FIELD_ORDER.pdf
PDF 34 KB Posted
- Solicitation number
- 22-ENG-03
- Issued by
- Hamilton County, Indiana
About this file
This is a Field Order template document from the City of Carmel, Indiana, used for the 116th Street and Hoover Road Roundabout Construction project. The Field Order form serves as an authorization mechanism for the contractor to execute work that interprets existing contract documents or implements minor changes without modifying the contract price or timeline. The document provides space for the engineer to describe the required work, list any attachments, and obtain approval from the engineer and owner's representative with corresponding dates. If the contractor determines that the proposed work requires changes to contract price or schedule, the contractor must submit an itemized proposal to the engineer before proceeding, which would then be superseded by a formal Change Order if approved.
The Field Order is a standard construction administration tool that does not independently establish pricing, set-asides, or other contractual terms. Rather, it functions within the existing contract framework for the roundabout construction project, which includes comprehensive infrastructure improvements such as HMA pavement, curb and gutter, shared-use path, enclosed storm sewer system, street lighting, landscaping, water main relocation, and raised crosswalks. The project has a substantial completion deadline of November 16, 2026, and final completion by May 1, 2027, with liquidated damages of $5,000 per calendar day for delays. Sealed bids were due February 4, 2026, and the contract requires performance bonds, payment bonds, and maintenance bonds from a U.S. Treasury-approved surety authorized to conduct business in Indiana.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF CARMEL
OWNER: CITY OF CARMEL
FIELD ORDER NUMBER
DATE:
PROJECT NAME:
PROJECT NO:
You are hereby directed to execute promptly this Field Order which interprets the Contract Documents or orders minor changes in the Work without change in Contract Price or Contract Time.
If you consider that a change in Contract Price or Contract Time is required, please submit your itemized proposal to the ENGINEER immediately and before proceeding with this Work. If your proposal is found to be satisfactory and in proper order, this Field Order will in that event be superseded by a Change Order.
Description:
Attachments:
ENGINEER:
Approved By: _______________________________________ Owners Representative
Date: ___________________________________