TOS Cover Letter w/Attachment

View the file

Other files for this federal contract opportunity

Other files attached to Test Operations and Support, newest first.
File Type Posted
Attachment_5_-_Davis_Bacon_Wage_Decisions.pdf PDF
Amendment_0004.pdf PDF
Attachment_4_-_Service_Contract_Labor_Standards_Wage_Determination.pdf PDF
Questions_from_Industry_Post_RFP_Amd_0003.pdf PDF
Attachment_L-7 _Cross_Reference_Matrix_(Revised).pdf PDF
Response_to_RFP_Comment.pdf PDF
Amendment_0002.pdf PDF
Amendment_0001.pdf PDF
Attachment_9 _Section_L.pdf PDF
PWS_22_84_89_91.pdf PDF
CDRL_30000_30001_81861.pdf PDF
Attachment_6_-_Award_Fee_Term_Plan.pdf PDF
Attachment_L-1_-_PPI_for_Offerors.pdf PDF
Attachment_L-4_-_Client_Authorization_Letter.pdf PDF
Exhibit_A_-_Contract_Data_Requirements_List.pdf PDF
Attachment_10_-_Section_M.pdf PDF
Attachment_L-6_-_Relevancy_Matrix.pdf PDF
Attachment_4_-_Service_Contract_Labor_Standards_Wage_Determinations.pdf PDF
Attachment_L-3 _PPQ_Cover_Letter.pdf PDF
Attachment_8_-_Performance_Work_Statement.pdf PDF
Attachment_L-7_-_Cross_Reference_Matrix.pdf PDF
Attachment_L-2_-_Past_and_Present_Performance_Questionnaire.pdf PDF
Attachment_L-5_-_Subcontractor_Consent_Letter.pdf PDF
ppi_tool.accdb —
AGENDA_Final_20140610.pdf PDF
Industry_Day_No._4_Registration.pdf PDF
Attachment_7_-_Statement_of_Objectives.pdf PDF
Attachment_L-11__TOS_Cost_Model.xlsx XLSX spreadsheet
Section_M_Draft_RFP.pdf PDF
Exhibit_B_-_Data_Item_Descriptions.pdf PDF
Attachment_8_-_TOS_PWS_Draft_Release_12_May_2014.pdf PDF
Cover_Letter_Draft_RFP.pdf PDF
Attachment_2_-_DoD_Contract_Security_Classification_Specification.pdf PDF
Informational_Announcement_ASP.pdf PDF
Question_to_Industry_Quality_22Jan14.pdf PDF
Informational_Announcement_to_Industry.pdf PDF
Industry_Familiarization_Session_Final_Agenda.pdf PDF
Request_for_Information_No._4.pdf PDF
RFI_No._3.pdf PDF
RFI_No._3_Delay_10Sep13.pdf PDF
RFI_No._3_Delay.pdf PDF
RFI_No._2_Amendment_02.pdf PDF
RFI_No._2_Amendment_01.pdf PDF
CDRL_30001_30049.pdf PDF
CDRL_30050_30099.pdf PDF
Amendment_01_RFI_No._1.pdf PDF
Atch_2_Map_to_ALC_GLC.pdf PDF
Atch_2 _OCI_Clause.pdf PDF
Atch_1_-_PWS.pdf PDF
RFI_No._1.pdf PDF
Show all 50

Test Operations and Support has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1

Changes to draft Request for Proposal

FA9101-13-R-0100, Test Operations and Sustainment (TOS)

DD FORM 1707 Added

STANDARD FORM 33

‐ Revised RATING from DX to DO ‐ Revised DATE ISSUED 28 AUG 2014

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

‐ Revised CLIN 0001 to refer to Offeror’s proposed Technical Volume ‐ Revised CLINs 0002, 0005, 0008, 0011, 0014, 0017, 0020, and 0023 to refer to

Contractor Performance Work Statement in lieu of Performance Work Statement ‐ Added B028 CONTRACT TYPE: FIRM FIXED PRICE (FEB 1997) (TAILORED) ‐ Revised B038 CONTRACT TYPE: COST-PLUS-AWARD-FEE (FEB 1997) (TAILORED)

SECTION C - DESCRIPTION/SPECS/WORK STATEMENT

‐ Removed C100 PERFORMANCE WORK STATEMENT (MAY 2014) ‐ Added C100 CONTRACTOR PERFORMANCE WORK STATEMENT (AUG 2014)

SECTION E - INSPECTION AND ACCEPTANCE

‐ Removed FAR Clause 52.246-16 RESPONSIBILITY FOR SUPPLIES (APR 1984)

SECTION F - DELIVERIES OR PERFORMANCE

‐ Added FAR 52.247-34 F.O.B. DESTINATION (NOV 1991)

SECTION G - CONTRACT ADMINISTRATION DATA

‐ Revised Fill-ins DFARS 252.232-7006 WIDE AREA WORKFLOW PAYMENT

INSTRUCTIONS (MAY 2013)

SECTION H - SPECIAL CONTRACT REQUIREMENTS

‐ Removed H050 RIGHTS IN INFORMATION AND DATA (MAY 2014) ‐ Added H050 RIGHTS IN INFORMATION AND DATA (AUG 2014) ‐ Removed H100 DIRECTIVE APPLICABILITY (MAY 2014) ‐ Added H100 DIRECTIVE APPLICABILITY (AUG 2014) ‐ Removed H102 MULTIPLE EMPLOYER BENEFIT PENSION PLAN (MAY 2014) ‐ Added H102 MULTIPLE EMPLOYER BENEFIT PENSION PLAN (AUG 2014) ‐ Removed H103 MINIMUM WAGE RATES (MAY 2014) ‐ Added H103 MINIMUM WAGE RATES (AUG 2014) ‐ Removed H104 ADVANCED COST AGREEMENT (MAY 2014) ‐ Added H104 ADVANCED COST AGREEMENT (AUG 2014) ‐ Removed H105 PERSONNEL LIABILITY (MAY 2014) ‐ Added H105 PERSONNEL LIABILITY (AUG 2014) ‐ Removed H106 CONTRACTOR CHANGEOVER (MAY 2014) ‐ Added H106 CONTRACTOR CHANGEOVER (AUG 2014) ‐ Removed H110 UNCLASSIFIED SECURITY (MAY 2014) ‐ Added H110 UNCLASSIFIED SECURITY (AUG 2014) ‐ Removed H123 ASSOCIATE CONTRACTOR AGREEMENTS (MAY 2014) ‐ Added H123 ASSOCIATE CONTRACTOR AGREEMENTS (AUG 2014) ‐ Added H125 CRITICAL KEY PERSONNEL (AUG 2014) ‐ Added H126 STRIKE PLAN (AUG 2014) ‐ Added H127 BASE SUPPORT (AUG 2014)

SECTION I - CONTRACT CLAUSES

‐ Removed FAR 52.203-05 COVENANT AGAINST CONTINGENT FEES (APR 1984) ‐ Added FAR 52.203-05 COVENENANT AGAINST CONTINGENT FEES (MAY 2014) ‐ Removed FAR 52.203-07 ANTI-KICKBACK PROCEDURES (OCT 2010) ‐ Added FAR 52.203-07 ANTI-KICKBACK PROCEDURES (MAY 2014) ‐ Removed FAR 52.203-08 CANCELLATION, RESCISSION, AND RECOVERY OF

FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY (JAN 1997)

‐ Added FAR 52.203-08 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS

FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)

‐ Removed FAR 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR

IMPROPER ACTIVITY (JAN 1997)

‐ Added FAR 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER

ACTIVITY (MAY 2014)

‐ Removed FAR 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS

AND REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS

(SEP 2013)

‐ Added FAR 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND

REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR

2014)

‐ Removed FAR 52.208-08 REQUIRED SOURCES FOR HELIUM AND HELIUM USAGE

DATA (APR 2002)

‐ Added FAR 52.208-08 REQUIRED SOURCES FOR HELIUM AND HELIUM USAGE

DATA (APR 2014)

‐ Removed FAR 52.208-09 CONTRACTOR USE OF MANDATORY SOURCES OF

SUPPLY OR SERVICES (OCT 2008)

‐ Added FAR 52.208-09 CONTRACTOR USE OF MANDATORY SOURCES OF SUPPLY

OR SERVICES (MAY 2014)

‐ Removed FAR 52.215-12 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA

(OCT 2010)

‐ Added FAR 52.215-16 FACILITIES CAPITAL COST OF MONEY (JUN 2003) ‐ Revised Fill-in for FAR 52.216-07 ALLOWABLE COST AND PAYMENT (JUN 2013) ‐ Removed FAR 52.219-08 UTILIZATION OF SMALL BUSINESS CONCERNS (JUL

2013) ‐ Added FAR 52.219-08 UTILIZATION OF SMALL BUSINESS CONCERNS (MAY 2014) ‐ Removed FAR 52.222-04 CONTRACT WORK HOURS AND SAFETY STANDARDS -

OVERTIME COMPENSATION (JUL 2005)

‐ Added FAR 52.222-04 CONTRACT WORK HOURS AND SAFETY STANDARDS -

OVERTIME COMPENSATION (MAY 2014)

‐ Removed FAR 52.222-06 DAVIS-BACON ACT (JUL 2005) ‐ Added FAR 52.222-06 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014) ‐ Removed FAR 52.222-07 WITHHOLDING OF FUNDS (FEB 1988) ‐ Added FAR 52.222-07 WITHHOLDING OF FUNDS (MAY 2014) ‐ Removed FAR 52.222-08 PAYROLLS AND BASIC RECORDS (JUN 2010) ‐ Added FAR 52.222-08 PAYROLLS AND BASIC RECORDS (MAY 2014) ‐ Removed FAR 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (JUL 2005) ‐ Added FAR 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014) ‐ Removed FAR 52.222-12 CONTRACT TERMINATION -- DEBARMENT (FEB 1988) ‐ Added FAR 52.222-12 CONTRACT TERMINATION -- DEBARMENT (MAY 2014) ‐ Removed FAR 52.222-13 COMPLIANCE WITH DAVIS-BACON AND RELATED ACT

REGULATIONS (FEB 1988)

‐ Added FAR 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE

REQUIREMENTS AND RELATED REGULATIONS (MAY 2014)

‐ Removed FAR 52.222-15 CERTIFICATION OF ELIGIBILITY (FEB 1988) ‐ Added FAR 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014) ‐ Removed FAR 52.222-16 APPROVAL OF WAGE RATES (FEB 1988) ‐ Added FAR 52.222-16 APPROVAL OF WAGE RATES (MAY 2014) ‐ Removed FAR 52.222-17 NONDISPLACEMENT OF QUALIFIED WORKERS (JAN

2013) ‐ Added FAR 52.222-17 NONDISPLACEMENT OF QUALIFIED WORKERS (MAY 2014) ‐ Removed FAR 52.222-20 WALSH-HEALEY PUBLIC CONTRACTS ACT (OCT 2010) ‐ Added FAR 52.222-20 CONTRACTS FOR MATERIALS, SUPPLIES, ARTICLES, AND

EQUIPMENT EXCEEDING $15,000 (MAY 2014)

‐ Removed FAR 52.222-30 DAVIS-BACON ACT – PRICE ADJUSTMENT (NONE OR

SEPARATELY SPECIFIED METHOD) (DEC 2001)

‐ Added FAR 52.222-30 CONSTRUCTION WAGE RATE REQUIREMENTS - PRICE

ADJUSTMENT (NONE OR SEPARATELY SPECIFIED METHOD) (MAY 2014)

‐ Removed FAR 52.222-37 EMPLOYMENT REPORTS ON VETERANS (SEP 2010) ‐ Added FAR 52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUL 2014) ‐ Removed FAR 52.222-41 SERVICE CONTRACT ACT OF 1965 (NOV 2007) ‐ Added FAR 52.222-41 SERVICE CONTRACT LABOR STANDARDS (MAY 2014) ‐ Added FAR 52.222-99 ESTABLISHING A MINIMUM WAGE FOR CONTRACTORS

(DEVIATION) (JUN 2014)

‐ Removed FAR 52.223-16 IEEE 1680 STANDARD FOR THE ENVIRONMENTAL

ASSESSMENT OF PERSONAL COMPUTER PRODUCTS (DEC 2007)

‐ Added FAR 52.223-16 ACQUISITION OF EPEAT - REGISTERED PERSONAL

COMPUTER PRODUCTS (JUN 2014)

‐ Removed FAR 52.232-17 INTEREST (OCT 2010) ‐ Added FAR 52.232-17 INTEREST (MAY 2014) ‐ Removed FAR 52.232-23 ASSIGNMENT OF CLAIMS (JAN 1986) ‐ Added FAR 52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014) ‐ Removed FAR 52.233-01 DISPUTES (JUL 2002) – ALTERNATE I (DEC 1991) ‐ Added FAR 52.233-01 DISPUTES (MAY 2014) - ALTERNATE I (DEC 1991) ‐ Removed FAR 52.237-07 INDEMNIFICATION AND MEDICAL LIABILITY INSURANCE

(JAN 1997)

‐ Removed FAR 52.242-03 PENALTIES FOR UNALLOWABLE COSTS (MAY 2001) ‐ Added FAR 52.242-03 PENALTIES FOR UNALLOWABLE COSTS (MAY 2014) ‐ Removed FAR 52.244-06 SUBCONTRACTS FOR COMMERCIAL ITEMS (DEC 2013) ‐ Added FAR 52.244-06 SUBCONTRACTS FOR COMMERCIAL ITEMS (JUL 2014) ‐ Added FAR 52.249-08 DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984) ‐ Removed FAR 52.251-01 INTERAGENCY FLEET MANAGEMENT SYSTEM (IFMS)

VEHICLES AND RELATED SERVICES (JAN 1991)

‐ Removed DFARS 252.225-7006 QUARTERLY REPORTING OF ACTUAL CONTRACT

PERFORMANCE OUTSIDE THE UNITED STATES (OCT 2010)

‐ Added DFARS 252.225-7027 DEFERRED ORDERING OF TECHNICAL DATA OR

COMPUTER SOFTWARE (APR 1988)

‐ Removed DFARS 252.232-7011 PAYMENTS IN SUPPORT OF EMERGENCIES AND

CONTINGENCY OPERATIONS (MAY 2013)

‐ Removed DFARS 252.237-7023 CONTINUATION OF ESSENTIAL CONTRACTOR

SERVICES (OCT 2010)

‐ Removed DFARS 252.244-7001 CONTRACTOR PURCHASING SYSTEM

ADMINISTRATION (JUN 2012)

‐ Added DFARS 252.244-7001 CONTRACTOR PURCHASING SYSTEM

ADMINISTRATION - BASIC (MAY 2014)

‐ Revised Fill-in AFFARS 5352.201-9101 OMBUDSMAN (APR 2014) ‐ Revised Fill-in for FAR 52.217-09 OPTION TO EXTEND THE TERM OF THE

CONTRACT (MAR 2000)

‐ Removed FAR 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL

HIRES (MAY 1989)

‐ Added FAR 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES

(MAY 2014)

‐ Removed FAR 52.204-08 ANNUAL REPRESENTATIONS AND CERTIFICATIONS

(JAN 2014)

SECTION J – LIST OF DOCUMENTS, EXHIBITS & ATTACHMENTS

‐ Revised Exhibit A PGS and DATE ‐ Revised Exhibit B PGS and DATE ‐ Revised Attachment 1 PGS and DATE ‐ Revised Attachment 2 PGS and DATE

‐ Revised Attachment 4 TITLE ‐ Revised Attachment 7 PGS and DATE ‐ Revised Attachment 8 PGS and DATE ‐ Revised Attachment 9 PGS and DATE ‐ Revised Attachment 10 DATE ‐ Added Attachment 11 ‐ Added Attachment 12

SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF

OFFERORS

‐ Added FAR 52.204-08 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2014)

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

‐ Removed DFARS 252.237-7024 NOTICE OF CONTINUATION OF ESSENTIAL

CONTRACTOR SERVICES (OCT 2010)

‐ Removed AEDC-L001 INFORMATION TO OFFERORS (MAY 2014) ‐ Added AEDC-L001 INFORMATION TO OFFERORS (AUG 2014)

Attachment 9, Section L, AEDC-L001, Information to Offerors, is changed as follows:

L-2.2.1, Page Limitations, last sentence is revised.

L-2.2.1.1, Page Size and Format, para (b): Information on foldout pages shall only be on one side. For tables, charts, graphs, and figures, the text shall be no smaller than 8 point.

L-2.2.2, Cost or Pricing Information Requirements, revised.

L-2.3, Electronic Offers, is revised.

L-4.2.1. Volume Organization, delete “Test and Analysis” from Technical volume table.

L-4.2.4.1. Test and Analysis, is deleted.

L-4.2.5. Subfactor 2: Management Approach, revised.

L-4.2.5.5, Subcontracting Management, is revised.

L-4.2.5.6, Organizational Conflict of Interest, is revised.

L-4.2.6. Subfactor 3: Qualified Personnel, is revised.

L-4.2.6.1. Key Personnel, is revised.

L-4.2.6.2. Staffing Plan, is revised.

L-5.1, Volume Organization, the Table of Contents is revised.

L-5.3.1, Number of PPI References, is revised.

L-5.3.2, PPI Submission, remove references to “key management personnel.”

L-5.3.3, Relevant Contracts and Recency Determination, the first paragraph is revised.

L-6.1.5, Rounding, is revised.

L-6.3.3.3, Labor Hour Skill Mix, is revised.

L-6.4.2, Funding Profile, is deleted.

L-6.4.2, Identification of Uncompensated Overtime, is revised.

L-6.4.3, Cost Summary by Cost Elements, is revised.

L-6.4.4, Schedule of Hours by Labor Skill Mix, is revised.

L-6.4.5, Schedule of Rates, is revised.

L-6.4.8, Defined Benefit Pension Plan (DBPP) Cost Accounting Standard (CAS) Contribution, is revised.

L-6.4.9, Material Costs, is revised.

L-7.3.4.2, Small Business Subcontracting Plan, is added.

L-7.3.4.3, OCI Mitigation Plan, is added.

L-7.3.4.6.1, Contractor Work Breakdown Structure is deleted, and subsequent paragraphs are renumbered.

L-7.3.4.6.2, Contractor Performance Work Statement is revised.

L-7.3.4.6.3, Applicable Documents, the first sentence is revised.

Attachment L-2, Past / Present Performance Questionnaire. Remove all references to “key management personnel.”

Attachment L-5, Personnel Consent Letter for the Release of Past Performance Information to the Prime Contractor. Remove all reference to “key management personnel.”

Attachment L-6, Relevancy Matrix, is updated.

Attachment L-8, Schedule of Rates, was deleted.

Attachment L-9, Number of Personnel by Skill Mix, was deleted.

Attachment L-10, Workload Resource Guide, is renumbered to L-8.

Attachment L-11, Cost Model, is renumbered L-9.

SECTION M – EVALUATION FACTORS FOR AWARD

‐ Removed FAR 52.217-03 EVALUATION EXCLUSIVE OF OPTIONS (APR 1984) ‐ Removed FAR 52.217-04 EVALUATION OF OPTIONS EXERCISED AT TIME OF

CONTRACT AWARD (JUN 1988)

‐ Removed AEDC-M001 EVALUATION CRITERIA (MAY 2014) ‐ Added AEDC-M001 EVALUATION CRITERIA (AUG 2014)

Attachment 10, Section M, AEDC-M001, Evaluation Factors for Award, is changed as follows:

M-.2.2.1, Technical Rating, is revised.

M-2.2.3. Subfactor 1: Technical Operations, is revised.

M-2.2.3.1, Test and Analysis, is deleted. Subsequent subfactors were renumbered.

M-2.2.3.3, Lifecycle Sustainment, is revised.

M-2.2.4. Subfactor 2: Management Approach, is revised.

M-2.2.5. Subfactor 3: Qualified Personnel, is revised.

M-2.2.5.1. Key Personnel, is revised.

M-2.2.5.2. Staffing Plan, is revised.

M-2.2.6. Innovations and Efficiencies, is revised.

M-2.3.2.2, Relevancy Assessment, is revised.

M-2.4.1 is revised.

M-2.4.4. is revised.

Changes to Attachment 8, Draft Performance Work Statement (PWS), Dated 12 May 2014, FA9101-13-R-0100

The Draft PWS is changed as follows:

All references to “NETCENTS” have been replaced with “Information Technology Support Contractor.”

1.2 Background

Removed reference to AbilityOne contract

2 General Requirements - Revised scope paragraph

2.1 Non-Personal Services - Deleted, and all subsequent 2.x bullets renumbered

2.5 Contractor Personnel, Disciplines, and Specialties - Deleted fifth bullet

3 Performance Requirements - Added sentence to scope paragraph

3.1 Test and Evaluation - Revised scope paragraph

3.1.1 - Revised requirement and scope paragraph

3.1.2 - Revised requirement and scope paragraph

3.1.3 - Revised scope paragraph

3.1.4.1 - Revised second and third scope paragraphs

3.1.4.2 - Revised second and third scope paragraphs

3.1.4.3 - Revised second and third scope paragraphs

3.1.4.4 - Revised second and third scope paragraphs

3.1.4.5 - Deleted last sentence in scope paragraph

3.1.5.2 - Revised requirement and scope paragraph

3.1.5.3 - Deleted last two sentences in scope paragraph

3.1.5.4 - Revised scope paragraph

3.1.5.5 - Revised scope paragraph

3.1.5.6 - Revised scope paragraph

3.1.6 - Revised scope paragraph

3.1.8 - Added “Applicable Documents” section

3.2.3 - Added sentence to scope paragraph

3.3 Operations of Test Assets and Test Articles - Added sentence to scope paragraph

3.3.2 - Revised scope paragraph and Table 3.3-1 formulas and descriptions

3.3.11 - Added sentence to scope paragraph

3.3.12 - Revised requirement and added scope paragraph

3.3.13 - Added “Applicable Documents” section

3.4.2 - Added “Applicable Documents” section

3.5 Lifecycle Sustainment of Test and Test Support Assets - Added sentence to scope paragraph

3.5.1.1 - Added sentence to scope paragraph

3.5.1.2 - Added sentence to scope paragraph

3.5.2 - Added sentence to scope paragraph

3.5.4 - Added “Applicable Documents” section and subsections

3.6 ID&C Engineering Services and Lifecycle Sustainment - Added sentence to scope paragraph

3.6.2 - Revised first three bullets within scope paragraph

3.6.3 - Revised requirement; added scope statement; deleted performance standard

3.6.5 - Revised scope paragraph

3.6.7 - Revised requirement and added scope statement

3.6.8 - Added scope statement

3.7.7 - Added “Applicable Documents” section and subsections

3.8 Capital Improvements - Revised second scope paragraph

3.8.1.1 - Deleted performance standard

3.8.1.2 - Deleted performance standard

3.8.1.2.1 - Deleted performance standard

3.8.1.3.1 - Deleted performance standard

3.8.1.3.2 - Deleted performance standard

3.8.1.3.3 - Deleted performance standard

3.8.1.4 - Deleted performance standard

3.8.2 - Added sentence to scope paragraph

3.8.3 - Added “Applicable Documents” section and subsections

3.9.16 - Added “Applicable Documents” section and subsections

3.10 Machining/Fabrication and Chemical/Material Analysis - Added two sentence to scope paragraph

3.10.2 - Revised scope paragraph

3.10.6 - Added “Applicable Documents” section

3.11 Operations and Lifecycle Sustainment of AEDC Base Support Assets - Revised scope paragraphs

3.11.1 - Revised requirement and scope paragraph

3.11.2 - Revised scope paragraph

3.11.3 - Revised scope paragraph

3.11.3.1 - Revised requirement and performance standards

3.11.3.2 - Deleted performance standard

3.11.3.4 - Revised requirement and scope paragraph

3.11.4 - Revised scope paragraph

3.11.5 - Revised scope paragraphs

3.11.5.1 - Revised requirement; deleted scope paragraph; revised performance standard

3.11.5.2 - Revised performance standard

3.11.6 - Revised scope paragraph

3.11.6.1 - Revised scope paragraph

3.11.6.2 - Added requirement

3.11.6.3 - Added requirement

3.11.7 - Revised requirement and revised scope paragraph

3.11.7.1 - Revised requirement and deleted scope paragraph

3.11.7.2 - Deleted performance standard

3.11.8 - Added “Applicable Documents” section

3.12 Utilities General Support - Revised scope paragraph

3.12.1 - Revised scope paragraph

3.12.2 - Corrected AFMCI reference in third bullet to “AFMCI 65-602.”

3.12.3 - Revised scope paragraph

3.12.5 - Added “Applicable Documents” section and subsections

3.13.7 - Added “Applicable Documents” section

3.14 AEDC Ground, Weapons and System Safety Programs - Revised scope paragraph and added deliverable

3.14.1 - Revised to requirement and performance standards

3.14.2 - Revised requirement and deleted scope paragraph

Deleted 3.14.2.1, 3.14.2.2, and 3.14.2.5; renumbered subsequent 3.14.2.X requirements

3.14.3 - Revised requirement and scope paragraph added performance standard; added deliverable

3.14.8 - Revised scope paragraph and removed reference to Class C mishaps

3.14.9 - Added requirement

3.14.10 - Added requirement

3.14.11 - Added “Applicable Documents” section and subsections

3.15 - Revised requirement and scope paragraph; moved list of compliance documents to Section 15.3

3.15.1 - Revised scope paragraph

3.15.2 - Revised requirement and scope paragraph

3.15.3 - Replaced with “Applicable Documents” section

3.15.4 - Deleted

3.16 - Revised Financial Management scope paragraph

3.16.2 - Revised scope paragraph

3.16.2 - Moved “FMFIA” reference at end of scope paragraph to “Applicable Documents” section.

3.16.4 - Added “Applicable Documents” section

3.17.3 – Deleted requirement and renumbered subsequent 3.17.X requirements

3.17.7 - Added requirement and performance standard

3.17.8 - Added requirement and subparagraph

3.17.9 - Added “Applicable Documents” section

3.18.3 - Revised scope paragraphs

3.18.6 - Revised scope paragraph

3.18.10 - Revised scope paragraph and moved content from Table 3.18-1 to Section

3.18.17 and subsections.

3.18.10.4 - Revised requirement

3.18.10.4.1 - Revised requirement

3.18.10.4.2 - Revised requirement and performance standards

3.18.10.7 - Revised requirement and deleted performance standards

3.18.10.7.1 - Added requirement and performance standards

3.18.11 - Deleted performance standards

3.18.12 - Revised scope paragraph

3.18.13 - Revised requirement and deleted performance standard

3.18.14 - Revised requirement

3.18.16 - Revised scope paragraph

3.18.17 - Added “Applicable Documents” section and subsections

3.19.2 - Replaced requirement with scope from 3.19.27

3.19.4 - Corrected AEDCOI reference to “AEDCOI 21-1.”

3.19.5 - Revised performance standard

3.19.12 - Revised scope paragraph

3.19.16 - Revised requirement and scope paragraph

3.19.17 - Revised requirement and scope paragraph

3.19.23 - Removed DTIC Submission requirement - this is provided by the IT Support Contractor.

3.19.26 - Revised requirement

3.19.27 - Added “Applicable Documents” section and subsections

3.20.2 - Deleted performance standard

3.20.2.1 - Revised requirement

3.20.2.2 - Revised requirement

3.20.2.3 - Revised requirement and scope paragraph

3.20.3 - Revised requirement

3.20.4 - Added “Applicable Documents” section

3.21 Foreign Technology - Revised scope paragraph

3.21.1.1 – 3.21.1.5 - Deleted performance standard and deliverable references (captured under 3.21.1)

3.21.1.1 - Revised requirement

3.22 Public Affairs - Revised scope paragraph

3.22.3 - Revised requirement

3.22.4 - Revised requirement

3.22.5 - Deleted performance standard

3.22.6 - Revised requirement and performance standard

3.22.6 - Deleted performance standard

3.22.7 - Revised scope paragraph and deleted performance standard

3.22.9 - Added “Applicable Documents” section

3.23 Real Property Management and Accountability Services - Revised scope paragraph

3.23.6 - Added “Applicable Documents” section

3.24.2 - Added “Applicable Documents” section

3.25 Integrated Performance Management Program - Revised scope paragraph

3.25.2 - Revised requirement

3.25.4 - Revised requirement

3.25.5 - Added deliverable

4 Special Requirements

Deleted Security and Public Safety. Subsequent 4.X sections renumbered accordingly.

Section 4.2 Transition was expanded.

Added Performance Requirements Summary table.

Appendix A - Added “Fuel System” asset descriptions. Added intercoms and building page systems under the “Information Systems” bullet within the “Instrumentation, Data Systems, and Control” section.

Appendix C - Removed “Fuel System” and “Natural Gas System” asset descriptions

Appendix D - Moved “Structures and Facilities” asset descriptions to top of Appendix, and removed “Base Civil Engineering Shops” asset descriptions

RFP Cover Letter
Changes to RFP
Draft PWS Change Log
1.2 Background
Removed reference to AbilityOne contract
2 General Requirements - Revised scope paragraph
2.1 Non-Personal Services - Deleted, and all subsequent 2.x bullets renumbered
2.5 Contractor Personnel, Disciplines, and Specialties - Deleted fifth bullet
3 Performance Requirements - Added sentence to scope paragraph
3.1 Test and Evaluation - Revised scope paragraph
3.3 Operations of Test Assets and Test Articles - Added sentence to scope paragraph
3.3.2 - Revised scope paragraph and Table 3.3-1 formulas and descriptions
3.5 Lifecycle Sustainment of Test and Test Support Assets - Added sentence to scope paragraph
3.6 ID&C Engineering Services and Lifecycle Sustainment - Added sentence to scope paragraph
3.8 Capital Improvements - Revised second scope paragraph
3.10 Machining/Fabrication and Chemical/Material Analysis - Added two sentence to scope paragraph
3.11 Operations and Lifecycle Sustainment of AEDC Base Support Assets - Revised scope paragraphs
3.12 Utilities General Support - Revised scope paragraph
3.14 AEDC Ground, Weapons and System Safety Programs - Revised scope paragraph and added deliverable
4 Special Requirements

File details come from the government source that posted it. Updated .