GFP RFI Questions.pdf
PDF 53 KB Posted
- Solicitation number
- Not on record
About this file
This document is a Request for Information (RFI) from the U.S. Air Force regarding the potential implementation of industry interest in the F117 Follow-On Contract. The Air Force is considering whether to provide or recall government-furnished property (GFP) in the form of tooling and test equipment for the follow-on F117 contract. The RFI poses four key questions to industry:
- Whether bidders would still be interested in the follow-on F117 contract if the USAF does not provide/recalls GFP tooling and test equipment.
- What specific challenges bidders would face if GFP tooling and test equipment is not provided/recalled.
- Whether the previously stated timeline to stand-up a depot would change if the USAF does not provide/recall GFP tooling and test equipment.
- What portions of the work bidders would still be interested in performing if GFP tooling and test equipment is not provided/recalled.
Responses to this RFI are requested to be submitted to alexandra.crothers@us.af.mil by 4pm CT on Friday, November 8, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Licensing RFI.docx | DOCX document | |
| Flight Data Questions.pdf | ||
| Supply Chain RFI Clarification.pdf | ||
| Supply Chain RFI.pdf | ||
| USAF responses to questions.pdf | ||
| GFP RFI Responses with Additional Questions.pdf | ||
| Small Business RFI.docx | DOCX document | |
| Industry Day 2 Question Clarification.docx | DOCX document | |
| Industry Day 2 QA.pdf | ||
| F117 Industry Day 2 Attendance.pdf | ||
| F117 ESS Industry Day 2 Slide Deck PA Approved.pptx | PPTX presentation | |
| OFFEROR QUESTIONS Industry Day 2 Updated.pdf | ||
| OFFEROR QUESTIONS .pdf | ||
| Agenda .pdf | ||
| 2nd Industry Day Agenda.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GFP RFI Questions
USAF respectfully requests responses submitted to alexandra.crothers@us.af.mil by 4pm CT on Friday 8 Nov 2024.
The USAF is considering the implementation on industry interest in the F117 Follow-On Contract if GFP in the form of tooling and test equipment is not provided/recalled by the USAF. This would not affect GFM provided by F77.
1. If the USAF does not provide/recalls GFP tooling and test equipment for the follow-on F117 contract, would you still be interested in bidding on the contract?
2. What specific challenges will you have if GFP tooling and test equipment is not provided/recalled?
3. Does the previous stated timeline given to stand-up a depot change if the USAF does not provide/recalled GFP tooling and test equipment?
4. What, if any, portion of the work would you still be interested in preforming if GFP tooling and test equipment was not provided/recalled?
File details come from the government source that posted it. Updated .