75F40120R00012_0001 Final.pdf
PDF 338 KB Posted
- Attached to
- NCTR Road & Drainage Improvements Federal contract opportunity
- Solicitation number
- FDA-RFP-75F40120R00012
About this file
This document contains an amendment to a solicitation for a federal contract and related questions and answers. The solicitation is for road and drainage improvements at the National Center for Toxicological Research facility. The amendment extends the offer due date to July 13, 2020. It also increases the period of performance to 270 calendar days and changes the bonding requirements. Questions from offerors sought an extension to the performance period due to weather concerns, and an extension to the offer due date to allow time to obtain an Arkansas contractor's license. The agency agreed to the requested changes to the due date and deemed the extended performance period adequate.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
FDA/OO/OFBA/OAGS/DAP
OAGS - Field Operations Branch ATTN: Jennifer Johnson 39000 NCTR Road, Bldg. 50, Rm. 429 Jefferson AR 72079
ALL OFFERORS
1222085
75F40120R00012
07/01/2020
06/05/2020
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of the amendment is to:
1. Extend the "Offer Due Date/Time” to 12:00 pm CT, 13 July 2020.
2. Change the period of performance/work shall be completed to 270 calender days.
3. Add 52.228-15 Performance and Payment Bonds-Construction (Deviation Apr 2020); removing the seal requirement.
4. Change section "G-5 Bonding Requirement" delivery method to: jennifer.johnson3@fda.hhs.gov.
5. Provide the Pre-Proposal Conference/Site Visit Minutes. *Attachment 1.
6. Provide answers to questions. *Attachment 2.
*No other questions will be entertained.
Attachment 1 ‐ Pre‐Proposal Conference/Site Visit Minutes
NCTR ‐ Road & Drainage Improvements
75F40120R00012
June 16, 2020
Attendees:
Contractors – 2 *The sign‐in sheet is attached.
Government Employees ‐ 4:
Brian Young, Office of Facilities Engineering and Mission Support Services (OFEMS)
Thomas Baioni, OFEMS
Viplav Patel, OFEMS
Jennifer Johnson, Contract Specialist, Office of Acquisition and Grants Services (OAGS)
Mrs. Jennifer Johnson, convened the meeting at 9:15 am Central Standard Time (CT).
A general overview of the solicitation was conducted by Mrs. Johnson, including a review of sections B, L, and M of the solicitation including: Summary of requirement, NAICS code, requirement magnitude, proposal submission instructions, and evaluation factors. Dates to reminder were also covered:
1. Question Submission Deadline: June 23, 2020, by 10:00 am CT.
2. Question & Answer/Site Visit Overview Modification Issuance on or before June 30, 2020.
3. Proposal submission deadline is July 6, 2020, 12:00 pm CT.
A technical overview of the solicitation was conducted by Brian Young including: Specifications, work phases, and drawings. Mr. Young then conducted a site walk through.
The proposal conference/Site Visit adjourned at 11:40 am CT.
U.S. FOOD & DRUG
A0MIHISIIIATIOII
Pre-proposal Site Visit~ RFP 75F40120R00012 NCTR - Road & Drainage Improvements June 16, 2020
* Attendees (Please Print Clearly)
Name Company/Office Telephone No.
FDA
EOA
Attachment 2 ‐ Questions & Answers
NCTR Road & Drainage Improvements
75F40120R00012
1. RFP, section 11, page 1 and subsequent mention of the 180 day period of performance throughout the RFP: Upon discussion with our Subs and our own intel gathered while at the site visit, we would like to ask for the 180 day performance period be changed to 365 days. There are several reasons for this request. The current proposal will take the project into mid‐
February. The overlaying cannot be applied unless the ambient temperature is 40 degrees (F) and rising. That is important to note as not the same as a High of 40. We would start having days as early as November that will restrict this process. These days will only grow in frequency as the performance period extends into winter. Also, rain is most common in the Winter on the warmer days. Progress will be at a crawl from Dec‐Feb. Based on the Winter accounting for almost half of the performance period; we are left with an actual Period of 75‐90 days, and that does not account for weekends, Holidays, and rain. This could be as little as 60 working days before we start losing days to temperatures being too low. The other factor of note is the increase in rain as Fall/Winter come across our calendars. The other large facet or work are grading ditches (which cannot be done satisfactorily if filled with water) and the installation of culverts (which need to be adequately compacted while back‐filling). Everyone at the Site‐visit seemed very understanding of these issues and anticipated them. However, the Performance and Payment Bonds would be issued prior to starting the work with 180 day terms. While the
Government has expressed understanding in the 180 day performance period, they would be within their rights to exercise those Bonds when outside the 180 days. This would be very unfavorable to the contractor for acquiring future bonds and financially. It would be appreciated, if this period were extended. The reason for 365 days and not 220 or something else intermediate; is that the days would be starting mid‐February and for the reasons outlined above, would not yield many productive days to the Contractor.
Answer: The Period of Performance has been increased to 270 days. After internal discussions along with input from the design engineer we feel that is adequate time to complete the project. Weather delays will be evaluated at the time they are submitted, and reasonable consideration will be given.
2. RFP, section 13, page 1 & : Part II ‐ Price Proposal Instructions, i), page 45. Would you consider extending the offeror date one week to July 13th? The reason I have asked for a week's delay in the quote submission is to fulfill the requirements of providing an Arkansas Contractor's
License. Arkansas uses the NASCLA ‐ Arkansas 6th edition as its current book for its Arkansas
Business Law Exam. In Section 3‐2, under exemptions, it states that performing "work on federal property under a contract with the federal government". Because of this exemption, we have not obtained a license.
I would like to amend my week's delay to simply asking for the removal of this requirement. If that is not the government's desire to do so, then please allow a delay in quote submission for the obtainment of the License. The Arkansas Licensing Board does not hold its next hearing till
July 10th (https://www.aclb.arkansas.gov/laws‐rules/hearing‐dates/).
Answer: We have no issue with extending the date one week to 13 July. It is important that the chosen contractor be recognized by the State of Arkansas as a licensed contractor.
| 75F40120R00012_0001 Draft pg. 1 |
| Attachment 1 - Pre-Proposal Conference-Site Visit Minutes |
| Attachment 2 - Questions & Answers |