0018-IDIQ-Addendum1-AENarrative.doc
DOC document 41 KB Posted
- Attached to
- Multiple Award, Indefinite Delivery/Indefinite Quantity (IDIQ) for WV & VA Federal contract opportunity
- Solicitation number
- GS-03P-13-CD-D-0018
About this file
0018-IDIQ-Addendum1-AENarrative
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Abingdon Federal Building and US Courthouse First and Second Floor Renovations
0018-IDIQ-WVVA
Addendum No. – August 12, 2013
This addendum is supplementary to the plans and specifications for the Abingdon Federal Building and US Courthouse first and second floor renovations, located on the corner of West Main and Cummings Streets in Abingdon, Virginia. All changes, deletions and additions shall be part of the contract as if originally shown in the plans and specifications.
DESCRIPTION OF AMENDMENT:
A. DRAWING ITEMS
ITEM NO A.1: REPLACE THE FOLLOWING SHEETS IN THEIR ENTIRETY
| ITEM NO. |
| SHEET NO. |
| SHEET NAME |
| REVISED DATE |
| A.1.001 |
| A-601 |
| DOOR SCHEDULE |
| 8.5.2013 |
| A.1.002 |
| EP102-02 |
| POWER NEW WORK PLAN, 2ND FLOOR |
| 8.5.2013 |
| A.1.003 |
| E-603 |
| ELECTRICAL PANEL BOARD SCHEDULES |
| 8.5.2013 |
| A.1.004 |
| F-101-01 |
| FIRE ALARM/ SECURITY NEW WORK PLAN, 1ST FLOOR |
| 8.5.2013 |
| A.1.005 |
| F-102-02 |
| FIRE ALARM/ SECURITY NEW WORK PLAN, 2ND FLOOR |
| 8.5.2013 |
| A.1.006 |
| F-103-B1 |
| FIRE ALARM/ SECURITY NEW WORK PLAN, BASEMENT |
| 8.5.2013 |
B. QUESTIONS FROM BIDDERS:
The following answers are provided in response to questions that have been submitted by Bidders:
B.1 Sheet S-501, Detail 5, Note 1, references a detail on Sheet S-502. Is there a Sheet S-502?
Answer: There is no sheet S-502, reference detail 2/S-501 for infill framing information.
B.2 Electrical: There are several conduit runs to the basement. There is no floor plan of the basement. Please provide a scaled and labeled floor plan for the basement.
Answer: Please refer to the Basement Floor Plan on sheet F103.
B.3 Section 260573 – Overcurrent Protective Device Coordination Study, This requirement is quite appropriate when a complete, multi-breaker panel is being installed. However, this project is only adding one to three new breakers to existing panels. The expense of a Coordination Study on these panels would be great. Please confirm that an Overcurrent Protective Device Coordination Study is to be included in the Scope of Work.
Answer: REFER TO AECOM ADDENDUM #1 DATED 8/08/2013: ITEM B3 Answer: PER GSA THE OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY WILL NOT BE REQUIRED FOR THE ABINGDON FIRST & SECOND FLOOR RENOVATION PROJECT.
B.4 Sheet EP-101, Room 126, East Wall, Please advise what the designations APP represent on two devices and UCR on another device.
Answer: “APP” designates a small appliance receptacle and “UCR” designates a receptacle for an under counter refrigerator.