25’ wide access road from the beginning of the wetland restoration area thru the entire site ending at Mountain View Road, approx. 17,000 LF, of which approx. 7,000 LF is removed and 10,000 LF is converted to a permanent access road (Note 12 on GC-5-04)?
The temporary road detail 7, GC-5-04, shows 6 to 24-inches of subbase.
What thickness do we base our bids on since this variable is a significant amount of stone?
-Is there a single, temporary 12’ wide access road along the top perimeter of the property line in a section of the main excavation area approx. 3,500 LF?
Isn’t an existing path in this location?
-Is a temporary access road required from the main temp./permanent access road to the consolidation area?
-Can the stone from the temporary access roads to be removed completely be placed in the onsite consolidation area?
Yes, Bid Item #17 include both temporary and long term construction access road. Drawings CT 2 01 through CT 2 14 and GC 5 04 provide detail of the 25' wide temporary access road and 30' wide long term Site Construction Access Road. The variation of compacted subbase for the Temporary Construction Access Road is to allow for the management of grade changes along the temporary road. A 12-foot wide temporary construction access is presented in Design Drawing G 4 01 and was intended to facilitate access to Zone 3 and Zone 4. An existing path is present in this area. Contractor may utilize the existing path at their own risk or may construct a temporary path as specified.
The Consolidation Area Access Road is considered a Permanent Access Road. The stone removed from temporary roads may be placed in the consolidation area.
An existing watermain is shown in the excavation area. Is this watermain active? What size is this main? What depth is the main?
The water main is not active and is anticipated to be present below excavation grades.
An existing sanitary sewer and manholes is shown in the excavation area. Is this sewer active? What size is this sewer? What depth is the sewer?
Sanitary sewer in northwest corridor is active; former facility sanitary sewer is not active. Inverts were provided on existing conditions drawings and are not anticipated to be within excavation grades.
Existing 15”, 24”, 36”, 42” and 48” RCP pipe and manhole abandonment is shown, are these pipes removed or are they cut, plugged and remain? The detail shows both. How can we determine which is removed and which remains?
Pipes that are completely ore partially above final grade will be demolished (see note 3 of detail on GC 5 05.
A Support Zone is shown on the drawings, approx. 86,000 square feet:
-Is this entire area to be prepared?
-Is a stone layer required in this area?
Is the stone required to be removed? Can it be placed in the consolidation area?
-Is this area the trailer, parking and staging area?
-Is electricity available to connect to the trailers?
Support zone shall be established per 01 50 00 Temporary Facilities and Controls.
Is the silt fence and haybale barrier around the entire perimeter removed or can it remain?
Upon completion of restoration, erosion control measures shall be removed.
s the silt fence, road geotextile, pipe, storm drains, decon pads and other items not placed onsite in the consolidation area disposed of offsite paid under item 21 - 02 Miscellaneous Debris?
Yes, materials and other items not placed in the onsite consolidation area that must be disposed offsite may be paid under Bid Item #21-02.
Excavation items 5, 6, 7 and 8 includes removing the stumps, grinding the stumps, screening the chips to separate the soil and disposal of the chips. It refers to section 02 81 00 that debris and wood chips be disposed of off-site:
-Is the screening of the chips to separate soil only apply to the trees in the burn pit excavation area, pistol range excavation area and Selenium/Naphthalene excavation area?
-Can the contractor shake the stumps prior to grinding in order to remove the soil?
-Can the payment for the removal of stumps, grinding and screening of the grindings to separate out the site soils be removed from the excavation pay items and be included in the clearing item?
-How can the contractors determine the quantity of grinding chips to be disposed of off-site? Can a separate unit price item be established?
Stumps in all impacted areas shall be ground and screened as specified. Stumps and root balls are ultimately part of the excavation volume and activities to separate the woody debris from soil shall be priced with that bid item. Contractors shall estimate the quantity of chipped vegetative waste that will be generated and shall include disposal costs.
Are the seams of the geotextile cap at the consolidation area sewn? Geotextile seams shal be sewn per 31 05 19
Section 31 22 00, what bid item is the Common Borrow Fill imported and used?
Bid Item #12 - Common borrow fill is used at the consolidation area.
Section 31 23 00 – Excavation, section 3.02 – please clarify, “Excavation will take place in 30 by 30-foot excavation control grid as shown on drawings.
The Contractor shall maintain grade stakes at the grid centers”. Can the contractor excavate a large area, then as-built and stake the area at 30 foot grids?
· Is the temporary Royce Brook Box culvert disposal, after removal, disposed of offsite paid under item 21-02 - Miscellaneous Debris?
Contractor may excavate areas up to 10-acres in accordance with the specifications. Contractor shall maintain quality control of excavation as specified in 31 23 16 §1.06.
Are perimeter air monitoring stations required?
-How many air monitoring stations are required?
-We assume they operate only during working hours, 8-hours per day, 5-days per week?
-Are we monitoring for dust only?
-Is wireless remote monitoring required?
-Is a noise meter required to be integrated into the wireless remote monitoring?
Air monitoring stations are to be placed and managed according to the Air Monitoring Plan provided as Appendix F of the RAWP.
Unit price item 1, general conditions description includes implementing the health and safety requirements – does this include the Health and Safety Officer and Unit price item 18, air, noise and dust monitoring, implementing the air monitoring plan, include the air monitoring technician?
Contractor shall propose adequate resources to monitor health and safety of workers within the work zone and to monitor the noise and dust monitoring required by the AMP.
How much retainage(%) will the GSA deduct from the monthly progress payment applications the contractor submits? Would the contractor receive the total retainage held at the end of the construction period?
There will be no automatic retainage on this requirement. The Government reserves the right to retain up to 10% from progress payments with notice to the Contractor.
2. Is the project maintenance period 2 years? Seeded Area maintenance is defined in 32 92 00 as 730 calendar days.
3. Please confirm NJ state sales tax is to be included? Contractors fixed and unit prices shall include all applicable taxes. This project will not be tax exempt.
Item 21‐01 Rail Ties Disposal is Lump Sum:
a. How can the contractors determine the number of tons to be disposed of for a 235‐acre site?
b. Can the Engineer revise this item to a Unit Price per Ton with an estimated quantity (tons). The Engineer is best suited to determine this quantity, not the contractors.
c. If the Engineer will not revise this item, please provide the number of miles of railroad, number of railroad ties per mile and the number of rail ties per ton
11/8/16 Addendum revises Rail Tie disposal to tons.
5. Item 19 is 1926 samples. The 1926 samples is comprised of 4272 total samples. How many blanks or QC samples are required per the 4272 samples?
QA samples per the QAPP should be included in Contractor's pricing.
However, field blanks will not be required if Contractor selects the use of dedicated disposable sampling equipment at each sample location.
Duplicates are required on a 1:20 ratio.
6. Item 19 is 1926 samples. Do the sample locations require to be recorded by GPS?
Contractor to provide location information for all post excavation soil samples per the QAPP. Location of confirmation samples should be surveyed to the accuracy required by NJDEP.
7. Item 19 is 1926 samples. What turnaround time does the Engineer require for the sample results?
Turnaround time is not specified and should be considered in offeror's schedule.
8. Currently the concrete removal is included in the excavation item 8.
There is a significant amount of concrete to be removed. This concrete needs to be processed to 6‐inch minus in order to be placed in the onsite consolidation area. The removal and processing of the concrete is a much more exhaustive (equipment and labor intensive) operation than the soil excavation. Can the concrete removal, processing and placement be separated from the excavation item into its own bid item?
There will be no change to this bid item.
9. Is the consolidation area topsoil (Item 14) 5 or 6‐inches thick? Topsoil to be placed to in place final thickness of no less than 5-inches.
10. Does the consolidation area cover soil (Item 12) need to meet specification section 31 22 00, section 2.04 or 2.01 (common borrow fill)?
Consolidation area cover soil shall meet sectoin 2.04 of 32 22 00.
11. The chain link fence to be replaced – does the contractor assume 6’ high or 8’ high?
Replacement fence shall be of similar height as existing fence (5 to 6 feet is typical).
12. Item 11 ‐ Topsoil and Seed is 235 acres. Item 14 – Consolidation Area Topsoil and Seed is 21 acres. Should Item 11 be revised to 214 acres?
11/8/16 addendum revised topsoil and seed quantity.
13. Plantings 32 90 00, Tables 1A‐1E. What Bid Item are these plantings included in? Where are they installed?
11/8/16 addendum removed planting tables in 32 90 00
14. Plantings 32 90 00, Tables 1A‐1E – are these items and quantities duplicated in any other tables or schedules in any of the other drawings?
11/8/16 addendum removed planting tables in 32 90 00
15. Item 16 – Wetland Plantings – 19.081 Acres: Is the bid quantity measured in the field by the total area of all the shaded areas per the legend shown on the top right of sheet LP 0 01?
Wetland plantings may be measured based on the field measurments of streambed and bank restoration, wetland restoration, riparian zone restoration, and transition area restoration as shown on LP 0 01.
DRCC stream corridor restoration is paid in upland tree mitigation Bid Item.
16. Drawings LP 1 01 to 10 – what bid item is this work included in?
Wetland plantings may be measured based on the field measurments of streambed and bank restoration, wetland restoration, riparian zone restoration, and transition area restoration as shown on LP 0 01.
DRCC stream corridor restoration is paid in upland tree mitigation Bid Item.
17. Drawings LP 0 01 has 5 tables – what items are these plantings included?
Tables presented on LP 0 01 include streambed and bank restoration, wetland restoration, riparian zone restoration, transition area restoration and DRCC stream corridor restoration.
18. Drawings LP 1 11‐16 – Landscape Buffer Drawings w/ Plant Schedules
– what item is this work included in. The quantities do not seem to match up.
Bid Item #15 includes the Landscape Buffer.
19. LP‐1‐16 – Native Prairie Basin Mix – where is this seed mix installed and what item is it included in?
Topsoil and Seeding (Bid Item #14); see Turfs and Grasses specfication 32 92 00.
20. LP‐1‐16 – Total Project Plant Schedule shows 633 trees and 513 shrubs
– what item is this included in? Is it a summary of the tables listed in LP‐1‐ 11 to 15. The quantities do not seem to match up.
11/8/16 addendum revises this table to Lanscaped Buffer Plant Schedule.
21. The landscape details shows details for Live Brush Mattresses ‐ can the Engineer provide a quantity and specification?
Contractor shall review quantities presented in L001 of the Permit drawings, cross sections LP-301 through LP-305, and details CG-502 and CG-505.
22. The landscape details shows details for Live Brush Mattresses ‐ what item is this included in?
Live brush mattress to be planted along riparian restoration areas and will be included in Bid Item #16.
23. The landscape details shows details for Coir Log / Fascine Bundle ‐ can the Engineer provide a quantity and specification – is coir log or fascine bundle required?
Contractor shall review quantities presented in L001 of the Permit drawings, cross sections LP-301 through LP-305, and details CG-502 and CG-505.
24. The landscape details shows details for Coir Log / Fascine Bundle ‐ what item is this included in?
Coir log . Facsine bundle to be planted along riparian restoration areas and will be included in Bid Item #16.
Reference C201‐SB Solicitation Section II.D Technical Proposals (3) Experience of Firm (Page 10 of 24), and SectionVI.F Non Price Factors (3) Experience of Firm (Page 24 of 24), where it states: “In descending order of importance, relevant components of these projects might include:” Please clarify that only projects meeting all criteria set forth for size, type, scope and regulatory will be considered.
All projects will be considered. Projects that meet or exceed all criteria listed will be reviewed more favorably.
2. Reference C201‐SB Solicitation Section II.D Technical Proposals (2) Management Approach (Page 9 of 24). We respectfully request that the project schedule be excluded from the 10‐page page count.
Project Schedule may be excluded from the page count.
Due to the considerable quantity of plan sheets and the limited time to provide a proposal will a CAD file for grading plan sheets (CD101 through CD134, CG101 through CG134, and CS101‐CS102) be provided by 11/3 to allow bidders to verify excavation quantities and embankment/backfill quantities?
Contractor shall base their quantities on Bid Schedule A.
2. Will the work required to restore the site to the grades as shown on plan sheets CG101 through CG134 after excavation has been completed be paid for under Bid Item 10, Site Grading? If so please provide embankment/fill quantities required to do so.
Yes grading activities on CG101 - CG134 will be paid under Bid Item #10. Cut and fill for these areas balance, so additional fill is required to meet grades. If grades cannot be met in the field, CM may approve lower grades or allow the import of fill as a change to the contract.
After digitizing the Contract Drawings we found an additional 143,000 CY of additional excavation in order to achieve the restoration grades (less topsoil). The specs & addendum instruct the bidders to assume the site is in balance but it is not in balance. How are we to deal with this excess soil?
Where do we place it? This is a significant variance. Can a unit price item be added to the bid to account for this excess excavation and where it is to be placed.
Design grades have been analyzed in Civil-3D and have been found to balance. Contractor shall assume that the quantities presented in Schedule A are accurate. Amounts in excess of the quantities on Schedule A-01 will be paid on unit rates based on Shedule A-02.
Section 01 11 00, 8. The Contractor shall dispose of chips at GSA approved off-site locations but no locations are given and Section 01 22 00, Bid Item 2, a., iv indicates the chips can be managed as non-contaminated. Please confirm there are no restrictions for the disposal of clean wood chips.
Refer to Section 1.04.B10 in Summary of Work in Specification 01 11 00-09
▪ Section 01 22 00, Bid Item 5, a., iii, requires the Contractor to grind stumps and roots in a tub grinder and then pass the chips generated from the grinding through a screen to remove entrained soil from the chips. Please confirm that screening wood chips in all areas is only required following tub grinder procedures required of stumps and/or roots and is not required during normal chipping of trees and brush.
Screening of chips to remove entrained soil is only required for stumps and roots and is NOT required during normal chipping of trees and brush.
▪ Section 01 22 00, Bid item 10, Site Grading, a., i., states “Assume that off-site borrow will not be required and that high spots and low spots …… will balance. Has AECOM performed the takeoff to determine if the site is in balance? Also is the Contractor expected to move existing soil from multiple zones to multiple zones in order to achieve the necessary grades? Why can’t the excavation plan be modified to incorporate the proposed final grades?
Designer has performed analysis in Civil-3D and has found that the design grades are in balance. It is possible that some 10-acre areas will have excess or require soil to meet proposed design grades.
Contractor will work with CM to address identified issues in the field.
The excavation plan is designed to remove impacted soil while limiting the colume to be moved to the consolidation area and will not be modified further.
▪ Section 01 22 00, Bid item 11, Bid item 14, topsoil and seed. Has the government considered utilizing any of the existing on-site topsoil in lieu of importing roughly 250,000 cubic yards?
Topsoil shall be imported as specified.
I got disconnected from the group when driving to the site; could you send me the exact address or coordinates where the entrance is relevant to this scope of work?
The main construction entrance is located at 40° 28' 48.47"N 74° 39' 48.59" W.
Charter RFI's
1. Please address the quantities of plantings:
1.1. There are 5 tables of plantings on Drawing LP-001 that total approximately, 3,500 shrubs; 10,500 trees; and 350 sedges/rushes.
1.2. There are 5 tables of plantings within Specification 32 90 00 that total, approximately, 1,800 shrubs; 5,000 trees; and 400 sedges/rushes.
1.3. There is a summary table of plantings on Drawing LP-116 that totals, approximately, 500 shrubs; 630 trees and zero sedges/rushes.
1.4. Bid items 15-01 and 15-02 indicate 8,000 trees and 3,000 shrubs, respectively.
Please explain these apparent discrepancies and which Bid Item each table will be paid under.
Addendum posted to FedBizOpps clarified tree plantings.
2. Please indicate where the limits of the 19.081 Acres of Wetland Riparian Zone Restoration and Plantings (Bid Item 16) are shown. Please provide a detailed scope of work for Bid Item 16.
Please refer to the NJDEP Freshwater Wetland General Permit, Flood Hazard Area Individual Permit, and Water Quality Certification Permit application document provided in the bid package. File name: <BMAD North Parcel, June 3, 2016 Permit Submission.pdf>
Reference: Drawing CG-132 shows a Sound Berm.
Question: Is this a feature of work under this contract? If so, please note that no detail has been provided.
Yes, this feature is part of the proposed work and is simply a soil berm.
No additional design…